REQUEST FOR PROPOSAL SPECIAL INSPECTIONS &...
Transcript of REQUEST FOR PROPOSAL SPECIAL INSPECTIONS &...
Page 1 of 7
REQUEST FOR PROPOSAL SPECIAL INSPECTIONS & TESTING
BROADWAY SANSOME APARTMENTS 255 BROADWAY ST.
SAN FRANCISCO January 30, 2013
Broadway Sansome Associates, L.P., a California Limited Partnership is soliciting proposals for special inspections and testing for the construction of an affordable housing development located at 255 Broadway Street in San Francisco, CA (corner of Broadway and Sansome). The description of the site and proposed development is provided below. The deadline for submission of the proposal is Wednesday, February 20, 2013 at 2:00 PM. I. DEVELOPMENT/CONSTRUCTION DESCRIPTIONS Project Team The team members for this development are:
Owner/Developer Broadway Sansome Associates, LP Owner Construction Consultant Gonzalo Castro Architect of Record Mithun Solomon Engineer of Record Tipping Mar Geotechnical Consultant Fugro West, Inc. General Contractor Cahill Contractors Fugro West, Inc. has been retained to provide monitoring of environmental soils and geotechnical-related inspections during the project. Schedule Proposals for the Special Inspections and Testing are due on Wednesday, February 20th at 2:00 pm. There will be a voluntary pre-bid meeting on Wednesday, February 6th at 10:00 am., at Cahill’s Office at 425 California Street (at California & Sansome), Suite 2200. Construction is expected to start in March 2013 and be complete by December 2014. Below is a list of milestone dates for the project.
• Voluntary Pre-Bid Meeting - February 6th at 10:00 am • Proposals Due - February 20th at 2:00 pm • Begin Construction - March 2013
Page 2 of 7
• Complete Construction - December 2014 • Project Duration - Approx. 21 months
Please see the attached construction schedule for your information (Attachment A).
Plans & Specifications Documents are available for review at the following locations:
Location Address Phone Cahill’s San Francisco Office 425 California Street, Suite 2300
San Francisco, Ca 94104 (415) 986-0600
Cahill’s Oakland office 1111 Broadway, Suite 2130 Oakland, CA 94607
(510) 250-8500
Cahill’s Yard* 1599 Custer Ave. San Francisco, CA
(415) 824-9100
Builders Exchange of San Francisco 850 So. Van Ness Ave. San Francisco, CA 94110
(415) 282-8220
Dodge Plan Room (McGraw Hill) 11875 Dublin Blvd., Suite A118 Dublin, CA 94568
(925) 833-9751
Builders Exchange of Alameda County 3055 Alvarado St. San Leandro, CA 94577
(510) 483-8880
Peninsula Builders Exchange 735 Industrial Rd., Suite 100 San Carlos, CA 94070
(650) 591-4486
Sacramento Regional Builders Exchange 1331 T. St. Sacramento, CA 95811
(916) 442-8991
Plans may also be purchased at:
ARC - Northern California 945 Bryant Street San Francisco, CA 94103 Phone: (415) 537-2224 Email: [email protected]
Plans can also be downloaded from Cahill’s File sharing site at the following address: https://cahillcontractors.box.com/s/7ks2rgtn1hs30g4lcs9k
If you have questions regarding the project please call or email
Casey Kasten, Estimator Cahill Contractors 425 California Street San Francisco, CA 94104
Page 3 of 7
(415) 986-0600 [email protected]
II. SCOPE OF SPECIAL INSPECTIONS This project, located at 255 Broadway Street, has a mat slab and 2 concrete podiums with 1 floor of metal stud framing and 7 floors of wood framing. When complete, the building will contain 75 residential units comprised of studios, 1, 2 and 3 bedroom units. The basement and level 1 will contain some common area, retail space, and offices. There will be roof decks at levels 6 and 7 and an exterior courtyard at level 1. Total area is approximately 88,000 SF.
This project is funded in part by the Mayor’s Office of Housing (MOH) / Human Rights Commission (HRC). As such, the HRC’s Local Business Enterprise (LBE), Construction Workforce and Prevailing Wage policies apply. The majority of the inspections are anticipated to occur from March 2013 thru May 2014. A construction schedule (Attachment A) is included for your information and use. The scope of inspections will be as dictated by the San Francisco Department of Building and Inspection. Your fee proposal shall be based upon the following scope of work. Reinforced Concrete
a. Drilled Piers – Approx 220 cy / 3 pours b. Grade Beams / Pipe Caps / Misc Footings - Approx 320 cy / 4 pours c. Slabs-On-Grade / Mat Slab – Approx 620 cy / 5 pours d. Columns – Approx 60 cy / 3 pours e. Shotcrete Walls - Approx 515 cy / 4 shoots f. Suspended Slabs – Approx 630 cy / 3 pours g. Miscellaneous Concrete – Approx 160 cy / 5 pours
Structural Steel
h. Miscellaneous Structural Steel i. Shop Inspections – Allow for 7 days
ii. Field Inspections – Allow for 15 days i. Structural Steel Stairs
i. Shop Inspections – Allow for 3 days ii. Field Inspections – Allow for 5 days
j. Misc Steel – Canopy Anchorage, Window Washing Davits, etc. i. Shop Inspections – Allow for 5 days
ii. Field Inspections – Allow for 15 days Shop inspections will be performed at a shop located in San Francisco.
Page 4 of 7
Wood Framing k. Wood Framing – Include Framing, Shear Wall, Nailing and other
inspections as required by the City and County of SF. The wood framing will occur over approximately 69,000 sf and involves the construction of 75 units. It is anticipated that much of the wood framing will be performed offsite at Bay Area Construction Framer’s yard located in Livermore. Wall panels will be assembled at this location and then hoisted into place and nailed off.
Dowels & Bolts in Concrete l. Epoxy Dowels – Allow for the inspection and requisite number of pull
tests for 100 epoxy dowels m. Anchor Bolts / Embeds for Structural Steel – Allow for the inspection of
100 anchor bolts and / or embeds. n. Sill / Anchor Bolts for Wood Framing – Allow for the inspection of 1,700
sill bolts o. Tie-Down Anchor Bolts – Allow for 300 tie down inspections.
Please refer to the drawings and specifications for additional information & details
All inspection reports shall be submitted to the Owner, Architect, Engineer, San Francisco Department of Building and Inspection, and Cahill Contractors. Any items that fail inspections shall be re-inspected and a revised report referencing the original failed inspection will be included for reference. All Final Affidavits or final inspection reports that are required by the San Francisco Department of Building and Inspection or Owner shall be included in the scope. If you have technical questions please contact Casey Kasten at Cahill Contractors
Casey Kasten, Estimator Cahill Contractors, Inc. Ph: (415) 986-0600 Fax: (415) 986-4406 [email protected]
III. EQUAL OPPORTUNITY GOALS The Developers of the project (Broadway Sansome Associates, LP) have committed to meeting the San Francisco Human Rights Commission (HRC) equal opportunity contracting and work force participation goals. In general, the project goals can be summarized as follows:
Page 5 of 7
Local Business Enterprises (LBE): LBE status will be considered in the award of this work. To claim LBE status, a business must be certified by the MOH / HRC on or before the bid date. Please provide your HRC Certification letter with your bid. Please list the involvement of any suppliers or lower tier-subcontractors that may be included in your bid as well as their LBE status. For more information on how to become LBE certified please visit the HRC website at http://www.sfgov.org/site/sfhumanrights_index.asp (scroll to the bottom of the page and click on the LBE link).
Prevailing Wage Provisions: This project is subject to federal and state prevailing wage requirements. Subcontractors must pay all trades in their employ the higher of the state or federal prevailing wage determination. Please see the California Department of Industrial Relations website (www.dir.ca.gov) or go to the links below for more info. If you do not understand which wage to include in your pricing, please contact Cahill Contractors.
State of California • Journeyman: http://www.dir.ca.gov/dlsr/PWD/Northern.html • Apprentice:
http://www.dir.ca.gov/DAS/PWAppWage/PWAppWageList.asp
Federal • http://www.gpo.gov/davisbacon/CA.html
Payroll Requirements Inspection Firms will be required to submit certified payrolls every week, through the Elations System [or LCP Tracker].
Preconstruction Meeting Inspection Firms shall be required to attend a preconstruction meeting with Cahill, the Mayor’s Office of Housing and City Build. This meeting must be held prior to the commencement of any subcontractor’s work onsite.
IV. PROPOSAL CONTENTS AND DEADLINE Proposals are due on Wednesday February 20th at 2:00 pm to Casey Kasten. Proposals shall include the following information which will be used to evaluate the proposals:
Page 6 of 7
1. A brief statement of your firm’s qualifications in completing the scope of work described above. Please provide references
2. Fee schedule, as follows:
a. Fees will be paid on a time and materials basis. Please provide i. Your rate schedule (hourly and overtime rates) including any
escalation during the project period, ii. Any minimum number of hours per inspection or minimum trip
charges. iii. Rates for reimbursable expenses.
Please note that all rates are to be good for the duration of the project. Escalation will not be allowed. b. Total estimated fee for the scope of work described above. Please itemize
your estimated fees for each inspection type listed in the scope. All fees or rates quoted shall be good for the duration of the job. Escalation will not be allowed.
3. Insurance – Please provide a sample insurance certificate with your proposal.
Minimum insurance limits are as follows:
Workers Comp - $1M Auto - $1M General Liability - $1M Umbrella - $5M Professional Liability - $1M The Owner (Broadway Sansome Associates, LP) shall be named as the primary insured on all insurance certificates. Inspection Firms will be required to include the following entities as additional insured:
• Mayor’s Office of Housing (MOH) / Human Rights Commission (HRC) • Chinese Community Development Center & their agents & consultants • Mithun Solomon (Architect) • Design Studios Gonzalo Castro (Construction Manager) • Cahill Contractors, Inc (Contractor)
4. If applicable, evidence of status as Local Business Enterprise as certified by the
Human Rights Commission or potential eligibility for Local Business Enterprise status and willingness to apply if your firm meets the requirements as spelled out by the Human Rights Commission.
Page 7 of 7
Broadway Sansome Associates LP will enter into a contract with the Special Inspections and Testing firm submitting the best overall proposal. The proposed fees, experience, insurance, LBE status and references will be evaluated to determine the successful firm. Broadway Sansome Associates, LP reserves the right to waive any irregularities in the proposals submitted.
Attachments to this RFP
1) Attachment A: Construction Schedule for Broadway Sansome Apartments dated 1/11/13
-End of Special Inspection & Testing Request for Proposal-
ID Task Name Duration Start Finish Predecessors
1 Authorization to Proceed 1 day Mon 3/4/13 Mon 3/4/13
2 Mobilize Equipment / Erect Fencing / Set up Trailer 5 days Tue 3/5/13 Mon 3/11/13 1
3
4 Earthwork & Site Utilities 97 days Tue 3/12/13 Wed 7/24/13
5 Earthwork 97 days Tue 3/12/13 Wed 7/24/13
6 Site Demo & Clearing 5 days Tue 3/12/13 Mon 3/18/13 2
7 Mass Excavation & Shoring 30 days Tue 3/19/13 Mon 4/29/13 6
8 Excavate, Place Detention Tank, WP Adjacent Building 12 days Fri 4/12/13 Mon 4/29/13 7FF
9 Install Piping for Detention Tank 5 days Tue 4/30/13 Mon 5/6/13 8
10 Backfill and Compact Detention Area + Fine Grade 5 days Tue 5/7/13 Mon 5/13/13 9
11 Backfill at Basement Walls 5 days Thu 7/18/13 Wed 7/24/13 25
12 Site Utilities 30 days Tue 4/30/13 Mon 6/10/13
13 SS & SD Lines 15 days Tue 4/30/13 Mon 5/20/13 7
14 DW, RCW & FW Lines 30 days Tue 4/30/13 Mon 6/10/13 7
15 Electrical Service 20 days Tue 4/30/13 Mon 5/27/13 7
16
17 Structure 246 days Tue 5/14/13 Tue 4/22/14
18 East Block - Foundation & Podium 90 days Tue 5/14/13 Mon 9/16/13
19 Drilled Piers - Basement - East 15 days Tue 5/14/13 Mon 6/3/13 10
20 Sub Slab Plumbing and Electrical - Basement - East 15 days Tue 5/28/13 Mon 6/17/13 19FS-5 days
21 Excavate Footings - Basement - East 15 days Tue 6/4/13 Mon 6/24/13 19
22 Grade Beams and Slab On Grade - Basement - East 20 days Tue 6/18/13 Mon 7/15/13 21FS-5 days
23 Columns & Walls - Basement - East 20 days Tue 7/16/13 Mon 8/12/13 22
24 Level 1 - East Podium 25 days Tue 8/13/13 Mon 9/16/13 23
25 Waterproof Shoring, Footings, Wall - East 20 days Thu 6/20/13 Wed 7/17/13 21FS-3 days
26
27 West Block - Foundation & Podium 90 days Thu 7/25/13 Wed 11/27/13
28 Drilled Piers - Level 1 - West 10 days Thu 7/25/13 Wed 8/7/13 11
29 Sub Slab Plumbing and Electrical - Level 1 West 10 days Thu 8/8/13 Wed 8/21/13 28
Authorization to Proceed
Mobilize Equipment / Erect Fencing / Set up Trailer
Earthwork & Site Utilities
Site Demo & Clearing
Mass Excavation & Shoring
Excavate, Place Detention Tank, WP Adjacent Building
Install Piping for Detention Tank
Backfill and Compact Detention Area + Fine Grade
Backfill at Basement Walls
Site Utilities
SS & SD Lines
DW, RCW & FW Lines
Electrical Service
Structure
East Block - Foundation & Podium
Drilled Piers - Basement - East
Sub Slab Plumbing and Electrical - Basement - East
Excavate Footings - Basement - East
Grade Beams and Slab On Grade - Basement - East
Columns & Walls - Basement - East
Level 1 - East Podium
Waterproof Shoring, Footings, Wall - East
West Block - Foundation & Podium
Drilled Piers - Level 1 - West
Sub Slab Plumbing and Electrical - Level 1 West
MarApr a Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan erte 2nd Quart 3rd Quarte 4th Quarte 1st Quarte 2nd Quart 3rd Quarte 4th Quarte 1st Qua
Sansome & Broadway Family Housing
Cahill Contractors, Inc. Page 1 January 11, 2013
ID Task Name Duration Start Finish Predecessors
30 Excavate Footings - Level 1 - West 15 days Thu 8/8/13 Wed 8/28/13 28
31 Grade Beams & Slab On Grade - Level 1 - West 20 days Thu 8/22/13 Wed 9/18/13 30FS-5 days
32 Concrete Columns & Walls - Level 1 & 2 - West 25 days Thu 9/19/13 Wed 10/23/13 31
33 Post-Tensioned Concrete Podium Level 3 - West 25 days Thu 10/24/13 Wed 11/27/13 32
34
35 Wood Framing and Sheathing 105 days Wed 11/20/13 Tue 4/15/14
36 Layout & Frame - Level 1 - East Block Only 5 days Wed 11/20/13 Tue 11/26/13 33FS-6 days
37 Joist / Subfloor - Level 2 - East Block Only 3 days Wed 11/27/13 Fri 11/29/13 36
38 Layout & Frame - Level 2 - East Block Only 5 days Mon 12/2/13 Fri 12/6/13 37
39 Joist / Subfloor - Level 3 - East Block Only 3 days Mon 12/9/13 Wed 12/11/13 38
40 Layout & Frame - Level 3 7 days Thu 12/12/13 Fri 12/20/13 39,33
41 Joist / Subfloor - Level 4 5 days Mon 12/23/13 Fri 12/27/13 40
42 Layout & Frame - Level 4 7 days Mon 12/30/13 Tue 1/7/14 41
43 Joist / Subfloor - Level 5 5 days Wed 1/8/14 Tue 1/14/14 42
44 Layout & Frame - Level 5 7 days Wed 1/15/14 Thu 1/23/14 43
45 Joist / Subfloor / Roof Joists & Crickets- Level 6 5 days Fri 1/24/14 Thu 1/30/14 44
46 Layout & Frame - Level 6 - West Block Only 5 days Fri 1/31/14 Thu 2/6/14 45
47 Joist / Subfloor - Level 7 - West Block Only 3 days Fri 2/7/14 Tue 2/11/14 46
48 Layout & Frame - Level 7 - West Block Only 5 days Wed 2/12/14 Tue 2/18/14 47
49 Roof Joists / Sheathing / Crickets / Penthouses - West 10 days Wed 2/19/14 Tue 3/4/14 48
50 Misc Pickup & Blocking 30 days Wed 3/5/14 Tue 4/15/14 49
51
52 Tower Crane 231 days Tue 6/4/13 Tue 4/22/14
53 Tower Crane Founation 15 days Tue 6/4/13 Mon 6/24/13 19
54 Erect Tower Crane 5 days Tue 6/25/13 Mon 7/1/13 53
55 Remove Tower Crane 5 days Wed 4/16/14 Tue 4/22/14 50
56
57 Exterior Skin & Roofing 204 days Thu 11/28/13 Tue 9/9/14
58 Scaffold Erection 10 days Thu 11/28/13 Wed 12/11/13 33
Excavate Footings - Level 1 - West
Grade Beams & Slab On Grade - Level 1 - West
Concrete Columns & Walls - Level 1 & 2 - West
Post-Tensioned Concrete Podium Level 3 - West
Wood Framing and Sheathing
Layout & Frame - Level 1 - East Block Only
Joist / Subfloor - Level 2 - East Block Only
Layout & Frame - Level 2 - East Block Only
Joist / Subfloor - Level 3 - East Block Only
Layout & Frame - Level 3
Joist / Subfloor - Level 4
Layout & Frame - Level 4
Joist / Subfloor - Level 5
Layout & Frame - Level 5
Joist / Subfloor / Roof Joists & Crickets- Leve
Layout & Frame - Level 6 - West Block Only
Joist / Subfloor - Level 7 - West Block Only
Layout & Frame - Level 7 - West Block Only
Roof Joists / Sheathing / Crickets / Penth
Misc Pickup & Blocking
Tower Crane
Tower Crane Founation
Erect Tower Crane
Remove Tower Crane
Exterior Skin & Ro
Scaffold Erection
MarApr a Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan erte 2nd Quart 3rd Quarte 4th Quarte 1st Quarte 2nd Quart 3rd Quarte 4th Quarte 1st Qua
Sansome & Broadway Family Housing
Cahill Contractors, Inc. Page 2 January 11, 2013
ID Task Name Duration Start Finish Predecessors
59 Exterior Shear Sheathing 70 days Thu 12/5/13 Wed 3/12/14 58FS-5 days
60 Window Installation 60 days Thu 2/20/14 Wed 5/14/14 59FS-15 days
61 Exterior Plaster, Cement Board Panels 60 days Thu 4/3/14 Wed 6/25/14 60FS-30 days
62 Canopies, Sunshades, Railings 40 days Thu 5/29/14 Wed 7/23/14 61FS-20 days
63 Paint & Sealers 20 days Thu 6/19/14 Wed 7/16/14 61FS-5 days
64 Rooftop Equipment and EBM 20 days Wed 3/5/14 Tue 4/1/14 49
65 Roofing & Flashing 30 days Wed 3/5/14 Tue 4/15/14 49
66 SHW Panels 30 days Wed 4/16/14 Tue 5/27/14 65
67 Remove Scaffold 15 days Thu 7/10/14 Wed 7/30/14 63FS-5 days
68 Patch Exterior Structure / Skin 20 days Wed 8/13/14 Tue 9/9/14 72
69
70 Personnel Lift 184 days Thu 11/28/13 Tue 8/12/14
71 Erect Personnel Lift 5 days Thu 11/28/13 Wed 12/4/13 33
72 Remove Personnel Lift 5 days Wed 8/6/14 Tue 8/12/14 210
73
74 Interiors 247 days Tue 10/29/13 Wed 10/8/14
75 Basement - Offices & Mechanical - East Block Only 219 days Tue 10/29/13 Fri 8/29/14
76 Basement - Metal Stud Framing 20 days Tue 10/29/13 Mon 11/25/13 24FS+30 days
77 Basement - MEPS Rough-In 45 days Tue 11/12/13 Mon 1/13/14 76SS+10 days
78 Basement - Insulation 5 days Wed 4/16/14 Tue 4/22/14 65
79 Basement - Sheetrock Taped & Sanded 18 days Wed 4/23/14 Fri 5/16/14 78
80 Basement - Interior Doors & Frames 10 days Mon 5/19/14 Fri 5/30/14 79
81 Basement - Install Paint Grade Trim 10 days Mon 6/2/14 Fri 6/13/14 80
82 Basement - Interior Paint 10 days Mon 6/16/14 Fri 6/27/14 81
83 Basement - Offices Cabinets & Countertops 15 days Mon 6/30/14 Fri 7/18/14 82
84 Basement - Common Area Flooring 15 days Mon 7/21/14 Fri 8/8/14 83
85 Basement - MEPS Trim & Accessories 15 days Mon 8/11/14 Fri 8/29/14 84
86
87 Level 1 - East Block - 9 Units 199 days Thu 12/12/13 Tue 9/16/14
Exterior Shear Sheathing
Window Installation
Exterior Plaster, Cement Boa
Canopies, Sunshades, Ra
Paint & Sealers
Rooftop Equipment and EBM
Roofing & Flashing
SHW Panels
Remove Scaffold
Patch Exterior Stru
Personnel Lift
Erect Personnel Lift
Remove Personnel Lift
Interiors
Basement - Offices
Basement - Metal Stud Framing
Basement - MEPS Rough-In
Basement - Insulation
Basement - Sheetrock Taped & S
Basement - Interior Doors & Fra
Basement - Install Paint Grade
Basement - Interior Paint
Basement - Offices Cabin
Basement - Common Ar
Basement - MEPS Tri
Level 1 - East Blo
MarApr a Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan erte 2nd Quart 3rd Quarte 4th Quarte 1st Quarte 2nd Quart 3rd Quarte 4th Quarte 1st Qua
Sansome & Broadway Family Housing
Cahill Contractors, Inc. Page 3 January 11, 2013
ID Task Name Duration Start Finish Predecessors
88 Level 1 - MEPS Rough-In 45 days Thu 12/12/13 Wed 2/12/14 39
89 Level 1 - Insulation 5 days Wed 4/23/14 Tue 4/29/14 78
90 Level 1 - Sheetrock Taped & Sanded 18 days Wed 4/30/14 Fri 5/23/14 89
91 Level 1- Interior Doors & Frames 10 days Mon 5/26/14 Fri 6/6/14 90
92 Level 1 - Install Paint Grade Trim 10 days Mon 6/9/14 Fri 6/20/14 91
93 Level 1 - Interior Paint 10 days Mon 6/23/14 Fri 7/4/14 92
94 Level 1 - Cabinets 10 days Mon 7/7/14 Fri 7/18/14 93
95 Level 1 - Closet Shelving 5 days Mon 7/7/14 Fri 7/11/14 94SS
96 Level 1 - Unit Flooring 10 days Thu 7/10/14 Wed 7/23/14 94SS+3 days
97 Level 1- Countertops 5 days Thu 7/24/14 Wed 7/30/14 96
98 Level 1- Unit Appliances, Trim & Accessories 15 days Wed 8/6/14 Tue 8/26/14 97FS+4 days
99 Level 1 - Corridor Flooring 5 days Wed 8/27/14 Tue 9/2/14 98
100 Level 1 - MEPS Trim & Accessories 15 days Wed 8/27/14 Tue 9/16/14 98
101
102 Level 1 & 2 West Block - Lobby, Offices, Comm Rm 145 days Wed 3/19/14 Tue 10/7/14
103 Level 1 - Metal Stud Framing 20 days Wed 3/19/14 Tue 4/15/14 147
104 Level 1 - MEPS Rough - In 45 days Wed 4/16/14 Tue 6/17/14 103
105 Level 1 - Insulation 5 days Wed 6/18/14 Tue 6/24/14 104
106 Level 1 - Sheetrock Taped & Sanded 15 days Wed 6/25/14 Tue 7/15/14 105
107 Level 1- Interior Doors & Frames 10 days Wed 7/16/14 Tue 7/29/14 106
108 Level 1 - Install Paint Grade Trim 10 days Wed 7/30/14 Tue 8/12/14 107
109 Level 1 - Interior Paint 10 days Wed 8/13/14 Tue 8/26/14 108
110 Level 1 - Lobby Cabinets & Millwork 15 days Wed 8/27/14 Tue 9/16/14 109
111 Level 1 - Common Area Flooring 15 days Wed 9/17/14 Tue 10/7/14 110
112 Level 1 - MEPS Trim & Accessories 15 days Wed 9/17/14 Tue 10/7/14 110
113
114 Level 2 - East Block - 9 Units 200 days Thu 12/12/13 Wed 9/17/14
115 Level 2 - MEPS Rough- In 45 days Thu 12/12/13 Wed 2/12/14 39
116 Level 2 - Gypcrete 3 days Wed 3/5/14 Fri 3/7/14 65SS
Level 1 - MEPS Rough-In
Level 1 - Insulation
Level 1 - Sheetrock Taped & San
Level 1- Interior Doors & Frame
Level 1 - Install Paint Grade T
Level 1 - Interior Paint
Level 1 - Cabinets
Level 1 - Closet Shelving
Level 1 - Unit Flooring
Level 1- Countertops
Level 1- Unit Applian
Level 1 - Corridor Fl
Level 1 - MEPS Tri
Level 1 & 2 Wes
Level 1 - Metal Stud Framing
Level 1 - MEPS Rough - In
Level 1 - Insulation
Level 1 - Sheetrock Taped
Level 1- Interior Doors &
Level 1 - Install Paint G
Level 1 - Interior Paint
Level 1 - Lobby Ca
Level 1 - Commo
Level 1 - MEPS T
Level 2 - East Blo
Level 2 - MEPS Rough- In
Level 2 - Gypcrete
MarApr a Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan erte 2nd Quart 3rd Quarte 4th Quarte 1st Quarte 2nd Quart 3rd Quarte 4th Quarte 1st Qua
Sansome & Broadway Family Housing
Cahill Contractors, Inc. Page 4 January 11, 2013
ID Task Name Duration Start Finish Predecessors
117 Level 2 - Insulation 5 days Wed 4/30/14 Tue 5/6/14 89
118 Level 2 - Sheetrock Taped & Sanded 18 days Wed 5/7/14 Fri 5/30/14 117
119 Level 2- Interior Doors & Frames 10 days Mon 6/2/14 Fri 6/13/14 118
120 Level 2 - Install Paint Grade Trim 10 days Mon 6/16/14 Fri 6/27/14 119
121 Level 2 - Interior Paint 10 days Mon 6/30/14 Fri 7/11/14 120
122 Level 2 - Cabinets 10 days Mon 7/14/14 Fri 7/25/14 121
123 Level 2 - Closet Shelving 5 days Mon 7/14/14 Fri 7/18/14 122SS
124 Level 2 - Unit Flooring 10 days Thu 7/17/14 Wed 7/30/14 122SS+3 days
125 Level 2- Countertops 5 days Thu 7/31/14 Wed 8/6/14 124
126 Level 2- Unit Appliances, Trim & Accessories 15 days Thu 8/7/14 Wed 8/27/14 125
127 Level 2 - Corridor Flooring 5 days Thu 8/28/14 Wed 9/3/14 126
128 Level 2 - MEPS Trim & Accessories 15 days Thu 8/28/14 Wed 9/17/14 126
129
130 Level 3 - 15 Units 193 days Mon 12/30/13 Wed 9/24/14
131 Level 3 - MEPS Rough-In 45 days Mon 12/30/13 Fri 2/28/14 41
132 Level 3 - Gypcrete 3 days Mon 3/10/14 Wed 3/12/14 116
133 Level 3 - Insulation 5 days Wed 5/7/14 Tue 5/13/14 117
134 Level 3 - Sheetrock Taped & Sanded 18 days Wed 5/14/14 Fri 6/6/14 133
135 Level 3- Interior Doors & Frames 10 days Mon 6/9/14 Fri 6/20/14 134
136 Level 3 - Install Paint Grade Trim 10 days Mon 6/23/14 Fri 7/4/14 135
137 Level 3 - Interior Paint 10 days Mon 7/7/14 Fri 7/18/14 136
138 Level 3 - Cabinets 10 days Mon 7/21/14 Fri 8/1/14 137
139 Level 3 - Closet Shelving 5 days Mon 7/21/14 Fri 7/25/14 138SS
140 Level 3 - Unit Flooring 10 days Thu 7/24/14 Wed 8/6/14 138SS+3 days
141 Level 3- Countertops 5 days Thu 8/7/14 Wed 8/13/14 140
142 Level 3- Unit Appliances, Trim & Accessories 15 days Thu 8/14/14 Wed 9/3/14 141
143 Level 3 - Corridor Flooring 5 days Thu 9/4/14 Wed 9/10/14 142
144 Level 3 - MEPS Trim & Accessories 15 days Thu 9/4/14 Wed 9/24/14 142
145
Level 2 - Insulation
Level 2 - Sheetrock Taped & Sa
Level 2- Interior Doors & Fram
Level 2 - Install Paint Grade
Level 2 - Interior Paint
Level 2 - Cabinets
Level 2 - Closet Shelving
Level 2 - Unit Flooring
Level 2- Countertops
Level 2- Unit Applian
Level 2 - Corridor Fl
Level 2 - MEPS Tri
Level 3 - 15 Units
Level 3 - MEPS Rough-In
Level 3 - Gypcrete
Level 3 - Insulation
Level 3 - Sheetrock Taped & Sa
Level 3- Interior Doors & Fra
Level 3 - Install Paint Grade
Level 3 - Interior Paint
Level 3 - Cabinets
Level 3 - Closet Shelving
Level 3 - Unit Flooring
Level 3- Countertops
Level 3- Unit Applian
Level 3 - Corridor Fl
Level 3 - MEPS Tri
MarApr a Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan erte 2nd Quart 3rd Quarte 4th Quarte 1st Quarte 2nd Quart 3rd Quarte 4th Quarte 1st Qua
Sansome & Broadway Family Housing
Cahill Contractors, Inc. Page 5 January 11, 2013
ID Task Name Duration Start Finish Predecessors
146 Level 4 - 15 Units 186 days Wed 1/15/14 Wed 10/1/14
147 Level 4 - MEPS Rough-In 45 days Wed 1/15/14 Tue 3/18/14 43
148 Level 4 - Gypcrete 3 days Thu 3/13/14 Mon 3/17/14 132
149 Level 4 - Insulation 5 days Wed 5/14/14 Tue 5/20/14 133
150 Level 4 - Sheetrock Taped & Sanded 18 days Wed 5/21/14 Fri 6/13/14 149
151 Level 4- Interior Doors & Frames 10 days Mon 6/16/14 Fri 6/27/14 150
152 Level 4 - Install Paint Grade Trim 10 days Mon 6/30/14 Fri 7/11/14 151
153 Level 4 - Interior Paint 10 days Mon 7/14/14 Fri 7/25/14 152
154 Level 4 - Cabinets 10 days Mon 7/28/14 Fri 8/8/14 153
155 Level 4 - Closet Shelving 5 days Mon 7/28/14 Fri 8/1/14 154SS
156 Level 4 - Unit Flooring 10 days Thu 7/31/14 Wed 8/13/14 154SS+3 days
157 Level 4- Countertops 5 days Thu 8/14/14 Wed 8/20/14 156
158 Level 4- Unit Appliances, Trim & Accessories 15 days Thu 8/21/14 Wed 9/10/14 157
159 Level 4 - Corridor Flooring 5 days Thu 9/11/14 Wed 9/17/14 158
160 Level 4 - MEPS Trim & Accessories 15 days Thu 9/11/14 Wed 10/1/14 158
161
162 Level 5 - 15 Units 179 days Fri 1/31/14 Wed 10/8/14
163 Level 5 - MEPS Rough-In 45 days Fri 1/31/14 Thu 4/3/14 45
164 Level 5 - Gypcrete 3 days Tue 3/18/14 Thu 3/20/14 148
165 Level 5 - Insulation 5 days Wed 5/21/14 Tue 5/27/14 149
166 Level 5 - Sheetrock Taped & Sanded 18 days Wed 5/28/14 Fri 6/20/14 165
167 Level 5- Interior Doors & Frames 10 days Mon 6/23/14 Fri 7/4/14 166
168 Level 5 - Install Paint Grade Trim 10 days Mon 7/7/14 Fri 7/18/14 167
169 Level 5 - Interior Paint 10 days Mon 7/21/14 Fri 8/1/14 168
170 Level 5 - Cabinets 10 days Mon 8/4/14 Fri 8/15/14 169
171 Level 5 - Closet Shelving 5 days Mon 8/4/14 Fri 8/8/14 170SS
172 Level 5 - Unit Flooring 10 days Thu 8/7/14 Wed 8/20/14 170SS+3 days
173 Level 5- Countertops 5 days Thu 8/21/14 Wed 8/27/14 172
174 Level 5- Unit Appliances, Trim & Accessories 15 days Thu 8/28/14 Wed 9/17/14 173
Level 4 - 15 Unit
Level 4 - MEPS Rough-In
Level 4 - Gypcrete
Level 4 - Insulation
Level 4 - Sheetrock Taped & S
Level 4- Interior Doors & Fra
Level 4 - Install Paint Grad
Level 4 - Interior Paint
Level 4 - Cabinets
Level 4 - Closet Shelving
Level 4 - Unit Flooring
Level 4- Countertops
Level 4- Unit Applia
Level 4 - Corridor
Level 4 - MEPS T
Level 5 - 15 Uni
Level 5 - MEPS Rough-In
Level 5 - Gypcrete
Level 5 - Insulation
Level 5 - Sheetrock Taped &
Level 5- Interior Doors & Fr
Level 5 - Install Paint Grad
Level 5 - Interior Paint
Level 5 - Cabinets
Level 5 - Closet Shelvin
Level 5 - Unit Flooring
Level 5- Countertops
Level 5- Unit Appli
MarApr a Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan erte 2nd Quart 3rd Quarte 4th Quarte 1st Quarte 2nd Quart 3rd Quarte 4th Quarte 1st Qua
Sansome & Broadway Family Housing
Cahill Contractors, Inc. Page 6 January 11, 2013
ID Task Name Duration Start Finish Predecessors
175 Level 5 - Corridor Flooring 5 days Thu 9/18/14 Wed 9/24/14 174
176 Level 5 - MEPS Trim & Accessories 15 days Thu 9/18/14 Wed 10/8/14 174
177
178 Level 6 - West Block Only - 6 Units 153 days Wed 2/12/14 Fri 9/12/14
179 Level 6 - MEPS Rough-In 30 days Wed 2/12/14 Tue 3/25/14 47
180 Level 6 - Gypcrete 3 days Fri 3/21/14 Tue 3/25/14 164
181 Level 6 - Insulation 5 days Wed 5/28/14 Tue 6/3/14 165
182 Level 6 - Sheetrock Taped & Sanded 12 days Wed 6/4/14 Thu 6/19/14 181
183 Level 6- Interior Doors & Frames 8 days Fri 6/20/14 Tue 7/1/14 182
184 Level 6 - Installl Paint Grade Trim 8 days Wed 7/2/14 Fri 7/11/14 183
185 Level 6 - Interior Paint 8 days Mon 7/14/14 Wed 7/23/14 184
186 Level 6 - Cabinets 8 days Thu 7/24/14 Mon 8/4/14 185
187 Level 6 - Closet Shelving 4 days Thu 7/24/14 Tue 7/29/14 186SS
188 Level 6 - Unit Flooring 8 days Tue 7/29/14 Thu 8/7/14 186SS+3 days
189 Level 6- Countertops 4 days Fri 8/8/14 Wed 8/13/14 188
190 Level 6- Unit Appliances, Trim & Accessories 12 days Thu 8/14/14 Fri 8/29/14 189
191 Level 6 - Corridor Flooring 5 days Mon 9/1/14 Fri 9/5/14 190
192 Level 6 - MEPS Trim & Accessories 10 days Mon 9/1/14 Fri 9/12/14 190
193
194 Level 7 - West Block Only - 6 Units 149 days Wed 3/5/14 Mon 9/29/14
195 Level 7 - MEPS Rough-In 30 days Wed 3/5/14 Tue 4/15/14 49
196 Level 7 - Gypcrete 3 days Wed 3/26/14 Fri 3/28/14 180
197 Level 7 - Insulation 5 days Wed 6/4/14 Tue 6/10/14 181
198 Level 7 - Sheetrock Taped & Sanded 12 days Wed 6/11/14 Thu 6/26/14 197
199 Level 7- Interior Doors & Frames 8 days Fri 6/27/14 Tue 7/8/14 198
200 Level 7 - Install Paint Grade Trim 8 days Wed 7/9/14 Fri 7/18/14 199
201 Level 7 - Interior Paint 8 days Mon 7/21/14 Wed 7/30/14 200
202 Level 7 - Cabinets 8 days Tue 8/5/14 Thu 8/14/14 186
203 Level 7 - Closet Shelving 4 days Tue 8/5/14 Fri 8/8/14 202SS
Level 5 - Corridor
Level 5 - MEPS
Level 6 - MEPS Rough-In
Level 6 - Gypcrete
Level 6 - Insulation
Level 6 - Sheetrock Taped &
Level 6- Interior Doors & Fra
Level 6 - Installl Paint Grad
Level 6 - Interior Paint
Level 6 - Cabinets
Level 6 - Closet Shelving
Level 6 - Unit Flooring
Level 6- Countertops
Level 6- Unit Applian
Level 6 - Corridor Fl
Level 6 - MEPS Tri
Level 7 - MEPS Rough-In
Level 7 - Gypcrete
Level 7 - Insulation
Level 7 - Sheetrock Taped &
Level 7- Interior Doors & Fr
Level 7 - Install Paint Grad
Level 7 - Interior Paint
Level 7 - Cabinets
Level 7 - Closet Shelvin
MarApr a Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan erte 2nd Quart 3rd Quarte 4th Quarte 1st Quarte 2nd Quart 3rd Quarte 4th Quarte 1st Qua
Sansome & Broadway Family Housing
Cahill Contractors, Inc. Page 7 January 11, 2013
ID Task Name Duration Start Finish Predecessors
204 Level 7 - Unit Flooring 8 days Wed 8/13/14 Fri 8/22/14 188FS+3 days
205 Level 7- Countertops 4 days Mon 8/25/14 Thu 8/28/14 204
206 Level 7- Unit Appliances, Trim & Accessories 12 days Fri 8/29/14 Mon 9/15/14 205
207 Level 7 - Corridor Flooring 5 days Tue 9/16/14 Mon 9/22/14 206
208 Level 7 - MEPS Trim & Accessories 10 days Tue 9/16/14 Mon 9/29/14 206
209
210 Install Elevators - West Block 80 days Wed 4/16/14 Tue 8/5/14 65
211
212 Site - Roof Terrace - East Block 70 days Thu 7/31/14 Wed 11/5/14
213 Terrace Waterproofing & Flashing 20 days Thu 7/31/14 Wed 8/27/14 67
214 Topping Slabs & Pavers at Terrace 25 days Thu 8/21/14 Wed 9/24/14 213FS-5 days
215 Irrigation & Plantings 15 days Thu 9/25/14 Wed 10/15/14 214
216 Site Furnishings, Fencing, Railings & Gates 20 days Thu 10/9/14 Wed 11/5/14 215FS-5 days
217
218 Site - Central Courtyard 70 days Thu 7/24/14 Wed 10/29/14
219 Concrete Stair, Planter & Seat Walls 25 days Thu 7/24/14 Wed 8/27/14 67FS-5 days
220 Waterproofing at Courtyard 20 days Thu 8/14/14 Wed 9/10/14 219FS-10 days
221 Topping Slabs at Ext Walks & Courtyard 20 days Thu 9/4/14 Wed 10/1/14 220FS-5 days
222 Pedestal & Permeable Pavers 20 days Thu 9/18/14 Wed 10/15/14 221FS-10 days
223 Irrigation & Plantings 10 days Thu 10/9/14 Wed 10/22/14 222FS-5 days
224 Site Furnishings, Fencing, Railings & Gates 15 days Thu 10/9/14 Wed 10/29/14 223FS-10 days
225
226 Site - City Sidewalks, Streets 60 days Thu 7/31/14 Wed 10/22/14
227 Site Utilities - Tel Data / Gas 20 days Thu 7/31/14 Wed 8/27/14 67
228 Demo Sidewalk & Street 15 days Thu 8/28/14 Wed 9/17/14 227
229 New Sidewalk & Paving 25 days Thu 9/11/14 Wed 10/15/14 228FS-5 days
230 Ground Level Trees and Irrigations 10 days Thu 10/9/14 Wed 10/22/14 229FS-5 days
231
232 Inspections, Testing & Commissioning 62 days Wed 10/8/14 Thu 1/1/15
Level 7 - Unit Flooring
Level 7- Countertops
Level 7- Unit Applia
Level 7 - Corridor
Level 7 - MEPS Tr
Install Elevators - West
Site - Roof T
Terrace Waterproofin
Topping Slabs &
Irrigation & Pla
Site Furnishi
Site - Central
Concrete Stair, Plant
Waterproofing at C
Topping Slabs at
Pedestal & Per
Irrigation & Pla
Site Furnishin
Site - City Sid
Site Utilities - Tel Dat
Demo Sidewalk &
New Sidewalk
Ground Level
Inspections, Testing & Commissioning
MarApr a Jun Jul u e Oct o e Jan e MarApr a Jun Jul u e Oct o e Jan erte 2nd Quart 3rd Quarte 4th Quarte 1st Quarte 2nd Quart 3rd Quarte 4th Quarte 1st Qua
Sansome & Broadway Family Housing
Cahill Contractors, Inc. Page 8 January 11, 2013
ID Task Name Duration Start Finish Predecessors
233 Life Safety Testing, Commissioning 10 days Wed 10/8/14 Tue 10/21/14 208,112
234 DBI / MOD Inspections 10 days Thu 11/6/14 Wed 11/19/14 233,229,224,216
235 Rain Delays 10 days Thu 11/20/14 Wed 12/3/14 234
236 Temporary Certificate of Occupancy 1 day Thu 12/4/14 Thu 12/4/14 235
237 Punch List 40 days Fri 11/7/14 Thu 1/1/15 236FS-20 days
Life Safety Testing, Commissioning
DBI / MOD Inspections
Rain Delays
Temporary Certificate of Occupancy
Punch List