Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY...

147
Republic of Rwanda Ministry of Infrastructure Urgent Electricity Rehabilitation Project (UERP) ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR THE PROPOSED CONSTRUCTION OF A 20 MW DIESEL POWER PLANT & 1.2KM TRANSMISSION LINE March 2009. E1040 v3 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY...

Page 1: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

Republic of Rwanda Ministry of Infrastructure Urgent Electricity Rehabilitation Project (UERP)

ENVIRONMENTAL IMPACT ASSESSMENT

REPORT FOR THE PROPOSED CONSTRUCTION OF A 20 MW DIESEL

POWER PLANT & 1.2KM TRANSMISSION LINE

March 2009.

E1040 v3P

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

ed

Page 2: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

2

EXECUTIVE SUMMARY Introduction and Study Objectives The construction of a 20 MW power plant and a connecting 1.2km long transmission line is one of the key activities that the Urgent Electricity Rehabilitation Project (UERP) planned to accomplish with the funding from the World Bank/International Development Association (IDA) in order to curb the power crisis experienced in Rwanda. In compliance with the regulation and operational policies of the World Bank and the Government of Rwanda through UERP has prepared an Environmental Impact Assessment (EIA) and Environmental Management Plan (EMP) for this proposed 20 MW diesel power plant. The proposed site for locating the 20MW diesel power plant is about 1.2km away from the existing Jabana substation and is along the main Kigali-Byumba-Gatuna road hence has adequate access necessary during construction, is on a highly elevated area, and even though a soil investigation is yet to be undertaken, the preliminary observations according to the contractor show that the soil texture is of the hardy nature. This site is quite extensive in terms of size and provides room for any future planned expansion if required. Finally, the proposed site only has two houses/structures in the required site thereby making the resettlement process that will occur before the construction begins fairly easy and straight forward. These two households who are previous legal land owners had already sold the land and were already fully compensated by Home of Hope Rwanda, a faith based organization the current land owners. However, the owners of the households have not yet moved out of this land because Home of Hope Rwanda is planning to construct a church and an orphanage some time later and have left the occupiers to use the land until that time that they will be ready to commence construction. The UERP/PCU also intends to acquire more land close to the site for technical and security reasons and has already identified the 4 owners of these small pieces of land and began negotiations for compensation. The transmission component of the project will involve the installation of towers from the proposed plant to the Jabana substation. There will be compensation of PAPs for the small parcels of land that will be acquired and crops/trees that will be cleared in order to install the towers and establish the Right of Way (ROW). Right of Way is the space or path required internationally when installing electricity transmission lines to ensure safety. Along this ROW no physical infrastructure is accepted and vegetation must also be cleared. A separate Abbreviated Resettlement Action Plan (ARAP) for the diesel power plant has been prepared and submitted for approval to the World Bank and REMA. The ARAP has been approved by REMA and the World Bank and has been disclosed in the World Bank infoshop. However, an ARAP for the transmission component has not been finalized and is under preparation and once finalized will be submitted to the bank and REMA for approval. The EIA and ARAP for this project has already been approved by Rwanda Environment Management Authority (REMA). See annex J for the copy of the EIA approval letter from REMA. This project is classified under Category B according to the World Bank Operational Procedure and as such requires the development of an EMP as per the World Bank requirements. However, in accordance with the regulations by REMA projects of this nature require a full EIA including an EMP and in compliance with the

Page 3: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

3

REMA regulations, the safeguards advisor has prepared an EIA and EMP to ensure compliance with the Banks and country regulations.

Project Description The construction of the 20MW diesel power plant comprises of 2 components; the generation component to be funded through a World Bank loan and transmission component that will be funded by the Government of Rwanda. Component 1. 20 MW Diesel Power Plant The UERP through ELECTROGAZ and its implementing agencies including RURA and MININFRA plans to install a 20 MW diesel power plant along the Kigali Byumba-Gatuna road and about 1.2km from the existing Jabana substation in the city of Kigali in the District of Gasabo. The project will involve the identification of a suitable location for this project and after compensation; the land will be cleared before the construction of the plant together with other ancillary infrastructure occurs. Component 2. 110 Kv Transmission Line Thereafter, diesel generator sets that will be installed into the site will generate electricity that will be connected into the national grid through the installation of a 110 kV transmission line from the new plant to the existing national grid following interconnectivity to the Jabana substation. The transmission line will include the erection of electricity towers and cables to channel the generated electricity via a high voltage line to the substation for integration into the national grid. The space required for installing one tower is 225m2 and a total of 7 towers will be installed along the transmission route from the yet to be constructed power plant to the Jabana substation. The size of land necessary for actual installation of the plant will be approximately 120m by 140m in size. However, there are other utility facilities including an engine hall, control building and a fuel handling house that are needed in the installation of a power plant. Therefore, a total of 3.59 ha of land have been acquired for the plant. The land to be acquired for the transmission line is primarily for locating the pylon (towers) which normally require 225m2 and altogether the total land that will be acquired for this according to the survey is 0.11 ha. A detailed description of the activities expected to lead in the final installation of this facility is summarised below. Project Activities The project activities will fall under planning, construction, operation and decommissioning phases. The project specific activities will include the following; Planning and Design Phase Activities expected to occur during the planning and design phase of the project include;

• Identification of project site including feasibility studies, site survey, soil testing, site mapping among others.

• Acquisition of land for construction of the 20 MW power plant and its ancillary structures • Survey for a suitable path for installing the 110 kV transmission line from the proposed new diesel

power plant to the existing Jabana substation. • Acquisition of land to locate the 110 kV 1.2 km long transmission line from the new proposed plant

to the existing Jabana sub station. • Assessment, valuation and compensation of Project Affected Parties (PAPs) for loss of land,

structures and crops as the case may be.

Page 4: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

4

Construction Phase During the construction phase of the project the following activities will be undertaken namely;

• Site clearing for the construction of the diesel power plant including its ancillary facilities • Clearing of path and establishing Right of Way (ROW) for locating the 110 kV 1.2 km transmission

line • Excavation related works for construction of the diesel power plant • Construction of the diesel power plant and related ancillary facilities • Construction and installation of the transmission towers

The construction of the power plant and the 1.2 km transmission line shall also include related engineering works, earthworks, and service utility buildings including an engine hall, control building, fuel handling house and the installation of the transmission tower lines. Site Clearing and Stripping The construction work shall involve the clearing of areas required for permanent works. Stripping shall include cutting and removal of topsoil, levelling and all other related works to strip off the site. Excavation and Foundation Ground excavations for the diesel power plant and the transmission line will be done to the lengths and widths and exact depths as indicated on the drawings for the construction of the works. In cases where the bearing capacity of the subsoil under foundations or roads is insufficient, the excavation shall be continued to such greater depth as may be necessary. All excavation will be carried out mechanically, but the final shaping and trimming of the sub grade below foundations, etc. shall be done by hand. Backfilling Filling of areas and around foundations and backfilling of trenches shall be executed in such a way and to such extra depths as will ensure that final surfaces after settlement and compaction conforms to the specified levels. All fill material shall be well compacted by mechanical means until a high degree of compaction is obtained. The filling material shall be placed in even layers of a depth not greater than 0.4m and each layer shall be thoroughly compacted. Road and Drainages Access internal roads to the project site will be constructed by clearing and levelling the areas with suitable materials for road construction. The internal roads shall be minimum 7 m wide, or otherwise allow transport of the equipment, and turning of vehicles, within the area. The roads shall be connected to the existing roads upon completion. The road shall be designed for trucks with a weight of 60 tons and 10 tons per wheel. Provisions shall be made for adequate drainage of the roads covered drainage pipes, concrete conduits and trenches for electric cables etc shall be provided as needed for the design. Construction of Service Utility Buildings A number of utility buildings will be constructed and will serve as auxiliary infrastructure to support the generation of electricity in the power plant. They include; Construction of shelter for the diesel plant There will be construction for a shelter facility for the diesel plant that will be installed in the project site.

Page 5: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

5

Construction of building block for control purposes A control block housing unit will also be constructed in the project site for the purposes of controlling the operations of the diesel power plant. Construction of access road & and drainage system for water Access road to the project site will be constructed to provide entry to the plant during construction and operation. There is an existing gravel road that is narrow and leads to the site after the main tarmac road. This access road will be widened and rehabilitated to accommodate the huge trucks and other motorised machinery like excavators and tippers that will be used during construction and operation. Suitable sewerage works will also be constructed to provide for water and sanitation services. Installation of fuel storage tanks A series of 6 heavy and light fuel storage tanks will be installed in the project site and will be primarily used for storing the fuel that will be for operating/driving the diesel generators to produce electricity. Installation of generators, transformers & fuel lines When the construction is finalised, the generators will be installed including the transformers and piping of the fuel lines. A perimeter wall will also be built all around the project area for security reasons. The diesel power plant project will have an installed capacity of 20MW being generated by 3 diesel generators. The project will involve installing the generators and connecting to the main grid running on Heavy Fuel Oil (HFO). The equipments/generators to be installed at the project site will be sets of generators, with a rated out put of 7.5 MVA and a rated voltage of 6.6 kV, rated current of 656 A, rated frequency of 50 Hz with 0.8 lagging and a speed of 1000 rpm. The plant shall have 2 sets of power transformers of 15 MVA, 6.6/110 Kv three phase, 50 HZ, two winding oil immersed with on-load tap charger complete with accessories under natural-oil-circulation and natural-air cooled operation referred to the 110 kV side of the transformer. Construction of Transmission Line There will be construction of a 110Kv transmission line that will be 1.2km long which will connect the new 20MW plant to the Jabana substation. The transmission line will transmit the electricity generated by the plant to the Jabana substation that is 1.2km away which will then be stepped down and distributed to the households and other institutions targeted. The construction of the transmission line will entail surveying of the possible route for the line before land clearing to create a Right of Way (ROW). Transmission towers and electric cables will be erected and installed along the route from the proposed diesel plant to the existing Jabana substation which is 1.2km away. The ROW will be standard in terms of size according to the international standards for ROW which is 7m by 7m for horizontal and vertical land clearance. There will be land acquisition and destruction of crops and trees that will be along the transmission route selected. Already survey of the transmission line route has been done and a total of 0.11 ha of land will be acquired from 7 PAPs to create space for the ROW and the erection of the 7 towers. This 1.2km transmission line will not be funded under the bank loan but will be supported with funds from the Government of Rwanda. Still, in spite of the different funding institutions, this report includes an analysis of the potential adverse impacts of the transmission component from the new 20MW diesel plant to the

Page 6: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

6

existing substation. A separate Abbreviated Resettlement Action Plan (ARAP) is also being prepared for this component of the programme in accordance with the REMA regulations and requirements. The ARAP for the transmission component will be submitted to the bank and REMA for approval. Operation Phase During the operation phase of the project activities to occur are mainly controlling and operating of the diesel power plant, and subsequent generating of electricity. Activities related to operating the plant will include, loading and unloading fuel oil in the tanks, running the diesel engines, regular maintenance works among others.

Project Alternatives The study assessed potential project alternatives in terms of

• Project site alternative • Alternative project with capacity to achieve the same goal • Process or material alternatives: Materials and process alternative looked at fuel types available

depending on the particular environmental effects • Technology alternative looked at solar, wind and hydro and other sources of electricity • No project alternative

Positive Impacts The positive impacts of the project on socioeconomic development of the people in the area include additional electricity for the region, provision of conditions for rational and effective use of natural resources in the country, creation of new jobs for related services and direct workers, and acceleration of the investment process in the country. The project will also contribute in reducing pressure on biomass which comes from the scarce and fragile forest resources. Although the installation of this diesel power plant is more expensive and will increase the cost of electricity generation in a system which is hydro dominated, the increased cost of generating electricity is much less in comparison to the cost on the economy of load shedding in absence of this project.

Adverse Impacts Destruction of Vegetation and Crops The proposed site for the construction of the diesel power plant and transmission line is located in an area that is mainly under small scale mixed cropping mainly mangoes, sorghum, guavas, nappier grass among others for subsistence by the land dwellers. Specifically in the proposed site for constructing the diesel plant is a collection of eucalyptus trees that to a great extent form a thicket of approximately 0.5 ha in size. Other trees in the plot are bamboo, grevillea, jacaranda, and local tress species. Part of the trees in the site will have to be destroyed to pave way for construction work related activities. The transmission line or 1.2km path leading to the Jabana substation from the constructed diesel plant has a variety of tree species (eucalyptus, napier grass, bamboo, grevillea) and crops grown by the land owners for subsistence use (maize, beans, cassava) who will be compensated as per the RPF for the land acquired and crops/trees destroyed to clear way for the line and Right of Way (ROW) area. Land Acquisition The proposed project site for the construction of the plant in terms of land ownership belongs to Home of Hope Rwanda which is a faith based institution and has plans to use the parcel of land for the construction of a church and a children’s orphanage centre. Home of Hope Rwanda legally acquired this land from two

Page 7: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

7

local owners who in spite of full compensation have not yet moved away from this site. The reason being, Home of Hope do not as yet have immediate plans to commence the construction and have thus allowed the previous owners to continued cultivating the well as to reside in the land until that time when they will be informed to vacate the premise by Home of Hope Rwanda. Therefore, other than the crops and trees, two houses made of burnt clay bricks are still present in the site. These will end up being demolished during the construction of this plant and the families will have to re-settle elsewhere. The transmission line runs along a 1.2 km path that is owned by 7 land owners following surveying done to locate a route. The Right of Way (ROW) will be 7m by 7m in terms of vertical and horizontal clearance all the way along the transmission path. There will also be electricity towers that will be installed along the path and will be used to erect the electricity transmission cables. The size required for each transmission tower is 225m2 and a total of 0.11 ha of land will be acquired by the project to install the towers. The total consolidated land that will be acquired to create the ROW and area for the towers and the plant when combined together is 3.7ha. Air Emissions The project will potentially have adverse impacts on air quality during operation mainly from stack gases emitted. Emissions will be comprised of particulate matter (PM), Sulphur Dioxide (SO2) at 59.5g/hr, oxides of nitrogen (NOX), carbon monoxide (CO), the Green House Gases (GHGs) and Carbon Dioxide (CO2), trace amounts of various metals, and trace amounts of organic and inorganic compounds. The proportions and amounts of pollutants emitted will depend on the fuel quality and condition of combustion. Noise Pollution Noise pollution from the operation of the generators is inevitable during the night and day periods. The noise levels (sound pressure) of the generators inside the plant will 85 dBA. Even though noise modeling has not been undertaken, the generators for the plant will be fully installed with silencers and containerized which in effect will lead to insignificant noise impacts. The generators are designed to ensure that no more than 65 dBA of sound pressure is emitted within the plant boundary. Rwanda does not yet have noise emission standards for this reason World Bank standards were used in determining the potential noise impact. The project area in terms of land use is mainly a mix of agricultural, residential and commercial/industrial land use where according to World Bank standards, a maximum level of 45-55dBA is allowed for residential and institutions during the day and night and 70 is allowed for industrial area. There are 3 houses within a radius of 50 metres from the plant fence on the northern part of the project site, and 4 other households within a radius of 1 km from the plant boundary. These households combined have a total of 35 people residing in the dwellings. Section 3.1.1 provides a sketch map of the project site and related households including the nearby Nyabugogo wetland. Given the fact that the plant is designed to emit no more than 65 decibel within the boundary, the noise impacts will moderately impact on the residents in the 3 households within the 50 m radius. However, according to the engine design the plant will not emit more than 75dBA within a distance of 10 metres from the plant boundary. Therefore the residents that are within a distance of 50 metres from the plant boundary will not be impacted by the noise. At the commissioning of the project, the contractor is bound by the contract documents to undertake noise emission tests at a distance of 10 metres interval from the plant boundary up to 500metres to determine noise impact at full load capacity. This test will determine if indeed the specifications presented by the contractor is correct. If the noise level is found to be above the standards for residential/institution then these residents will have to be relocated.

Page 8: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

8

Fire Hazards Potential adverse impacts related to fire hazards remain a main feature of this project during the operation phase of this facility. The plant will deal with combustible products and the risk associated with fire occurrences form a significant adverse impact and risk on the human health and environment. Soil Erosion There is a likelihood of localized soil erosion during the civil works which entail compacting, earth excavations and moving works. However, these impacts will be largely localized to the project area and will only occur during the construction phase. Oil Spills The transferring of the Heavy Fuel Oil (HFO) and Automotive Diesel Oil (ADO) also known as ordinary diesel from the tankers and pumping for use to the generator sets could result in oil spills around the tank storage areas. This could lead to potential contamination of soil and for this reason; mitigation measures will be put in place to manage any accidental spills. Waste and Waste oil pollution Waste oil is also an output of the project that poses potential environmental hazard in case of poor handling and disposal methods. Poor disposal of waste oil filters also has a potential of adversely affecting the environment through soil contamination. Workers Health and Safety Adverse impacts on the workers health and safety is likely to occur especially through workers interaction with the equipments and machines during construction and operation of the plant. Accidents are likely to occur during construction and operations when the equipments are in use, and further to this if workers are exposed to the air emissions and incessant noise of the equipments could lead to potential harm on health of the workers. Traffic Congestion During the construction phase, heavy moving vehicles in and out of the project site are likely to increase traffic along the Kigali –Byumba-Gatuna –Uganda road and could cause congestion.

General Environmental Management Conditions and Measures The annex section F of this report contains generalized environmental management conditions that the contractor will be obligated to fulfill. These are general conditions providing an overall guidance and conditions to ensure environmental safeguards. However, specific mitigation measures are also highlighted and are included in summary below with the detailed mitigation measures found in the EMP section.

Specific Mitigation Measures Compensation for Land The land to be acquired for the construction of the power plant belongs to the Home of Hope Rwanda a faith based organization with plans to construct a church and an orphanage in the site. 4 other individuals also own some small portion of land that the UERP/PCU intends to acquire for technical and security reasons. Home of Hope Rwanda will have to be compensated for the land in accordance with the requirements set out in the Resettlement Policy Framework (RPF) document. A separate Abbreviated Resettlement Action Plan (ARAP) has been prepared and approved by the Bank. Compensation for Loss of Crops and structures The UERP/PCU will compensate for all the crops that will be destroyed to pave way for the construction at the time of construction of the power plant. This compensation will be calculated according to the

Page 9: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

9

Resettlement Framework Policy document. Compensation for the structures existing in the site will also be undertaken in full compliance with the RPF. Emissions Mitigation Measure(s)

• UERP will create a buffer zone using trees which will serve as natural filters and sinks for the gaseous emissions emanating from the power plant.

• Mitigation measures for emissions will include use of low sulphur fuel (0.5% sulphur content) that is

recommended and also the generators will be fitted with filters and silencers to reduce flue gas emissions and noise impacts. These conditions have been specified in the tender documents and suppliers of the diesel power plant will be expected to meet these requirements.

• Emissions will be controlled by limiting the sulphur content of the fuel by procuring fuel with low

sulphur content and ensuring that the diesel engines procured meet the international emission standards as recommended by the International Pollution Centre.

• Particulate emissions will be reduced through good combustion control to minimise the products of

incomplete combustion.

• Plant operators will be required to install and operate dedicated stack gas samplers or analyzers, and report both summary data and violations of standards or limits.

• Source testing will also routinely required to confirm continued compliance with emission limits.

Noise Abatement Measures

• All equipments and machinery installed must be tested to verify if they are compliant with the World Bank acceptable standards of noise as contained in the World Bank Pollution Prevention and Abatement Handbook (PPAH) 1998. The tested noise levels should be recorded as baseline and used for future monitoring.

• Each diesel engine shall be provided with one exhaust silencer and the design will provide the

required sound attenuation to meet the outside noise level requirements with minimum pressure loss. The silencer and the exhaust gas piping shall be provided with condensation drain traps at low points. Horizontal pipes shall incline downwards away from the engine.

• The contractor shall state the noise level of the radiator coolers in dB(A) in one meter distance at

full radiator load.

• Noise emitting equipment should comply with the applicable Rwanda and World Bank noise standards and should be properly maintained. The World Bank environmental regulations allow a maximum 70 dB noise level in industrial or commercial zones and between 45-55 dB for residential areas. The diesel engines have been designed to emit noise of 85dB inside of the plant and 60-65 at the plant boundary. This means that the plant will adhere to the World Bank maximum noise level requirements for plant boundary. In terms of maximum noise level for residential area, the project site is a mix of industrial/commercial and residential area. Within a radius of 1 km from the plant boundary there are 7 houses. However the closest structures are 3 residential houses within a distance of 50 metres from the plant boundary. According to the design of the plant, no more than 70 dBA can be emitted by the engines at a distance of 10metres from the plant boundary. This means that the residential structures standing at a distance of 50 metres will not be impacted

Page 10: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

10

by the noise. However as stated the contractors is required by the client to conduct noise test once the plant is commissioned within a radius of 500metres to verify if indeed the specifications of the engines are correct. This will be done and if the results indicate standards above the bank’s specification, the 3 residents will be compensated and relocated as required by the RPF.

• All workers in the project site must be equipped with the necessary and required Personal

Protective Equipment (PPE) prescribed by the Directorate of Occupation Health and Safety of the Ministry of Health but not limited to facilities to protect against noise impacts, ear muffs, safety helmets, hearing protection etc.

Soil Erosion Mitigation Measure(s)

• The final site grade should facilitate drainage and avoid flooding and pooling. A site drainage plan should be developed to protect against erosion through storm water. Protecting stockpiles through the use of silt fencing and reduced slope angles should be used to minimize soil erosion during construction and the storm water channeled into the drainage developed.

• Installation of drainage ditches, construction of runoff and retention ponds is necessary.

Minimization of disturbances and scarification of the surface should be observed to reduce erosion impacts.

• Borrow pit areas (if any) should avoid other non site areas; borrow areas should be reworked to

blend into the surroundings. Re-vegetation should be performed using local plants. All slopes and working surfaces should be returned to a stable condition.

Oil Spill Mitigation Measure(s)

• To prevent oil spills and environmental contamination, the power plant and pipelines should be designed with spill prevention and detection systems to protect the environment. With spill prevention and protection measures there should no adverse effects to the ground and surface water and soil.

• Storage and liquid impoundment areas for fuels, raw and in-process material solvents, wastes and

finished products should be designed with secondary containment (e.g. dikes) to prevent spills and the contamination of soil, ground and surface water.

• A written emergency response plan should be prepared and retained on the site and the workers

should be trained to follow specific procedures in the event of a spill.

• For the waste oil or used oil, the company contracted to supply the oil will collect this used oil for proper disposal. In the Environmental Management Plan (EMP), disposal of used oil will be the responsibility of the supplier. All waste oils and lubricants from maintenance of construction equipment should be segregated and disposed properly in accordance with the solid waste disposal plan.

• The proponent will identify a reputable company to handle disposal of oil filters. These filters will be

stored on site under lock before they are collected by the agent of the company for proper disposal. The contacting company should ensure that the filters are properly disposed and should apply the principle of cradle to grave.

Page 11: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

11

Dust Emission Mitigation Measure(s) • Fugitive emissions from roads and site work to be eliminated or minimized by applying water on a

need to need basis to dirt roads, unpaved surfaces and exposed construction areas during the dry season.

Flue Gas Mitigation Measure(s) To mitigate the effects of flue gas affecting the micro-climate of the area, the stack chimney of the generators have been designed to reach a height 30 metres. This will enable plume dispersal to be high preventing smoke and heat from affecting the surrounding area. A 30 metres high chimney for a diesel power plant is the recommended height by the International Pollution Centre for avoiding plume effect. The generator sets will be provided with embedded temperature detectors of at least six for stator winding and one for each bearing. A temperature recorder will be provided to indicate the temperature as measured by the embedded temperature detectors of generator windings and bearings. As a long term mitigation measure to reduce emissions, carbon offsets programs should be pursued by the proponent including plating of tress to act as carbon sinks, increasing efficiency and even purchasing emission credits. Workers Health and Safety Mitigation Measure(s)

• All workers entering the construction site must be equipped with PPE including ear muffs, factory boots, overalls, gloves, dust masks, among others. The PPE should be those that meet the international standards of PPE.

• Personal protection gear must be provided and its use made compulsory to all. The entire

workforce of the plant should be trained in the use of protective gear, handling of chemical products and acid storage cells, electric safety equipment, procedures for entering enclosed areas, fire protection and prevention, emergency response and care procedures. Training given to the employees should be backed by regular on- site training in safety measures.

• ‘Restricted ENTRY’ signs should be installed to keep away unqualified workers from access to

restricted areas.

• Machines and equipments must be operated only by qualified staff and a site supervisor should be on site at all times to ensure adherence.

• The contactor must develop a workers Health and Safety Manual for which all the workers should

be conversant with for response in case of accidents.

• The contractor and UERP should develop an Emergency Response Plan for handling any emergencies arising thereof during the construction.

Fire Suppression Measure(s) The construction site must contain fire fighting equipments of recommended standards and in key strategic points all over the site. Fire pumps, hydrants, sprinkler/water spray systems, hose houses, dry chemical systems, carbon dioxide systems, detection/alarm systems and portable fire extinguishers are all specified in the tender documents as necessary in the plant. All these fire suppression equipments are required in a power plant and must all be present at key strategic points. The contractor is expected to provide all these equipment for fire suppression as stipulated in the tender documents.

Page 12: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

12

A fire evacuation plan should be developed by UERP/ELECTROGAZ and must be posted in various points of the construction site including procedures to follow when a fire is reported. All workers must be trained on fire management and fire drills undertaken regularly. Solid waste pollution and littering

• The Contractor and UERP should develop a solid waste disposal plan which includes the provision of receptacles at strategic points within the construction site, recycling programmes for recyclable wastes, separation of wastes.

• The contractor and UERP should engage a refuse handling company to remove the wastes from

the site to the recommended waste management site.

• Warning signs against littering and dumping in wrong places within the construction site should be erected by the contactor.

Accidents at the work place from operating of machineries and equipment by workers

• Personal protection gear will be provided and its use made compulsory to all. The entire workforce of the plant should be trained in the use of protective gear, handling of chemical products and acid storage cells, electric safety equipment, procedures for entering enclosed areas, fire protection and prevention, emergency response and care procedures.

• Training given to the employees should be backed by regular on- site training in safety measures

• Restricted ENTRY signs should be installed to keep away unqualified workers from access to

restricted areas.

• UERP should construct a perimeter fence all around the project site to keep of and restrict unauthorised persons from the site. This will reduce accidents that can be caused by unauthorised entry or encroachment.

• Machines and equipments must be operated only by qualified staff and a site supervisor should be

on site at all times to ensure adherence.

• The contactor must develop a workers Health and Safety Manual for which all the workers should be conversant with for response in case of accidents.

• The contractor should develop an Emergency Response Plan for handling any emergencies arising

thereof during the operation.

Monitoring Plan The EMP proposes parameters to be monitored during preparation, operation and decommissioning of the plant. Noise levels should be monitored from different sensitive receptors. Soils within and without the area should also be monitored for oil spills. Storm water from the site should also be monitored of oil traces to prevent surface and groundwater contamination. Emissions from the plant also should be monitored. Parameters to be monitored should include Volatile Organic Compounds (VOC), Particulate Matter (PM), SO2 and NO2.

Page 13: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

13

Conclusion and Recommendations On the basis of the EIA/EMP study of the diesel power plant, the following conclusions have been drawn by the UERP/PCU Safeguards Advisor:

• The project in the short term is environmentally feasible with the implementation of the mitigation measures prescribed in the EMP. The benefit of the project outweighs the costs of the project and being an emergency stop gap measure to save the country from long term outages, the environmental implications can be mitigated against the costs of the project on environment.

• The contractor’s tender documents have elaborately spelt out the mitigation requirements against environmental degradation during construction and installation and thus serve as a good basis for developing the EMP.

Recommendations • An Environmental Audit (EA) should be conducted annually to review compliance to the proposed

Environmental Management Plan. According the EIA regulations of REMA, an annual environmental audit must be conducted at the end of every year once the diesel plant begins operating. The audit will be conducted by registered REMA consultants or the environmental safeguards advisor as required by the Organic Law on environmental protection.

• The goal of this EA is to establish and ascertain the extent to which the project achieved

compliance with the environmental mitigation measures and requirements that were specified in the approved EIA report and make recommendations for correcting any problematic or non-compliant activities.

• It is expected as required by the REMA EIA regulations that the cost of the environmental audit will

be paid for by the client in this case ELECTROGAZ who will engage competent registered consultants.

REMA Approval This EIA report has been submitted to Rwanda Environment Management Authority for approval and required approval and go ahead to proceed with the project with conditions have been accorded by REMA upon review of the report. These conditions for approval are included in the annex J section of this report.

Page 14: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

14

CONTENTS EXECUTIVE SUMMARY..................................................................................................................2

Introduction and Study Objectives........................................................................................................................... 2 Project Description...................................................................................................................................................... 3 Project Alternatives ..................................................................................................................................................... 6 Positive Impacts ............................................................................................................................................................ 6 Adverse Impacts ........................................................................................................................................................... 6 General Environmental Management Conditions and Measures ....................................................................... 8 Specific Mitigation Measures ...................................................................................................................................... 8 Monitoring Plan...........................................................................................................................................................12 Conclusion and Recommendations ........................................................................................................................13

Recommendations..................................................................................................................13 INTRODUCTION ...........................................................................................................................16 STUDY SCOPE AND .....................................................................................................................18 METHODOLOGY ...........................................................................................................................18

2.1 Study Scope...........................................................................................................................................................18 2.2 Methodology.........................................................................................................................................................18

Baseline Assessment ..............................................................................................................18 Project Alternatives ...............................................................................................................18 Public Consultation ................................................................................................................18 Impact Prediction and Evaluation ........................................................................................19

PROJECT AREA DESCRIPTION AND BASELINE DATA........................................................20 Geographical Location ........................................................................................................................................20 Administrative Divisions ....................................................................................................................................20 Population.................................................................................................................................................................20 Family Composition and Size ..........................................................................................................................21 Education Level ......................................................................................................................................................21 Land use by type ....................................................................................................................................................21 Access to piped water .........................................................................................................................................22 Households with access to power..................................................................................................................22 Specific Site Description ....................................................................................................................................23 3.1 Physical Environment ..........................................................................................................................................23

3.1.1 Location..........................................................................................................................23 3.2 Biological Environment.......................................................................................................................................24

3.2.1 Physical ...........................................................................................................................24 3.2.2 Flora ................................................................................................................................24 3.2.3 Fauna...............................................................................................................................24 3.2.4 Sensitive Ecosystem ......................................................................................................24

3.3 Socio-Economic Environment...........................................................................................................................24 3.3.1 Population and Demography .......................................................................................24 3.3.2 Socio Economic Profile .................................................................................................25 3.3.3 Land Uses .......................................................................................................................26 3.3.4 Infrastructure.................................................................................................................26

PROJECT ALTERNATIVES...........................................................................................................27 4.1 Alternative Fuel....................................................................................................................................................27 4.2 Alternative Site.....................................................................................................................................................29 4.3 Alternative Generation Technologies for Rwanda.......................................................................................30 4.4 Alternative Processes and Materials................................................................................................................32 4.5 Combined Cycle Project....................................................................................................................................33 4.6 No Project Alternatives .....................................................................................................................................34

Page 15: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

15

LEGISLATIVE, POLICY AND INSTITUTIONAL FRAMEWORK............................................35 5.1 Organic Law on Environment Protection and Management ......................................................................35 5.2 Energy Policy.........................................................................................................................................................37

Short and medium term policy priority actions ..........................................................................39 5.3 Land Policy ............................................................................................................................................................40 5.4 Relevant Policies ..................................................................................................................................................43 5.4.1 International Legislations ................................................................................................................................43

5.4.2. World Bank Environment and Social Safeguards Policy .........................................43 5.4.3 Climate Change Convention........................................................................................44

PROJECT DESCRIPTION..............................................................................................................45 6.1 Project Technology Description ......................................................................................................................48 6.2 Plant Design ..........................................................................................................................................................49 6.4 Project Outputs ...................................................................................................................................................52 6.5 Project Operations and Management..............................................................................................................53

POWER PLANT – ADVERSE ENVIRONMENTAL IMPACTS..................................................54 7.1 Positive Impacts ...................................................................................................................................................54

7.1.1 Socio-economic Benefits ..............................................................................................54 7.1.2 Environmental Benefits ................................................................................................54

7.2 Adverse Impacts ..................................................................................................................................................55 7.2.1 Impacts on Physical Environment –Construction Phase ..........................................................................55 7.2.2 Adverse Impacts –Operation Phase .............................................................................................................60 7.2.3 Project Decommissioning...............................................................................................................................69

PUBLIC DISCLOSURE AND CONSULTATION PROCEDURE..............................................71 8.1 List of people met................................................................................................................................................71

ENVIRONMENTAL MANAGEMENT PLAN FOR 20 MW DIESEL POWER PLANT ...........74 Development of internal tracking/monitoring system.......................................................76 Responsibility of Institutions in Implementing the EMP ....................................................76 Role of Rwanda Environment Management Authority (REMA): ......................................76 Role of the Contractor...........................................................................................................77 Role of the Safeguards Advisor/UERP..................................................................................77 Kigali Fire Brigade ..................................................................................................................77 World Bank .............................................................................................................................78 Role of ELECTROGAZ ..........................................................................................................78

9.2 Monitoring Plan..................................................................................................................................................102 9.2.1 Responsibilities and Costs for Environmental Mitigation Measures......................103

CONCLUSION AND RECOMMENDATIONS..........................................................................110 10.1 Recommendations...........................................................................................................................................110

REFERENCE...................................................................................................................................111 ANNEX...........................................................................................................................................112

ANNEX A. MINUTES OF THE MEETING RELATING TO THE JABANA PLOT WHERE ELECTROGAZ PLAN TO INSTALL THE 20 MW DIESEL POWER PLANT. ...........................................112 ANNEX B. AMBIENT AIR QUALITY .................................................................................................................114 ANNEX C. EQUIPMENT TECHNICAL SPECIFICATIONS ..........................................................................117 ANNEX D. EMERGENCY RESPONSE PLAN FOR PROPOSED PLANT...................................................120 ANNEX E. INCIDENT REPORTING SYSTEM AND INVESTIGATION PROCEDURE.........................131 ANNEX F. GENERAL ENVIRONMENTAL MANAGEMENT CONDITIONS..........................................134 ANNEX G. Example Format: EHS Report ........................................................................................................141 ANNEX H. Example Format: EHS Incident Notification................................................................................142 ANNEX I. Site Layout Map and Location Map...................................................................................................144

Page 16: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

16

INTRODUCTION Energy is crucial to Rwanda’s economic growth. In Rwanda, electricity is the second most important source of commercial energy for the formal sector after petroleum fuels. Commercial and industrial establishments as well as institutions and households in the country use electricity. Rwanda remains among the lowest per capita electricity and petroleum products consumption countries in the world. Only about 65,000 (6-8percent) of households have access to grid supplied power, almost entirely in the main urban areas. Diesel remains the primary fuel for self-generation in rural areas, and also fro back up in urban areas during the current crisis, and kerosene for lighting for the vast majority. Grid extension has been extremely limited, and economically justified only to meet rural industrial loads and emerging population clusters. Rwanda’s post conflict genocide economic recovery is under threat from severe power supply shortages. A combination of strong demand growth with unexpectedly low water levels in its hydro power sourced lakes further exacerbated by high technical losses and unreliability of ELECTROGAZ dilapidated network, have led to extensive and lengthy power cuts. Despite re-commissioning of an old diesel power plant, load shedding has increased to about 25% of peak demand with serious adverse consequences. Supply shortages have raised the cost of doing business, in particular for short export enterprises, and weakened the prospect of attracting new investments. Power supply shortages have also worsened water supply problems in the main urban areas, leaving ELECTROGAZ to switch to diesel water pumping and adding to its financial woes. Rwanda already imports 60% of its electricity needs, mostly from SNEL and Sinelac plants in the Democratic Republic of Congo, and there is a little scope to increase this further. In the near term before any new hydro or gas based power can be brought on line, Rwanda will have to increasingly rely on higher costs diesel power (about 150USc/kWh compared to 2003 average bulk supply cost of around 5USc/kwh). Urbanization and industrial growth, combined with limited access to electricity and high cost of petroleum products have led to an even more rapid growth in urban charcoal demand. Severe deforestation during conflict, in part by internally displaced persons and returning refugees has been further compounded by the large scale demands for charcoal making, construction materials, and agro industrial, institutional and commercial customers. By the end of 2004 Rwanda has faced year energy crisis that has never happened before. The Government Rwanda of (GoR) through ELECTROGAZ has managed to mitigate the crisis by putting in place diesel power plants with additional capacity of about 12.5 MWS. The effort to get rid of the deficit has continued. As part of the strategy of the Government of Rwanda to arrest the energy crisis in the country, the GoR has asked the World Bank for support of its Urgent Electricity Rehabilitation Project (UERP). The overall development objectives of the proposed project are to: (i) Alleviate the power shortages: and (ii) enhance the capabilities of energy sector institutions. The UERP project is intended to further mitigate the power crisis in Rwanda and to help to restore good utility practice at the heart of its facilities. The project is being coordinated by the Project Coordination Unit (PCU) housed in ELECTROGAZ and which works under the overall responsibility of a Steering Committee chaired by the Ministry of Infrastructure (MININFRA).

Page 17: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

17

The diesel power project expected to produce 20 MW is one of the proposed projects under the World Bank funding expected to contribute to the alleviation of power shortages in Rwanda.

Page 18: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

18

STUDY SCOPE AND METHODOLOGY The scope of the study was determined by the influence of the potential impacts and stakeholders input. The terms of reference also helped in shaping the scope as well as the methodology to be applied in assessing the impacts. The study was undertaken in Jabana area and its environs. The area falls within the Cyerere Cell, Kabuye Sector of Gasabo District, Kigali City in the Republic of Rwanda.

2.1 Study Scope A rapid scoping study was undertaken at the beginning of the study. This exercise helped the EIA to define the spatial and contextual scope of the study. The scoping process helped the EIA identify the issues that were likely to be of priority importance during the study and eliminates those that were of little concern. The rapid scoping exercise also enabled the consultants identify the stakeholders and public concerns. Scoping exercise also helped in introducing the project to stakeholders and involving them in determining the scope and focus of the EIA study.

2.2 Methodology Baseline Assessment Baseline data was collected from secondary data and primary data. Data collected included information on physical environment, soils; biological environment: flora; fauna; including significant natural sites etc.; socio-cultural environment: population, land use. Project Alternatives The EA analysed the various project alternatives available to achieve this project’s objectives but with the least adverse environmental impacts. The alternatives were identified and evaluated determining impacts and cost implications of each alternative. Alternatives assessed during this process included; Alternative sources of energy including renewable energy sources other than generators; site alternatives in project location particularly with regards to location based impacts and land use conflicts was assessed; process alternatives including evaluation of the alternatives in process open to the project with an objective of minimising raw material use, waste generation and energy requirements; technology alternatives examining any alternatives in technology to generate electricity open to the project and alternatives in equipment and facilities so as to determine best affordable options and finally; a No Project alternative was also assessed to determine the impact of this No Project Scenario. Public Consultation During the scoping process, a stakeholder mapping exercises was undertaken to identify Interested and Affected Parties (I&AP) to the project. The mapping exercise was conducted simultaneously with the scoping exercise. The exercise identified all the stakeholders in the area. After identifying the relevant stakeholders, a gleaning exercise was undertaken to do away with those who would not be impacted both positively and adversely.

Page 19: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

19

The stakeholders’ consultation also helped in highlighting the serious socio-economic and environmental concerns and impacts that could arise from the project and was instrumental in helping to come up with feasible mitigation measures. During the stakeholder consultation process issues raised were noted and responses provided as appropriate as possible. Impact Prediction and Evaluation Various methods and techniques were applied in impact identification, prediction and evaluation. The EA identified and analysed potential impacts linking these with specific project activities and phase.

Page 20: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

20

PROJECT AREA DESCRIPTION AND BASELINE DATA This chapter gives a general background and information of the project area as a whole then narrows down to project specific site in terms of its location, administrative set-up, climate, settlement patterns, and the major environment attributes, which will play a crucial role in the identification and development of the project. Geographical Location Kigali City, the capital of Rwanda, is situated almost in the centre of the country. Its geographical position is on Latitude 1º 57’S and on longitude 30º 04’ E. Kigali city is situated in the natural region called Bwanacyambwe within the proximity of the Nyabugogo river basin, between Mount Kigali (1852 m high) and Mount Jali. The city is built on interlocking hills, which progressively converge and are separated from each other by large valleys giving them oval shapes. Originally the city occupied the hills of Nyarugenge and Nyamirambo which covered an area of about 200 hectares at the time of independence. The city stretches from the centre to include the following:

• Towards the east, the hills if Kacyiru, Kimihurura, Mburabuturo, Nyarutarama, Remera and Kanombe.

• Towards the south over the slope of mount Nyarutarama. • Towards the west over the slope of mount Kigali, on slopes of Kabusunzu hills, Kimisagara and

Butamwa and towards the north over the slopes of mount Jali and hills of Gisozi, Gaculiro, Kagugu and Kibagabaga.

Administrative Divisions The actual urban provincial boundaries of Kigali as defined by the decree No. 896/90 of 1990 was composed of three communes (districts) namely: Nyarugenge, Kicukiro, and Kacyiru. These communes comprised of a total of 20 sectors and 91 cellules. Today the city is made up of 8 districts (communes), namely: Nyarugenge, Kacyiru, Nyamirambo, Kicukiro, Gikondo, Kanombe, Gisozi and Butamwa. Population The population of Kigali city has been growing over the last two decades, but a new growth trend developed after the 1994 war and genocide, when there was a dramatic rise in the population caused by the return of Rwandans from various parts of the World. Most of the returning Rwandans tended to go to the capital where there was considerable security. The population growth of Kigali City was estimated by different surveys carried out through out the country as follows: In 1960, the population was 6,000 peoples growing to 235,664 in 1991 and more than doubled between 1991 and 2000 reaching a figure of 604,966 people. It is further observed that in 2000, women constituted about 52 percent of the city’s population and that about 56 percent of the entire City’s population was age below 20 years. They gives a dependence ratio of 1.4:1 i.e. the population which is below 20 and above 60 compared to that between 20 and 60 years of age (one economically active person support about one and half persons who are non economically actives).

Page 21: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

21

The actual city population’s annual growth is estimated to be 10%. The population growth in the city will continue at this high rate because of the rural to urban migration tendency. It is estimated in the Kigali City Master plan 2020 that only 43 percent of the city population were originally natives of the city, while 56.8% had migrated from other areas as shown by the figure below. The 56.8% migrants to CoK were composed of 14.6% who were born in other countries, 13.1% from Gitarama prefecture, 6.8% from Butare, 5.8% Kigali rural and 16.6% from other prefectures. Family Composition and Size Kigali City is estimated to have 131,106 households and a total population of 604,966 inhabitants. The average size of household is therefore 5 persons. It is estimated that 51% of heads of household are male while 44% are women and 5% are children. Education Level The socio-economic survey of August 2000 shows that 10% of Kigali City’s population aged 7 years and above has never had any formal education, 54% have primary education and 5% have post-secondary education. The level of education is extremely low and therefore the majority of urban dwellers lack the knowledge and skills to work productively in an urban environment. Most of the people lack capacity to utilise available and useful information to reduce the poverty that is permeating their lives. Land use by type The total planned area is about 47.21%, covering only 1666 hectares and non-planned area is about 52, 69%, which covers 1859, 3 hectares. The new urban area of Kigali City is around 349 km2, consisting of original area of 112 km2, which was defined by decree-law no 11/97 of 20/04/1979, and modified by the presidential order no 896/90 of 27/11/1990 to include additional area of about 237 km2.

Page 22: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

22

Land use Area (ha)

Forests 7241.5 Cemeteries 135.4 Landfill 24.6 Airport coverage/area 10290 Military zones 838.68 Religious centers 72.6 Health facilities 37.6 Education facilities 249.4 Green space 163.7 Swampy area 5506.2 Developed area 13 National police zone 47 Telecommunications 98.5 Administrative area 307.5 Commercial area 129.3 Industrial area 280.8 Residential area 4777.4 Sports centres 32.9 Area of Kigali City 4653.92 Total 34900

Access to piped water It is noted that out of 131,106 households in Kigali, 43% of the households (52,682) have access to pipe water, either found indoors or within the plot. 40% of the households (48,444) get their water from public stand pipes. The remaining 17% fetch water either from the ponds, wells, or lakes around their dwelling areas. Households with access to power

Cooking Lighting

District Population Firewood Charcoal Electricity Kerosene Electricity

Gisozi 22,446 37 63 67 33

Kanombe 12,130 53 47 53 47

Gikondo 17,854 23 77 30 70

Nyamirambo 12,540 17 80 3 13 87

Butamwa 10,091 95 5 95 5

Nyarugenge 23,959 5 92 3 23 77

Kicukiro 10,196 46 54 48 52

Kacyiru 18,890 17 77 6 27 73

Kigali Economic Development Strategy

Page 23: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

23

Specific Site Description The proposed site for the 20 MW power plant is located in the City of Kigali about 1.2 km from the already existing Jabana sub station. The site is located along Kigali-Byumba road which divides the area into industrial and residential zones to the east and north respectively. On the Administrative plan, the site is located in Gisozi District, Kabuye Sector in Cyerere Cell.

3.1 Physical Environment This section of the study provides a general description of the Kigali city including climate, flora and fauna as well as the physical environment.

3.1.1 Location The proposed project is located along the main Kigali Byumba-Gatuna road in the city of Kigali of Gasabo District.

Page 24: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

24

3.2 Biological Environment 3.2.1 Physical The project site is located approximately 300m from the main tarmac road and slopes upwards to the north. The soil from visual inspection is the hard type; however a detailed soil investigation is underway to determine key soil characteristics. The area has a cluster of eucalyptus trees of approximately 0.5 hectares in size that can be termed as plantation of trees. The rest of the land has been transformed entirely into agricultural production through the cultivation of bananas, beans and napier grass.

3.2.2 Flora The plants that are observed in the project site include food crops like mangoes, guavas, sorghum, banana tress, napier grass, and fruit trees like avocado among others. There are no natural floral species of plants in the project area other than exotic eucalyptus thicket that has been grown in some parts of the project site. Other tress in the site includes grevillea, jacaranda, bamboo and some indigenous tree species.

Photo of trees and crops present in the project site (nappier grass, bananas, eucalyptus and grevillea).

3.2.3 Fauna There are no animal species of importance within and around the site that would require specific mentioning.

3.2.4 Sensitive Ecosystem The Gikondo-Nyabugogo wetland traverses very close to the project site and can be sited approximately 2 kms from the project site. “The Gikondo and Nyabugogo wetland system forms part of inter-connected water networks that belong to the Nyabugogo - Akagera Basin. Therefore, the wetland system serves as a vital source of domestic water supply for the majority of homesteads. The Nyabugogo wetland is an important resource and other than being part of the wider Akagera Basin, it is a vital source of water, habitat for water fowls, and bird life and provides buffering capacity, source of natural papyrus, used for extensive cultivation of rice among other ecological services.

3.3 Socio-Economic Environment 3.3.1 Population and Demography The site identified for the construction of the power station is situated on the road paved Kigali-Byumba-Gatuna and is about 1.2 kms from the existing Jabana substation. The population around the proposed

Page 25: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

25

project area is minimal and mainly constitute of the members of the staff of the Cooperative of the Rice Growers of Kabuye (CORIKA), staff of a nearby sugar manufacturing factory of Kabuye, and the staff of the existing substation at Jabana. About 1.2 km before the proposed project site, and adjacent to the existing Jabana substation, there is an oil storage depot owned by Total, a health centre is nearby and a Catholic Church parish. Also a primary and technical secondary school can be observed around the project area.

Photo of house in the project site; this house will be demolished to pave way for the construction

3.3.2 Socio Economic Profile The general project area is an agricultural, agro based and industrial centre combined together. One can observe that the on going industrial activities and ventures in the project area mainly agro based in nature including the existing sugar factory of Kabuye which is about 1km from the project site. There is a rice milling factory owned by CORIKA. Agriculture mainly rice growing is carried out in the nearby Nyabugogo River by the local population and organized groups like the CORIKA. Subsistence agriculture, mainly growing of food crops like cassava, beans, maize, yams and others is also practiced by the local population. The existing Jabana substation, the Kabuye Sugar Factory, the fuel station and the oil depot are all indicative of the type of economic activities that can be profiled in the area. These activities are however approximately 1.2 kms from the proposed project site. In the immediate surrounding of the project site, the dominant activity is mainly subsistence agriculture.

Photo of the existing Jabana substation about 1.2kms from the proposed site for the 20MW plant A number of restaurants and bars are also observed at about 1km from the project area and mainly provide food and drinks to the workers in the mentioned enterprises as well as truck drivers who come to the fuel

Page 26: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

26

depot to stock and load oil. There is also a bank that serves the local industrial activities in terms of offering financial services.

3.3.3 Land Uses The major land uses around the proposed project area are industrial (agro-industry,) agriculture (large and small scale), residential and commercial. Although the area is zoned as industrial there is a mix of different land uses. Immediate surrounding (within a radius of 1 KM) of the proposed project site has residential and subsistence farming as the dominant land uses. A total of 7houses are visible around the project site within the plant boundary and on going cultivation of food crops demonstrates practise of small scale subsistence agriculture. At about 1.2km from the proposed site, a school, fuel station, oil depot, a sugar factory and a few scattered residential houses can be observed. Other neighbouring land uses include residential, social and industrial.

Photo of Existing oil depot about 1.2 km from proposed new site.

3.3.4 Infrastructure Roads, Electricity and Communication The area project area is along the bitumen paved Kigali-Byumba-Gatuna road. Electricity lines traverse the project area along the main highway and connect to the existing Jabana substation.

Photo of trucks parking along the Kigali-Byumba road.

Page 27: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

27

PROJECT ALTERNATIVES This chapter describe and examine the various alternatives available for the project. Alternatives examined during the study included alternative sources of energy including renewable energy sources other than generators, site alternatives in project location particularly with regards to location based impacts and land use conflicts was assessed, process alternatives including evaluation of the alternatives in process open to the project with an objective of minimising raw material use, waste generation and energy requirements, Technology alternatives examining any alternatives in technology to generate electricity open to the project and alternatives in equipment and facilities so as to determine best affordable options and finally a No Project alternative was also assessed to determine the impact of this No Project Scenario. Preferred Alternative-20MW Diesel Power Plant Rwanda’s post-genocide economic recovery is under threat from severe power supply shortages. A combination of strong demand growth with unexpectedly low water levels in its hydro power sourced lakes, further exacerbated by high technical losses and unreliability of ELECTROGAZ’s dilapidated network, have led to extensive and lengthy power cuts. Rwanda is currently facing a deficit in energy of 50 MW. In order to overcome this deficit, the Government of Rwanda is planning to curb this deficit by setting up 20MW diesel power plant which will then be connected to the national grid. The Government of Rwanda as part of its strategy to deal with this crisis has adopted an emergency action plan (6-12 months) to normalize the power supply situation in the country. In addition to the expedited procurement of 20MW of diesel generation capacity noted above, GoR has granted a temporary reduction of some duties and taxes on ELECTROGAZ diesel purchases. Despite re-commissioning of an old diesel plant, load shedding has increased to about 25% of peak demand, with serious adverse consequences. Supply shortages have raised the cost of doing business, in particular for short export enterprises, and weakened the prospects of attracting new investments. Power supply shortages have also worsened water supply problems in the main urban areas, leaving ELECTROGAZ to switch to diesel water pumping and adding to its financial woes. The purpose of this project is thus to inject 20MW of electricity to the grid-using diesel generators running on Heavy Fuel Oil (HFO) as an urgent short term solution and mitigation measure. The construction is planned to commence in the month of October 2007. The decision to embark on the installation of an emergency diesel power generating plant to address the acute energy crisis in the country was made by the GoR as the only quick intervention to the energy crisis leading to the seeking of a loan from IDA. Definitely before IDA provided the loan to the GoR they must have considered other options and overall project objective especially the currently crisis. So to a great extent, the decision to install a diesel power plant was made by the GoR with the approval or consent from the World Bank.

4.1 Alternative Fuel The preferred fuels for operating this diesel engines is Heavy Fuel Oil (HFO) and ordinary diesel oil also known as Low Fuel Oil (LFO). Low Fuel Oil will be used in small quantities to start the engines before switching to HFO which will be used extensively for running the engines and generating the electricity.

Page 28: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

28

There are other different types of fuel available in the market that can be used for generating electricity depending on the engine. These fuels have environmental and economic advantages and disadvantages and can be used to run the diesel engines. Environmental advantages include low pollutant levels and combustion efficiency while economic advantages include cost effectiveness. The alternative fuels that can be used to run the diesel plant other than the HFO include; Low Fuel Oil (LFO), Industrial Diesel Oil (IDO); and methane gas. The diesel power plant will use Heavy Fuel Oil (HFO) for running the generators. This is because HFO is cheap and is not required in large quantities and volumes to run the generators unlike LFO which is expensive and will be needed in great amounts. HFO is more viscous that it has to be heated, which requires a special heating system, before use and it contains relatively high amounts of sulphur, which forms sulphur dioxide upon combustion. However, its undesirable properties make it very cheap. In fact, it is the cheapest liquid fuel available. HFO has less energy per litre than lighter fuels like ordinary diesel. The plant will require about 400 litres of HFO daily when operating at 60-100% load capacity. Ordinary Diesel Oil The other fuels that can be used to run the generators as mentioned above include ordinary diesel oil and industrial diesel oil. These are generally light and less viscous oil that do not require prior heating to make them less viscous and light. They do not also contain as much sulphur content as the HFO. One of the most important characteristics of diesel oil is its low-temperature behaviour. Sulphur content in ordinary diesel oil produced today contains at most 50, in respect 10 mg/kg. However, they are very expensive and will be required in such large quantities that it will be unsustainable economically to run the generators on this fuel type. It is for this reason that the use of ordinary diesel oil to run the plant at 100% load was not considered. Instead ordinary diesel will be used only when starting and shutting down the plant. The sulfur content of HFO and diesel fuels commercially used in Rwanda is provided in the table below. Test Test methods Units Value

Viscosity at 50°C ASTMD 445 mm2/s 180 Pour point ASTM D 97 °C Max 24 Density 20°C ASTM D 1298 Kg/m3 Max 985 Flash Point PMCC ASTM D 93 °C Min 66 Net Calorific Value ASTM D 2382 MJ/kg Min 41.1 Water content ASTM D 95 % Volume Max 0.75 Sediment ASTM D 473 % mass Max 0.15 Ash content ASTM D 482 % mass Max 0.08 Conradson carbon Residue ASTM D189 % mass Max 12 Asphaltenes IP 143 % mass Max 10 Surphur content ASTM D 4294 % mass Max 3% Strong Acid N0 ASTM 974 Nil 139 Alminum + silicon content ASTM D 5184 PPM Max 80 Source; Ministry of Energy-MININFRA

Lot 2 DIESEL SPECIFICATION TEST LIMITS TEST METHOD ASTM D Density at 20 0c kg/m3 820-875 4052

Page 29: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

29

Flash PMCC 0c min 66 93 Sulphur % max 1 4294 Cloud point 0c max 12 2500 CFPP 0c max 6 305 Water % max 0,05 95 Distillation at 365 0c % min 90 FBP 0c max 400 Viscosity at 40 0c Cs 2.2 - 5.5 445 Colour max 3,5 1500 Copper corrosion max 1 130 Sediment % max 0,01 473 Strong Acid No. mgKOH/g max NIL 974 Total Acid No.mgKOH/g max 0,5 974 Source; Ministry of Energy-MININFRA Methane Gas UERP and ELECTROGAZ intend some time in future to convert the 20 MW diesel power plant to use methane gas instead of HFO. The existing equipment that will be procured can also run on methane gas subject to certain modifications. This is a long term plan and is dependent on the quantities of methane gas produced in Lake Kivu. Extraction of methane gas in Lake Kivu is still at the exploratory stage and therefore cannot solve the urgent energy crisis. However methane gas is highly considered as a clean energy and the conversion of the plant from diesel to methane will greatly contribute to clean energy options. According to the tender documents, the contractor is expected to supply a diesel engine that can operate on diesel oil and later convert to methane gas. In conclusion therefore, HFO was chosen as the fuel type of choice owing to its affordability even though not necessarily the best or most environmentally sound. The construction of the diesel run power plant is though an IDA loan, where funds have already been committed and there is very little or no opportunity to provide for more funding for using a different type of fuel that can be much cleaner. Ordinary diesel oil will be used but in very small quantity in starting and shutting down the plant.

4.2 Alternative Site(s) Assessment of the proposed site and comparing with other alternative site was considered in this study. In the assessment, land use and environmental impacts and technical feasibility of the two were used to arrive to a viable alternative. As a general conventional rule, diesel power plants should be ideally located very close to or within a sub station. This way, the energy generated from the power plant is directly directed to the sub station under HV to the substation for its integration into the national grid. Locating a power generation plant too far away sub stations will involve the construction of a transmission line which brings with it additional cost investments. Therefore, the selection of an appropriate site for locating the power plant was influenced by the present location of available substations in Kigali. Kigali is currently supplied in electric power by several substations namely:

1. Gikondo Substation Site The 110kV substation of Gikondo is situated in the center of Kigali city and is located in a densely populated area and is the most important substations, serving the biggest load in Kigali and the country.

Page 30: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

30

The sub station site lacks adequate space for locating the plant and would require a lot of compensation hence costly. For this reason it does not become a very appropriate site alternative for locating the proposed diesel power plant. 2. Gasogi Substation Site The Gasogi Substation in the East Kigali is located at a ridge which is not suitable for locating a new substation and an extension, mainly because of the challenges that will be experienced in the transportation of bulk goods and equipment. Poor accessibility of roads does not favor location of such a facility and for this reason it was rejected. Locating the plant here would entail construction of longer access roads that would increase the project cost.

3. Mt. Kigali Substation Site The Mt Kigali Substation located at the South of the city of Kigali is right inside and within a town housing development area thus making it unsuitable in terms of location for any extension for that matter.

4. Jabana Substation Site The Jabana Substation, which would be the next the preferred choice of site is situated in the West (Byumba Road) with the incoming line from the Mukungwa Ntaruka and Hydropower stations, and was established in 1960 and rehabilitated in the mid 80s. The 70 kV line to the East Rwanda has its origin at this substation. However, this site is next to an existing swamp and therefore siting it in this area would lead to possible environmental risk. REMA would not also approve having the project in this site as the new law (Organic Law) does not allow for construction in wetlands.

5. Preferred Site The newly identified site which is about 1.2 kms from the previously proposed Jabana site is located in an area that is sparsely populated, is far from the Nyabugogo wetland, contains hard soil, is spacious and thus provides the best alternative in terms of site selection.

Due to the above reason, the new proposed site that is about 1.2 km from the previously proposed Jabana site in comparison to the other sites presents the most appropriate site for locating the new diesel power plant.

4.3 Alternative Energy Generation Sources The project being an emergency intervention to the energy sector in Rwanda, alternatives that are available for similar objective of the project are quite few. Actually all the alternatives sources of energy discussed below cannot solve the quick attention and solution needed to arrest the energy crisis. Still these alternatives however remote have been discussed as an indicator that due consideration was given to alternative sources of energy before deciding upon the preferred alternative. Wind and Solar: There is little potential for wind-generated electricity to contribute to the national network, as Rwanda is not favored with a windy climate. While Rwanda does have potential for solar electricity generation, the potential for solar power as a significant provider to the national network is low due to its comparatively high kW/h purchase price. Thus, at present in Rwanda, wind and solar, along with micro and mini hydro, are considered to be viable sources of electricity primarily for rural, off-grid people but not for large-scale, reliable, base load power. For example, in Kenya, more rural homes rely on photovoltaic (pv) systems for electricity, than rely on the grid. The Photovoltaic Market Transformation Initiative (PVMTI) of the International Finance Corporation and the Global Environment Facility has been present in Kenya since 1998, with the aim to promote the sustainable commercialization of photovoltaic technology in the developing world by providing examples of successful and replicable business models that can be financed on a commercial basis.

Page 31: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

31

Biomass With a population characterized by low household incomes and low purchasing power of consumers preventing the trading of commercial forms of energy, Biomass – mainly firewood, charcoal and crop residues – accounts for 95% of traditional energy consumed in the urban and in the rural areas owing to low economic capacity to import other alternatives, and also owing to low technological capacity to develop alternative sources of higher energy intensity such as natural gas and hydropower. As a consequence, households and medium scale enterprises are forced to utilize charcoal, firewood, and agricultural residues as the only source and choice of process energy for their home use and businesses. The situation has resulted into the hillsides being denuded of trees, causing serious erosion, which in part has led to decreasing agricultural productivity of the arable land. Use of biomass is not able to solve the national acute energy problem in the country and is thus not a favoured short term objective. Lake Kivu Methane Gas For the long term, the GoR has signed an agreement with a private company to develop methane gas from Lake Kivu for power generation; it will bring to the grid some 30 MW in 2007. The exploitation of the natural gas resource at Lake Kivu (some 55 billion m3 of methane) remains the GoR’s priority. Lake Kivu is regarded as the best alternative for a number of reasons including its relatively low construction cost and short lead time, its relatively low estimated operating costs, its potential for serial development in response to Rwanda’s changing demand need and its diversification away from hydro power. The methane resource is also attractive from a global environmental view, as the replacement of fossil fuels by methane would lead to reductions in greenhouse gas emissions. Methane could also possibly be used in the future as a fuel source in various industries and also as an automotive fuel and such uses would all have net positive environmental impacts. Further, a methane fired generation facility would provide as by-production ammonia, which could be used to generate a fertilizer industrial facility. Having identified Lake Kivu as its preferred alternative energy source the GoR has been limited in the development of this initiative due to lack of sufficient funds. However, as mentioned earlier, the energy crisis in Rwanda necessitated the urgent need for a project that could stem the crisis on a short term basis as other options are getting explored. Methane gas in Lake Kivu is still at the exploratory stages and thus cannot be relied upon to resolve the energy crisis. Geothermal Located in Cyangugu and Gisenyi the resources can provide between 170MW and 320 MW. This project is still under feasibility studies and cannot address the emergency power problem in Rwanda which needs urgent intervention. Peat With 150 million tonnes potential, the GoR has already signed a contract with Canadian company for potential studies. This project is still under feasibility studies and cannot address the emergency power problem in Rwanda which needs urgent intervention. Hydro Power Projects Development of hydro schemes are considered to be the most economical source of reliable and sustainable electricity for the grid in Rwanda in the medium to long term, with the cost of generation much less than diesel generation. The Regional Rusumo Hydro Power Falls Project to be funded by the World Bank and expected to be completed in 2011 will inject an increased capacity of electricity to the GoR. Other

Page 32: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

32

hydro power projects in the pipeline include, Rukarara, Nyabarongo and other small micro hydro dams that again will take a few years before they are commissioned. However, all these hydro schemes are at the feasibility stage where environmental assessment studies are currently under preparations. They cannot therefore solve the crisis in Rwanda because they are all planned to be commissioned by 2012-2015.

4.4 Alternative In-Put Materials The process materials that are required by the proposed project include construction materials like cement, sand, ballast etc during construction and HFO for running the plant during operation phase, water for cooling the generators, lubricants for the engines and ordinary diesel oil for starting up the generators and shutting down. Water Utilisation There are no alternative materials for cooling the engine jets and plant other than water. The generators must be cooled and water is the only substance that can be used to cool the engines effectively and cost effectively. So the task was to assess existing and alternatives water sources for use to cool the engines. The study had 3 alternatives sources; piped municipal water; surface river water and rainwater. 55,000 litres needed as the base storage capacity of the cooling system meaning that during commissioning, the storage tank will be filled with water upto a maximum of 55,000 litres. Thereafter the diesel power plant requires 200 litres per day as top up and this will be through an automated system. This water is poured into the radiators daily and it is recycled. A portable water treatment facility will be designed in the water system of the diesel plant in order to purify the engine cooling water before using it is used. Impure water is likely to spoil the efficient functioning of the plant or even breakdown. There will be no waste water from the radiators that will require special disposal this is because the water will be recycled. The plant operators will also require approximately 500 of water litres daily domestic use especially in the staff quarters. The waste water from domestic use including from the toilet will be channelled into the existing sewer line. Surface water Option Surface water from the nearby Nyabugogo River would be a viable option for the plant. However, the water used to cool the engines requires purification in order to remove any impurities that could spoil the engines. River water is generally impure and would require additional costs for purifying the river water. This water is also used for agricultural irrigation and using it as an option would cause conflict or competition. For this reason this option was rejected. Rain Water Harvesting Tapping and harvesting rainwater would also be an option but it would require the proponent to have a large roof catchment surface. The project should consider building a water tank for roof catchment as a supplement for general washing and toilet use or as a back up during water shortages. This option is reliant on availability of rain and hence cannot be fully considered as a stand alone source of water for the plant. Hence this option was not rejected and should be considered. Municipal Water (Preferred Option) Water supply from ELECTROGAZ thus is the only viable option for the project. The project intends to draw water from the already existing water line which will be directed into the plant system including fire fighting tank and the cooling tank. The water will still be treated before it is used to cool the plant and also for domestic purposes.

Page 33: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

33

The use of municipal water in this diesel plant will impact on other water users who depend on the water source but the impacts will be minor and not significant in terms of magnitude. This is because the plant does not require a lot of water for cooling. The water used in cooling the diesel engines is recycled over and over again. The diesel plant thus requires 55,000 litres of water during the commencement of operation and thereafter it will requires 700 litres per day for daily use(domestic) and top up of the cooling plant. Rwanda’s ELECTROGAZ water supply is not going to be significantly affected or impacted by the withdrawal of 700 litres for use in the plant daily. The water will be abstracted from the Nyanze pump station in Kigali that generates 30million litres of water per day. The 55,000 litres storage tank capacity also acts as a back up in cases of water shortage. In principle the plant will only use 200 litres of water per day.

4.5 Combined Cycle Project Another alternative technology is for the project to be converted into a combined cycle plant. Combined-cycle plant produces electricity from two sources instead of one. When the exhaust from the combustion turbine is used to make steam in a heat recovery steam generator this is called combined cycle. Both sources of energy then drive turbines and electric generators to produce electricity. Integrating combustion turbine and steam turbine technology provides an extremely efficient electricity production process. Combined cycle is about 30 percent more efficient than a traditional steam plant. A combined cycle project would operate cleaner and more efficiently than the fuel-powered units. As a result, air emissions will be significantly reduced. However the project being an emergency plant and the duration and costs of installing a combined cycle would not be feasible for the project objective. Major advantages of combined cycle plant over the proposed project include

I. higher thermal efficiency, II. lower fuel consumption,

III. lower emission of NOx, IV. no SO2 and particulate matter emission, V. no solid waste generated such as coal ash,

Combine Cycle was not considered during the project conceptualization hence as an alternative it has not been rejected and is a possible option that can be pursued. The fact that heat recovery was not considered during the conceptualization phase does not rule out the possibilities of installing this technology in future. A heat recovery plant can still be installed to capture the exhaust heat from the engines and used to generate electricity projected to almost 1 MW at the moment. However, such recovery heat systems must be connected to a nearby factory that would use the heat for running boilers immediately. This is the only inadequacy in capturing the heat. There are no industrial plants nearby that can capture the heat and use it right away. For this reason, this option cannot be explored right away. The sugar factory that is about 1km from the site can be considered even though the distance is far away.

4.5.1 Energy Efficiency Energy efficiency is using less energy to provide the same level of energy service. Efficient energy use is achieved primarily by means of a more efficient technology or process rather than by changes in individual behaviour. This is thus the idea of meeting energy needs by increasing efficiency instead of increasing energy production. The alternative energy section of this report has described the possible sources of alternative energy that increase efficiency and lead to less emissions.

Page 34: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

34

In terms of energy efficiency at the domestic/household level, a UERP/ELECTROGAZ project is already promoting the installation of fluorescent lights instead of incandescent lights to attain the same level of illumination but with less energy use hence reduced emissions. Even though this is a viable alternative to the existing project, it is not able to lead to the injection of more MW into the national grid which is needed to address the current energy shortage in Rwanda. Hence it has not been really rejected because it is a project running concurrent to the proposed diesel power plant, but it is not able to increase electricity supply needed through increased efficiency. There is need for the GoR to introduce other projects in the country that will increase efficiency in energy use and should target the industrial sector, transport sector, manufacturing sector etc. Such programs will play a great role in reducing emissions and associated impacts.

4.6 No Project Alternative A no project scenario was also looked into in this study. The forgone costs of not having the project could results in economic loses in terms of power cuts to industrial operations, agriculture and agro industries, domestic operations among other targeted socio-economic activities of the proposed project. The no-project scenario will mean the status quo of the area remains and no occurrence of adverse impacts as well as positive impacts posed by the project implementation. The no project option will have the forgone costs and benefits including

• The targeted consumers will forgo improved electricity supply. • Generation of employment opportunities through expansion of business activities that would have

been spurred by availability of electric power will occur. • The rural electrification programme will suffer.

Page 35: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

35

LEGISLATIVE, POLICY AND INSTITUTIONAL FRAMEWORK The chapter of the study reviews the relevant legal and institutional arrangements that would hinder or guide the development of the project in line with the national and international laws. Rwanda being a signatory to various international conventions and laws, it’s important that national projects are in line with these laws and as such some of the relevant international conventions are reviewed in this chapter.

5.1 Organic Law on Environment Protection and Management The law sets out the general legal framework for environment protection and management in Rwanda. It also constitutes environment as a one of the priority concerns of the Government of Rwanda. Under the fundamental principle on national environmental protection policy develops national strategies, plans and programs, aiming at ensuring the conservation and use of sustainable environmental resources. The law gives right to every natural or legal person in Rwanda to live in a healthy and balanced environment. They also have the obligation to contribute individually or collectively to safeguard country’s natural, historical and socio-cultural heritage. The framework of the law on the protection and management of natural resources centres on avoiding and reducing the disastrous consequences on environment. It measures result from an environmental evaluation of policies, programs and projects, aimed at preventing the consequences of such activities. The principle of sustainability of environment and equity among generation emphasizes human beings at the core of sustainable development. They therefore, have a right to a healthy and productive life in harmony with nature. They must so as to equitably meet the needs of the present and future generation. The protection and management of environment is currently registered in the environmental organic law that has been published in the official Rwanda newspaper in May 1st 2005. MINITERRE which is the ministry responsible for the environment under the article 65 puts the in place Rwanda Environment Management Authority (REMA) which is the institution now charged with the responsibility of ensuring environmental protection by demanding for EIA studies to be undertaken before projects are executed. The present organic law has the following objectives:

• To protect human and natural environment; • To establish fundamental principles of management and protection of environment against all

forms of degradation so as to develop natural resources and to fight all kinds of pollutions and nuisances;

• To improve the living conditions of the population while preserving ecosystems and available resources;

Page 36: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

36

• To ensure sustainable environment and resources as well as rational and sustainable use of resources, taking into account the equality between the present and future generations;

• To guarantee to all Rwandans an economically viable, ecologically rational and socially acceptable development;

• To establish the precaution principle in order to reduce the negative effects on Environment and ensure the rehabilitation of degraded areas.

Chapter IV of the Organic Law Article 65 clearly calls for the need to subject projects to mandatory Environmental Impact Assessment. Article 3: States that every person has the duty to protect safeguard and promote environment. The State shall protect, conserve and manage the environment. Article 65: Further specifies that every project shall be subjected to environmental impact assessment prior to its commencement. It shall be the same for programs, plans and policies likely to affect the environment. Specific details of projects referred to in this Article shall be spelt out by the order of the Minister in charge of environment. Article 66: The Environmental Impact Assessment (EIA) shall include at least the following:

• A brief description of the project and its variants. • Analysis of direct and indirect foreseeable consequences on the environment. • Analysis of the initial state of the environment. • Measures envisaged reducing, preventing or compensating for the consequences. • Reasons for the choice. • A summary of requisitions from clause1 to 5 of this article; • A definition of the evaluation and monitoring methods used regularly and environmental

indicators before (initial state), during and after implementation of the project or, as the case may be, at the final evaluation stage of the project;

• A financial evaluation of measures recommended preventing, reducing or compensating for the negative effects of the project on the environment and measures for regular monitoring and control of relevant environmental indicators.

Article 67: States that the analysis and approval of environmental impact assessments is done by the Rwanda Environmental Protection Authority or any other person given a written authorisation. The project promoter shall pay a levy which shall be assessed from the amount invested or to be invested, excluding the amount of operating cost. The assessment of this levy shall be fixed by law establishing the National Fund for the Environment. The impact study shall be done at the expense and under the responsibility of the promoter. The Organic Law also puts in place the National Fund of the Environment in Rwanda (FONERWA). The composition, the working and the assignments of these institutions will be determined by particular laws. The article 66 of the Organic Law on the environment specifies that it has created, to the level of the Provinces, of the City of Kigali, of the Districts, the Cities, the Sectors and the Cells, Committees responsible for the conservation and the protection of the environment. The composition, the working and the assignments of these committees will be determined by Decree of the prime minister. Title IV of Article 67 of the Organic Law requires that the execution of Policies, Plans and Projects must be subject to mandatory EIA studies to identify the potential adverse impacts they could have on the environment.

Page 37: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

37

Further to this through the Ministerial Decree, a list of all the project that must be subjected to mandatory EIA has been put in place under article 68 of the Organic Law. Article 30 further stipulates that works of public or private construction as roads, dams etc must be subjected to EIA studies. Article 69 of the Organic Law further specifies that the EIA studies undertaken must be submitted to REMA for approval and the studies must be undertaken at the proponent’s expense. The Environmental Impact Assessment Regulations, 2007 REMA has now developed the EIA regulations which provide a guideline and requirements for EIA in Rwanda. According to these new regulations Sub Article 1 makes it mandatory for all the projects listed under schedule I to be subjected to a full scale EIA. The Sub Article further states that: Sub Article 1) No environmental authorization shall be granted by the Authority for any project in Schedule I to these Regulations if no environmental impact assessment has been submitted to the Authority in accordance with the provisions of these Regulations. Sub Article 2) states Any project listed under Impact Level III of Schedule I to these Regulations shall require a full environmental impact assessment by the preparation of an environmental impact report, unless the Authority refuses permission. The construction of a power project facility is in this category and thus must be subjected to full scale EIA. Public Hearing Process Article 47: The Authority shall on receipt of the developer’s environmental impact report, arrange for a public hearing to take place within twenty (20) working days from the first day of public notification, at which relevant Lead Agencies, local governments, civil societies and concerned members of the public may comment on the environmental impact report and express views on impact of the proposed development. The Authority shall cover all costs incidental to the public hearing. Article 48: All projects classified under Impact Level III shall be subjected to a public hearing prior to the decision-making process.

5.2 Energy Policy The national policy goal is to meet the energy challenges and needs of the Rwandan population for economic and social development in an environmentally sound and sustainable manner. Since 1994, the energy sector as well as the overall economy has gone through structural modifications, where the role of the Government has changed, markets have been liberalised and private sector initiatives encouraged. Hence, the energy policy document has to take into account structural changes in the economy and political transformations at national and international levels. The national policy objective for the development of the energy sector is to provide an input in the development process by establishing an efficient energy production, procurement, transportation, distribution, and end-user systems in an environmentally sound manner. The Energy Policy, therefore, focuses on market mechanisms and means to reach the objective, and achieve an efficient energy sector with a balance between national and commercial interests. An interactive and participatory process between Government, other stakeholders and relevant groups has been necessary as part of the formulation process in order to incorporate views of market actors and energy

Page 38: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

38

consumers to address the complex nature of the sector. Specifically, the energy policy takes into consideration the need to; (a) Have affordable and reliable energy supplies country wide; (b) Reform the market for energy services and establishes an adequate institutional framework, which facilitates investment, expansion of services, efficient pricing mechanisms and other financial incentives

(c) Enhance the development and utilisation of indigenous and renewable energy sources and technologies (d) Adequately take into account environmental considerations for all energy activities (e) Increase energy efficiency and conservation in all sectors; and (f) Increase energy education and build gender-balanced capacity in energy planning, implementation and monitoring. Domestic energy demand has grown rapidly due to population growth and the increase in economic activities especially during the last ten years Biomass based fuels dominate the energy scenario, with an estimated 95% of the total energy supply made up of firewood, charcoal, and agricultural residues. This is likely to remain so in the near or even medium term future, unless income levels substantially increase. Lack of investment for about 20 years in electricity generation capacity has resulted in severe capacity deficits in electricity supply in Rwanda. At the same time, overuse of existing hydropower capacity has added a deficit in energy resources that not only deteriorates electricity but also water supply, due to its effect on water pumping stations. No new generating plant has been constructed in Rwanda since 1982 and, given the current electricity supply shortage; new investment in generation is urgently needed. It has been clear for some time that Rwanda’s current energy crisis was looming due to the necessary over exploitation of hydropower water resources in the preceding years. However, despite identifying multiple longer term investment opportunities including Lake Kivu methane gas, Rusumo Falls, Nyabarongo and Rusizi III, only limited progress has been made in securing funding for enhanced generation capacity.

Given that Rwanda is a land characterised by many hills and small rivers there is also significant potential for the exploitation of micro-hydro power. Studies by the Ministry of Infrastructure have identified more than 160 sites with potential ranging from 20 KW to over 600 KW. There is also wind data that indicate there are potential sites for wind farms. However, without rising incomes and greater disposable incomes it will be some time before electricity be affordable by the rural communities. Transmission costs for small amounts of electricity over larger distances will remain a barrier to connecting wind turbines to the Grid. Studies have shown that there is a considerable quantity of peat existing in Rwanda, in the order of 155 million tonnes. However, there has been very little exploitation of peat due to technical and economic difficulties, and also possible environmental impacts. Other renewable energy sources, but so far not fully tapped, which could be harnessed to meet the growing energy requirements include solar and geothermal. Rwanda continues to rely on imported petroleum products; Electricity generation is mainly hydro-based, while diesel plants will soon provide 15 MW. Discussions on the development of Methane gas for electricity

Page 39: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

39

are ongoing. The dissemination of renewable energy technologies has been limited to the promotion of improved stoves, improved charcoal production techniques, solar, biogas and to a lesser extent photovoltaic. Initiatives to increase utilisation of peat for electricity generation and windmills are being explored. The vision of the energy sector is to effectively contribute to the growth of the national economy and thereby improve the standard of living for the entire nation in a sustainable and environmentally sound manner. The mission of the energy sector is to create conditions for the provision of safe, reliable, efficient, cost-effective and environmentally appropriate energy services to all sectors on a sustainable basis. By fulfilling its vision and mission, the energy sector will contribute to social economic development, and in the long-term framework, poverty reduction. The national energy policy objectives are to ensure availability of reliable and affordable energy supplies and their use in a rational and sustainable manner in order to support national development goals. The national energy policy, therefore, aims to establish an efficient energy production, procurement, transportation, distribution and end-use systems in an environmentally sound and sustainable manner.

Short and medium term policy priority actions The priority for Rwanda is to implement projects now, to overcome the current electricity crisis, to prevent the next electricity crisis, to tackle proactively the wood crisis, to begin to provide greater access to modern energy and to reduce reliance on petroleum products due to the oil price crisis. Without implementation further capacity building and studies will have no value. Our management and institutional capacity has to continue to progress if these projects are to be delivered effectively and efficiently. This will require further external support and guidance. Several policy actions will be implemented in order to achieve the broad and specific objectives of this energy policy. Strategic financial interventions required to move forward the policy priority actions are indicated alongside the proposed actions. Priority policy actions

1. Meet the crisis of blackouts caused by delayed investment and drought

2. Provide economic power by developing the use of Lake Kivu methane, and by bringing on line more hydro power.

3. Enhance overall electrical infrastructure to meet demand growth and supply quality needs

generation, transmission and major distribution construction and rehabilitation.

4. Deliver a programme of rural electrification on the basis of enhanced distribution networks, micro hydro, and solar power.

5. Implement a wood and charcoal efficiency and substitution strategy to counter the deforestation

crisis.

6. Continue steady progress to a viable electricity and gas sector, consistent with meeting social needs.

Page 40: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

40

7. Commence utilisation of Kivu gas for other than power generation.

8. Determine options for response to oil prices and petroleum products costs, and their impact on the

economy. Reduce reliance on petroleum products.

5.3 Land Policy Apart from a few scattered land regulations, most of which date back to the colonial period, Rwanda has never had a proper land policy nor has it ever had a land law, a situation that enhances the existing duality between the very restrictive written law and the widely practised customary law, giving rise to insecurity, instability and precariousness of land tenure. The Rwandan Government, therefore, found it compelling and necessary to establish a national land policy that would guarantee a safe and stable form of land tenure, and bring about a rational and planned use of land while ensuring sound land management and an efficient land administration. The following are the main obstacles that hinder the efficient management of land in Rwanda, necessitating the establishment of a national land policy that would guide the essential land reforms: • Strong pressure on the already spatially limited land resources by a rapidly growing population;

• Domination of the agricultural sector which lacks any specialization in terms of human resources and

equipment, and lack of alternative concrete and realistic options that would reduce the pressure on land resource;

• A land tenure system dominated by customary law which favours land fragmentation, a practice which

reduces further the size of the family farms which are already below the threshold of the average surface area that is economically viable;

- A considerable number of landless persons who have to be resettled at all costs

- Scattered farming plots that are difficult to manage due to the scattered mode of human

settlement

- Lack of a reliable land registration system that would guarantee the security of land tenure;

- Weak and inadequate existing methods of land-use planning and land improvement (outline of land potential, land use and land development; reliable methods of soil and water conservation);

- Disorderly and fraudulent land transactions, necessitating the establishment of regulations that

would enable the authorities to give to the land a recognised market value which brings considerable profit to the Government Treasury;

- Unplanned use of marshlands which, in spite of their good agricultural soil, cannot be wholly

recovered for agricultural purposes, in view of the following factors:

• Abundance of water which is necessary as a useful water reservoir;

• The soil make-up, which does not lend itself easily to the current cultivation methods;

Page 41: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

41

• The biotic environment and biodiversity which should be protected at all costs;

• The obvious poor coordination among various institutions which use with land to support

their activities; Currently, the land tenure system in Rwanda operates in a dual legal system: On one hand, there is:

• The customary law, which governs almost all the rural land and promotes the excessive parcelling out of plots through the successive father-to-son inheritance system. And on the other, there is

• The written law, which mostly governs land in urban districts and some rural lands managed by

churches and other natural and legal persons. This law confers several land tenure rights to individuals such as land tenancy, long term lease and title deeds (particularly in towns).

On the whole, Rwanda’s land tenure system requires comprehensive reforms, from the elaboration of a national land policy to the establishment of a land law and land code, which will guide the judicious use and management of the land resource for the economy to be able to take off in such a way that our country is freed from the grips of poverty. In the perspective of the harmonious and sustainable development, the overall objective of the national land policy of Rwanda is to establish a land tenure system that guarantees tenure security for all Rwandans and give guidance to the necessary land reforms with a view to good management and rational use of national land resources. Specific Objectives

• To put in place mechanisms which guarantee land tenure security to land users for the promotion of investments in land resource.

• To promote good allocation of land in order to enhance rational use of land resources according to their capacity.

• To avoid the splitting up of plots and promote their consolidation in order to bring about economically viable production.

• To establish mechanisms which facilitate giving land its productive value in order to promote the country’s socio-economic development.

• To focus land management towards more viable and sustainable production by choosing reliable and time-tested methods of land development.

• To develop actions that protects land resources from the various effects of land degradation. • To establish institutional land administration arrangements that enable land to have value in the

market economy. • To promote research and continuous education of the public in all aspects of duties and obligations

with regard to land tenure, land management and land transactions. • To establish order and discipline in the allocation of land and land transactions in order to control

and/or curb pressure on land, inappropriate development, land speculation and land trafficking. • To promote the involvement and sensitization of the public at all levels in order to infuse land use

practices that are favourable to environmental protection and good land management. • To promote conservation and sustainable use of wetlands.

Land tenure may be considered as a set of modes or procedures of land acquisition and ownership. It is, in other words, a combination of rules that define the modes of access, use and control of land and its

Page 42: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

42

renewable natural resources. It is therefore a relationship between men or social groups and land or its underlying resources. Land tenure has a multidisciplinary dimension that includes social, technical, economical, institutional, legal and political aspects. Debates on land issues must deal with various aspects of the environment, including the vision of space and nature, forms of land ownership, the role of the government, etc. In Rwanda, there are currently two modes of land acquisition, namely acquisition according to customary law or conceptions, and acquisition according to the rules of the written law. According to custom, land ownership is held by whoever occupies the land first. This rule has always been respected in our society. However, in modern times, land acquisition by occupation has become obsolete since all vacant land belongs to the State. Likewise, the provisions of the decree-law No. 09/76 of 4th March 1976, article 1, stipulate that ‘all land not held under the written law and affected or not by customary law or land occupation belongs to the State’. Customarily, land rights are passed on from father to son through inheritance. Girls are excluded from inheritance of the family land from the father. Concerning inheritance rights of widows, the custom merely gives them the right to use the land that belonged to their deceased husbands. In its original customary conception, land was owned collectively. Any disposal of land was therefore inconceivable, since such land was considered as family property that belonged to the ancestors, as well as to present and future generations. With the introduction of the subdivision of land into individual plots due to successive inheritance procedures, each family owner of a plot of land was considered as the real owner of the plot, having the right to dispose of it as it wishes. However, Article 2 of the decree-law No. 09/76 of 4th March 1976 stipulates that nobody may sell off his land rights except with the written authorization of the Minister of Lands upon the recommendation of the Municipal Council where the land is located. In actual fact, ownership through prescription originates from the written law since traditionally, title deeds were unheard of. Rwandans consider that once a right has been acquired or recognized, even customarily, it is indefeasible. This is why the many existing landless people, not having received any new land, continue to feel cheated and left out because they have no right over the land which they owned customarily over 30 years ago, since the law has fixed the time limit of acquisition by prescription to 10 years. Method of acquisition through written law

• Tenancy contracts of plots for building purposes for a 3-year period in urban areas. • Long lease contracts of land for agricultural purposes for a period of 15 years or more in rural

areas. • Free assignment contracts in both rural and urban areas to natural or legal persons for social

activities with real impact on the welfare of the people. • Sale contracts and title deeds for plots that are built in urban areas. This is a system of land tenure

by urban residents who first lease plots with the contractual obligation of developing them. The Ministry of Lands delivers the title deeds after confirming that the plots have been developed.

• Right of access: mode of land acquisition which is common for public institutions. Apart from the above-mentioned different modes of land acquisition and land ownership, there is the case of the landless people who live in rural areas and who must live from farming. These are mostly the refugees

Page 43: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

43

of 1959 who were forced into exile for political reasons and left their land behind. These same refugees have now returned to their country and find themselves landless. They cannot claim back their previously owned land which has been occupied by other Rwandans who remained in the country, because the Arusha Peace Accord’s fixed the time limit for acquisition by prescription to 10 years

5.4 Relevant Policies

5.4.1 International Legislations Rwanda is a signatory to a number of conventions on sustainable development and is a member of various bilateral and multilateral organizations. Some of the relevant development partners in this project are the World Bank and a number of United Nations agencies.

5.4.2. World Bank Environment and Social Safeguards Policies World Bank Operational Policies (OP) and Bank Procedures (BP) Environmental Assessment - BP4.01 and OP 4.01 (January 1999 all of which require environmental assessment of projects proposed for World Bank financing to help ensure that they are environmentally sound and sustainable. Environmental Assessment is one of the 10 safeguard policies of the World Bank. The World Bank Environment and Social Safeguard Policy aims at improving decision making, to ensure that project options under consideration are sound and sustainable, and that potentially affected people have been properly consulted. The World Bank's environmental assessment policy and recommended processing are described in Operational Policy (OP)/Bank Procedure (BP) 4.01. The World Bank system assigns a project to one of three project categories, as defined below: Category “A” Projects An EIA is always required for projects that are in this category. Impacts are expected to be ‘adverse, sensitive, irreversible and diverse with attributes such as pollutant discharges large enough to cause degradation of air, water, or soil; large-scale physical disturbance of the site or surroundings; extraction, consumption or conversion of substantial amounts of forests and other natural resources; measurable modification of hydrological cycles; use of hazardous materials in more than incidental quantities; and involuntary displacement of people and other significant social disturbances. Category “B” Projects The construction of the diesel power plant falls under Category B of the World Bank Operational. A proposed project is classified as Category B if it’s potential adverse environmental impacts on human populations or environmentally important areas—including wetlands, forests, grasslands, and other natural habitats—are less adverse than those of Category A projects. These impacts are site-specific; few if any of them are irreversible; and in most cases mitigation measures can be designed more readily than for Category A projects. The scope of EA for a Category B project may vary from project to project, but it is narrower than that of Category A Environmental Assessment. Like Category A Environmental Assessment, it examines the project’s potential negative and positive environmental impacts and recommends any measures needed to prevent, minimize, mitigate, or compensate for adverse impacts and improve environmental performance.

Page 44: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

44

Category “C” Projects No EIA or other analysis is required. Category C projects result in negligible or minimal direct disturbance of the physical environment. Typical projects include education, family planning, health, and human resource development.

5.4.3 Climate Change Convention The Convention on Climate Change sets an overall framework for intergovernmental efforts to tackle the challenge posed by climate change. It recognizes that the climate system is a shared resource whose stability can be affected by industrial and other emissions of carbon dioxide and other greenhouse gases. Rwanda having ratified and signed the convention has the obligation to adopt national policies and take corresponding measures on the mitigation of climate change, by limiting its anthropogenic emissions of greenhouse gases. The project falls under the Climate Change Convention due to the fact that it generates greenhouse gas emissions. Article 4 of the protocol calls for development of measures to mitigate climate change by addressing anthropogenic emissions by sources and removals by sinks of all greenhouse gases not controlled by the Montreal Protocol, and measures to facilitate adequate adaptation to climate change.

Page 45: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

45

PROJECT DESCRIPTION Rwanda is currently facing a deficit in energy of 50 MW. In order to overcome this deficit, the Government of Rwanda is planning to curb this deficit by setting up 20MW diesel power plant which will then be connected to the national grid. The purpose of the project is to provide 20MW of electricity to the grid-using diesel running on Heavy Fuel Oil (HFO). The UERP through ELECTROGAZ and its implementing agencies including RURA and MININFRA plans to install a 20 MW diesel power plant along the Kigali Byumba-Gatuna road and about 1.2km from the existing Jabana substation in the city of Kigali in the District of Gasabo. A 1.2 km 110Kv transmission line from the proposed diesel power plant will be constructed to connect to the Jabana substation. The plan is to channel the electricity generated from the 20MW plant to the substation for stepping down before being introduced into the national grid. The project will involve the identification of a suitable location for this project and a viable transmission route for the 110Kv line and after compensation, it is expected that the land will be cleared and stripped before the construction of the plant occurs together with other ancillary infrastructure. Thereafter, diesel generator sets will be installed into the site which will generate electricity to be connected to the exiting national grid following interconnectivity to the Jabana substation. The connection to the Jabana substation will involve installation of transmission towers, and the electricity cables. The size of land necessary for installing the plant will be approximately 120 by 140m in size. However, there are other auxiliary facilities that are needed in the installation of a power plant. Therefore more land will be acquired for security and future expansion reasons. Therefore, a total of 3.59 hectares of land have been acquired for the plant. The consolidated size of land that will be acquired for the transmission line is 0.11ha and the PAPs will be compensated according to the requirements in the RPF and ARAP to be prepared. This means that jointly combining the 2 components a total of 3.7ha of land will be acquired for the project to be implemented. Project Activities The project activities will fall under planning, construction, operation and decommissioning phases. The project specific activities will include the following; Planning and Design Phase Activities expected to occur during the planning and design phase of the project include;

• Identification of project site including feasibility studies including site survey, soil testing, site mapping among others.

• Acquisition of land for construction of the 20 MW power plant and its ancillary structures. • Survey for transmission route for the 110Kv line from the diesel power plant to be constructed to

the Jabana substation. • Acquisition of land for construction of the 1.2 km 110 Kv transmission line and ancillary structures.

Page 46: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

46

• Valuation and compensation of Project Affected Parties (PAPs) for loss of land, structures and crops.

Construction Phase During the construction phase of the project the following activities will be undertaken namely;

• Site clearing for the construction of the diesel power plant including its ancillary facilities • Excavation related works • Construction and installation of the power plant and related ancillary facilities • Installation of the transmission towers and electric cables

The construction of the power plant and installation of the 1.2 km 110 Kv transmission lien shall also include related engineering works, earthworks, and service utility buildings including an engine hall, control building a fuel handling house, and installation of towers. Site Clearing and Stripping The construction work shall involve the clearing of areas required for permanent works. Stripping shall include cutting and removal of topsoil, levelling and all other related works to strip off the diesel power plant site and the transmission line route.

Photo of the site and vegetation that will be cleared Excavation and Foundation Ground excavations for the diesel power plant and transmission line to the lengths and widths and exact depths as indicated on the drawings for the construction of the works will be undertaken. In cases where the bearing capacity of the subsoil under foundations or roads is insufficient, the excavation shall be continued to such greater depth as may be necessary. All excavation will be carried out mechanically, but the final shaping and trimming of the sub grade below foundations, etc. shall be done by hand. Backfilling Filling of areas and around foundations and backfilling of trenches shall be executed in such a way and to such extra depths as will ensure that final surfaces after settlement and compaction conforms to the specified levels. All fill material shall be well compacted by mechanical means until a high degree of compaction is obtained. The filling material shall be placed in even layers of a depth not greater than 0.4m and each layer shall be thoroughly compacted. A suitable power-driven roller of at least 5 tons weight, making at least 10 passes for each layer shall be used.

Page 47: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

47

Road and Drainages The diesel power plant will involve the construction of a road and drainages fro storm water management. The internal roads shall be minimum 7 m wide, or otherwise allow transport of the equipment, and turning of vehicles, within the area. The roads shall be connected to the existing roads. The road shall be designed for trucks with a weight of 60 tons and 10 tons per wheel. Provisions shall be made for adequate drainage of the roads covered drainage pipes, concrete conduits and trenches for electric cables etc shall be provided as needed for the design. Construction of Service Utility Buildings A number of utility buildings will be constructed and will serve as auxiliary infrastructure to support the generation of electricity in the power plant. They include; Construction of shelter for the diesel plants There will be construction for a shelter facility for the diesel plants that will be installed in the project site. Construction of building block for control purposes A control block housing unit will also be constructed in the project site for the purposes of controlling the operations of the diesel power plant. Construction of access road & and drainage system for water Access road to the project site will be constructed to provide access to the diesel power plant during construction and operation. There is an existing gravel road that is narrow and leads to the site after the main tarmac road. This access road will be closed and another road will be constructed to accommodate the huge trucks and other motorised machinery like excavators and tippers that will be used during construction. All surface water shall be connected to the drainage system. The drainage system shall be designed for the actual rainfall conditions. Open ditches within the perimeters are not allowed. Drainage water from the storage tank area, the unloading area and the day tank area shall be connected to an oil trap before disposal.

Photo of the existing murram road leading to the site will be closed and a new access road constructed. Construction of fuel storage tanks A series of several fuel storage tanks will be constructed in the project site and will be primarily used for storing the fuel that will be for operating/driving the diesel generators to produce electricity.

Page 48: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

48

Installing of generators and transformer & piping of fuel lines When the construction is finalised, the generators will be installed including the transformers and piping of the fuel lines. A perimeter wall will also be built all around the project area for security reasons. The diesel power plant project will have an installed capacity of 20MW being generated by 4 diesel generators. The project will involve installing the generators and connection to the main grid running on Heavy Fuel Oil (HFO). The equipments/generators to be installed at the project site will be sets of generators, with a rated out put of 7.5 MVA and a rated voltage of 6.6 kV, rated current of 656 A, rated frequency of 50 Hz with 0.8 lagging and a speed of 1000 rpm. The Diesel Power Plant shall have 2 sets of power transformers of 15 MVA, 6.6/110 Kv three phase, 50 HZ, two winding oil immersed with on-load tap charger complete with accessories under natural-oil-circulation and natural-air cooled operation referred to the 110 kV side of the transformer. Operation Phase During the operation phase of the project activities to occur are mainly controlling and operating of the diesel power plant, and subsequent generating of electricity. Activities related to operating the plant will include, loading and unloading fuel oil in the tanks, running the diesel engines, regular maintenance works among others.

6.1 Project Technology Description The project is using a simple but expensive technology for electricity generation using diesel driven generators. This is combustion of fuel oil in open chambers in order to generate electricity. In-Put/Raw Materials The diesel power plant will primarily use the following few materials that can be described as raw materials in order to function and generate electricity. They include;

1. Fuel oil for running the engines -The plant when operating at 60-100% load will require an estimated amount of 100,000 litres per day.

2. Lubricating oil for the engines for the plant is estimated to be about 85 litres per day when operating at 60-100% load.

3. Natural air to mix with the HFO for combustion 4. Water for cooling the engines is estimated to be about 55,000 litres at the commissioning which will

act as the storage and then 200 litres will be used daily as top up. Water used in cooling will be recycled using a closed circuit cooling system and hence will not emanate as waste.

5. It is estimated that 500 litres of water will be used daily by the staff in the project site for domestic use.

6. Engine coolant to assist the radiators to cool the engines will be required and about 100 litres will be used every 2 months.

Fuel Type The diesel power plant will use 2 types of fuel oil to generate electricity. At the start of the operations, when the engines are cranked up, ordinary diesel oil (Low Fuel Oil) will be used to start up the engines and this is because ordinary diesel is light, viscous and recommended for start up of the engines. The plant will then after 3 minutes switch to the use of Heavy Fuel Oil (HFO) for generator combustion and electricity generation. The HFO system shall be designed for fuels with minimum viscosity of 125 CSt at 50°C maximum viscosity of 180 CSt at 50°C. Short stoppages for a few hours shall be possible on HFO.

Page 49: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

49

During shut down of the engines, again the HFO system will be switched off and for 3 minutes, the engines will be shut down using ordinary diesel oil. During normal unit operation (60 to 100% load on HFO) exhaust gas at the stack outlet shall be nearly invisible, i.e. the Bacharach Smoke Number shall not exceed two. Operation on ordinary diesel fuel shall only be necessary for regular start-stop procedure and flushing the fuel system before overhaul. Amount/Quantities of HFO utilised per day Operating at 60-100% load capacity, the HFO that will be used by the power plant is estimated at 100,000 litres of per day. Actual specification of the Heavy Fuel Oil and restricted values are provided in the table below. These values are based on international specifications and are included in the tender documents which the contractors are expected to meet at the time of bid submission.

Test Test Methods Units Value

Viscosity at 50°C ASTMD 445 mm2/s Min. 125, max. 180 Pour Point ASTM D 97 oC Max 24 November to April

Max 21 May to October Density at 20 oC ASTM D 1298 kg/m3 Max 985 Flash Point PMCC ASTM D 93 oC Min 66 Net Calorific Value ASTM D 2382 MJ/kg Min 41,1 Water content ASTM D 95 % Volume Max 0,75 Sediment ASTM D 473 % Mass Max 0,15 Ash content* ASTM D 482 % Mass Max 0,08 Conradson Carbon Residue * ASTM D 189 % Mass Max 12 Asphaltenes * IP 143 % Mass Max 10 Sulphur content * ASTM D 4294 % Mass Max 3,0% Vanadium content * IP 288 ppm Max 300** Sodium content * IP 288 ppm Max 50** Aluminum + Silicon Content * ASTM D 5184 ppm (Al+Si) max 80 Nitrogen content * ASTM D 3228 % Mass Max 0,4

Values to be confirmed by the Fuel supplier before final signing of the Contract.

** Independent of the absolute content, the Sodium / Vanadium ratio should not exceed ¼ or 25% .

Source; Contractor bid tender documents

Water Water is required to cool the diesel engines through a series of radiators and fans. This is municipal water that is treated first and then mixed with a coolant to ensure that the water does not corrode the engines. The engines will require approximately 5,000litres of water during the initial stages of starting up the power pant. Thereafter, the engine is in built with a recycling system whereby the water will be recycled and re-used just like in a motor vehicle engine.

Page 50: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

50

The cooling water of the diesel engines shall be cooled by means of a two-circuit table design radiator cooler as to guarantee trouble free operation of the engines. The design of the coolers and their installation shall avoid short circuit circulation of hot cooling air, as well as short circuit circulation of exhaust gas of the units.

6.2 Plant Design The plant is a 20MW diesel generators running on Heavy Fuel Oil (HFO). The equipments/generators to be installed at the project site will include 4 sets of generators, with a rated out put of 7.5 MVA and a rated voltage of 6.6 kV, rated current of 656 A, rated frequency of 50 Hz with 0.8 lagging and a speed of 1000 rpm. The Diesel Power Plant shall have 2 sets of power transformers of 15 MVA, 6.6/110 Kv three phase, 50 HZ, two winding oil immersed with on-load tap charger complete with accessories under natural-oil-circulation and natural-air cooled operation referred to the 110 kV side of the transformer. Diesel Engines The prime mover shall be a four stroke medium speed diesel engine with in-line or V cylinder configuration suitable to operate on HFO continuously on base load mode.

Rating a) Rated Output: 7.5 MVA at alternator terminals b) Number of Units: 4 c) Nominal Speed: 1000 rpm (maximum) d) Generator Rating: 6.6 kV*, 50 HZ, 0.8 power factor e) Performing class: Class G 3 (according to ISO 8528-5)

Exhaust Gas System The diesel engine gas system shall generally be designed to dispose off the engine exhaust quietly with the minimum loss of performance. The system shall include silencers, platforms and stacks. Each diesel engine shall be provided with one exhaust silencer and the design will provide the required sound attenuation to meet the outside noise level requirements with minimum pressure loss. Lubricating Oil System Filters, pumps and coolers shall be installed with adequate drip pans and drain pipes to the sludge tank. Fuel Oil System The HFO system shall be designed for fuels with minimum viscosity of 125 CSt at 50°C maximum viscosity of 180 CSt at 50°C. The unloading pump module shall unload the HFO to only one HFO tank while the second tank shall be operated as a storage-settling tank. The water and sediments regularly drained from the storage tanks shall be directly piped to the static 3-chamber oil-water separator for treatment. All fuel tanks shall be installed within a sealed concrete basin. The basin shall have a retaining wall designed to cater the volume of the biggest tank plus 15%. The HFO tanks shall be separated from the LFO tanks by a partition wall. Each basin shall have a slope to a big pump sump for draining all fluids from the basins. The pump sump shall be connected by means of manual operated drain valves with the oil-water separator. Each independent basin shall be provided with at least one access stair with safety railing. Two state of the art automatic self-cleaning skid mounted fuel separators shall be provided. One separator shall be operated as purifier and one as clarifier. The separator’s capacity shall be laid out for 100%

Page 51: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

51

capacity separation of IF 180 (at 50°C) fuel for total 25 MW (including one future extension by one diesel unit). After separation, the fuel shall be pumped into the HFO day tank. The HFO separators shall be fully automatic, self cleaning and self controlling, designed for unattended service including control and alarm system, steam pre-heaters, fuel pumps, sludge tanks, level controlled sludge pumps, accessories, piping etc. Storage Tanks There will be 6 fuel storage tanks made out of metal and leak proof material to be used to store fuel for running the plant. Fuel Unloading Module All components of the truck unloading module shall be mounted on a common steel base frame with leak oil pan with drain connection for emptying the pan by gravity into a can. Oily Water Treatment System Sludge Tank The overall design shall aim at collecting of sludge from the plant and pump/drain the same into a sludge tank for unloading the same on to sludge trucks for further disposal. The disposal of the sludge is the responsibility of the client in this case ELECTROGAZ. The sludge can be re-used in road construction or for firing boilers as a source of fuel in factories. Water Treatment System The oily water leakages and drains from the plant, especially from the fuel tank farm shall be collected in intermediate tanks and piped & pumped into a static minimum three chamber oily water separator of proven design. The separator shall be located close to the tank farm and consist of interconnected concrete basins were the oily water suspension is slowed down in flow and the oil is physically separated from the water. The 3rd chamber shall have on the sloped bottom a connection to the storm water system. This outlet shall be provided with an oil alarm devise. The skimmed oil is collected in one chamber. This chamber shall be fitted with a suction pipe and one weather-protected manual operated electric driven pump in order to pump the oil into the sludge tank. The sludge is generally caked HFO which will be collected and can be used in road construction because it is asphalt or for firing of boilers. ELECTROGAZ plans to sell the sludge to road construction companies or to factories. The project therefore plans to have interested companies in road construction or industries using boilers to collect the sludge regularly for use. The water separated from the oil during the separation process is mainly clean water and does not contain any hazardous substances. The water will be channelled to the existing storm water drain. However, because there can be leaks with the treatment system, monitoring of the effluent will be undertaken periodically. Water Supply, Sewage and Sanitation Water supply and sewage shall be installed as necessary in the plant site. A water tank of sufficient capacity connected to the public water-supply system shall be provided. The toilet shall be equipped with a water closet of low flush type and a lavatory basin with tap with hot and cold water. All sewage pipes shall be connected to existing sewage system.

Page 52: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

52

Control Building The control building shall be located close to the engine hall. The connection between the engine hall and the control room building shall be designed so structure-borne sounds cannot be transmitted between the engine hall and the control room building. The control room building shall include the control room, changing room, toilets and showers adequate for the operation staff, one office and one conference room. These rooms shall be equipped with air conditioning units. The control room building shall also include a storage room, MV-switchgear room, LV-switchgear room with charger and battery room. Engine Hall The engine hall shall be equipped with an electrified overhead crane suitable for maintenance of two units. The engine room shall be designed so the required noise level data will be fulfilled. Fuel handling House A separate building shall be designed for oil handling.

6.4 Project In Puts, Outputs and Wastes Generated The aim of the project is to generate electricity, however in the process the principle of input-output applies. The input of the project as mentioned earlier include, HFO, lubricating oil, water and air. The positive output of the process will include 20 MW of electricity. Wastes Generated The main wastes from the process include;

1. Emissions are expected as stated in the earlier section of the report to be emitted from the motorised trucks during the construction process and also at the operation phase when the diesel plant will be operational. These will be managed as outlined in the impact mitigation section 7 of this report.

2. Used lubricating oil will emanate from the engines during operations especially when the engines

are being serviced requiring draining of the used oil for replacement. The used oil will be collected and given to companies who like iron smelting companies etc. After every 2,000 hours of running the lubricating oil will be changed and it is estimated that 4,600 litres of used oil will emanate from this action once every 2000 hours.

3. Sludge will come out during the separation of water from the HFO and the sludge will be given to

road construction industry or factories with boilers. The estimated quantities of sludge are 400 cubic metres.

4. Used engine oil filters are wastes that will emanate at the time of engine servicing and

maintenance. These oil filters will be disposed in accordance with the REMA guidelines for disposal.

5. Waste water from general cleaning and washing of the plant, domestic use within the plant and

from the oily water separation tank constitutes the other set of liquid wastes that will be generated during the operation phase of the plant. The waste water will be channelled into the existing storm water drain and sewage line.

Page 53: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

53

6. General solid waste materials from the staff quarters and the plant for example domestic household wastes, papers, etc will be generated and disposed through the collection by waste providers to the dumping site in Kigali.

7. Construction debris which will be removed from the site and disposed in a landfill approved for

handling construction debris in Rwanda.

6.5 Project Operations and Management As described in chapter one of this report, UERP/PCU through ELECTROGAZ will contract a company to install generators for the purposes of producing electricity to be connected to the existing grid. Upon commission of the plant, the contracted firm will hand over the plant and its operations back to ELECTROGAZ.

Page 54: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

54

POWER PLANT – POTENTIAL ADVERSE ENVIRONMENTAL IMPACTS This chapter address the potential adverse impacts of the construction and installation of the diesel power plant. In this report, environmental impacts are defined in totality to mean, socio-economic, cultural, physical as well as biological. The chapter is structured into two parts one describing positive impacts of the development and the second part addressing the adverse impacts of the project on the environment. The project being a national development agenda in the energy sector has immense benefits that could save the country losses in terms of power rationing and frequent outages. However poor planning of the project could also affect the environment that supports millions of Rwandese through the project potential hazards that the project could pose to the public, pollution of water resources and atmospheric resources.

7.1 Positive Impacts Positive impacts of these project are various and diverse in nature. They range from employment opportunities, to wealth creation, industrialization, improvement in service delivery to technology transfer and capacity building.

7.1.1 Socio-economic Benefits The impacts of the Project on socioeconomic development of the people in the area include additional electricity for the region, provision of conditions for rational and effective use of natural resources in the country, creation of new jobs for related services and direct workers, and acceleration of the investment process in the region. Employment Opportunities On employment the project expects to employ local casual and skilled labor on-site. This is exclusive of indirectly employed people who will provide support and related services including those trading in foodstuff for the workers on site and construction personnel during the site preparation phase of the project. Steady supply of power to the region will also boost the industrial capacity of the area thus creating additional employment opportunities. Electricity The project aims to provide an additional 20 MW to in the national grid which is significant to the country. With additional electricity in the regional grid, the country as a whole is expected to attract more investments.

7.1.2 Environmental Benefits The proposed diesel power project has potential for contributing to the good of the environment of the area. The project will supply an additional 20 MW to the regional grid which will enable ELECTROGAZ connect more consumers leading to a substantial reduction in other sources of energy that have impacts on the forest cover and greenhouse.

Page 55: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

55

7.2 Adverse Impacts Adverse impacts of the diesel power project are those unintended effects of the project that have negative to sustainable development and the environment.

7.2.1 Impacts on Physical Environment –Construction Phase Land Acquisition/Compensation Power Plant Component The land targeted for the construction of the diesel power plant is owned Home of Hope of Rwanda which is a faith based Christian organization and plans to utilize the land to construct a church and a children’s orphanage center. The contractor requires land that is 2.06ha in size for the installation of the power plant even though a larger parcel of land than this will be acquired to provide room for any future planned expansions of the diesel power plant. In terms of compensation, the construction activities will lead to the destruction of crops and vegetation including Guavas, Bananas, Mangoes, Bamboo trees, and Napier grass among others. Land Acquisition/Compensation Transmission Component The land targeted for establishing the route for the 1.2km transmission line from the new diesel plant to the Jabana substation is 0.11ha and owned by 7 different land owners. Acquisition of this land will lead to crop and vegetation destruction along the transmission path in order to establish the required ROW. Generally land required for erecting the transmission towers and ROW is 15m by 15m (225m2) for the towers that will be 7 in number and 7m by 7m the space on both sides of the line which is referred to as the Right of Way. Mitigation There will be compensation for the land to be acquired from the Home of Hope Rwanda who is the current legal owners of this land in question. There will also be compensation for the crops that will be destroyed to pave way for construction. Therefore, Home of Hope of Rwanda will upon successful land valuation and crop and structure valuation be compensated in full for the loss of land to be acquired and crops/structures to be damaged. There are other 4 PAPs who will also be compensated for the loss of land and crops. Compensation will be undertaken in strict accordance to the already developed Resettlement Policy Framework (RPF) and a Resettlement Action Plan (RAP) will have to be developed before compensation occurs. Similarly, a survey and valuation of the land to be acquired for the transmission component has been undertaken and compensation for land and crops accorded to the 7 identified PAPs as specified in the RPF document and a separate ARAP will be developed before any compensation or resettlement occurs. Fugitive Dust Fugitive dust may be emitted from construction works and stock piles of materials including machinery as well as from truck traffic. This could cause health related impacts to the communities around and workers in the project site. The diesel power construction machinery and vehicles will also have other air quality impacts even though negligible. Mitigation

• The dirt roads and exposed construction areas should be moisturised during the dry season to prevent or minimise the fugitive dust emissions.

• Installation of speed bumps and speed limit signs to reduce speed of construction equipments

capacity to blow dust

Page 56: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

56

• Install Heavy duty muffler systems on heavy equipment and vehicles

• Proper location of material stockpiles, especially sand and soil downwind from the commercial, residential and other establishments will be required; Frequent wetting of the stockpile and working area; screening of or providing wind breaks for stockpiles;

• Diesel powered construction equipment and vehicles should be well maintained to minimise

tailpipe emissions; Covering of trucks; and proper selection of equipment and control of speed limits in construction area.

• Workers in the project site must be equipped with the necessary and required Personal Protective

Equipment (PPE) prescribed by the construction industry but not limited to safety helmets, Soil Erosion During the construction phase, activities involving preparation, stripping, grading, soil removal, backfilling, compacting, disposal of surplus and excavation of the earth surface to pave way for the installation of the diesel power plant will lead to fugitive dust emission and accelerate soil erosion and run off. Another impact of the project on soil and geology will be compaction, soil erosion and increased runoff. The compaction will prevent infiltration of surface water to the ground. This impact will only occur on site where compaction will be done. Mitigation

• To prevent soil erosion during site preparation, disturbed soils should be compacted immediately. Development of storm water drains around the site should prevent erosion occurring on the site.

• Wind blown erosion is to be prevented by soil compaction and wetting the ground to prevent rising

of soil particles.

• The final site grade should include the development of a drainage channel to facilitate drainage and avoid flooding and pooling by storm water. A site drainage plan should be developed to protect against erosion. Protecting stockpiles through the use of silt fencing and reduced slope angles should be used to minimize soil erosion during construction.

• Borrow areas (if any) should avoid agricultural areas; borrow areas should be reworked to blend

into the surroundings. Re-vegetation should be performed using local plants. All slopes and working surfaces should be returned to a stable condition

Vehicular Emission During the construction phase of the power plant, use of heavy equipment and machinery like trucks, and excavators will cause increased vehicular emission (CO2) in the atmosphere and will cause to some extent some form of atmospheric pollution. This impact is expected to occur during the construction and operation phase. During the operation phase it is projected that at least 4 trucks will be supplying HFO and ordinary diesel oil to the plant every day and hence localised vehicular emissions are also expected during this time. Mitigation

• Install vehicles with emission reduction gadgets to reduce the quantities of emissions.

• Ensure that the vehicles are regularly services and properly maintained so as to reduce emissions.

Page 57: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

57

Visual Impacts The construction works for the installation of the diesel power plant and associated civil works is likely to cause visual impacts in the immediate surrounding. Mitigation Construction of lower profile structures, use of less visible colors, planting of screening vegetation around the plant boundary, Proper design of the stack and dispersion characteristics. UERP should create a natural buffer of trees which will be important in reducing the visual impacts and screen the area while retaining a natural ambience. This is a long term mitigation measure especially because the trees are expected to grow tall over a period of 6-7 years. Noise Pollution The machinery and equipment that will be used to undertake different civil works during the construction phase of the diesel power plant will cause noise pollution in the immediate surrounding of the project area. The noise impact related to construction is expected to last only during the construction phase and will be short term in nature and not very significant in terms of magnitude and scope. The immediate surrounding of the plant within a distance of 1 km there are 7 houses spread out. The construction equipment and machinery are mainly motorised trucks, excavators, tippers and conventionally these machines do not emit noise that would be adverse to the neighbouring residents within a 50 m distance. This is what leads to the conclusion that noise impacts during the construction phase will be insignificant on the immediate surrounding. The workers on the other hand will experience noise related impacts of a fairly high magnitude because of the close proximity when operating the motorised vehicles during construction. During the operation stage, noise from the engines is expected to lead to potential impacts and this is discussed in the operation phase of impact analysis. Mitigation

• Noise emitting equipment should comply with the applicable Rwanda standards and World Bank noise standards. Rwanda does not have noise emission standards and thus World Bank standards will be use for compliance purposes.

• Construction traffic off-site will not contribute significantly to noise levels on public highways

because roads leading to the site already have very heavily traffic.

• Noisy equipment should be operated only during daytime.

• The construction activity during daytime is not expected to seriously affect the noise level in areas adjacent to the construction site and there will be no construction at night.

• All workers in the project site must be equipped with the necessary and required Personal

Protective Equipment (PPE) prescribed by the construction industry but not limited to facilities to protect against noise impacts, safety helmets, boots, dust masks, gloves, overall, goggles, helmets etc.

Page 58: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

58

• Workers and personnel operating equipments and machinery producing incessant noise and vibration should stick to no more than 5 hours a day in handling of equipment and machinery.

• Vehicles will be fitted with noise reducing equipment to minimize noise impacts during construction.

Destruction of vegetation cover/crops The project area is present with a variety of crops including beans, papaya trees, cassava, bananas, and maize among others. There is also a considerable thicket of eucalyptus tree species planted on the project site covering an area of approximately 0.5 ha. These crops and trees will inevitably have to be removed to pave way for the construction of the diesel power plant. This is the same with the transmission component of the project. In order to establish a ROW for erecting the towers crops and vegetation along the surveyed route will be destroyed. Mitigation This impact is unavoidable. However, UERP/PCU will compensate for the crops and tress that will be damaged as a result of the construction activities. The plant area will also be landscaped by replanting and replacing the trees that will be destroyed in the process of clearing the site for construction works. Accidents/Hazards As a result of the operation of equipment and machinery, there is a likelihood of accidents occurring especially to the workers when operating the equipments on and off the site. Unauthorised entry and encroachment into the site can also lead to accidents. Mitigation

• All workers need to be provided with the recognised and appropriate Personal Protective Equipment (PPE) while at the construction site including gloves, dust masks, boots, goggles, and overalls among others.

• UERP should create a high perimeter fence all around the project site complete with a gate and

guard to ensure that unauthorised entry is restricted at all times during the construction and operation phases of the project.

• During the construction the project site should be completely sealed off and warning signs erected

informing the general public to keep off the construction site when construction is in progress.

• Personal protection gear must be provided and its use made compulsory to all. The entire workforce of the plant should be trained in the use of protective gear, handling of chemical products and acid storage cells, electric safety equipment, procedures for entering enclosed areas, fire protection and prevention, emergency response and care procedures. Training given to the employees should be backed by regular on- site training in safety measures.

• No ENTRY signs should be installed to keep away unqualified workers from access to restricted

areas.

• The contactor must develop a workers Health and Safety Manual for which all the workers should be conversant with for response in case of accidents.

• The contractor should develop an Emergency Response Plan for handling any emergencies arising

thereof during the construction.

Page 59: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

59

Increased Traffic/Road Accidents It is expected that during the construction, an increase in traffic will be experienced along the Kigali-Byumba-Gatuna road and more specifically closer to the construction site because of the several vehicles that will be getting in and out of the construction site. This increased vehicle movement will increase the general traffic of the area as a result if heavy vehicles and is likely to cause traffic congestion. Also the area could experience road accidents owing to the increased traffic. Mitigation The entire heavy vehicles that is likely to cause traffic congestion when delivering goods in the construction yard should provide these services during traffic off peak hours to reduce traffic congestion. To reduce potential road accidents, there is need to erect speed bumps closer to the project area and warning signs limiting the speed when approaching the construction site.

• Install advance warnings and traffic signs indicating on going construction and heavy machinery frequently using the area. Install speed bumps to warn other road users of on going construction and also to reduce speed when approaching the area.

• Transport of heavy goods likely to congest traffic should be undertaken during off-peak times to

reduce congestion

• Request for the support of traffic police officers prior to construction works to control the traffic especially when heavy equipment is planned or scheduled for transporting.

Surface water contamination from waste water and site run-off Minor short-term lowering of the groundwater table during dewatering of foundation excavations is not expected to have a significant impact. Mitigation

• Water from dewatering activities and storm water discharges should be managed to minimise water quality impacts to nearby surface water resources such as the nearby irrigation canals.

• A site drainage plan which includes a suitable drainage canal and channel should be developed in the project site and used to channel storm water away from the plant into the nearest and appropriate water body or valley.

Storage and treatment of solid waste Solid waste materials during the construction include paper wrapping, scrap metal, excavated soils, polythene, plastic and metal containers will cause pollution and littering of the immediate and localized environment. Mitigation

• Contractor should develop a solid waste disposal plan which includes the provision of receptacles at strategic points within the construction site, recycling programmes for recyclable wastes, separation of wastes.

• The contractor and ELECTROGAZ should engage a refuse handling company to remove the

wastes from the site to the recommended dumping site.

• Warning signs against littering and dumping within the construction site should be erected by the contractor.

Page 60: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

60

• The contactor must construct toilets for use in the site during the construction which will be

connected to the sewer line.

• The disposal of used oil filters should be the sole responsibility of the supplier who should advise on the environmentally sound disposal method an dif possible should recapture back all the filters from ELECTROGAZ.

Fire Hazards/Accidents During the construction phase the chances of fire hazards occurring cannot be overlooked due to the use of combustible machinery and equipment in undertaking the construction works. Mitigation

• A robust fire prevention program and fire suppression system should be developed by the contactor. (A draft fire suppression plan is attached in annex D but needs further refinement by UERP and ELECTROGAZ who must carry out a vulnerability assessment before developing into a final suppression program). The plan for fire suppression should borrow from the already existing fire management plan available in other plants owned by ELECTROGAZ.

• The construction site must contain fire fighting equipments of recommended standards and in key

strategic points all over the site. Fire pumps, Hydrants, Sprinkler/water spray systems, Hose houses, Dry chemical systems, -alternative systems, Carbon dioxide systems, Detection/alarm systems, Portable fire extinguishers among others.

• All workers must be trained on fire management and fire drills undertaken regularly.

7.2.2 Adverse Impacts –Operation Phase The following adverse impacts are anticipated to occur during the operation phase of the diesel power plant. Emissions to air Combustion of the distillate oil will result in emissions of sulphur dioxide, nitrogen oxides, carbon monoxide, carbon dioxide, and particulate matter. Air pollution Carbon dioxide levels in flue gases vary depending on the type of fuel used and the excess air level used for optimal combustion conditions. Flue gas volumes also depend on these two variables. Operational phase of the project effects of the air emissions on air quality will include particulate emissions which represent the main pollutant of concern, with gaseous emissions such as sulphur dioxide (SO2), oxides of nitrogen (NOx) and carbon monoxide (CO) potentially significant due to combustion of Heavy Fuel Oil. Quantities and Types of Emissions Air quality impacts during operation of the power plant will consist primarily of stack gases emitted following fuel combustion. Emissions will be comprised of particulate matter (PM), sulphur dioxide (SO2), oxides of nitrogen (NOX), carbon monoxide (CO), the greenhouse gases (GHGs), carbon dioxide (CO2), and methane (CH4), trace amounts of various metals, and trace amounts of organic and inorganic compounds. The proportions and amounts of pollutants emitted will depend on the fuel quality and combustion strategy.

Page 61: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

61

Carbon Dioxide (CO2) Emissions The Intergovernmental Panel on Climate Change (IPCC) guidelines for calculating emissions inventories require that an oxidation factor be applied to the carbon content to account for a small portion of the fuel that is not oxidized into CO2. For all oil and oil products, the oxidation factor used is 0.99 (99 percent of the carbon in the fuel is eventually oxidized, while 1 percent remains un-oxidized). Finally, to calculate the CO2 emissions from a gallon of fuel, the carbon emissions are multiplied by the ratio of the molecular weight of CO2 (m.w. 44) to the molecular weight of carbon (m.w.12): 44/12. CO2 emissions from a gallon of petrol

= 2,421 grams x 0.99 x (44/12) = 8,788 grams = 8.8 kg/gallon = 19.4 pounds/gallon CO2 emissions from a gallon of HFO/diesel

= 2,778 grams x 0.99 x (44/12) = 10,084 grams = 10.1 kg/gallon = 22.2 pounds/gallon For the basis of this calculation 1 gallon is equated with 3.785 litres while 1 pound is equated to 0.4549kg. A gallon of diesel is calculated to produce 22.2 pounds (10.1) of CO2 emissions. Based on this, 1 litre of diesel is expected to result in; 10.1kg divided by 3.785 litres (1 gallon) = 2.668 kg/l. Two thousand (2000) litres – used per week - will therefore produce (2000 litres x 2.668 kg/l) 5,336 kg of carbon dioxide. The plant’s CO2 emissions will therefore amount to 5,336kg. This is equal to 31.8 kg/day. There are currently no national or international standards which define maximum CO2 emission levels (in mg/Nm3 or in gC/kWh produced). Given current technologies and those being developed, a maximum emission level of 120 g/kWh produced is considered best practice. Mitigation To reduce CO2 emissions timely and frequent service and maintenance of the generators should be undertaken. This will improve combustion of fuel which will be efficient and reduce emissions. Carbon emission offsets Another mitigation measure even though long term that the project could adopt in order to reduce the emissions is embracing the carbon offset mechanism. This should include planting trees to act as carbon sinks, increasing plant efficiency and even purchasing carbon emission reduction credits. World Bank Emissions Standards Pollutant Maximum 24-hour Average (Nm3) Particulate matter 50mg/Nm3

Nitrogen oxides 2000mg/Nm3 provided the ambient maximum is below 150 mg/m3 for a 24-hour average

Sulphur dioxide 0.2 tons per day per MWe Capacity 1.e. 4 tonnes per day for 20MW with maximum concentration of 2000mg/Nm3

Source: Emission Standards for new Thermal Power Plants; World Bank Industry Sector Guidelines Nitrous Oxide (N2O) Emissions Emissions of N2O are minor and the uncertainty is high in fuel combustion. Reliable emission factors are not yet available for all sources.

Page 62: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

62

According to the tender documents provided to the contractor, the maximum NOx, SO2 must be no more than a maximum of 2000mg/Nm3. This is the calculated emission limit that is internationally recommended to ensure that the emissions do not adversely affect the atmosphere. The contractor will undertake testing of the engines during commissioning to determine if these standards are met. The plant engines will be designed to ensure that the international emission standards for emissions are complied with. Sulphur Dioxide (SO2) Emissions This is a dual fuel plant that uses ordinary diesel for starting up the generators and then as soon as the generators pick up, a switch to HFO is made. In the same way, during shut down of the engines, a switch is made from HFO to ordinary diesel oil. Sulphur Dioxide emissions depend on sulphur content of the fuel. For fuel oil (including heavy fuel oil) sulphur content varies from 0.3 to over 5 per cent. Lighter products may contain minimal sulphur (<0.3 per cent), whilst heavy fuel oil can contain from up to 3-5 per cent sulphur. Currently the world average sulphur content of crude oil is around 1.3 per cent, although there are considerable variations between different sources (Vernon and Jones, 1993). Sulphur content in diesel oil produced today contains at most 50, in respect 10 mg/kg. SO2 emission factor for diesel is approximately 0.05. Generally, all sulphur content present in the fuel is converted to SO2. Therefore, the pollution load (SO2) for the generation plant per week will be as follows. Pollution load = emission factor x fuel consumption = 0.005 x 2000 litres This is equal to 10 kg/week. This translates to 59.5g/hr, against the World Bank standard limits of 125(g) as stated in table above. According to the tender documents provided to the contractor, the maximum NOx, SO2 must be no more than a maximum of 2000mg/Nm3. This is the calculated emission limit that is internationally recommended to ensure that the emissions adversely affect the atmosphere. The plant engines will be designed to ensure that the international emission standards for emissions are complied with. Below are details of the sulphur content in HFO available in Kigali. In order to meet the sulfur dioxide standards of 4 tons per day and a maximum concentration of 2000 mg/Nm3, given the available fuel quality, the diesel generators will be fitted with filters to ensure reduction of flue gas emission. The tender documents provided to the contractors clearly specified the quality of oil and the sulphur content expected to be met. Test Test methods Units Value

Viscosity at 50°C ASTMD 445 mm2/s 180 Pour point ASTM D 97 °C Max 24 Density 20°C ASTM D 1298 Kg/m3 Max 985 Flash Point PMCC ASTM D 93 °C Min 66 Net Calorific Value ASTM D 2382 MJ/kg Min 41.1 Water content ASTM D 95 % Volume Max 0.75

Page 63: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

63

Sediment ASTM D 473 % mass Max 0.15 Ash content ASTM D 482 % mass Max 0.08 Conradson carbon Residue ASTM D189 % mass Max 12 Asphaltenes IP 143 % mass Max 10 Surphur content ASTM D 4294 % mass Max 3% Strong Acid N0 ASTM 974 Nil 139 Aluminum + silicon content ASTM D 5184 PPM Max 80 Source; MININFRA and Tender Documents Nitrogen Dioxide (NO2) Emissions The major source of NOX is the high temperature combination of atmospheric nitrogen and oxygen, in combustion processes, there being also a lesser contribution from combustion of nitrogen contained in fuels. Mitigation The plant engines will be designed to ensure that the international emission standards for emissions are complied with. During the performance test period measurement and recording, emission levels at the property will be measured and monitored according IEC-651 & 804 class 2. The contractor will measure and record the following to determine the level to which they comply with the international standards.

1. NOx emission according to ISO 10849. 2. SO2 emissions according to ISO 7935. 3. Particular matters according to ISO 9096.

In order to determine the ambient air emissions samples were undertaken around the project site and then analysed and the results are in the tables below. Ambient air emissions for nitrogen dioxide around the project site

Project surrounding Maximum 24-hour Average

(µg/m³)

Samples collected around sugar factory and Jabana substation

186 (as NOx)(f)

Ambient air emissions for sulphur dioxide around the project site

Project surrounding Maximum 24-hour Average

(µg/m³)

Samples collected around sugar factory and Jabana substation

198(h)

The results show that the ambient emissions for nitrogen and sulphur dioxide in the project area are above the maximum average over a 24 hour period recommended by World Bank.

Page 64: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

64

The mean PM10 values obtained in this study were observed to be 239 ±126 µg m-3 with a range of 66.7 to 444.5 µg m-3. The levels are higher than the recommended WHO guidelines; in some cases up to over 150 % or even higher (WHO, 1999). Creation of Natural Buffer Zone The project should also plant trees all around the perimeter wall to act as a buffer zone as well as mitigation measure to act as carbon sinks by filtering the resultant gaseous emissions from the power plant. Tree planting is part of the carbon offsets approach and is expected to be a long term mitigation measure. Noise Pollution Noise pollution from the operation of the generators is inevitable during the night and day periods. Even though ambient noise levels at the time of the study was not conducted on receptors at the edges of the property boundary and on an average hourly basis, as defined in the World Bank guidelines, noise impacts is not expected to be high outside the site boundary as the generators are containerized in sound proof walls and have installed silencers. The Contractor shall state the noise level of the radiator coolers in dB(A) in 500 meter distance at full radiator load. These engines will be designed internationally to ensure that within the plant boundary the emission level must be ranging from 60-65 decibels. The bank’s maximum limit in industrial and residential areas is specified in table below for day and night. The project site and surrounding can be classified as a mixture of industrial, agro based, commercial and residential/institutional. A total of 7 houses that can be observed in the project surrounding and they are approximately between 50-1000 metres away from the plant. According to the World Bank maximum noise level as shown in table below, in residential areas a level of 55dB and 45dB is allowed for day and night and 70dB for industrial or commercial areas. Since the project area is a mix of different zones, this project considers residential/institutional as the standard of consideration. Outside of the plant boundary, 3 houses are within a distance of 50 metres and the residents could possible be adversely impacted by the generator noise since. Even though out of the plant boundary the noise emitted will be 60-65dBA, these engines have been designed to emit no more than 70dBA at a distance of 10m from the plant boundary. Since the first house closest to the plant boundary is 50 metres away, these households should not be affected but this is subject to verification if indeed the plant specifications for noise are correct. For this reason upon commissioning the contractor has signed a clause requiring testing of noise at full load capacity form different distances up to 500metres. Further more each diesel engine shall be provided with one exhaust silencer and the design will provide the required sound attenuation to meet the outside noise level requirements with minimum pressure loss. The silencer and the exhaust gas piping shall be provided with condensation drain traps at low points. World Bank Maximum Noise Levels Location/Zone Day Night Residential, educational or institutional area 55 dB(A) 45 dB(A) Industrial or 70 dB(A) 70 dB(A) Commercial area However to ensure that the engines are actually meeting the required noise levels as stated above, during the commissioning of the power plant, noise level tests will be conducted in the following manner to confirm the levels at different distances as specified in the tender contract documents;

Page 65: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

65

• Maximum noise level inside the machine room with all DGU's running at 100% load. All measurements at 1 m distance of each DGU.

• Maximum noise level outdoor with all DGU's running at 100% load. All measurements at 500 m distance of the noise source, e.g. air openings at machine room, exhaust outlet, etc.

• Maximum noise level inside Plant Control Room and Associated Rooms with all DGU's running at 100% load. All measurements within the respective rooms at 1 m above floor level (Above mentioned values shall be guaranteed by the Contractor. The guaranteed figures all necessary tolerances for accuracy of testing, shall include all sampling, instrumentation, notwithstanding the performance test code standard. No further tolerances of any kind shall be permitted.

Mitigation

• The generators as described have industrial and marine silencer preinstalled. The noise levels thus will not exceed maximum noise levels prescribed for industrial area as shown above in table above. This is because the generators have been designed internationally not to exceed the stated limits.

• For the workers who will be working in the plant, will require to have ear muffs to prevent damaging

the ears.

• The equipment will be designed and enclosed in an acoustic enclosure to limit noise to 85 decibels inside of the plant. Workers in close proximity to this equipment would be required to use hearing protection. Off-site noise would not exceed 70 dB (A) because the engines have been designed and built in such a way that the maximum noise level at the plant boundary does not exceed 65 decibels.

• All equipment and machinery installed MUST and will be tested to verify if they are compliant with

the World Bank acceptable standards of noise as contained in the World Bank PPAH 1998. The tested noise levels should be recorded as baseline and used for future monitoring.

• All workers in the project site must be equipped with the necessary and required Personal

Protective Equipment (PPE) prescribed by the construction industry but not limited to facilities to protect against noise impacts, hearing protection etc.

• Personal protection gear will be provided and its use made compulsory to all. The entire workforce

of the plant should be trained in the use of protective gear to handle noise impacts.

• Noise monitoring will be conducted every 1 month upon commissioning for one year and the periodically after every 4 months through out the project life or whenever complaints are made related to noise pollution.

• The project should also plant trees all around the perimeter wall to act as a noise buffer zone and

in effect serve to reduce the noise impact from the power plant. The planting of trees as a noise attenuating measure is regarded as a long term mitigation measure.

• During the performance test period measurement and recording of noise levels at the boundary of the property will be measured and monitored according IEC-651 & 804 class 2.

Page 66: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

66

Oil spills Occurrences Oil spills could occur during the transport, unloading and transfer of the fuel to on-site storage and could contaminate the existing soil resources and the nearby Nyabugogo River. Even though the river is 1.2km away from the project site this impact cannot be overlooked. Mitigation

• Need to design appropriate protection devices against accidental discharge of toxic substances (bases/air-tight tanks for machines, reservoirs etc.).

• Storage and liquid impoundment areas for fuels, raw and in-process material solvents, wastes and

finished products should be designed with secondary containment (e.g. dikes) to prevent spills and the contamination of soil, ground and surface water. The secondary containment dikes will be used through out the life of the project mainly to offer secondary spill protection and avoid contamination.

• All the fuel storage tanks should have secondary containment with sufficient volume to contain a

spill from the largest tank in the containment structure. The containment area should have a means of removing accumulated water.

• A spill and emergency response plan would be developed and put in place prior to commencement

of construction. (Annex D contains a draft response plan that has been developed for further refinement by the UERP).

• Frequent inspection and maintenance of facility

Wastewater/Oily water discharge and treatment Waste water and oily water discharge emanating from the power plant will be separated and the separated or treated water will be channelled to the existing storm water drain because it is not hazardous. Mitigation

• The wastewater discharge will be designed to comply with World Bank standards. • The overall design shall aim at collecting the sludge from the whole power plant and then

pump/drain the same into a sludge tank for unloading the same on to sludge trucks for further application in the road construction industry as asphalt or for firing boilers in factories. As stated earlier, the sludge will be used as asphalt for road construction or for firing boilers in factories. It is estimated that approximately 400 litres of sludge will be produced monthly if the plant is operating at 60-100% load. The sludge will be collected in drums and stored for further collection by road contractors or factories contracted by ELECTROGAZ.

• Testing of samples of the waste water before they are channelled into the storm water drainage for

presence of oil residue will be undertaken every time that HFO/water separation occurs in the oily water separation tank.

• All the used oil from the engines especially when the engines are serviced and the used oil is

drained will be recycled. As a general rule the supplier of the oil will also collect the used oil. Used oil is generally used in curing electricity poles but it will be up to the contractor hired to collect the used oil to decide how to recycle. In other ELECTROGAZ plants for example, Total is the company contracted to supply diesel and other lubricants. They provide the oil and lubricants in

Page 67: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

67

drums and also collect the used oil for recycling. This is the same model that will be used in this new plant.

Solid waste pollution and littering Solid wastes generated from the operation of the plant will include used engine oil filters, oil lubricant packaging material, engine coolant containers as well as domestic wastes that will emanate from the staff housing units. Mitigation

• Contractor should develop a solid waste disposal plan which includes the provision of receptacles at strategic points within the construction site, recycling programmes for recyclable wastes, separation of wastes.

• The contractor should engage a refuse handling company to remove the wastes from the site to

the recommended dumping site within Kigali city

• Warning signs against littering and dumping within and around the construction site should be erected by the contactor.

Accidents at the work place from operating of machineries and equipment by workers The potential for accidents and hazards occurring in the diesel power plant during the operation of the equipment and machinery is a likely adverse impact that could lead to loss of life or injury to the workers. Mitigation

• All workers entering the construction site must be equipped with PPE including goggle, factory boots, overalls, gloves, dust masks, among others. The PPE should be those that meeting the international standards of PPE.

• Personal protection gear will be provided and its use made compulsory to all. The entire workforce

of the plant should be trained in the use of protective gear, handling of chemical products and acid storage cells, electric safety equipment, procedures for entering enclosed areas, fire protection and prevention, emergency response and care procedures.

• Training given to the employees should be backed by regular on- site training in safety measures.

• No ENTRY signs should be installed to keep away unauthorised workers from accessing the

restricted areas.

• Machines and Equipments must be operated only by qualified staff and a site supervisor should be on site at all times to ensure adherence.

• The contactor must develop a workers Health and Safety Manual for which all the workers should

be conversant with for response in case of accidents.

• The contractor should develop an Emergency Response Plan for handling any emergencies arising thereof during the operation.

Page 68: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

68

Fire risk and accidental discharge of products Heavy fuel used by the plant has a relatively low fire or explosion risk however the risk of fire outbreaks in the diesel power plant cannot be overlooked. Mitigation

• The diesel engines should be fitted with a vapor monitor and a toxic vapor ignition monitoring system.

• A robust fire prevention program and fire suppression system should be developed by the

contactor. (A draft fire suppression plan is attached as annex D but needs further refinement by ELECTROGAZ who must carry out a vulnerability assessment before developing a final suppression program). It is suggested here that the proposed diesel power plant borrow the existing fire prevention program that is being used by ELECTROGAZ in other energy stations.

• The site must contain fire fighting equipments of recommended standards and in key strategic

points all over the site. Fire hydrants, sprinkler/water spray systems, dry chemical systems, carbon dioxide systems, detection/alarm systems, foam and portable fire extinguishers are all included in the tender documents as necessary fire suppression equipments that must be in the plant as part of the elaborate fire fighting system.

• Staff should be trained in fire emergency procedures and refresher drills organised after every 6

months by the contractor, ELECTROGAZ and jointly with the Kigali Fire Department if this department will be available.

• A fire evacuation plan must be posted in various points of the construction site including

procedures to take when a fire is reported. CFCs Emissions from the Central cooling systems likely to exacerbate the Green House Effect The presence of CFCs from the central cooling system of the diesel power plant is likely to increase the GHGs effect in the atmosphere thereby contributing to some level of global warming. Mitigation

• Processes, equipment and central cooling systems involving the potential release to the environment of CFCs will not be installed. The central cooling system is a closed circuit and does not use any CFCs.

Micro-climate The operation of the diesel power plant in the site is likely to modify the micro-climate of the area due to heat and air pollution from flue gas, dust and noise. There is need to conduct further studies around the area to determine the project impacts on the micro climate. The plant life is estimated to be about 30 years in the absence of malfunctions etc. However, it is not the intention of the MININFRA to have the plant working full time through out the project life span. MININFRA intends to stop using the diesel power plant once the energy crisis is resolved upon which the diesel plant will be shut down and only used as during emergency. Water Resources Water from the main ELECTROGAZ network will be used for cooling the diesel power plant. The power plant requires 200 litres of water to cool the engines per day. An initial 55,000 litres is needed as the base capacity of the cooling tank where after, 700 litres will be used per day.

Page 69: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

69

Water for use in this plant will come from Yanze pumping plant which supplies 30 million litres per day and hence the abstraction of 55,000 at once and 700 litres per day is insignificant in terms of impacting on other water users. This is not the only water source for Kigali city which has other 5 pumping stations for water capable of supporting the city. The system will constitute a back in itself this means that only 200 litres of water will be used daily. The 55,000 litres in the tank is the back up. Visual Impacts During operation of the plant might present unwanted visual impacts, both by its physical presence and profile against the surrounding area, and by visual impacts of the plume (particularly during periods of poor atmospheric dispersion) and secondary formation of aerosols that can reduce visibility. Large structures such as stacks and fuel tanks towers may also adversely impact the visual quality of the area. Mitigation

• Mitigation against visual impact can be through landscaping the area with trees to screen the project stacks and fuel tanks. This is the reason ELECTROGAZ acquired a bigger parcel of land and did not develop the entire section but instead left these sections with eucalyptus trees to reduce the visual impacts.

• The plant chimneys are 30m high and have been designed according to the requirements of the

International Pollution Centre in such a way to reduce plume hence the plume effect will be negligible. At a height of 30m it is a guarantee that the plume will be dispersed higher up in the atmosphere hence minimizing the visual impacts associated with plume.

Encroachment Illegal and unauthorized access to the power plant during its operation stage can lead to accidents and hazards. Mitigation The UERP should fence the entire project site using a high perimeter wall in order to avoid unauthorized access to the site.

7.2.3 Project Decommissioning The power plant has a life span of over 30 years for as long as the plant equipment and associated infrastructure is well maintained. The plant may be decommissioned after its life span or if the government decides to close down the plant for any other reason for that matter. The decommissioning plan will be prepared by ELECTROGAZ who will upon project commissioning take ownership and responsibility for operating the plant from the contractor. The cost of decommissioning including implementation of the decommissioning plan will be met by the client in this case ELECTROGAZ as clearly stipulated by REMA in the EIA guidelines and thus in this case ELECTROGAZ will be responsible for decommissioning the project. Decommissioning of the plant will involve shutting down the generators, removing the generators from site, dismantling the supporting infrastructure including fuel tanks, cables and all those structures that were not on site before the project implementation.

Page 70: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

70

Some of the impacts of this project phase are similar to those that have been discussed during construction and operational phase. But there are those impacts that are specific to project decommissioning after the project life is over. During this phase, there is a possibility of leftover oil spilling when the handling structures, pipes and generators are dismantled. After the project decommissioning, the proponent will be required to rehabilitate the site to its former status or near what it was before the project was commissioned. The client in this case ELECTROGAZ is expected to prepare a decommissioning plan if and when it will intend to decommission this facility. This plan must be submitted to REMA for approval before activities for decommissioning are undertaken. As per the regulations of REMA the proponent will bear the costs for decommissioning and site rehabilitation.

Page 71: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

71

PUBLIC DISCLOSURE AND CONSULTATION PROCEDURE Public consultation and dialogue was held during the study with the following persons with an aim of ensuring that the stakeholder views and comments are used to inform the decision making and guide the study in terms of scope. They include:

8.1 List of people met • Mrs. HAJABAKIGA Patricia: Secretary of state in the MINITERE • MASHINGA Theobald: Director Compliance of REMA • Claudine NYINAWAGAGA Mayor of Gasabo District • GAKUBA Felix : Project Manager/Coordinator of the UERP • Jean Pierre Mutsinzi Past UERP/PCU Manager • Mr Kimenyi, Executive Secretary of Jabana Sector • Mr Hussen Technician from Gasabo District • KANYAMUHANDA Jean: Responsible of the Development of the sector of

Transportation in the MININFRA

• Mr Charles KANYAMIHIGO Director of Electricity Department/ELECTROGAZ • Ms.Jeanne-Isabelle GASANA Financial Manager/UERP-PCU • Mr Gérase NGIRABABYEYI Procurement Officer/UERP-PCU • Mr. Kimenyi Burakari Onesmu Executive Secretary of Jabana Sector • Mr. Elroy Pankratz Word of Life • Mr. SHEMA G. Charles Legal adviser of Word of Life • Mr. Ntagora Emmanuel Pastor of Word of Life Jabana • Mr. Nshimiyimana Stephen Assistant Pastor of Word of Life • Mr. Muhorane Alain Accountant of Home of Hope Rwanda • Kabaka Francois Regis Land Owner • NYIRAZUBA Flavia Land Owner • NDAHIRO Emmanuel Land Owner • INEMWENYEWE Jean Bosco Land Owner • CORIKA Cooperative Land Owner • Rwanda Chicken Land Owner • Jabana sector Land Owner • Jyambere Munyarwanda cooperative Land Owner • Pope Charles Land Owner • Nshimiyimana Pope Land Owner • Venuti Rose Land Owner

There have been a series of several meetings held during the month of August and September 2007 to consult with the following stakeholders namely:

Page 72: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

72

• Word of Life the umbrella institution in charge of Home of Hope Rwanda • Officials and administration personnel from the Jabana sector • Rwanda Environment Management Authority staff • Officials from Gasabo District • PAPs-Land Owners

Annex 1 of the report contains minutes of meetings held to discuss the issues of land acquisition for the construction of the plant.

Photo showing UERP/PCU staff with the local residents engaged in discussion over land acquisition. The table below shows the issues raised and responses provided to the PAP during the month of August-September 2007. PAP Issue Raised Response

Would like to be compensated for the 500 USD they paid initially for surveying the land during the purchase from the initial land owners

UERP accepted to pay this as part of the compensation

Would like assistance in identification of another land for construction of the church

UERP accepted to assist in identification of another piece of land.

Home of Home Rwanda Date of meeting; 11th September Venue of Meeting; Electorogaz Office Also refer to the minutes of the meeting attached in the annex A section of this report.

Would like to get access to the electricity and water when the construction is complete

UERP accepted to honour this request

INEMWENYEWE Jean Bosco. Meeting held on 5th and 19th September at the home of PAP.

Was dissatisfied with the results of land measurements undertaken by the government officials

UERP requested him to engage an independent surveyor to confirm his doubts with the survey fee paid by UERP.

Page 73: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

73

REMA Several meetings held with REMA staff in August and September at the project site and at REMA office

Possible pollution of Nyabugogo River through spills. Close proximity of the initial site to the Nyabugogo wetland

UERP has prepared an emergency response and spill plan for containment in the EMP UERP relocated the plant from the original site to the new project site

Kabaka Francois Regis-Land Owner Nyarizuba Flavia-Land owner Ndahiro Emmanuel-Land owner -Meetings held several times with all these PAPs in August and September

These PAPs did not raise any issues. They were only concerned and wanted to know when they would be compensated.

UERP promised to fully compensate them once the measurements and valuation of assets was finalised.

Page 74: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

74

ENVIRONMENTAL MANAGEMENT PLAN FOR 20 MW DIESEL POWER PLANT This Environmental Management Plan (EMP) has been developed for this project and will be implemented by the consulting contracted company and ELECTROGAZ. The EMP defines the measures needed to prevent, minimize, mitigate, or compensate for adverse impacts, improve environmental performance and ensure compliance with applicable safeguard policies, and these are being incorporated in the proposed project. The recommendations for main environmental mitigation measures are summarized in the EMP document. This EMP defines the measures needed to prevent, minimize, mitigate, or compensate for adverse impacts, and to improve environmental performance while ensuring compliance with applicable environmental standards during the planning and design phase, construction and operation and eventual decommissioning of the plant. The recommendations for main environmental mitigation measures include waste management and disposal planning, noise and air abatement measures, emergency and oil spill response planning as well as the purchase of necessary response equipment. These mitigation measures are being incorporated in the project design and are already included in the tender documents for procurement of the equipments.

From the on set the Safeguards Advisor (EA) would like to recommend that before the construction works begin, there is every need for assessments to be done to ascertain the ambient air quality of the project site and the noise levels including the water quality of the irrigation canal. This vital information is imperative if effective monitoring of compliance is to be achieved because they will set the baseline situation.

At the time of the initial preparation of this report, the ambient baseline analysis in terms of air and water had not been undertaken. However, these have now been conducted and they are as follows;

Water quality tests on the Nyabugogo River were taken from different points and the samples were analyzed in a laboratory where a full chemical analysis was conducted. The results are as follows;

Mean measured values of physical water quality parameters at various sampling points. Mean concentration values Sampling point Q (m3 s-1)

TSS (mg l-1)

COND (㎲ cm-1)

TDS (mg l-1)

TUR (NTU)

A B C D E

0.772 1.376 2.140 5.083 5.341

157.6 129.4 255.7 199.2 95.5

392.1 397.7 564.5 509.5 474.8

239.7 244.2 290.9 310.9 298.8

69.4 69.3 65.5 67.8 28.5

Page 75: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

75

Variability of toxic and organic substances at different sampling stations and river basins.

Mean concentrations per sampling station and river basin Parameter A B C D E

Fe (mg l-1) 1.99 1.59 1.3 1.44 0.60 Mg (mg l-1) 8.4 9.6 7.8 7.2 4.4 Na (mg l-1) 59 45.8 69.5 46.6 42.5 Cl (mg l-1) 47 38.8 46.3 39.5 29 F (mg l-1) 0.8 0.6 1.1 0.6 1.17 BOD5 (mg l-1) 143.3 59.5 82.8 COD (mg l-1) 301.3 266.2 253.1 TSS (mg l-1) 298.5 180.5 244.6 COND(㎲ cm-1) 558.2 605.9 459.0

TDS (mg l-1) 337.5 375.4 282.3 Source: Field data It was not possible to undertake ambient noise levels due to lack of instruments in Kigali but before the commissioning of the plant UERP plans to procure a noise meter which will be used to undertake the tests. The noise meter will also be used to conduct initial tests to the engines at different distances to verify the noise levels. The contractor has also been mandated to conduct noise tests up to a distance of 500m along the plant boundary upon commissioning at full load to determine the noise impacts with respect to World Bank standards. Ambient air quality test was also undertaken at different points within the plant site using the passive approach. The parameters that were analyzed and results are shown below; Ambient air emissions for nitrogen dioxide around the project site

Project surrounding Maximum 24-hour Average

(µg/m³)

Samples collected around sugar factory and Jabana substation

186 (as NOx)(f)

Ambient air emissions for sulphur dioxide around the project site

Project surrounding Maximum 24-hour Average

(µg/m³)

Samples collected around sugar factory and Jabana substation

198(h)

Relevant World Bank standards included in this report are for noise levels at the plant perimeter, effluent standards and ambient air quality around the plant for which the new plant must comply with. These guidelines and requirements have also been included in the tender documents and remain the specifications for which the bidding contractors should embrace when responding to the expression of interest. Prior to accepting the diesel engines and the associated infrastructure, mandatory testing as stipulated in the tender documents will be undertaken to verify and confirm whether or not the equipments comply with the World

Page 76: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

76

Bank regulations. Environmental testing will seek to verify the noise and emission qualities of the equipments among others. In order to develop institutional capacity in implementing and enforcing the EMP, training should be provided with adequate budgets to ensure satisfactory achievement of sound environmental performance. The training proposed here should include capacity building and training in environmental assessment, environmental mitigation plans, and environmental monitoring for the ELECTROGAZ staff. In some cases, it may be appropriate to include the staff from the environmental implementation agencies, such as the pollution control board, REMA, and other relevant ministries involved in the implementation of the UERP. Training and capacity building will be vital in implementing the EMP especially ELECTROGAZ staff who will be responsible for primarily ensuring that mitigation and monitoring of the key activities are followed. The proposed training will target relevant UERP, ELECTROGAZ, REMA, RURA and MININFRA staff and will entail training in monitoring and evaluation, impact mitigation and internal self environmental audit. Development of internal tracking/monitoring system The Environmental Advisor is in the process of developing a participatory computer based monitoring and tracking sheet that will be used to monitor the mitigation of the adverse impacts of the project. The tracking sheet will use Microsoft Access program application and upon its completion, all the UERP/PCU and its implementing agencies will be trained on how to use this tool to monitor compliance. Responsibility of Institutions in Implementing the EMP The company that will be awarded the contract to construct and install the diesel power plant will remain the key responsible institution for undertaking the mitigation measures proposed as well as the monitoring activities/measures associated with this mitigation plan. The other institutions mainly ELECTROGAZ, REMA, UERP/PCU, Ministry of Agriculture (MINAGRI) etc. will be solely involved in supporting the monitoring to ensure compliance. Upon successful installation, commissioning and handing over of the plant to ELECTROGAZ by the contractor, ELECTROGAZ shall henceforth become the sole and lead institution responsible for ensuring proper mitigation measures and monitoring as indicated in the EMP document is followed. However the contractor will provide one technical advisor for a period of one year to provide capacity building support in all the related management and maintenance field. Specifically in Monitoring and Evaluation the following institutions will play the following roles namely; Role of Rwanda Environment Management Authority (REMA): Oversight Monitoring As the lead agency responsible for the protection of environment in Rwanda, REMA will play the leading oversight role of monitoring the activities of the project according to the Organic Law establishing REMA and its functions. Site Inspection Visits REMA will undertake regular site visits to inspect and verify for themselves the nature and extent of the impacts. REMA will undertake also undertake regular site visits to inspect and verify for themselves the extent to which the mitigation measures proposed in this EMP are being complied with or vice versa. They will then be expected to make viable recommendations based on their findings to the EA and ELECTROGAZ.

Page 77: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

77

REMA is designated to undertake site inspection visits at will and at any time as stipulated for by the Organic law. During the construction phase, REMA will be making monthly site visits to assess the progress and compliance to the EMP. During the operation phase, the site visits by REMA will be determined by the available staff capacity in REMA. Presently, REMA has allocated one of its staff to provide support to the project on a full time basis. Periodic Reports REMA will prepare periodic environmental consolidated reports on their analysis of the compliance progress of the construction of the power plant. REMA will submit these reports at its own discretion to whoever is specified in the Organic Law. Role of the Contractor Daily and Routine Monitoring The company/firm that will be awarded the contract to install the diesel power plant will undertake the major role of ensuring the mitigation measures in the EMP are followed to the detail. During construction the contactor will undertake regular monitoring of all the activities occurring in the project site to ensure compliance to the EMP. The contactor will bear all the costs related to monitoring activities during the construction and installation phase of the diesel power plant. Role of the Safeguards Advisor/UERP The UERP/PCU assisted by the Safeguards Advisor will undertake regular monitoring of all their planned activities during all the phases of the project as specified in the EMP document. The Safeguards Advisor will assist the UERP/PCU to develop suitable records of the site inspections and visits for submission to REMA and the World Bank. This will involve efforts towards building the capacity of the UERP/PCU towards this end as well. The Safeguards Advisor will also be responsible for assisting in building capacity of the UERP/PCU in monitoring the impacts and mitigation measures resulting from the action of the contractors, transporters and suppliers and all third parties in the course of their duties under the project. Kigali Fire Brigade Site Inspection During the construction and installation of equipments in the project area, the Kigali Fire Brigade which is the agency responsible for fire management in the City Kigali will undertake site inspection to verify if a fire management plan is in place before construction works begin. Thereafter upon commissioning of the project, this agency will further ascertain that the correct fire management equipments as stipulated in the fire response plan are in place and in the right points. Fire Drills The EMP provides for regular fire drills preferably twice annually. The overall objective is to ensure that there is a high level of preparedness against fire outbreaks at all times. ELECTROGAZ will arrange for its own fire drills and will engage the Kigali Fire Brigade depending on their availability.

Page 78: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

78

World Bank Approval The World Bank will provide approval to the final EMP and RAP for the power plant developed before construction activities begin. This approval will only be given if the World Bank is satisfied with the EMPs and RAPs developed. Role of ELECTROGAZ Routine Monitoring ELECTROGAZ will provide routine monitoring at all the stages of the project implementation as indicated in the EMP. More specifically during the operation phase of the plant, ELECTROGAZ will be the main responsible institution for undertaking all the mitigation and monitoring requirements in the EMP. Monitoring Equipment (s) Needed by ELECTROGAZ The UERP PCU will purchase two equipments that are necessary for monitoring of air emissions and noise levels at the Jabana plant and which will be used by ELECTROGAZ for regular monitoring of the same. The Annex C section of this report contains the specifications of these equipments whilst the EMP highlights the costs of the same equipment. Emission Measurement Equipment In order to undertake the emission levels at the regular intervals specified in the EMP, instruments for measuring emissions of the gaseous must be purchased and used by the ELECTROGAZ site managers at the plant. The UERP/PCU will purchase this equipment which will be at the plant for regular use and upon the end of the UERP this equipment will remain the property of ELECTROGAZ. Noise Measurement Equipment In order to undertake the noise levels at the regular intervals specified in the EMP, instruments for measuring noise levels must be purchased and used by the ELECTROGAZ site managers at the plant. The UERP/PCU will purchase this equipment which will be at the diesel plant for regular use and upon the end of the UERP this equipment will remain the property of ELECTROGAZ. Effluent Measurement In order to undertake the effluent release levels at the regular intervals specified in the EMP, the relevant ELECTROGAZ staff at the plant will collect water samples at regular intervals as specified in the EMP and submit for testing at accredited laboratories in Kigali for testing and results. The UERP/PCU will meet the cost of testing for effluent until the life of the project and thereafter, ELECTROGAZ will be expected to take samples to the laboratory for testing at its own cost. Clarification of responsibilities related to monitoring Contractor The contracted company will be solely responsible for ensuring that monitoring and adherence to the EMP beginning from the construction phase up to the point where they install the plant and it is commissioned. Thereafter there responsibility to the project monitoring ceases henceforth. However, the contractor will for a period of one year provide one technical person to provide capacity building support in all the related management and maintenance field. UERP/PCU

Page 79: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

79

The UERP PCU will provide oversight monitoring of the project in accordance with the EMP up until the 4 year life span of the project. Upon the end of the project duration, the UERP PCU will no longer be responsible for any monitoring activities associated with the project thereafter. ELECTROGAZ ELECTROGAZ will remain the sole institution that will fundamentally be responsible for undertaking monitoring through out the project phase, when the contactor hands over the project and also after the UERP PCU winds up as a project. ELECTROGAZ will be expected to ensure monitoring through out the project phase until if it gets decommissioned. Complaints from PAPs During the construction phase of the project complaints from PAPs on any adverse impacts will be directed to the plant manager. However, as required by the Organic Act, the local population needs to be made aware of the fact that they can raise their complaints to REMA which is the institution that can enforce environmental regulations. For that matter REMA needs to up its communication and awareness strategy so that the population is conversant with who they can lodge their complaints. EMP Responsibility and Costs The table below is the Environmental Management Plan for mitigating the project’s potential adverse impacts. The principal responsible actors in implementing the EMP at each stage have been highlighted in red and underlined and the rest of the actors provide oversight support.

• Specifically during the design phase of the project, the responsibility of implementation will lie with UERP and ELECTROGAZ. During the construction phase, the contractor and ELECTROGAZ will be responsible fully for implementing the mitigation in the EMP. At the operation and decommissioning phase, ELECTROGAZ will be solely responsible for implementing the EMP.

• In terms of cost of implementation, the resettlement and compensation costs will be met by UERP

and are reflected in the ARAP.

• Mitigation costs at the construction phase cannot be quantified in the EMP because they are in built in the overall bidding cost by the contractor. The contractor is going to meet all the costs related to construction related impacts.

• Costs for mitigating potential impacts at the operation and decommissioning phase will be met by

ELECTROGAZ.

• ** In the EMP table the principal responsible party for each mitigation is underlined. However, in any EMP no single party has overall mandate over mitigation and monitoring. The rest of the parties mentioned will be responsible for undertaking oversight monitoring and enforcement as is the case with REMA and this is why they have all been included**.

Page 80: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

PLANNING AND DESIGN PHASE Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators Implementation

Schedule Responsible

Person(s) Cost Estimates

Ensure that the land identified for the project is acquired as per the requirements of the Government of Rwanda and World Bank guidelines in relation to land acquisition, resettlement and compensation.

Evidence of records showing stakeholder engagement and consultation of PAPs e.g. Minutes of meetings

Involve and meaningfully engage the PAPs, general public including administration, and local/traditional leaders in the transparent acquisition of the land.

Land Acquisition Conflict over land acquisition, ownership and compensation Dispute and possible conflict over the land identified can arise owing to forced eviction, and absence of compensation and dialogue with the PAPs.

Utilize the RPF document available and develop RAP to be used in acquisition of the land.

Availability of Compensation Action Plan document approved by World Bank and REMA.

Before Construction works begin

UERP/PCU Safeguards Advisor

ELECTROGAZ REMA

Costs are reflected in the RAP and will be met by ELECTROGAZ

Do not select sites that trigger any of the World Bank’s Operational policies on: Natural Habitats; Forestry; Cultural Property.

Review the screening checklist and EMSF to verify whether any OP is triggered

Do not select land that contravenes the regulations of the Government of Rwanda in relation to natural resources and sensitive ecosystems

Do not select land that will trigger concerns in relation to international convention on environment and natural resources.

Site Selection Inappropriate/incompatible site selected. Poor selection of project site for the plant can cause conflict over environmental degradation including the destruction of sensitive ecosystems and or protected areas

Undertake detailed EIA study on selected site

Before Construction works begin (Already performed Task)

ELECTROGAZ Safeguards Advisor

UERP/PCU REMA

World Bank

No costs involved

Plan Designs Ensure during planning and design to incorporate

environmental sound design concepts as appropriate. Review tender documents to ascertain clauses on environmental specifications

Before Construction works begin

Safeguards Advisor UERP/PCU

No costs involved

Page 81: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

81

Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators Implementation Schedule

Responsible Person(s) Cost Estimates

All designs, equipment and machineries to be procured should include instructions on their environmental specifications and requirements.

Poor designs of plans, inadequate equipment and machinery specification Inadequate and poor designs and plans including equipments and machinery can possibly cause environmental degradation.

All instructions or planning for civil, mechanical, engineering and electrical specifications including technical specifications must have stringent environmental obligations in accordance with the World Bank guidelines, international or local guidelines whichever emerges as stringent in terms of environmental and social requirements.

Review tender documents to ascertain inclusion of World Bank conditions on environmental specifications.

Before Tender is advertised and Tender Documents dispatched to selected bidders (Already performed Task)

ELECTROGAZ UERP/PCU

No Costs incurred

Page 82: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

82

CONSTRUCTION PHASE ON AND OFF SITE

Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators

Implementation Schedule

Responsible Person(s) Cost Estimates

Vegetation cover available that will be destroyed should be replaced by landscaping and replanting of trees and grass when construction is complete.

Number of trees and grass replanted, landscaping undertaken.

While few trees could be affected by the site work, no trees should be cut that do not interfere with the site work, and any cleared wood should be made available to local residents.

The final site grade should facilitate drainage and avoid flooding and pooling. A site drainage plan should be developed to protect against erosion. Protecting stockpiles through the use of silt fencing and reduced slope angles should be used to minimize soil erosion during construction.

Installation of drainage ditches, construction of runoff and retention ponds is necessary. Minimization of disturbances and scarification of the surface should be observed to reduce erosion impacts.

Borrow areas (if any) should avoid agricultural areas; borrow areas should be reworked to blend into the surroundings. Re-vegetation should be performed using local plants. All slopes and working surfaces should be returned to a stable condition.

Existence of a drainage system including ditches and run off detention ponds.

During the construction and to continue after completion of construction

Safeguards Advisor

UERP/PCU CONTRACTOR

REMA ELECTROGAZ

To be met by the contactor. The actual cost will be reflected by tenders in the financial proposal which includes this component

Civil Works Removal/destruction of all vegetation from the project site./Site Clearing/Civil Works/Earth Moving

Site earthworks activities include, but not limited to, site preparation, clearing, stripping, grading, soil removal, backfilling, compacting, disposal of surplus, landscaping, shoring as required and final site clean-up.

Topsoil on the final site would be graded and planted as appropriate. Contractor to refer to general environmental management conditions in annex f.

Existence of a drainage system including ditches and run off detention ponds.

During the construction and to continue after completion of construction

Safeguards Advisor

UERP/PCU CONTRACTOR

REMA ELECTROGAZ

To be met by the contactor.

Visual Impacts and Accidents Construction of a cement perimeter wall around the site, construct

lower profile structures, Use of less visible colors, Planting of screening vegetation around the plant boundary, Proper design of the stack and dispersion characteristics.

During the construction and to continue after completion of construction

Safeguards Advisor

UERP/PCU CONTRACTOR

REMA ELECTROGAZ

Page 83: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

83

Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators

Implementation Schedule

Responsible Person(s) Cost Estimates

Availability of compensation plan approved by World Bank and REMA Compensation for crop loss should be undertaken as per the ARAP

document attached and in accordance with the World Bank and Government of Rwanda resettlement and compensation guidelines and procedures. An ARAP is being developed covering compensation modalities.

Evidence in terms of records showing cash compensation to PAPs including copies of cheques issues and amounts.

Documented evidence of meaningful Public Consultation in determining the compensation process.

Loss of crops and trees by the local communities

Meaningful Public Consultation in development of the Compensation Plan.

Adherence to the ARAP implementation schedule

To be finalised before construction works begin.

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor

Costs are reflected in the RAP and will be met by ELECTROGAZ through the UERP/PCU

The dirt roads and exposed construction areas should be moisturised during the dry season to prevent or minimise the fugitive dust emissions.

Availability of speed bumps and signs controlling speed in the construction area.

Watering to be undertaken regularly during the construction and when it is dry and dusty

Installation of speed bumps and speed limit signs to reduce speed of construction equipments capacity to blow dust

Observations if trucks are duly covered when carrying dust prone materials.

Install Heavy duty muffler systems on heavy equipment and Vehicles Availability of observable dust mufflers in equipments.

PPE should be available before construction works begin.

Contractor UERP/PCU

ELECTROGAZ Safeguards

Advisor

To be met by the contactor. The actual cost will be reflected by tenders in the financial proposal which includes this component.

Dust Emissions to air from Heavy Equipment/On site processes Fugitive dust may be emitted from construction works and stock piles of materials including machinery as well as from truck traffic. This could cause health related impacts to the communities around and workers in the project site.

Emissions from concrete batching plants should be controlled with fabric filters or cyclone separators.

Presence of fabric filters or cyclone separators at the site

PPE should be available before construction works

Contractor UERP/PCU

ELECTROGAZ

Page 84: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

84

Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators

Implementation Schedule

Responsible Person(s) Cost Estimates

Proper location of material stockpiles, especially sand and soil downwind from the commercial, residential and other establishments will be required; Frequent wetting of the stockpile and working area; screening of or providing wind breaks for stockpiles;

Verification on siting of the stockpiles.

Diesel powered construction equipment and vehicles should be well maintained to minimise tailpipe emissions; Covering of trucks; and proper selection of equipment and control of speed limits in construction area.

Verification of PPE availability through observation during the construction if workers are in PPEs.

Workers in the project site must be equipped with the necessary and required Personal Protective Equipment (PPE) prescribed by the construction industry but not limited to safety helmets, boots, dust masks, gloves, overall, goggles etc.

The diesel power construction machinery and vehicles will also have other air quality impacts even though negligible.

The emissions from the construction equipment and trucks will be too low to affect the SO2 and NOx levels within and adjacent to the construction site. Plant trees around the site to create a buffer zone to act as a sink for filtering gaseous emissions and noise impacts Contractor to refer to general environmental management conditions in annex f.

Verification of PPE availability through observation during the construction if workers are in PPEs.

begin. Safeguards Advisor

To be met by the contactor. The actual cost will be reflected by tenders in the financial proposal which includes this component

Noise emitting equipment should comply with the applicable Rwanda standards and World Bank noise standards. Plant trees around the site to create a buffer zone to act as a sink for absorbing noise impacts

Noise levels from all the noise prone equipments will be monitored at the start of each construction phase and thereafter every month to test compliance with the appropriate noise standards described in this report.

During the construction and to continue after completion of construction into the operational phase.

To be met by the contactor. The actual cost will be reflected by tenders in the financial proposal which includes this component

Incessant Noise and Vibrations from Heavy Equipment Operation Noise from construction activity may be significant. Although the relevant Government of Rwanda noise standard is not likely to be exceeded during the construction period, construction noise Construction traffic off-site will not contribute significantly to noise

levels on public highways because roads leading to the site already have very heavily traffic.

Noise will also be monitored at any time if legitimate complaints of excessive noise are received from the

During the construction and to continue after completion of

Contractor UERP/PCU

REMA ELECTROGAZ

Safeguards Advisor

Page 85: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

85

Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators

Implementation Schedule

Responsible Person(s) Cost Estimates

construction into the operational phase.

Noisy equipment should be operated only during daytime. World Bank environmental regulations allow a maximum 70 dB noise level at the boundary of a construction area.

local community. Verification of the quality of materials for noise attenuating characteristics and quality

Considering the existing background noise level, the construction activity during daytime is not expected to seriously affect the noise level in areas adjacent to the construction site.

Verification of PPE availability through observation during the construction if workers are in PPEs

During the construction and to continue after completion of Construction into the operational phase.

To be met by the contactor. The actual cost will be reflected by tenders in the financial proposal which includes this component

Use of noise attenuating materials in the construction

Use of noise absorbing materials in enclosures around switchyards and transformer stations.

All workers in the project site must be equipped with the necessary and required Personal Protective Equipment (PPE) prescribed by the construction industry but not limited to facilities to protect against noise impacts, safety helmets, boots, dust masks, gloves, overall, goggles etc.

may nevertheless be disturbing especially to the workers and personnel on the project site.

Workers and personnel operating equipments and machinery producing incessant noise and vibration should stick to no more than 5 hours a day in handling of equipment and machinery. They should also be provided with a pint of milk everyday and a supervisor should be available to oversee these requirements. Contractor to refer to general environmental management conditions in annex f.

Review of individual workers log book to verify log in time and log out to ascertain adherence to stipulated time.

During the construction and to continue after completion of Construction into the operational phase.

Contractor UERP/PCU

REMA ELECTROGAZ

Safeguards Advisor

Surface water contamination from

Water from dewatering activities and storm water discharges should be managed to minimise water quality impacts Undertake effluent

monitoring which will have to take place in the discharge pipe of wastewater.

During the construction and to continue after completion of

Contractor UERP/PCU

REMA ELECTROGAZ

To be met by the contactor. The actual cost

Page 86: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

86

Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators

Implementation Schedule

Responsible Person(s) Cost Estimates

construction into the operational phase.

Visual Inspection of dewatering water for observable oil contamination.

During the construction and to continue after completion of construction into the operational phase

A drainage canal should be built around the stockpile areas to divert the surface runoff and storm water from the stockpile into a water body or valley

Sediment control measures such as sediment sumps and retention weirs could be used, as necessary, to minimise sediment transport off site.

A site drainage system should be installed with solid settlement areas to reduce the sediment load of the runoff and oil interceptors.

generation of waste water and site run-off Minor short-term lowering of the groundwater table during dewatering of foundation excavations is not expected to have a significant impact.

Channeling and retention of water to reduce erosion and siltation. Contractor to refer to general environmental management conditions in annex f.

Availability of a drainage system and presence of secondary containment for temporary storage of fuel.

During the construction and to continue after completion of construction into the operational phase.

Safeguards Advisor

reflected by tenders in the financial proposal which includes this component

Workers should be trained in the proper handling, storage and disposal of hazardous or toxic materials.

Specific designated areas for storage of bulk oil and other fuels should be constructed with notices limiting access to authorised persons only.

Records showing trainings conducted to workers on waste management.

Before the construction and to continue after completion of construction into the operational phase.

Precautionary bunding/construction of dikes around fuel and chemical stores, in combination with oil/water separators, should be used to prevent contaminated water from reaching the canal.

Visual observation of presence of designated areas for bulk storage of oil and other fuels.

Accidental/oil spills Accidental spills of fuels or other materials could lead to ground contamination

Fuel storage tanks should have secondary containment with sufficient Warning notices available

Before the construction and to continue after completion of construction into the operational phase.

Contractor UERP/PCU

REMA ELECTROGAZ

Safeguards Advisor

Page 87: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

87

Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators

Implementation Schedule

Responsible Person(s) Cost Estimates

volume to contain a spill from the largest tank in the containment structure. The containment area should have a means of removing accumulated water. Drains should be routed through the site/water separator.

and observed cautioning unauthorised persons against access.

A spill and emergency response plan should be developed and put in place prior to commencement of construction. This must be a written emergency response plan and the workers should be trained to follow specific procedures in the event of a spill.

Presence of secondary containment areas for oil spills and drainage system.

Availability of an approved spill response plan before construction works begin.

(An annex of a draft Emergency Response Plan has been developed for further refinement by the UERP).

Records showing that workers have been trained on emergency response procedures.

UERP and the contractor should engage a refuse handling company to remove the wastes from the site to the recommended dumping site.

Presence of receptacles for dumping solid wastes observed before construction works begin.

Before the construction and to continue after completion of construction into the operational phase.

To be met by the contactor. The actual cost will be reflected by tenders in the financial proposal which includes this component

Warning signs against littering and dumping in wrong places within the construction site should be erected by the contactor.

Records showing private refuse handling collecting wastes

The contactor must construct toilets for use in the site during the construction which must be connected to the existing sewer line. Alternative use of the existing toilets and washrooms in the substation should be explored if viable as an option. Contractor to refer to general environmental management conditions in annex f.

Observable visual signs against littering and indiscriminate erected in the construction site.

During the construction and to continue after completion of construction into the operational phase.

Contractor UERP/PCU

REMA ELECTROGAZ

Safeguards Advisor

To be met by the contactor. The actual cost will be reflected by tenders in the financial proposal which includes this component

Page 88: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

88

Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators

Implementation Schedule

Responsible Person(s) Cost Estimates

Install advance warnings and traffic signs indicating on going construction and heavy machinery frequently using the area. Install speed bumps to warn other road users of on going construction and also to reduce speed when approaching the area.

Transport of heavy goods likely to congest traffic should be undertaken during off-peak times to reduce congestion.

To be met by the contactor. The actual cost will be reflected by tenders in the financial proposal which includes this component

Full time vigilance at the site during construction

Observable visual signs including speed bumps against speeding and indicating on going construction erected in the construction site and along the Kigali Byumba road.

Request for the support of traffic police officers prior to construction works to control the traffic

Presence of the concrete perimeter wall all around the project site.

Traffic Disruption congestion and or Road Accidents

Adherence to road load cargo bearing capacity for Rwanda Contractor to refer to general environmental management conditions in annex f.

Records showing police acceptance to assist in traffic control during construction including observable presence of traffic police in the area during the works.

Before the construction and to continue after completion of construction into the operational phase.

Contractor UERP/PCU

REMA ELECTROGAZ

Traffic Police Department Safeguards

Advisor

All workers entering the construction site must be equipped with PPE including goggles, factory boots, overalls, gloves, dust masks, among others. The PPE should be those that meeting the international standards of PPE.

Personal protection gear must be provided and its use made compulsory to all. The entire workforce of the plant should be trained in the use of protective gear, handling of chemical products and acid storage cells, electric safety equipment, procedures for entering enclosed areas, fire protection and prevention, emergency response and care procedures. Training given to the employees should be backed by regular on- site training in safety measures.

Verification of PPE availability through observation during the construction if workers are in PPEs.

Accidents at work place during construction from operating of machineries and equipment by workers

Machines and Equipments must be operated only by qualified staff and Background records

During the construction and to continue after completion of construction into the operational phase.

Contractor UERP/PCU

REMA ELECTROGAZ

Safeguards Advisor

To be met by the contactor. The actual cost will be reflected by tenders in the financial proposal which includes this component

Page 89: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

89

Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators

Implementation Schedule

Responsible Person(s) Cost Estimates

a site supervisor should be on site at all times to ensure adherence.

The contactor must develop a workers Health and Safety Manual for which all the workers should be conversant with for response in case of accidents.

including resume of all staff operating machines and equipments. Availability of a supervisor on site at all times.

Presence of a workers Health and Safety manual and records showing workers have been trained on managing accidents including for example first aid care.

The contractor and UERP should develop an Emergency Response Plan for handling any emergencies arising thereof during the construction. Contractor to refer to general environmental management conditions in annex f. Availability of an emergency

response plan document and procedure in cases of accidents.

To be met by the contactor. The actual cost will be reflected by tenders in the financial proposal which includes this component

A robust fire prevention program and fire suppression system should be developed by the contactor. (A draft fire suppression plan is attached as annex D but needs further refinement by the UERP who must carry out a vulnerability assessment before refining this plan into a final suppression program).

Availability of a fire response plan

The construction site must contain fire fighting equipments of recommended standards and in key strategic points all over the site. Fire pumps, Hydrants, Sprinkler/water spray systems, Hose houses, Dry chemical systems, -alternative systems, Carbon dioxide systems, Detection/alarm systems, Portable fire extinguishers among others.

Availability of all the observable fire containment equipments specified in the tender documents and fire response plan including: Fire detection, alarm and protection equipment in accordance with the NFPA Codes and standards

Fire Hazards/Accidents

A fire evacuation plan must be posted in various points of the construction site including procedures to take when a fire is reported.

Evacuation Plan posted in strategic places in the plant as required in the Fire

Before the construction and to continue after completion of construction into the operational phase.

Contractor UERP/PCU

REMA ELECTROGAZ

Kigali Fire Brigade Safeguards

Advisor

To be met by the contactor. The actual cost will be reflected by tenders in the financial proposal which includes this component

Page 90: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

90

Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators

Implementation Schedule

Responsible Person(s) Cost Estimates

response plan.

All workers must be trained on fire management and fire drills undertaken regularly. Contractor to refer to general environmental management conditions in annex f.

Availability of records (log books) showing trainings conducted by a competent firm on fire management regularly but at least bi-annually.

Page 91: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

91

OPERATION PHASE

Adverse Impacts Mitigation Measure(s) Monitoring Program/ Indicators Implementation Schedule Responsible Person(s) Cost Estimates

The generation facility MUST be designed to meet the more stringent World Bank emission and ambient air quality impact standards.

Presence of these guidelines and specifications in the tender document

During the planning phase, installation and to continue after completion of construction into the operational phase.

An attachment to this EMP is the World Bank Guidelines for construction of new thermal plants as per the PPAH and contains the standard specifications for air quality for which all procured thermal plants must oblige with.

Visit to the plants country of origin to verify purchased equipment before shipment.

Testing for emissions should be undertaken on a Quarterly basis, semi annually and annually or if complaints are raised by local residents and request made from relevant authority.

Further verification of equipments upon arrival in Kigali to confirm adherence to instructed specification.

Monitoring must use either Surrogate Emission monitoring, Extractive Sampling or Extractive Monitoring.

These guideline requirements and specifications have been incorporated in the tender documents and the contractor will be expected to adhere to these specifications to the letter.

Mandatory Environmental Tests to be carried upon installation and before handing over of facility to ELECTROGAZ.

During the commissioning of the plant, to continue during the operation phase on a regular basis

US$ 15,000 Cost to be met by UERP/PCU

The maximum Sulfur content of the fuel should be 3%. Reduction of sulphur content in emissions through Flue Gas Desulphurization (FGD)

Emissions from the main stack will be routinely monitored to demonstrate compliance with emission standards and guidelines.

During the commissioning of the plant, to continue during the operation phase on a regular basis.

Regular monitoring of the emissions of the main pollutants will be undertaken as required in order to ensure compliance with maximum levels

Emissions Combustion of the distillate oil will result in emissions of sulphur dioxide, nitrogen oxides, carbon monoxide, carbon dioxide, and particulate matter less than 10 microns, and total suspended particulate. The particulates may contain small amounts of trace metals.

Parameters that will be measured must include: Stack gas velocity, stack gas temperature, stack gas moisture content, visible emissions

During the commissioning of the plant, to continue during the operation phase on a regular basis

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Contactor

Page 92: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

92

Adverse Impacts Mitigation Measure(s) Monitoring Program/ Indicators Implementation Schedule Responsible Person(s) Cost Estimates

(VE), particulate matter (PM), sulphur dioxide (SO2), oxides of nitrogen (NOX), carbon dioxide (CO2), carbon monoxide (CO), oxygen (O2), and volatile organic compounds (VOC).

Plant operators will be required to install and operate dedicated stack gas samplers or analyzers, and report both summary data and violations of standards or limits.

CO, CO2 and O2 should be measured for determinations of combustion efficiency, while stack gas velocity and temperature will be used in calculations of concentrations at standard temperature and pressure (STP)

Each diesel engine shall be provided with one exhaust silencer

Source testing will also routinely required to confirm continued compliance with emission limits. Contractor to refer to general environmental management conditions in annex f.

With regard to sulphur dioxide emissions, monitoring can alternatively be based on the sulphur content in fuel oil.

During the commissioning of the plant, to continue during the operation phase on a regular basis

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Contactor

Presence of these guidelines in the tender document

The equipment should be designed and enclosed in an acoustic enclosure to limit noise to 65 decibels in plant boundary, and thereby meet World Bank requirements. Workers in close proximity to this equipment would be required to use hearing protection. Off-site noise would not exceed 65 dB (A).

Visit to the plants country of origin to verify purchased equipment before shipment.

Testing for noise should be undertaken on a Quarterly basis, semi annually and annually or if complaints are raised by local residents and request made from relevant authority.

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Contractor

US$ 4,000 Cost to be met by UERP/PCU

Noise and Vibration

Significant noise levels will result from operation of the diesel plant The transformers in the switchyard will also generate significant noise levels that can be harmful to workers and adjacent

All equipment and machinery installed MUST be tested to verify if they are compliant with the World Bank acceptable standards of noise as contained in the World Bank PPAH 1998. The tested noise levels should be recorded as baseline and used for future

Further verification of equipments upon arrival in Kigali to confirm specification.

During the commissioning of the plant, to continue during the operation phase on a regular basis

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Contractor

Page 93: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

93

Adverse Impacts Mitigation Measure(s) Monitoring Program/ Indicators Implementation Schedule Responsible Person(s) Cost Estimates

monitoring.

An attachment to this EMP is the World Bank Guidelines for construction of new thermal plants as per the PPAH and contains the standard specifications for noise quality for which all procured thermal plants must oblige to.

Noise emitting equipment should comply with the applicable Rwanda and World Bank noise standards and should be properly maintained. The Rwanda/World Bank environmental regulations allow a maximum 75 Db noise level at the boundary of an area.

Mandatory Environmental Tests to be carried upon installation and before handing over of facility to ascertain noise levels.

Considering the existing background noise level, the operations activity during daytime is not expected to seriously affect the noise level in areas adjacent to the construction site.

Noise will be monitored at the start of each construction phase and thereafter every month to test compliance with the appropriate noise standards described in this report.

During the commissioning of the plant, to continue during the operation phase on a regular basis

Install Heavy duty muffler systems on heavy equipment

Noise will also be monitored at any time if legitimate complaints of excessive noise are received from the local community.

All workers in the project site must be equipped with the necessary and required Personal Protective Equipment (PPE) prescribed by the construction industry but not limited to facilities to protect against noise impacts, hearing protection etc.

local communities.

Personal protection gear will be provided and its use made compulsory to all. The entire workforce of the plant should be trained in the

Verification of PPE availability through observation during the construction if workers are in PPEs

During the commissioning of the plant, to continue during the operation phase on a regular basis

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Contractor

To include costs for purchasing of PPE for all workers in the plant regularly. This cost will be met by ELECTROGAZ.

Page 94: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

94

Adverse Impacts Mitigation Measure(s) Monitoring Program/ Indicators Implementation Schedule Responsible Person(s) Cost Estimates

use of protective gear to handle noise impacts.

Training given to the employees should be backed by regular on- site training in safety measures. Plant a buffer zone using trees to mitigate noise impacts Contractor to refer to general environmental management conditions in annex f.

Need to design appropriate protection devices against accidental discharge of toxic substances (bases/air-tight tanks for machines, reservoirs etc.).

Before construction works begin an oil response plan should be developed.

Storage and liquid impoundment areas for fuels, raw and in-process material solvents, wastes and finished products should be designed with secondary containment (e.g. dikes) to prevent spills and the contamination of soil, ground and surface water.

Regular inspection of secondary containment areas and other sumps regularly Construction of fuel protection devices and

secondary containments should be undertaken before the construction phase, into the construction and operational phases too.

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Kigali Fire Brigade

Contractor

All the Fuel storage tanks should have secondary containment with sufficient volume to contain a spill from the largest tank in the containment structure. The containment area should have a means of removing accumulated water.

Daily routine monitoring must be conducted to observe for leakages or spills from the containing facilities.

Cost for designing impoundment and secondary containment measures will be met by the Contractor.

A retention area should be designed that surrounds the fuel storage tanks; During the operation phase

Oil spills/Spill prevention

Oil spills could occur during the transport, unloading and transfer of the fuel to on-site storage.

The plant operator should provide containers for the storage of chemical and lubricating products

Availability of an oil spill response plan.

Retention area should be designed during the construction phase and used in the operation phase too.

UERP/PCU

REMA ELECTROGAZ

Safeguards

Page 95: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

95

Adverse Impacts Mitigation Measure(s) Monitoring Program/ Indicators Implementation Schedule Responsible Person(s) Cost Estimates

Drains should be routed through a site/water separator.

he spill response plan should be designed before operation begins and should be used in the construction phase where spills could occur too

Advisor ELECTROGAZ

Kigali Fire Brigade

A spill and emergency response plan would be developed and put in place prior to commencement of construction. (An annex of a response plan has been developed for further refinement by the contractor).

A written emergency response plan should be prepared and retained on the site and the workers should be trained to follow specific procedures in the event of a spill.

All waste oils and lubricants from maintenance of construction equipment should be segregated and disposed properly in accordance with the solid waste disposal plan.

Availability of an oil spill response plan.

Inspection of the fuel area facility should be done routinely and daily to observe any leakages and or spills

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Kigali Fire Brigade

Contractor

A floating boom should be used to contain spillage during unloading and disconnection procedures.

Frequent inspection and maintenance of facility can minimise spilling from the transfer pipeline

Constructing and maintaining facilities to remove rainwater from the secondary containment structures and properly removing oil from the surface of the accumulated. Contractor to refer to general environmental management conditions in annex f.

Availability of an oil spill response plan.

Inspection of the fuel area facility should be done routinely and daily to observe any leakages and or spills

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Kigali Fire Brigade

Contractor

Page 96: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

96

Adverse Impacts Mitigation Measure(s) Monitoring Program/ Indicators Implementation Schedule Responsible Person(s) Cost Estimates

The wastewater discharge will be designed to comply with World Bank standards. Monitor discharges continuously.

Dredge settled solids from sludge, recycled decanted water from ash disposal ponds into ash slurry.

Levels of suspended solids, oil and grease and residual chlorine to be measured daily.

Cost of testing all the 24 parameters in an accredited laboratory at one interval is approximately USD 800.00 Cost to be met by UERP/PCU.

The treatment plant should comprise a collection and decantation basin (self-supporting floating skimmer and three floater detectors) and a primary and secondary treatment (a starting jar filter with its vacuostat and a coalscer filter (with its feed and extraction pump). Non-oil and non-chemical wastewater should be collected into a separate collection circuit.

The overall design shall aim at collecting of sludge from the whole power plant and pump/drain the same into a sludge tank for unloading the same on to sludge trucks for recycling.

Wastewater/Oily water discharge and treatment

Installation of a back-up incinerator for all the wastewater contaminated by hydrocarbons and sludge from the settling tank. All the used oils should be recycled through sub-contractors. Contractor to refer to general environmental management conditions in annex f.

All effluent monitoring will take place in the discharge pipe of wastewater.

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Kigali City Council:

Department of Sewerage Contractor

Provide training to ELECTROGAZ and the site operation staff.

UERP/PCU

REMA Training costs to be provided

Page 97: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

97

Adverse Impacts Mitigation Measure(s) Monitoring Program/ Indicators Implementation Schedule Responsible Person(s) Cost Estimates

by UERP/PCU.

Areas with hazardous materials on the site to be clearly marked out and the entire workforce trained to recognize the danger signs and familiarize themselves with procedures to be followed before entering hazardous areas.

Storage of waste, fuels and toxic substances with the appropriate safety and sealing measures Design of special areas for containing hazardous wastes costs

Availability of effective storage facilities in the plant.

Hazardous waste

The amount of hazardous waste created will be very low and possibly originate from maintenance sources.

The engine hall and the fuel treatment building should be connected to the oily water treatment system. Drainage water from the storage tank area, the unloading area and the day tank area shall be connected to an oil trap before disposal.

Temperature, pH, and flow rate will be monitored continuously and conductivity will be monitored at intervals. Other parameters that will be monitored include; Turbidity, BOD ,COD TSS,SS,PO4 ,SO4 ,N-NH3 ,Total N ,NH3 ,Cl, Detergents, Oil and Grease, Cr ,Cr 6+ , Cu , Ni , Fe , Zn , Al ,Cd ,Pb Ag,CN , Odour and Color.

Levels of suspended solids, oil and grease and residual chlorine to be measured daily.

ELECTROGAZ Safeguards

Advisor Contractor

Solid waste pollution and littering

Contractor should develop a solid waste disposal plan which includes the provision of receptacles at strategic points within the construction site, recycling programmes for recyclable wastes, separation of wastes.

Availability of a solid waste disposal plan.

Solid wastes must be collected from the site daily and disposed as per the requirements in the solid waste plan.

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor

Cost will include normal costs for hiring the services of a refuse

Page 98: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

98

Adverse Impacts Mitigation Measure(s) Monitoring Program/ Indicators Implementation Schedule Responsible Person(s) Cost Estimates

Presence of receptacles for dumping solid wastes observed before construction works begin

handling company annually. Cost to be met by ELECTROGAZ

The contractor should engage a refuse handling company to remove the wastes from the site to the recommended dumping site within Kigali city

Records showing private refuse handling collecting wastes

Warning signs against littering and dumping in wrong places within the construction site should be erected by the contactor. Contractor to refer to general environmental management conditions in annex f.

Contractor

All workers entering the construction site must be equipped with PPE including goggle, factory boots, overalls, gloves, dust masks, among others. The PPE should be those that meeting the international standards of PPE.

Verification of PPE availability through observation during the construction if workers are in PPEs.

On going /continuous activity to start during the construction phase all the way to the operational phase of the project.

Personal protection gear will be provided and its use made compulsory to all. The entire workforce of the plant should be trained in the use of protective gear, handling of chemical products and acid storage cells, electric safety equipment, procedures for entering enclosed areas, fire protection and prevention, emergency response and care procedures.

Availability of an emergency response plan document and procedure in cases of accidents

Accidents at the work place from operating of machineries and equipment by workers

Training given to the employees should be backed by regular on- site training in safety measures.

Presence of a workers Health and Safety manual and records showing workers have been trained on managing accidents including for example first aid care

On going /continuous activity to start during the construction phase all the way to the operational phase of the project.

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Contractor

Will include the cost for purchasing PPEs for all which will be met by ELECTROGAZ.

Page 99: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

99

Adverse Impacts Mitigation Measure(s) Monitoring Program/ Indicators Implementation Schedule Responsible Person(s) Cost Estimates

No ENTRY signs should be installed to keep away unqualified workers from access to restricted areas.

Observable restriction signs

Machines and Equipments must be operated only by qualified staff and a site supervisor should be on site at all times to ensure adherence.

Background records including resume of all staff operating machines and equipments. Availability of a supervisor on site at all times.

The contactor must develop a workers Health and Safety Manual for which all the workers should be conversant with for response in case of accidents.

Availability of a workers health and safety manual

The contractor should develop an Emergency Response Plan for handling any emergencies arising thereof during the operation. Contractor to refer to general environmental management conditions in annex f.

Records showing workers training on Occupational Health and Safety

On going /continuous activity to start during the construction phase all the way to the operational phase of the project.

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Contractor

Will include the cost for purchasing PPEs for all which will be met by ELECTROGAZ.

The diesel engines should be fitted with a vapor monitor and a toxic vapor ignition monitoring system.

Verification of vapour ignition monitoring system on diesel power plants.

To be verified upon arrival of equipments from the manufacturing company.

A robust fire prevention program and fire suppression system should be developed by the contactor. (A draft fire suppression plan is attached herewith but needs further refinement by the contactor who must carry out a vulnerability assessment before refining this plan into a final suppression program).

Availability of a fire prevention plan approved by the fire department

Fire risk and accidental discharge of products:

Heavy fuel used by the plant has a relatively low fire or explosion risk.

The site must contain fire fighting equipments of recommended standards and in key strategic points all over the site. Fire pumps, Hydrants, Sprinkler/water spray systems, Hose houses, Dry chemical systems, Carbon

Availability of all the observable fire containment equipments specified in the tender documents and fire response plan including: Fire detection, alarm and

The fire response plan should be developed before construction begins and used through out the operations of the plant.

UERP/PCU

REMA ELECTROGAZ

Safeguards Advisor

Kigali Fire Brigade Contactor

Cost for purchasing the fire management equipment and fire suppression plan will be met by the contractor. Regular maintenance of the equipment and related

Page 100: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

100

Adverse Impacts Mitigation Measure(s) Monitoring Program/ Indicators Implementation Schedule Responsible Person(s) Cost Estimates

dioxide systems, Detection/alarm systems, Portable fire extinguishers among others. Contractor to refer to general environmental management conditions in annex f.

protection equipment in accordance with the NFPA Codes and standards Availability of an

Evacuation Plan posted in strategic places in the plant as required in the Fire response plan. A fire evacuation plan must be posted in

various points of the construction site including procedures to take when a fire is reported.

Availability of records (log books) showing trainings conducted by a competent firm on fire management regularly but at least bi-annually

The fire response plan should be developed before construction begins and used through out the operations of the plant.

costs to be met by ELECTROGAZ

CFCs Emissions from the Central cooling systems likely to exacerbate the Green House Effect

Processes, equipment and central cooling systems involving the potential release to the environment of CFCs (including Halon) should not be installed.

Verification on site of the central cooling systems for manufactures indication on CFCs emissions.

The verification to ensure that no CFCs emission emanate from cooling plant should be undertaken when the equipments arrive.

UERP/PCU REMA

ELECTROGAZ Safeguards

Advisor Contactor

Page 101: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

101

DECOMMISSIONING PHASE

Activity/Adverse Impacts Mitigation Measure(s) Monitoring Program/Indicators Implementation Schedule

Responsible Person(s) Cost Estimates

Waste Debris from Equipments and Machines when plant is dismantled.

Ensure all the machines and equipment are disposed in the right places

Site supervision during the decommissioning

During decommissioning

ELECTROGAZ

All costs related to decommissioning will be met by ELECTROGAZ

Noise and dust impacts during the dismantling

Apply the noise reduction /mitigation impacts specified in the construction phase of the project

Site supervision during the decommissioning

During decommissioning

ELECTROGAZ

All costs related to decommissioning will be met by ELECTROGAZ

Accidents during decommissioning including oil spills

Apply the accidents reduction /mitigation impacts specified in the construction phase of the project

Site supervision during the decommissioning

During decommissioning

ELECTROGAZ

All costs related to decommissioning will be met by ELECTROGAZ

Page 102: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

MONITORING PROTOCOL FOR THE DIESEL POWER PLANT 9.2 Monitoring Plan A detailed environmental monitoring plan has been developed to verify that predictions of environmental impacts are accurate and that unforeseen impacts are detected at an early stage and allow corrective measures to be implemented, if needed. During the construction phase the plan provides for dust, noise and safety monitoring. During the operation period, monitoring is planned for air emissions and air quality, noise, water quality and effluent monitoring as well as a routine inspection of the oil tanks storage and handling area. Baseline water quality analysis was conducted at several points along the Nyabugogo River and the results of these analyses are reflected in the table below. Mean measured values of physical water quality parameters at various sampling points.

Mean concentration values Sampling point Q (m3 s-1)

TSS (mg l-1)

COND (㎲ cm-1)

TDS (mg l-1)

TUR (NTU)

A B C D E

0.772 1.376 2.140 5.083 5.341

157.6 129.4 255.7 199.2 95.5

392.1 397.7 564.5 509.5 474.8

239.7 244.2 290.9 310.9 298.8

69.4 69.3 65.5 67.8 28.5

Variability of toxic and organic substances at different sampling stations.

Mean concentrations per sampling station and river basin Parameter A B C D E

Fe (mg l-1) 1.99 1.59 1.3 1.44 0.60 Mg (mg l-1) 8.4 9.6 7.8 7.2 4.4 Na (mg l-1) 59 45.8 69.5 46.6 42.5 Cl (mg l-1) 47 38.8 46.3 39.5 29 F (mg l-1) 0.8 0.6 1.1 0.6 1.17 BOD5 (mg l-1) 143.3 59.5 82.8 COD (mg l-1) 301.3 266.2 253.1 TSS (mg l-1) 298.5 180.5 244.6 COND(㎲ cm-1) 558.2 605.9 459.0

TDS (mg l-1) 337.5 375.4 282.3 Source: Field data

Page 103: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

103

It was not possible to undertake ambient noise levels due to lack of instruments but before the commissioning of the plant UERP plans to procure a noise meter which will be used to undertake the tests. The noise meter will also be used to conduct initial tests to the engines at different distances to verify the noise levels. Ambient air quality test was also undertaken at different points within the plant site using the passive approach. The parameters that were analyzed and results are shown below; Ambient air emissions for nitrogen dioxide around the project site

Project surrounding Maximum 24-hour Average

(µg/m³)

Samples collected around sugar factory and Jabana substation

186 (as NOx)(f)

Ambient air emissions for sulphur dioxide around the project site

Project surrounding Maximum 24-hour Average

(µg/m³)

Samples collected around sugar factory and Jabana substation

198(h)

9.2.1 Responsibilities and Costs for Environmental Mitigation Measures Table below outlines the overall package of environmental mitigation measures that will be implemented in relation to the diesel power facility. The table also assigns general responsibilities for implementing each group of mitigation measures. A detailed implementation schedule has also been developed. Consistent with the UERP/PCU and World Bank’s contracting strategy of integrating environmental protection and mitigation activities into the Contractor’s Scope of Work, the specifications for many of the activities were included in the bid package upon which the Contractor is developing its base rates. Therefore, since many of the costs associated with environmental protection and mitigation activities are included in the Contractor’s base rates, it is not possible to present a detailed accounting of all the monies devoted to the project’s construction phase environmental protection and mitigation activities. These costs are therefore described as ‘Within contract budget’ in Table below. Similarly, mitigation or monitoring measures that will be carried out by ELECTROGAZ staff, with no additional expenditure required, are described as ‘Within operational budget’ in Table below.

Page 104: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

104

Capital cost related activities

Activity Estimated Cost in (USD) Cost to be met by Compensation for displaced persons or destroyed crops and vegetation

This cost is yet TBD and will be reflected in the ARAP which is under development.

ELECTROGAZ/UERP/PCU

Mitigating Impacts of civil construction related works

Within Contractor’s Budget. The costs associated to mitigating the impacts of the construction activities will be met by the contractor.

Contractor

Procurement of an Emission Testing Equipment 15,000.00 ELECTROGAZ/UERP-PCU

Procurement of Noise Testing Equipment 4,000.00 ELECTROGAZ/UERP-PCU

TOTAL CAPITAL COSTS 19,000.00

Page 105: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

Recurring cost related activities

Activity Estimated Cost in (USD) Cost to be met by

Procurement of PPE for ELECTROGAZ staff

10,000 and costs to be incurred depending on the rate of wear and tear of the PPE.

ELECTROGAZ

Water Quality Analysis Tests

800.00 after every 2 months

ELECTROGAZ/UERP/PCU

Training on OHS

10,000 ELECTROGAZ/UERP/PCU

Procuring services of Solid Waste Disposal Company

500.00 per month ELECTROGAZ

Regular Maintenance of Fire Equipment

5,000.00 after every 6 months

Total Recurring Costs 26,300.00

ELECTROGAZ

• The parameters for water quality analysis are available in the monitoring plan section in the next

table. • 10,000 USD for PPE is based on cost estimated provided by ELECTROGAZ staff following

incurred costs in other power plants or sub stations. The cost is recurrent and spread over 4 years. It is not related to monitoring but to mitigation costs.

• The maintenance of fire equipment is going to be the responsibility of ELECTROGAZ. The contractor will hand over the plant to the client after commissioning and would only retain 2 experts if agreed with ELECTROGAZ for a period of one year to offer technical advice after which the plant will be fully operated and managed by ELECTROGAZ. According to the contract, the client does not provide financial resources and support for maintenance instead the contractor only offers technical support.

• ELECTROGAZ will outsource this services related to OHS training.

Page 106: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

MONITORING PLAN

Monitoring Issue Parameter Monitoring Method Indicator Frequency of Measurement Responsibility

Stack Emission Measurements Measured Level vis a vis sulphur content in fuel

Monthly and when complaints are received from PAPa

Sulphur Oxides (SOx)

Fuel Quality Measurements Sulphur Content in fuel Testing each fuel shipment received.

ELECTROGAZ, independent laboratory

for verification, REMA, UERP/PCU

Nitrogen Oxides (NOx) Stack Emission Measurements Measured Levels of nitrogen oxides

Monthly using manual gravimetric method or similar

ELECTROGAZ, independent laboratory

for verification, REMA, UERP/PCU

Air Emissions

Particulate Matter (PM) Fuel Quality Measurements Measured Levels of particulate matter Ash content in fuel

Testing each fuel shipment received and at least 4 random samples per year.

ELECTROGAZ, independent laboratory

for verification, REMA, UERP/PCU

Monitoring Issue Parameter Monitoring Method Indicator Frequency of Measurement Responsibility

Sulphur Oxides (SOx) Continually Analysed at agreed intervals

24 hour and annual average Monthly ELECTROGAZ, independent laboratory for verification, REMA, UERP/PCU

Nitrogen Oxides (NOx) Continually Analysed at agreed intervals

24 hour and annual average Monthly ELECTROGAZ, independent laboratory for verification, REMA, UERP/PCU

Ambient air Quality

Climatic Conditions Keeping record of meteorological data at the nearest station which is at the airport.

Wind Speed and direction, temperature, humidity

Continuous recording Meteorological Department at Kigali Airport; This is the nearest station

Ambient Water /Effluent Quality

Effluent from storm drains and Nyabugogo river

Continuous Analysis on daily basis

PH, Mg,F, Cl, Na BOD, COD, Oil ,PM, Fe, TSS,

Daily ELECTROGAZ, independent laboratory for verification, REMA,

Page 107: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

107

TDS, UERP/PCU

Effluent discharge from oil interceptors/oily water treatment unit

Grab samples for laboratory analysis

Measured levels of: • Oil and grease • Total suspended

solids

Daily ELECTROGAZ, independent laboratory for verification, REMA, UERP/PCU

Monitoring Issue Parameter Monitoring Method Indicator Frequency of Measurement Responsibility

Occupational Noise Periodic measurements with a noise meter

Time averaged measurements in Db(A) at receptors inside the plant boundary

Daily and whenever complaints are received

ELECTROGAZ, independent laboratory for verification, REMA, UERP/PCU

Noise

Ambient Noise Measuring Noise levels at 100% full load operation using an integrating noise analyser

Time averaged measurements in Db(A) at receptors outside the plant boundary

Weekly and whenever complaints are received

ELECTROGAZ, independent laboratory for verification, REMA, UERP/PCU

Solid Waste Tracking the volume of solid waste generated and establishing the treatment, storage, recycling, transport and disposal methods

Wastes streams and volumes generated on site

Continuous ELECTROGAZ, REMA, UERP/PCU, Local Authority

Waste Management

Hazardous Waste Tracking all hazardous wastes and establishing the treatment, storage, handling and disposal methods

Generated quantities of: • Used oils • Solvents • Sludge • Process residue

Continuous ELECTROGAZ, independent laboratory for verification, REMA, UERP/PCU

Page 108: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

108

Monitoring Issue Parameter Monitoring Method Indicator Frequency of Measurement Responsibility

Adoption and Implementation of EHS policies

Annual EHS Audits Status of identified and established targets

Continuous as necessary ELECTROGAZ, REMA, UERP/PCU

Employee EHS training Inspection of records of training programs including fore drills

Annual record of staff training programs executed or attended

Annually ELECTROGAZ, REMA, UERP/PCU

Development and maintenance of EHS plans, procedures and manuals

Annual EHS Audit Inspection of plans, procedures and manuals

Annual record of status and updates

Continuous as necessary ELECTROGAZ, REMA, UERP/PCU

Occupational Health and Safety monitoring

Reporting of accidents and incidents, safety breaches and damage to equipment

Annual statistical records and safety reports

Continuous ELECTROGAZ, REMA, UERP/PCU

Health and Safety Management

EHS Audits Inspection of previous EHS internal and external audit records

• Number and type of corrective actions raised

• Status on implementation of corrective actions

Quarterly for internal audits and annually for external audits

ELECTROGAZ, REMA, UERP/PCU

Monitoring Issue Parameter Monitoring Method Indicator Frequency of Measurement Responsibility

Soil Contamination • Visual Assessment of oil stains

• Soil Analysis during

spill incidents

• Presence of oil stains/spills

• Measured levels of VOCs/TPH

• Daily visual inspections

• As necessary

ELECTROGAZ, REMA, UERP/PCU

Other Environmental Health and Safety Issues

Maintenance of Fire Appliances Inspection of maintenance and servicing records of al fire appliances

Quarterly record of inspection reports by local fire appliance dealers

Quarterly ELECTROGAZ, REMA, UERP/PCU, Local Fire Appliance Dealer

Page 109: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

109

Monitoring Issue Parameter Monitoring Method Indicator Frequency of Measurement Responsibility

Ozone Depleting Substances (ODS)

Inspection schedule of phase outs of ODS

Status of the phase out of ODS

Every 2 years or as agreed in the phase out schedule

ELECTROGAZ, REMA, UERP/PCU

Efficient use of resources Consumption record of water, electricity, fuel and other resources.

Financial savings in subsequent bills

Monthly ELECTROGAZ, UERP/PCU

Social Concerns • Inspection of record of concerns from the community

• Review of records of

stakeholder consultation

• Number, type of complaints

• Socio-economic

status

• Status on implementation of agreed actions

• Annually

• Bi-Annually

ELECTROGAZ, REMA, UERP/PCU, Stakeholders

Legislation and Standards Inspection of register for the current and anticipated applicable local and international regulations, legislations and standards

• Valid licences

• Inspection certificates

• Other compliance

records

Annually or as necessary ELECTROGAZ, REMA, UERP/PCU, legislative authorities

N/B The principal responsible party is underlined in the table above. Any complaints on the implementation of the EMP by the communities will be channelled through the local authorities who will alert ELECTROGAZ. ELECTROGAZ will also conduct its own assessments.

Page 110: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

CONCLUSION AND RECOMMENDATIONS Demand for electricity in Rwanda continues to outstrip supply, with the total shortfall in electricity supply across the country. Industrial, commercial, and domestic electricity consumption is restricted by supply, thus additional generation is required to promote economic growth and poverty alleviation for a shorter period before long term projects under construction and improvement are completed. The diesel power plant will provide an additional 20 MW to the national grid. The plant will also promote regional investment and rural electrification programme thus reducing pressure on biomass energy source. The plants will also create short-term construction employment and long-term operational jobs. Based on the findings of the study, the project is environmentally and socially viable with minimal adverse environmental impacts. Being an emergency project, most of the impacts will be short term with low magnitude confined within the project site. Some of the impacts are inevitable and can only be minimised due to inadequate or lack of effective technology. If the Environmental Management is implemented, the impacts of the project will either be eliminated or minimised to a manageable and sustainable levels.

10.1 Recommendations An annual environmental audit should be undertaken after the first year of plant operations. The areas to be assessed should include oil, air and noise pollution. The audit should also review the projects compliance of environmental management plan and standards prescribed in the EMP. When decommissioning the project, the proponent should rehabilitate the site to its former status and remedial action undertaken to ensure the land is not contaminated. For future reference it would be advisable to have gas combined cycle plant as opposed to diesel fuelled generators which is expensive and unsustainable for a country like Rwanda which has no oil deposit.

Page 111: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

111

REFERENCE

1. Bikwemu G, 2001: The types of the swamps of Rwanda. MINAGRI 2. ELECTROGAZ/UERP, 2005: Tender document supply and installation of 12 MWS diesel power

plantation. 6. Technical Specification 3. Environmental, Health, And Safety Guidelines General EHS Guidelines: Environmental Air

Emissions and Ambient Air Quality, World Bank 2007. 4. European Union Ambient Air Quality Standards, 2000. 5. Institute of the energy and the environment of the French speaking countries, 1999-2000:

Environmental Assessment. Networks of E7 appraisal for the Global environment. 6. MININFRA, 2005: Survey of environmental and social impact of the Rehabilitation of the Kigali-

Gatuna road. Draft report 7. MINITERE: Organic Law carrying management and protection of the environment, the law N°

4//2005 of April 8, 2005 8. MINITERE: Organic Law carrying regime fundamental N°08/2005 of the 14/07 /2002 9. PNUE, 2001 : Convention of Stockholm on the Obstinate Organic Pollutants and its appendices 10. REMA Report of visit of the Jabana site of April 14, 2005 11. UERP, 2004: Environmental and Social Management Framework 12. UERP, 2004: Resettlement Policy Framework 13. USEPA Ambient Air Quality Standards, 2005. 14. World Bank, 1999 Manual on environmental assessment. Policies, procedures and sectoral

guidelines. 15. World Bank, December 2004: UER Project appraisal document 16. World Bank, Environment Department, "Initial Draft of Industrial Pollution Prevention and

Abatement Handbook," Jan 1995.

Page 112: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

112

ANNEX ANNEX A. MINUTES OF THE MEETING RELATING TO THE JABANA PLOT WHERE ELECTROGAZ PLAN TO INSTALL THE 20 MW DIESEL POWER PLANT. Date: September 11, 2007 Venue: UERP-PCU/Board room Time: 15:30 Pm Attendance

• From PCU-UERP/ELECTROGAZ: - Mr. Félix GAKUBA/PCU Manager and Chairman of the meeting. - Mr. Gérase Ngirababyeyi/Procurement Officer.

• From Jabana sector:

- Mr. Kimenyi Burakari Onesmu/ Executif Secretary of Jabana Sector

• From Word of Life: - Mr. Elroy Pankratz/ Word of Life - Mr. SHEMA G. Charles/ Legal adviser of Word of Life - Mr. Ntagora Emmanuel/Pastor of Word of Life Jabana - Mr. Nshimiyimana Stephen/Assistant Pastor of Word of Life - Mr. Muhorane Alain/Accountant of Home of Hope Rwanda

Definitions: UERP: Urgent Electricity Rehabilitation Project PCU: Project Coordination Unit Home of Hope Rwanda is under Word of Life Agenda

How will Word of Life get the new plot to set up its infrastructures since its old plot will be used to install the 20 MW diesel power plants for ELECTROGAZ?

Meeting After seeing the importance of the 20 MW diesel power plant project, realising that, two years ago, the old plot given to Word of life was identified for installation of the 20 MW diesel power plant and it was only one convenient plot for 20 MW project due particularly to technical advantages that it offers, all the participants agreed to go ahead looking how to speed up the land acquisition process initiated by Gasabo District with regards to the new plot where Word of Life could develop its project. The new identified site located at around 300 meters from the old one. The discussions ended by agreeing on the followings:

Page 113: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

113

- Gasabo District has started the inventory of items to be discarded within the identified plot for Word of Life and the relevant compensation document will be available within one week.

- The said plot shall be with the same value as the old one and relevant amount shall be transferred by PCU-UERP/ELECTROGAZ immediately after signature of these minutes and upon presentation of the account number by the Beneficiary (Word of Life).

- Compensation shall cover also receipted costs for the topographic survey initially performed by Word of Life totalling 500 USD.

- Word of Life/Home of Hope Rwanda and UERP agreed to co-operate in connection to access road for the two sites, water supply, electricity connection etc.

Signed by, for and behalf of PCU-UERP/ELECTROGAZ Félix Gakuba Signature……………….. ….Date: …………. UERP/PCU Manager Signed by, for and behalf of Word of Life Elroy Pankratz Signature…………………….Date: …………. Pastor Samuel RUSHOMBO Signature…………………….Date: …………. Signed by, for and behalf of Jabana Sector/Gasabo District Mr. Kimenyi Burakari Onesmu Signature……………………Date: …………. Executif Secretary of Jabana Sector

Page 114: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

114

ANNEX B. AMBIENT AIR, NOISE and EFFLUENT QUALITY STANDARDS The guidelines presented in the tables below are to be used only for carrying out an environment assessment and monitoring in the absence of local ambient standards as is the case with Rwanda where there are no ambient quality standards yet. They were constructed as consensus values taking particular account of WHO, USEPA, and EU standards and guidelines. They do not in any way substitute for a country’s own ambient air quality standards.

Table 1. Ambient Air Quality in Thermal

Power Plants (micrograms per cubic meter)

24-hour Annual Pollutant average average

PM10 150 50 TSPa 230 80 Nitrogen dioxide 150 100 Sulfur dioxide 150 80

Measurement of PM10 is preferable to measurement of TSP.

For plants smaller than 50 MWe, including those burning non fossil fuels, PM emissions levels may be as much as 100 mg/Nm3. If justified by the EA, PM emissions levels up to 150 mg/Nm3 may be acceptable in special circumstances. The maximum emissions levels for nitrogen oxides remain the same, while for sulfur dioxide, the maximum emissions level is 2,000 mg/Nm3. Ambient Noise Noise abatement measures should achieve either the levels given below or a maximum increase in background levels of 3 decibels (measured on the A scale) [dB (A)]. Measurements are to be taken at noise receptors located outside the project property boundary.

Maximum allowable log Equivalent (hourly Measurements), in dB (A) Day Night

Receptor (07:00–22:00) (22:00–07:00) Residential, Institutional, Educational 55 45 Industrial, Commercial 70 70 Liquid Effluents The effluent levels presented in Table 2 (for the applicable parameters) should be achieved daily without dilution. Where leaching of toxics to groundwater or their transport in surface runoff is a concern, suitable preventive and control measures such as protective liners and collection and treatment of runoff should be put in place.

Page 115: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

115

Table 2. Effluents from Thermal Power Plants

(milligrams per liter, except for pH and temperature) Parameter Maximum value

pH 6–9 TSS 50 Oil and grease 10 Total residual chlorine 0.2 Chromium (total) 0.5 Copper 0.5 Iron 1.0 Zinc 1.0 Temperature increase ≤ 3°Cb

Institutional requirements and monitoring UERP will undertake environmental monitoring to ensure that the construction and operation of the diesel power plant complies with high environmental standards and the requirements of the environmental legislation applicable in Rwanda and the policies and guidelines by World Bank. Annual monitoring reports arising from the monitoring activities will be made available to REMA and World Bank and others as requested and appropriate. If any standards have been exceeded, the operator will investigate probable causes and if any are traced to the operation of the plant, remedial measures will be implemented to restore compliance. UERP/PCU will submit to World Bank and REMA an annual report containing the summary of the

(i) Monitoring results for the stack emissions, noise, and water quality; (ii) Copies of all permits, licenses, and clearances related to the environment and safety issued by

the relevant government agencies; and (iii) In the event that in the reporting period the project has been cited for violation of any

environmental or safety regulations, the report will include a certification from the relevant government agency that the defect has been corrected or an acceptable plan to correct the defect has been approved.

Emissions from the main stack will also be monitored to demonstrate compliance with emission standards and guidelines. Noise will be monitored at the start of each construction phase and thereafter every month to test compliance with the appropriate noise standards described in this report. Noise will also be monitored at any time if legitimate complaints of excessive noise are received from the local community. If the appropriate noise standards are exceeded, action will be taken to reduce noise levels. All effluent monitoring will take place in the discharge pipe of wastewater. Temperature, pH, and flow rate will be monitored continuously and conductivity will be monitored at intervals. With regard to monitoring emissions and air quality: In addition to the control of combustion conditions in real time, required to ensure the best (and therefore most economic) energy output possible, regular monitoring of the emissions of the main pollutants is also required in order to ensure compliance with maximum levels. With regard to sulphur dioxide emissions, monitoring can alternatively be based on the sulphur content in fuel oil. Monitoring data will be analyzed and reviewed at regular intervals and compared with the operating standards so that any necessary corrective actions can be taken. Records of monitoring results will be kept

Page 116: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

116

in an acceptable format. The results will be reported in summary form, with notification of exceptions, if any, to the responsible government authorities and relevant parties, as required. In the absence of specific national or local government guidelines, actual monitoring or surrogate performance data will be reported at least annually.

Page 117: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

117

ANNEX C. EQUIPMENT TECHNICAL SPECIFICATIONS Noise Measurement Kit with Calibrator The NM 102 Sound Level Meter is available as part of a Noise Measurement Kit, order code NM102-K, which includes:

• Sound Level Meter • Sound Level Calibrator • Wind Shield • Hard Carrying Case (for all items) • Soft Carrying Case (for meter) • Batteries for Meter and Calibrator • Manual for Meter and Calibrator

Specifications Display 4 Digit LCD with black and white, update rate 0.5s Indicators Low battery, frequency and time weighting, min/max Resolution/Accuracy 0.1dB/1.5 Db (ref 94 dB@ 1 kHz) Frequency Range 31.5 Hz to 8 kHz Level Range 30 to 130 Db (A), 35 to 130 Db (C) Frequency Weighting A and C Microphone 1/2'” electret condenser Time Weighting Fast (125ms) and Slow (1s) Dynamic Range 50 Db Battery One 9V battery supplied Battery Life About 50 hours (alkaline battery) Temp. & Humudity 5 C to 40 C, BELOW 80% RH Dimensions 8” X 2.1” X 1.5”, 6 ounce (inc. battery) NoiseMeters USA 14781 Memorial Drive, Suite # 2174 Houston, TX 77079, USA Email: [email protected] Air Emission Testing Kit Testo 335 Flue Gas Analyzer-Air Emission The 335 Flue Gas Analyzer is capable of measuring NO, CO, CO2, O2, and SO2 efficiency. Testo 335 flue gas analyzer comes with the following accessories:

• Rechargeable battery • Calibration protocol • Equipped with O2 and CO sensor.

Testo 335 is the new generation flue gas analyzer is specially tailored to industrial applications requirements. Testo 335 can be used for all emission monitoring applications by the operators of industrial furnaces such as processing and power plants, by service technicians for burner/furnace manufacturers, for plant construction as well as for stationary motors. Even spot measurements for up to 2 hours are possible.

Page 118: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

118

• Large graphic display. • NO, NO2, CO, CO2, O2 SO2 measurement. • Exhaust gas loss measurement. • Efficiency measurement. • Absolute Pressure Temperature measurement.

Technical Specifications

• Display Graphic Display 160 X 240 Pixels

• Storage Temperature -20 to +50C

• Operating Temperature-5 to +50 C

• Weight 600 g

• Dimensions 270 X 90 X 65 mm Probe type Type K Measuring Range -40 to +1200 °C Accuracy ±0.5 °C (0 to +99 °C) ±0.5 % of mv (remaining range) Resolution 0.1 Probe type Differential pressure Meas. Range -200 to 200 hPa Accuracy ±0.5 hPa (-49.9 to 49.9 hPa) ±1.5 % of mv (remaining range) Resolution 0.1 hPa Probe type NO Meas. Range 0 to 300 ppm Accuracy ±2 ppm (0 to 39.9 ppm) ±5% of mv (remaining range) Reaction time t90 <30 s Probe type Exhaust gas loss measurement Meas. Range 0 to 99.9 % Accuracy ±10 ppm or ±10% of mv (0 to 200 ppm) ±20 ppm or ±5% of mv (201 to 2000

ppm) ±10% of mv (2001 to 10000 ppm) Resolution 1 ppm Probe type Electrochemical measurement CO2 Meas. Range 0 to CO2 max. Accuracy ±0.2 Vol. % Resolution 0.1 Vol. % Probe type Electrochemical measurement NO Meas. Range 0 to 3000 ppm Accuracy ±5 ppm (0 to 99 ppm) ±5% of mv (100 to 1999 ppm) ±10% of mv (2000 to 3000

ppm) Resolution 0.1 ppm

Page 119: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

119

Probe type Electrochemical measurement SO2 Meas. Range 0 to 5000 ppm Accuracy ±10 ppm (0 to 99 ppm) ±10% of mv (remaining range) Resolution 1 ppm Probe type Electrochemical measurement O2 Meas. Range 0 to 25 Vol. % Accuracy ±0.2 Vol. % Resolution 0.01 Vol. % Probe type Efficiency Measurement (Eta) Meas. Range 0 to 120 % Resolution 0.1 % Probe type Absolute pressure probe Meas. Range 600 to +1150 hPa Accuracy ±10 hPa Resolution 1 hPa Probe type Typ R (Pt13RH Pt) Meas. Range 0 to +1600 °C Accuracy ±1 °C (0 to +199 °C) ±0.5 % of mv (remaining range Resolution 1 °C

Page 120: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

120

ANNEX D. EMERGENCY RESPONSE PLAN FOR PROPOSED PLANT The construction and installation including the operation of the proposed diesel power plant in J is expected to trigger the likelihood of potential incidences which require the need for the development of an Emergency Response Plan to arrest such incidences whenever and if they occur. This is a framework of how the emergency response plan is for the diesel plant is expected to look and is by no way the actual response plan. It is expected that the winning company to be awarded the contract of constructing the diesel power plant will develop a comprehensive response plan which will be guided by a vulnerability assessment for which the company will have to undertake. This emergency response plan has incorporated separate sections handling responses to fire hazards in the plant including steps for reporting incidences. Why develop an Emergency Response Plan? An ERP is a definite plan to deal with major emergencies in any enterprise and in effect is an important element in all diesel power plants and programs. Besides the major benefit of providing guidance during an emergency, developing the plan has other advantages. Unrecognized hazardous conditions that would aggravate an emergency situation may be uncovered, allowing them to be eliminated. The planning process may bring to light deficiencies, such as the lack of resources (equipment, trained personnel, supplies), items that can be rectified before an emergency occurs. In addition an emergency plan promotes safety awareness and shows the organization's commitment to the safety of workers. The lack of an emergency plan could lead to severe losses such as multiple casualties and possible financial collapse of the organization. An attitude of "it can't happen here" may be present. People may not be willing to take the time and effort to examine the problem. However, emergency planning is an important part of company operation. Since emergencies will occur, preplanning is necessary to prevent possible disaster. An urgent need for rapid decisions, shortage of time, and lack of resources and trained personnel can lead to chaos during an emergency. Time and circumstances in an emergency mean that normal channels of authority and communication cannot be relied upon to function routinely. The stress of the situation can lead to poor judgment resulting in severe losses. What is the overall objective of this plan? This emergency plan specifies procedures for handling sudden unexpected situations. The objective is to reduce the possible consequences of the emergency by:

• Preventing fatalities and injuries; • Reducing damage to buildings, stock, and equipment; and • Accelerating the resumption of normal operations.

Development of the plan begins with a vulnerability assessment. The results of the study will show:

• How likely a situation is to occur • What means are available to stop or prevent the situation and • What is necessary for a given situation

From this analysis, appropriate emergency procedures can be established. At the planning stage, it is important that several groups be asked to participate. Among these groups, the setting up of a joint occupational health and safety committee can provide valuable input and a means of wider worker involvement. Appropriate municipal officials should also be consulted since control may be exercised by the

Page 121: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

121

local government in major emergencies and additional resources may be available. Communication, training and periodic drills will ensure adequate performance if the plan must be carried out. Vulnerability assessment Although emergencies by definition are sudden events, their occurrence can be predicted with some degree of certainty. The first step is to find which hazards pose a threat to any specific enterprise. When a list of hazards is made, records of past incidents and occupational experience are not the only sources of valuable information. Since major emergencies are rare events, knowledge of both technological (chemical or physical) and natural hazards can be broadened by consulting with fire departments, insurance companies, engineering consultants, and government departments. The company to be contracted will be expected to undertake a comprehensive vulnerability assessment for the Jabana project site. The hazards identified here are merely the common hazards associated with diesel power plants. They are classified into two categories mainly: Technological hazards Areas where flammables, explosives, or chemicals are used or stored should be considered as the most likely place for a technological hazard emergency to occur. Examples of these hazards are:

• Fire • Explosion • Building collapse • Major structural failure • Spills of flammable liquids • Accidental release of toxic substances • Deliberate release of hazardous biological agents, or toxic chemicals • Loss of electrical power • Loss of water supply • Loss of communications

Natural Hazards

• Floods • Earthquakes • Other severe wind storms • Severe extremes in temperature (hot).

The possibility of one event triggering others must be considered. An explosion may start a fire and cause structural failure while an earthquake might initiate all the events noted in the list of chemical and physical hazards. What is the series of events or decisions that should be considered? Having identified the hazards, the possible major impacts of each should be itemized, such as:

• Sequential events (for example, fire after explosion) • Evacuation • Casualties • Damage to plant infrastructure • Loss of vital records/documents • Damage to equipment • Disruption of work

Page 122: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

122

Based on these events, the required actions are determined. For example: • Declare emergency • Sound the alert • Evacuate danger zone • Close main shutoffs • Call for external aid • Initiate rescue operations • Attend to casualties • Fight fire

The final consideration is a list and the location of resources needed:

• Medical supplies • Auxiliary communication equipment • Power generators • Respirators • Chemical and radiation detection equipment • Mobile equipment • Emergency protective clothing • Fire fighting equipment • Ambulance • Rescue equipment • Trained personnel

Elements of the emergency plan to be developed by the contractor The emergency plan should include; All possible emergencies, consequences, required actions, written procedures, and the resources available

• Detailed lists of personnel including their home telephone numbers, their duties and responsibilities • Floor plans, and • Large scale maps showing evacuation routes and service conduits (such as gas and water lines).

Since a sizable document will likely result, the plan should provide staff members with written instructions about their particular emergency duties. The following are examples of the parts of an emergency plan. These elements may not cover every situation in every workplace but serve they are provided as a general guideline when writing a workplace specific plan: Objective The objective is a brief summary of the purpose of the plan; that is, to reduce human injury and damage to property in an emergency. It also specifies those staff members who may put the plan into action. The objective identifies clearly who these staff members are since the normal chain of command cannot always be available on short notice. At least one of them must be on the site at all times when the premises are occupied. The extent of authority of these personnel must be clearly indicated. Organization One individual should be appointed and trained to act as Emergency coordinator as well as a "back-up" coordinator. However, personnel on the site during an emergency are key in ensuring that prompt and efficient action is taken to minimize loss. In some cases it may be possible to recall off-duty employees to help but the critical initial decisions usually must be made immediately.

Page 123: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

123

Specific duties, responsibilities, authority, and resources must be clearly defined. Among the responsibilities that must be assigned are:

• Reporting the emergency • Activating the emergency plan • Assuming overall command • Establishing communication • Alerting staff • Ordering evacuation • Alerting external agencies • Confirming evacuation complete • Alerting outside population of possible risk • Requesting external aid • Coordinating activities of various groups • Advising relatives of casualties • Providing medical aid • Ensuring emergency shut offs are closed • Sounding the all-clear

This list of responsibilities should be completed using the previously developed summary of countermeasures for each emergency situation. In organizations operating on reduced staff during some shifts, some personnel must assume extra responsibilities during emergencies. Sufficient alternates for each responsible position must be named to ensure that someone with authority is available onsite at all times. External organizations that may be available to assist (with varying response times) include:

• Fire department • Ambulance services • Police departments • Telephone company • Hospitals • Utility companies • Industrial neighbours • Government agencies

These organizations should be contacted in the planning stages to discuss each of their roles during an emergency. Mutual aid with other industrial facilities in the area should be explored.

Pre-planned coordination is necessary to avoid conflicting responsibilities. For example, the police, fire department, ambulance service, rescue squad, company fire brigade, and the first aid team may be on the scene simultaneously. A pre-determined chain of command in such a situation is required to avoid organizational difficulties. Under certain circumstances, an outside agency may assume command.

Possible problems in communication have been mentioned in several contexts. Efforts should be made to seek alternate means of communication during an emergency, especially between key personnel such as overall commander, on-scene commander, engineering, fire brigade, medical, rescue, and outside agencies. Depending on the size of the organization and physical layout of the premises, it may be advisable to plan for an emergency control centre with alternate communication facilities. All personnel with alerting or reporting responsibilities must be provided with a current list of telephone numbers and addresses of those people they may have to contact.

Page 124: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

124

Procedures Many factors determine what procedures are needed in an emergency, such as

• The degree of emergency, • The size of organization, • The capabilities of the organization in an emergency situation, • The immediacy of outside aid, • The physical layout of the premises, and • The number of structures determines procedures that are needed.

Common elements to be considered in all emergencies include pre-emergency preparation and provisions for alerting and evacuating staff, handling casualties, and for containing of the emergency. Natural hazards, such as floods or severe storms, often provide prior warning. The plan should take advantage of such warnings with, for example, instructions on sand bagging, removal of equipment to needed locations, providing alternate sources of power, light or water, extra equipment, and relocation of personnel with special skills. Phased states of alert allow such measures to be initiated in an orderly manner. The evacuation order is of greatest importance in alerting staff. To avoid confusion, only one type of signal should be used for the evacuation order. Commonly used for this purpose are sirens, fire bells, whistles, flashing lights, paging system announcements, or word-of-mouth in noisy environments. The all-clear signal is less important since time is not such an urgent concern. The following are "musts":

• Identify evacuation routes, alternate means of escape make these known to all staff; keep the routes unobstructed.

• Specify safe locations for staff to gather for head counts to ensure that everyone has left the danger zone. Assign individuals to assist handicapped employees in emergencies.

• Carry out treatment of the injured and search for the missing simultaneously with efforts to contain the emergency.

• Provide alternate sources of medical aid when normal facilities may be in the danger zone. • Containing the extent of the property loss should begin only when the safety of all staff and

neighbours at risk has been clearly established. Testing and Revision Completing a comprehensive plan for handling emergencies is a major step toward preventing disasters. However, it is difficult to predict all of the problems that may happen unless the plan is tested. Exercises and drills may be conducted to practice all or critical portions (such as evacuation) of the plan. A thorough and immediate review after each exercise, drill, or after an actual emergency will point out areas that require improvement. Knowledge of individual responsibilities can be evaluated through paper tests or interviews. The plan should be revised when shortcomings have become known, and should be reviewed at least annually. Changes in plant infrastructure, processes, and materials used and key personnel are occasions for updating the plan. It should be stressed that provision must be made for the training of both individuals and teams, if they are expected to perform adequately in an emergency. An annual full-scale exercise will help in maintaining a high level of proficiency.

Page 125: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

125

FIRE RISKS AND MANAGEMENT PLAN ELECTROGAZ, through the Urgent Electricity Rehabilitation Project is in the process of selecting a company to install a diesel power plant as part of the Urgent Electricity Rehabilitation that is aimed towards alleviating the power problems experienced in Rwanda. An Environmental Management Plan for the project has been developed and is contained as part of the EIA study report. Even though the EMP contains measures for mitigating the potential risk of fire occurrences in the power plant, the UERP Environmental Safeguards Advisor has developed a Fire Risk and Fire Management Plan aimed at setting out an outline of procedures to manage and suppress any fire out breaks that could occur during the functioning of the plant. This plan is a draft guideline and it is expected that the selected company will refine this plan upon the undertaking of a vulnerability/risk assessment. This fire safety plan has been developed and will make every effort to comply with and enforce the requirements of the Government of Rwanda Fire Code, and all other statues, policies, protocol, procedures and instructions as may be issued by the Kigali Fire Brigade. The plan is expected to provide for the safety of plant occupants through the elimination and control of fire hazards, maintenance of fire protection and life safety systems, establishment and implementation of fire safety plans, procedures, and inspections of the plant. The eventual contracted company to install the equipments will be expected to develop a written fire safety plan which is intended to protect occupants from fire and helps to ensure effective evacuation of the building under all emergency conditions. Application This Plan will have to be refined to incorporate the existing substation facility as well. Training Fire safety training and emergency evacuation practice drills for workers must be conducted jointly by a competent Security/Fire Safety firm no less than once every twelve months. Emergency Evacuation In the event of fire or other emergencies that require emergency evacuation of the plant, the procedures contained in this Fire Safety Plan shall be carried out upon refinement by the contractor. Emergency Procedures for Occupants Emergency procedures signage will be affixed to the wall at all key strategic points within the plant. Note: It should be mandatory to evacuate the plant upon sounding of the Fire Alarm. Upon Discovery of Fire: • Leave the fire area immediately and close all doors • Activate the Fire Alarm • Call the Kigali Fire Brigade • Leave building via nearest Exit • Do not return until it is declared safe to do so by a Fire Official

Page 126: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

126

Upon Hearing Fire Alarm: • Before opening doors, feel door and doorknob for heat. If they are not hot, brace yourself against

the door and open it slightly. If you see smoke, or feel air pressure or a hot draft, close the door quickly.

• Leave building via nearest Exit • Close all doors behind you

Fire Alarm Systems The purpose of the fire alarm system is to alert all occupants to a fire emergency so that evacuation procedures can be initiated. The fire alarm audible devices should be heard throughout the plant. The fire alarm system should consist of the following components: Alarm Initiating Devices – These devices should be installed throughout the plant designed to detect heat, smoke or flame causing an electrical signal to be sent to the Central Control Panel. Central Control Panel – A microprocessor-based device that receives and processes electrical signals from alarm initiating devices located throughout the plant including heat detectors, smoke detectors, manual pull stations, sprinkler system alarm switches, etc, then transmits signals that cause audible and visual alarm devices such as bells, horns, strobe lights, etc to operate. Annunciator Panel – a lighted or graphical display device, located in the main entrance to the plant that indicates the location or zone of the activated initiating device, e.g. detector that has responded to the presence of smoke, heat or flame; or a manual pull station that has been activated by an occupant. Signaling Devices – audible and visual devices (horns and strobe lights) located throughout the building in corridors and rooms to indicate the actuation of the fire alarm system. FIRE CODE MAINTENANCE REQUIREMENTS A certified firm should be contracted and made responsible to implement the following schedule of checks, tests & inspections; and will maintain records of tests, inspections and maintenance work performed. Records will be kept in a Fire Log Book at the Physical Plant Office and will be made available to the Chief Fire Official upon request. Required item Daily Check to ensure that all exit lights are not damaged, are illuminated and clearly legible.

• Check Fire alarm system for indication of trouble in the system. • Check Fire pump room temperature during freezing weather • Check that all fire separation doors are kept closed.

Weekly

• Check that unsupervised fire protection water supply system control valves are always fully open. • Check that air pressure on dry pipe sprinkler system is being maintained • Check Water level in fire pump reservoirs • Inspect Operate fire pump. The fire pump discharge pressure, suction pressure, Lubricating oil

level, operative condition of relief valves, priming water and general operating conditions shall be inspected during the weekly operation of the fire pump.

• Check Hoods, filters and ducts subject to combustible deposits and clean as necessary

Page 127: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

127

Monthly • Inspect all portable fire extinguishers • Check all fire alarm components, including standby power batteries • Test Fire alarm system • Test Voice communication to and from floor areas to the central alarm control facility • Inspect Hose cabinets to ensure hose position and that equipment is in place report deficiencies to

Fire Department. • Check all doors in fire separations • Test sprinkler alarms using alarm test connection (mechanical signal only) • Test all components of the emergency power systems, operate the emergency power generator

set under at least 30% of rated load for 60 minutes Every Two Months

• Test Electrical sprinkler supervisory transmitters and water flow devices Every Six Months

• Check and clean crankcase breathers, governors and linkages on emergency generators Annually

• Service All portable fire extinguishers • Test Fire alarm system in accordance with Government of Rwanda- "Inspection and Testing of Fire

Alarm Systems". • Test Fire alarm system voice communication in accordance with Government of Rwanda

"Inspection and Testing of Fire Alarm Systems". • Inspect Hose valves to ensure tightness and to ensure no water leakage • Inspect remove and re-rack hose and replace worn gaskets • Inspect Remove plugs or caps on fire department standpipe and hose system connections and

inspect the threads for wear, rust or obstruction. Plugs or caps will be secured wrench tight. • Check exposed sprinkler system pipe hangers • Check all sprinkler heads • Inspect remove plugs or caps on fire department sprinkler connections and inspect the threads for

wear, rust or obstruction. Plugs or caps will be secured wrench tight. • Test water flow on wet sprinkler system using most remote test connection • Test Trip-test dry pipe trip system • Test Flow of water supply using main drain valve • Test Fire pump at full rated capacity • Inspect All fire dampers and flue pipes and clean as necessary

As Required

• Recharge Extinguishers after use or as indicated by an inspection or when performing maintenance.

• Test hydrostatically test standpipe systems that have been modified, extended or are being

restored to use after a period of disuse exceeding one year • Check All doors in fire separations to ensure that they are closed

• Check to ensure that the fire department sprinkler and standpipe connections are clearly identified

and maintained free of obstructions for use at all times

Page 128: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

128

• Check to ensure that fire access routes and access panels or windows provided to facilitate access for fire fighting operations are not obstructed at all times by vehicles, gates, fences, building

• materials, vegetation, signs or any other form of obstruction

• Check maintain corridors free of obstructions Elimination of Ignition Sources All non essential ignition sources must be eliminated where flammable liquids are used or stored. The following is a list of some of the more common potential ignition sources: Open flames, such as cutting and welding torches, furnaces, matches, and heaters-these sources should be kept away from flammable liquids operations. Cutting or welding on flammable liquids equipment should not be performed unless the equipment has been properly emptied and purged with a neutral gas such as nitrogen. Chemical sources of ignition such as D.C. motors, switched, and circuit breakers-these sources should be eliminated where flammable liquids are handled or stored. Only approved explosion-proof devices should be used in these areas. Mechanical sparks-these sparks can be produced as a result of friction. Only non-sparking tools should be used in areas where flammable liquids are stored or handled. Static sparks-these sparks can be generated as a result of electron transfer between two contacting surfaces. The electrons can discharge in a small volume, raising the temperature to above the ignition temperature. Every effort should be made to eliminate the possibility of static sparks. Also proper bonding and grounding procedures must be followed when flammable liquids are transferred or transported. The storage of any flammable or combustible liquid shall not physically obstruct a means of egress from the building or area. Containers of flammable or combustible liquids will remain tightly sealed except when transferred, poured or applied. Remove only that portion of liquid in the storage container required to accomplish a particular job. Ventilation Every inside storage room will be provided with a continuous mechanical exhaust ventilation system. To prevent the accumulation of vapors, the location of both the makeup and exhaust air openings will be arranged to provide, as far as practical, air movement directly to the exterior of the building and if ducts are used, they will not be used for any other purpose. Removal of Incompatibles Materials that can contribute to a flammable liquid fire should not be stored with flammable liquids. Examples are oxidizers and organic peroxides, which, on decomposition, can generate large amounts of oxygen. Flammable Gases Generally, flammable gases pose the same type of fire hazards as flammable liquids and their vapors. Many of the safeguards for flammable liquids also apply to flammable gases, other properties such as toxicity, reactivity, and corrosivity also must be taken into account. Also, a gas that is flammable could produce toxic combustion products.

Page 129: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

129

Location and Marking of Extinguishers Extinguishers should be conspicuously located and readily accessible for immediate use in the event of fire. They should be located along normal paths of travel and egress. Wall recesses and/or flush-mounted cabinets should be used as extinguisher locations whenever possible. Extinguishers should be clearly visible. In locations where visual obstruction cannot be completely avoided, directional arrows should be provided to indicate the location of extinguishers and the arrows will be marked with the extinguisher classification. If extinguishers intended for different classes of fire are located together, they will be conspicuously marked to ensure that the proper class extinguisher selection is made at the time of a fire. Extinguisher classification markings will be located on the front of the shell above or below the extinguisher nameplate. Markings will be of a size and form to be legible from a distance of 3 feet. Condition Portable extinguishers should be maintained in a fully charged and operable condition. They should be kept in their designated locations at all times when not being used. When extinguishers are removed for maintenance or testing, a fully charged and operable replacement unit should be provided. Mounting and Distribution of Extinguishers Extinguishers should be installed on hangers, brackets, in cabinets, or on shelves. Extinguishers having a gross weight not exceeding 40 pounds should be so installed that the top of the extinguisher is not more than 3-1/2 feet above the floor. Extinguishers mounted in cabinets or wall recesses or set on shelves should be placed so that the extinguisher operating instructions face outward. The location of such extinguishers should be made conspicuous by marking the cabinet or wall recess in a contrasting color, which should distinguish it from the normal decor. Extinguishers must be distributed in such a way that the amount of time needed to travel to their location and back to the fire does not allow the fire to get out of control. OSHA requires that the travel distance for Class A and Class D extinguishers not exceed 75 feet. The maximum travel distance for Class B extinguishers is 50 feet because flammable liquid fires can get out of control faster that Class A fires. There is no maximum travel distance specified for Class C extinguishers, but they must be distributed on the basis of appropriate patterns for Class A and B hazards. Emergency Egress Every exit should be clearly visible, or the route to it conspicuously identified in such a manner that every occupant of the building will readily know the direction of escape from any point. At no time should exits be blocked. Any doorway or passageway which is not an exit or access to an exit but which may be mistaken for an exit should be identified by a sign reading "Not An Exit" or a sign indicating it actual use (i.e., "Storeroom"). Exits and accesses to exits should be marked by a readily visible sign. Each exit sign (other than internally illuminated signs) should be illuminated by a reliable light source providing not less than 5 foot-candles on the illuminated surface. Fire Drills The purpose of the fire drill is to ensure that supervisory staff and occupants are totally familiar with emergency evacuation procedures, resulting in orderly evacuation with efficient use of exit facilities.

Page 130: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

130

The Kigali Fire Brigade should oversee the fire drill and direct designated supervisory personnel to carry out the requirements of the Fire Safety Plan. All designated supervisory personnel should be provided access to the approved Fire Safety Plan prior to being assigned any fire related duties/responsibilities. The drill should be reported to the Fire Department prior to commencement, in accordance with “Required Procedures for the Conducting of Fire Drills”. The fire drill should include, but not necessarily be restricted to:

Checking of the annunciator panel Identifying the alarm source/location (the elevators are not to be used) Reviewing the fire alarm systems, silence and re-set procedures. Reviewing the Fire Safety Plan documents required By the Fire Code Practicing the emergency evacuation plan

Following each drill, all persons with delegated responsibility should attend a debriefing session to report on the actions and the reactions of the participants. The Plant Manager should keep a record of the date of the drill, who directed the drill, what actions were taken, any problems with supervisory personnel and what corrective actions can be taken. Information regarding the fire drills and Fire Code maintenance tasks should be entered in the Fire Log Book for inspection by the Chief Fire Official, if requested, and kept at the plant Reception Desk.

Page 131: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

131

ANNEX E. INCIDENT REPORTING SYSTEM AND INVESTIGATION PROCEDURE The Incident Reporting System should be designed to:

• Track and analyze employee injuries and illnesses, property and machinery damage, as well as serious events or near misses which might have resulted in personal injury, illness, or property and machinery damage

• Initiate the worker's compensation process, if necessary • Meet regulatory reporting requirements

All incidents (accidents resulting in injury or causing illness to employees) and events (near-miss accidents) should be reported in order to:

• Establish a written record of factors, which cause injuries and illnesses and occurrences (near-misses), which might have resulted in injury or illness but did not, as well as property and machinery damage.

• Maintain a capability to promptly investigate incidents and events in order to initiate and support corrective and/or preventive action.

• Provide statistical information for use in analyzing all phases of incidents and events involving personnel.

• Provide the means for complying with the reporting requirements for occupational injuries and illnesses

The Incident Reporting System requirements apply to all incidences involving personnel arising out of or in the course of employment, which results in (or might have resulted in) personal injury, illness, and/or property and machinery damage. A. Incidents (Occupational injuries and illnesses) Injuries and illnesses that require reporting include those injuries and illnesses occurring on the job which result in any of the following: lost work time, restrictions in performing job duties, requirement for first aid or outside medical attention, permanent physical bodily damages, or death. Examples of "reportable injuries and illnesses include, but are not limited to, heat exhaustion from working in hot environments, strained back muscles from moving equipment, acid burns on fingers, etc. Other incidents requiring reporting include those incidents occurring on the job which result in any of the following: injury or illness, damage to a machine, fire/explosion, property damage or chemical releases requiring evacuation of at least that immediate spill area. Examples of reportable incidents include denting the fender of machines/equipment, and release of pressurized air through a leaking valve into a room. Examples of "non-reportable" injuries and illnesses include small paper cuts, common colds, and small bruises not resulting in work restrictions or requiring first aid or medical attention. B. Events (Near Misses) Other incidents which, strictly by chance, do not result in actual or observable injury, illness, death, or property damage required to be reported. The information obtained from such reporting can be extremely useful in identifying and mitigating problems before they result in actual personal or property damage. Examples of near miss incidences required to be reported include the falling of a compressed gas cylinder, overexposures to chemical, biological, or physical agents (not resulting in an immediately observable manifestation of illness or injury), and slipping and falling on a wet surface without injury.

Page 132: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

132

Personnel Responsibilities All personnel have a responsibility to report all occupational injuries and illnesses, and other incidents or events under the Incident Reporting System. A. Committee of Health and Safety OHS has the overall responsibility for implementing the Incident Reporting System, including review of incident/event reports, recommendation of corrective and/or preventive actions, and maintaining record keeping required by the regulations. B. Supervision Supervisors are primarily responsible for ensuring that the Incident Report and appropriate workers compensation forms are completed and distributed as indicated on the forms in a timely manner. C. Personnel All employees must be familiar with the procedures for reporting occupational injuries and illnesses and hazardous conditions or situations in which employees may be potentially exposed. All personnel have the responsibility to initiate the incident reporting sequence by informing their supervisors immediately of an actual or potential injury or illness as soon as possible after an incident has occurred. Incident Reporting Procedures and Practices This section describes the specific procedures that shall be followed by personnel in order to effectively report occupational injuries and illnesses and other incidents or events. A. Incidents (Injuries and Illnesses) Serious injury or illness posing a life-threatening situation should be reported immediately to the local emergency response medical services (Call 911). Injuries and illnesses should be reported by the injured employee to his or her supervisor in person or by phone as soon after any life-threatening situation has been addressed. If the injured employee is unable to report immediately, then the incident should be reported as soon as possible. B. Events Incidents not involving injury or illness, but resulting in property damage, must also be reported on within 48 hours of the incident. In cases of a fire or explosion that cannot be controlled by one person, vehicular accident resulting in injury or damage, or a chemical release requiring a building evacuation, the involved party must immediately report the incident to the emergency response services in the area (911 - police, fire, etc.) If injuries or illnesses occur, the reporting must follow those procedures outlined in above. All near miss incidences are also required to be reported on the Incident Report Form within 48 hours of occurrence. In place of indicating the result of the incident (i.e., actual personal or property damage), the reporting person shall indicate the avoided injury or damage.

Page 133: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

133

Events, hazardous working conditions or situations, and incidents involving contractor personnel must be reported to OHS immediately. C. Record keeping OHS will maintain the required and summary of (recordable) Occupational Injuries and Illnesses and the Supplementary Record of Occupational Injuries and Illnesses for each calendar year. Incident Investigations OHS personnel should review each reported incident and event to:

1. Determine if further investigation is required and then perform the investigation 2. Make recommendations for corrective and/or preventative actions necessary to reduce or eliminate

hazardous conditions and monitor the status of the abatement actions. Health and Safety Manual Each new employee should be given a copy of the Health and Safety Manual upon starting employment. This manual describes health and safety programs and is available to the employee as a reference dealing with health and safety issues. Training To ensure that personnel are cognizant of the Incident Reporting System requirements and are aware of their own and other's responsibilities, a series of informational and instructional training opportunities should exist. Personnel new to the plant should attend New Employee Orientation training, which will inform them on organizational structure, resources, and procedures. This orientation will ensure that new personnel are aware of the existence of this Manual and of its contents, and who the responsible persons in their organizations are. Review and Audit The effectiveness of a program can only be accomplished if the program is implemented. Therefore, periodic reviews and audits should be conducted to confirm that all employees have obtained a copy of this Manual and are familiar with the incident reporting requirements. Furthermore, review and auditing should include an inspection of report submissions and filing systems. Implementation Implementation of the Incident Reporting System should be effected through a combination of mechanisms. The general theme of these means is focused on program education, understanding, and awareness which include:

• Distribution of the Health and Safety Manual • Training for supervisors • Program review and audit

Page 134: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

134

ANNEX F. GENERAL ENVIRONMENTAL MANAGEMENT CONDITIONS • In addition to these general conditions, the Contractor shall comply with any specific Environmental

Management Plan (EMP) for the works he is responsible for. The Contractor shall inform himself about such an EMP, and prepare his work strategy and plan to fully take into account relevant provisions of that EMP. If the Contractor fails to implement the approved EMP after written instruction by the Supervising Engineer (SE) to fulfil his obligation within the requested time, the Owner reserves the right to arrange through the SE for execution of the missing action by a third party on account of the Contractor.

• Notwithstanding the Contractor’s obligation under the above clause, the Contractor shall implement all

measures necessary to avoid undesirable adverse environmental and social impacts wherever possible, restore work sites to acceptable standards, and abide by any environmental performance requirements specified in an EMP. In general these measures shall include but not be limited to:

(a) Minimize the effect of dust on the surrounding environment resulting from earth mixing sites, asphalt mixing sites, dispersing coal ashes, vibrating equipment, temporary access roads, etc. to ensure safety, health and the protection of workers and communities living in the vicinity dust producing activities.

(b) Ensure that noise levels emanating from machinery, vehicles and noisy construction activities (e.g. excavation, blasting) are kept at a minimum for the safety, health and protection of workers within the vicinity of high noise levels and nearby communities. (c) Ensure that existing water flow regimes in the adjacent Nyabugogo river and other natural or irrigation channels is maintained and/or re-established where they are disrupted due to works being carried out. (d) Prevent bitumen, oils, lubricants and waste water used or produced during the execution of works from entering into the Nyabugogo River, and CORIKA rice irrigation channel and also ensure that stagnant water in uncovered borrow pits is treated in the best way to avoid creating possible breeding grounds for mosquitoes. (e) Prevent and minimize the impacts of quarrying, earth borrowing, piling and building of temporary construction camps and access roads on the biophysical environment including protected areas and arable lands; local communities and their settlements. In as much as possible restore/rehabilitate all sites to acceptable standards. (f) Upon discovery of ancient heritage, relics or anything that might or believed to be of archeological or historical importance during the execution of works, immediately report such findings to the SE so that the appropriate authorities may be expeditiously contacted for fulfilment of the measures aimed at protecting such historical or archaeological resources.

(g) Implement soil erosion control measures in order to avoid surface run off and prevents siltation, etc.

(h) Ensure that garbage, sanitation and drinking water facilities are provided in for construction workers. (i) Ensure that, in as much as possible, local materials are used to avoid importation of foreign material and long distance transportation.

Page 135: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

135

(j) Ensure public safety, and meet traffic safety requirements for the operation of work to avoid accidents.

• The Contractor shall indicate the period within which he/she shall maintain status on site after completion

of civil works to ensure that significant adverse impacts arising from such works have been appropriately addressed.

• The Contractor shall adhere to the proposed activity implementation schedule and the monitoring plan /

strategy to ensure effective feedback of monitoring information to project management so that impact management can be implemented properly, and if necessary, adapt to changing and unforeseen conditions.

• Besides the regular inspection of the sites by the SE for adherence to the contract conditions and

specifications, the Owner may appoint an Inspector to oversee the compliance with these environmental conditions and any proposed mitigation measures. State environmental authority (REMA) may carry out similar inspection duties. In all cases, as directed by the SE, the Contractor shall comply with directives from such inspectors to implement measures required to ensure the adequacy rehabilitation measures carried out on the bio-physical environment and compensation for socio-economic disruption resulting from implementation of any works.

Worksite Waste Management • All vessels (drums, containers, bags, etc.) containing oil/fuel/surfacing materials and other hazardous

chemicals shall be bunded in order to contain spillage. All waste containers, litter and any other waste generated during the construction shall be collected and disposed off at designated disposal sites in line with applicable government waste management regulations.

• All drainage and effluent from storage areas, workshops shall be captured and treated before being

discharged into the drainage system in line with applicable government water pollution control regulations.

• Used oil from maintenance shall be collected and disposed off appropriately at designated sites or be re-used or sold for re-use locally.

• Entry of runoff to the site shall be restricted by constructing diversion channels or holding structures such

as banks, drains, dams, etc. to reduce the potential of soil erosion and water pollution. • Construction waste shall not be left in stockpiles along the road, but removed and reused or disposed of

on a daily basis. • If disposal sites for clean spoil are necessary, they shall be located in areas, approved by the SE, of low

land use value and where they will not result in material being easily washed into drainage channels. Whenever possible, spoil materials should be placed in low-lying areas and should be compacted and planted with species indigenous to the locality.

Material Excavation and Deposit • The Contractor shall obtain appropriate licenses/permits from relevant authorities to operate quarries or

borrow areas.

Page 136: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

136

• The location of quarries and borrow areas shall be subject to approval by relevant local and national authorities, including traditional authorities if the land on which the quarry or borrow areas fall in traditional land.

• New extraction sites:

a. Shall not be located in the vicinity of settlement areas, cultural sites, wetlands or any other valued ecosystem component, or on on high or steep ground or in areas of high scenic value, and shall not be located less than 1km from such areas.

b. Shall not be located adjacent to stream channels wherever possible to avoid siltation of river channels. Where they are located near water sources, borrow pits and perimeter drains shall surround quarry sites.

c. Shall not be located in archaeological areas. Excavations in the vicinity of such areas shall proceed with great care and shall be done in the presence of government authorities having a mandate for their protection.

d. Shall not be located in forest reserves. However, where there are no other alternatives, permission shall be obtained from the appropriate authorities and an environmental impact study shall be conducted.

e. Shall be easily rehabilitated. Areas with minimal vegetation cover such as flat and bare ground, or areas covered with grass only or covered with shrubs less than 1.5m in height, are preferred.

f. Shall have clearly demarcated and marked boundaries to minimize vegetation clearing. • Vegetation clearing shall be restricted to the area required for safe operation of construction work.

Vegetation clearing shall not be done more than two months in advance of operations. • Stockpile areas shall be located in areas where trees can act as buffers to prevent dust pollution.

Perimeter drains shall be built around stockpile areas. Sediment and other pollutant traps shall be located at drainage exits from workings.

• The Contractor shall deposit any excess material in accordance with the principles of these general

conditions, and any applicable EMP, in areas approved by local authorities and/or the SE. • Areas for depositing hazardous materials such as contaminated liquid and solid materials shall be

approved by the SE and appropriate local and/or national authorities before the commencement of work. Use of existing, approved sites shall be preferred over the establishment of new sites.

Rehabilitation and Soil Erosion Prevention • To the extent practicable, the Contractor shall rehabilitate the site progressively so that the rate of

rehabilitation is similar to the rate of construction. • Always remove and retain topsoil for subsequent rehabilitation. Soils shall not be stripped when they are

wet as this can lead to soil compaction and loss of structure. • Topsoil shall not be stored in large heaps. Low mounds of no more than 1 to 2m high are recommended.

Page 137: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

137

• Re-vegetate stockpiles to protect the soil from erosion, discourage weeds and maintain an active population of beneficial soil microbes.

• Locate stockpiles where they will not be disturbed by future construction activities. • To the extent practicable, reinstate natural drainage patterns where they have been altered or impaired. • Remove toxic materials and dispose of them in designated sites. Backfill excavated areas with soils or

overburden that is free of foreign material that could pollute groundwater and soil. • Identify potentially toxic overburden and screen with suitable material to prevent mobilization of toxins. • Ensure reshaped land is formed so as to be inherently stable, adequately drained and suitable for the

desired long-term land use, and allow natural regeneration of vegetation. • Minimize the long-term visual impact by creating landforms that are compatible with the adjacent

landscape. • Minimize erosion by wind and water both during and after the process of reinstatement. • Compacted surfaces shall be deep ripped to relieve compaction unless subsurface conditions dictate

otherwise. • Revegetate with plant species that will control erosion, provide vegetative diversity and, through

succession, contribute to a resilient ecosystem. The choice of plant species for rehabilitation shall be done in consultation with local research institutions, forest department and the local people.

Water Resources Management • The Contractor shall at all costs avoid conflicting with water demands of local communities. • Abstraction of both surface and underground water shall only be done with the consultation of the local

community and after obtaining a permit from the relevant Water Authority. • Abstraction of water from wetlands shall be avoided. Where necessary, authority has to be obtained from

relevant authorities. • Temporary damming of streams and rivers shall be done in such a way avoids disrupting water supplies

to communities down stream, and maintains the ecological balance of the river system. • No construction water containing spoils or site effluent, especially cement and oil, shall be allowed to flow

into natural water drainage courses. • Wash water from washing out of equipment shall not be discharged into water courses or road drains. • Site spoils and temporary stockpiles shall be located away from the drainage system, and surface run off

shall be directed away from stockpiles to prevent erosion. Traffic management • Location of access roads/detours shall be done in consultation with the local community especially in

important or sensitive environments. Access roads shall not traverse wetland areas.

Page 138: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

138

• Upon the completion of civil works, all access roads shall be ripped and rehabilitated. • Access roads shall be sprinkled with water at least five times a day in settled areas, and three times in

unsettled areas, to suppress dust emissions. Disposal of unusable elements • Unusable materials and construction elements such as electro-mechanical equipment, pipes, accessories

and demolished structures will be disposed of in a manner approved by the SE. The Contractor has to agree with the SE which elements are to be surrendered to the Client’s premises, which will be recycled or reused, and which will be disposed of at approved landfill sites.

• As far as possible, abandoned pipelines shall remain in place. Where for any reason no alternative

alignment for the new pipeline is possible, the old pipes shall be safely removed and stored at a safe place to be agreed upon with the SE and the local authorities concerned.

• AC-pipes as well as broken parts thereof have to be treated as hazardous material and disposed of as

specified above. • Unsuitable and demolished elements shall be dismantled to a size fitting on ordinary trucks for transport. Health and safety • In advance of the construction work, the Contractor shall mount an awareness and hygiene campaign.

Workers and local residents shall be sensitized on health risks particularly of AIDS. • Adequate road signs to warn pedestrians and motorists of construction activities, diversions, etc. shall be

provided at appropriate points. • Construction vehicles shall not exceed maximum speed limit of 40km per hour. Repair of private property • Should the Contractor, deliberately or accidentally, damage private property, he shall repair the property

to the owner’s satisfaction and at his own cost. For each repair, the Contractor shall obtain from the owner a certificate that the damage has been made good satisfactorily in order to indemnify the Client from subsequent claims.

• In cases where compensation for inconveniences, damage of crops etc. are claimed by the owner, the

Client has to be informed by the Contractor through the SE. This compensation is in general settled under the responsibility of the Client before signing the Contract. In unforeseeable cases, the respective administrative entities of the Client will take care of compensation.

Contractor’s environment, health and safety management plan Within 6 weeks of signing the Contract, the Contractor shall prepare an EHS-MP to ensure the adequate management of the health, safety, environmental and social aspects of the works, including implementation of the requirements of these general conditions and any specific requirements of an EMP for the works. The Contractor’s EHS-MP will serve two main purposes: For the Contractor, for internal purposes, to ensure that all measures are in place for adequate EHS management, and as an operational manual for his staff.

Page 139: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

139

For the Client, supported where necessary by a SE, to ensure that the Contractor is fully prepared for the adequate management of the EHS aspects of the project, and as a basis for monitoring of the Contractor’s EHS performance. The Contractor’s EHS-MP shall provide at least:

• A description of procedures and methods for complying with these general environmental management conditions, and any specific conditions specified in an EMP;

• A description of specific mitigation measures that will be implemented in order to minimize adverse impacts;

• A description of all planned monitoring activities (e.g. sediment discharges from borrow areas) and the reporting thereof; and

• The internal organizational, management and reporting mechanisms put in place for such. The Contractor’s EHS-MP will be reviewed and approved by the Client before start of the works. This review should demonstrate if the Contractor’s EHS-MP covers all of the identified impacts, and has defined appropriate measures to counteract any potential impacts. EHS Reporting The Contractor shall prepare bi-weekly progress reports to the SE on compliance with these general conditions, the project EMP if any, and his own EHS-MP. An example format for a Contractor EHS report is given below. It is expected that the Contractor’s reports will include information on:

• EHS management actions/measures taken, including approvals sought from local or national authorities;

• Problems encountered in relation to EHS aspects (incidents, including delays, cost consequences, etc. as a result thereof);

• Lack of compliance with contract requirements on the part of the Contractor; • Changes of assumptions, conditions, measures, designs and actual works in relation to EHS

aspects; and • Observations, concerns raised and/or decisions taken with regard to EHS management during site

meetings. It is advisable that reporting of significant EHS incidents be done “as soon as practicable”. Such incident reporting shall therefore be done individually. Also, it is advisable that the Contractor keeps his own records on health, safety and welfare of persons, and damage to property. It is advisable to include such records, as well as copies of incident reports, as appendixes to the bi-weekly reports. Example formats for an incident notification and detailed report are given below. Details of EHS performance will be reported to the Client through the SE’s reports to the Client. Training of Contractor’s Personnel The Contractor shall provide sufficient training to his own personnel to ensure that they are all aware of the relevant aspects of these general conditions, any project EMP, and his own EHS-MP, and are able to fulfil their expected roles and functions. Specific training should be provided to those employees that have particular responsibilities associated with the implementation of the EHS-MP. General topics should be:

• EHS in general (working procedures); • emergency procedures; and • Social and cultural aspects (awareness raising on social issues).

Page 140: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

140

Cost of compliance It is expected that compliance with these conditions is already part of standard good workmanship and state of art as generally required under this Contract. The item “Compliance with Environmental Management Conditions” in the Bill of Quantities covers these costs. No other payments will be made to the Contractor for compliance with any request to avoid and/or mitigate an avoidable EHS impact.

Page 141: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

141

ANNEX G. Example Format: EHS Report Contract: Period of reporting: EHS management actions/measures: Summarize EHS management actions/measures taken during period of reporting, including planning and management activities (e.g. risk and impact assessments), EHS training, specific design and work measures taken, etc. EHS incidents: Report on any problems encountered in relation to EHS aspects, including its consequences (delays, costs) and corrective measures taken. Include relevant incident reports. EHS compliance: Report on compliance with Contract EHS conditions, including any cases of non-compliance. Changes: Report on any changes of assumptions, conditions, measures, designs and actual works in relation to EHS aspects. Concerns and observations: Report on any observations, concerns raised and/or decisions taken with regard to EHS management during site meetings and visits. Signature (Name, Title Date): Contractor Representative

Page 142: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

142

ANNEX H. Example Format: EHS Incident Notification Provide within 24 hrs to the Supervising Engineer Originators Reference No: Date of Incident: Time: Location of incident: Name of Person(s) involved: Employing Company: Type of Incident: Description of Incident: Where, when, what, how, who, operation in progress at the time (only factual) Immediate Action: Immediate remedial action and actions taken to prevent reoccurrence or escalation Signature (Name, Title, Date): Contractor Representative

Page 143: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

143

Example Format: Detailed EHS Incident Report The Incident Notification should be follow-up by a Detailed EHS Incident Report containing the following information where applicable 1. Incident Summary 2. Specific Details

• Date • Time • Place • Weather/Visibility • Road conditions

3. Persons Involved

• Name/s • Age/s • Experience • Date joined Company • Last Medical Check • Current Medical Treatment • Evidence of Drugs/Alcohol • Last Safety Meeting attended • Infringements/Incidents record

4. Equipment Involved 5. Description of Incident 6. Findings of Investigation Team Interim/Final

• Investigation Team Members • Persons Interviewed • Recommendations & Remedial Actions • Investigation Methodology

7. Signature (Name, Title, Date): 8. Attachments

• Photographs • Witness Statements and Incident Notification Report

Page 144: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

144

ANNEX J. REMA Approval of EA Report

Page 145: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

145

ANNEX L. Site Layout Map and Location Map

Page 146: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility

146

Page 147: Republic of Rwanda - World Bankdocuments.worldbank.org/curated/en/... · EXECUTIVE SUMMARY Introduction and Study Objectives ... • Identification of project site including feasibility