Report Department for Transport€¦ · trains and main depot. 19% Percentage increase in the...
Transcript of Report Department for Transport€¦ · trains and main depot. 19% Percentage increase in the...
HC 1924 SESSION 2017–2019 28 FEBRUARY 2019
A picture of the National Audit Office logo
Reportby the Comptroller and Auditor General
Department for Transport
A memorandum on the Crossrail programme
Our vision is to help the nation spend wisely.
Our public audit perspective helps Parliament hold government to account and improve public services.
The National Audit Office scrutinises public spending for Parliament and is independent of government. The Comptroller and Auditor General (C&AG), Sir Amyas Morse KCB, is an Officer of the House of Commons and leads the NAO. The C&AG certifies the accounts of all government departments and many other public sector bodies. He has statutory authority to examine and report to Parliament on whether departments and the bodies they fund, nationally and locally, have used their resources efficiently, effectively, and with economy. The C&AG does this through a range of outputs including value-for-money reports on matters of public interest; investigations to establish the underlying facts in circumstances where concerns have been raised by others or observed through our wider work; landscape reviews to aid transparency; and good-practice guides. Our work ensures that those responsible for the use of public money are held to account and helps government to improve public services, leading to audited savings of £741 million in 2017.
HC 1924 | £10.00
Report by the Comptroller and Auditor General
Ordered by the House of Commons to be printed on 25 February 2019
This report has been prepared under Section 6 of the National Audit Act 1983 for presentation to the House of Commons in accordance with Section 9 of the Act
Sir Amyas Morse KCB Comptroller and Auditor General National Audit Office
22 February 2019
Department for Transport
A memorandum on the Crossrail programme
© National Audit Office 2019
The material featured in this document is subject to National Audit Office (NAO) copyright. The material may be copied or reproduced for non-commercial purposes only, namely reproduction for research, private study or for limited internal circulation within an organisation for the purpose of review.
Copying for non-commercial purposes is subject to the material being accompanied by a sufficient acknowledgement, reproduced accurately, and not being used in a misleading context. To reproduce NAO copyright material for any other use, you must contact [email protected]. Please tell us who you are, the organisation you represent (if any) and how and why you wish to use our material. Please include your full contact details: name, address, telephone number and email.
Please note that the material featured in this document may not be reproduced for commercial gain without the NAO’s express and direct permission and that the NAO reserves its right to pursue copyright infringement proceedings against individuals or companies who reproduce material for commercial gain without our permission.
Links to external websites were valid at the time of publication of this report. The National Audit Office is not responsible for the future validity of the links.
007232 02/19 NAO
This memorandum sets out background information about the Crossrail programme and the current position.
Contents
What is Crossrail? 7
Introduction to this guide 4 Key facts 5 Summary 6
Why are the government and TfL building Crossrail? 10
Who is paying for Crossrail? 13
Who is delivering Crossrail? 15
How is Crossrail being delivered? 21
When will Crossrail be complete and open? 24
Introduction
History of the Crossrail project
Elizabeth line services
Increasing capacity and reducing congestion
Improving connectivity
Government and TfL projections of the benefits of Crossrail
The governance and delivery structure
How governance and delivery works
Crossrail Ltd
Crossrail Ltd, previous Board
Issues identified with governance and information on the programme
Events leading to the announcement of delays
Progress against the timetable for opening the railway
Remaining work
The main component parts of the programme
Integration of a complex programme
Crossrail funding and financing model
How the funding position has changed
Design & Production by NAO External Relations | DP Ref: 007232-001
The National Audit Office study team consisted of: Hedley Ayres, Lee Nicholson, Kristian Barrett and Riaz Rahman, under the direction of Lee-Anne Murray.
This report can be found on the National Audit Office website at www.nao.org.uk
For further information about the National Audit Office please contact:
National Audit Office – Press Office 157–197 Buckingham Palace Road Victoria, London, SW1W 9SP
Tel: 020 7798 7400
Enquiries: www.nao.org.uk/contact-us Website: www.nao.org.uk Twitter: @NAOorguk
3
Previous examinations of Crossrail by PAC and the NAO 27
A memorandum on the Crossrail programme Introduction to this guide 4
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Introduction to this guide
We have produced this memorandum on the Crossrail programme to support Parliamentary scrutiny of Crossrail in light of events that transpired during the second half of 2018. From July 2018, it became clear that programme costs were increasing significantly. In August 2018 Crossrail Ltd announced that it would not meet planned opening dates for the railway. In November 2018, the Chair of the Committee of Public Accounts wrote to the Comptroller and Auditor General and asked him to examine the reasons for cost and schedule increases.
The final cost remains uncertain. There is currently no date for when the railway will be fully operational.
This Memorandum sets out the background to the Crossrail programme, including why and how it is being built, and who is building and paying for it. It also includes public statements about when the Department for Transport (the Department), Transport for London (TfL) and Crossrail Ltd expect services to operate, how much they currently estimate the programme will cost, and what funding has been committed to the programme. It is based mainly on publicly available information.
The National Audit Office (NAO) will be publishing a value-for-money study on the programme in Spring 2019. The NAO’s report will examine:
• the underlying causes of the delays and cost increases;
• the reasons why the programme unravelled in 2018, and why issues emerged so quickly and with such a significant cost increase; and
• the actions sponsors and Crossrail Ltd have taken to get the programme on track, and our assessment of whether these actions are likely to be sufficient.
Depending on the progress of the programme by the time we report, it will also set out the expected forecast cost and delivery schedule, and assess the programme’s remaining future risks.
A memorandum on the Crossrail programme Key facts 5
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
December 2018
Original date when the Crossrail sponsors and Crossrail Ltd expected to start running services on the central section of the railway.
£2.05 billion
Value of loans from HM Government, including £1.3 billion to the Greater London Authority and £750 million as contingency to TfL to cover the increased cost of Crossrail, as announced in December 2018. The Greater London Authority has also committed a cash contribution of £100 million.
£600 million
Current assumption of revenue losses to TfL between 2019-20 and 2023-24, as a result of delays to the opening of Crossrail services.
118 kilometres
Approximate length of the line between Heathrow and Reading in the west and Shenfield and Abbey Wood in the east, on which Elizabeth line services will operate once the Crossrail programme is complete.
26 miles/42 kilometres
Approximate length of new tunnels in the central section of the railway.
10
New stations being built as part of the Crossrail programme.
Unknown
Revised opening date for Crossrail.
£14.8 billion
Funding package, including contingency, agreed in the 2010 Spending Review to cover the delivery of the Crossrail programme, excluding trains and main depot.
19%
Percentage increase in the funding available for the Crossrail programme.
£17.6 billion
Current total funding package for Crossrail, including contingency, but excluding trains and depots following government announcements in July and December 2018.
Key facts
A memorandum on the Crossrail programme Summary 6
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Summary
Crossrail is a complex programme to provide new rail services between Reading and Heathrow west of London and Shenfi eld and Abbey Wood. It includes a new underground railway beneath central London.
It remains unclear when the central section of the railway will open, with Crossrail Ltd having missed its target to open this section in December 2018. Crossrail Ltd does not yet have a fi rm estimate of the revised cost to complete the programme.
The Department and TfL are sponsoring and funding Crossrail jointly. The sponsors expect the railway to reduce congestion, increase capacity, reduce journey times and enable economic growth.
During 2018 sponsors and Crossrail Ltd made a series of announcements about signifi cant cost increases and delays to the programme.
Crossrail Ltd is responsible for delivering the programme, from building the line and stations, through to integrating systems and providing an operational railway. Crossrail Ltd is a company wholly owned by TfL with an independent board.
A memorandum on the Crossrail programme What is Crossrail? 7
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Introduction History of the Crossrail project
Elizabeth line services
Introduction
Crossrail is a major programme to run new, direct rail services between Reading and all passenger terminals of Heathrow Airport at the western ends of the railway, through a new underground section beneath central London to Shenfield in Essex and Abbey Wood in south-east London at the eastern ends.
When complete, the railway will be around 118km long, with around 26 miles (42 kilometres) of new tunnels in the central section between Paddington and Canary Wharf, and at Woolwich. There are 10 new stations being built as part of the Crossrail programme, and a further 31 are being improved.
Once Crossrail is open, it will become part of TfL’s rail and underground network, and will be known as the Elizabeth line.
READING
HILLINGDON
EALING
HA
MM
ERSM
ITH &
FULH
AM
WINDSOR & MAIDENHEAD
SLOUGH
SOUTH BUCKSISLINGTON
CAMDEN
WESTMINSTER
KENSIN
GTON &
CHELSEA
BEXLEY
BRENTWOOD
HAVERING
BARKING & DAGENHAM
REDBRIDGE
GREENWICH
NEWHAM
TOWER HAMLETS
CITY OF LONDON
WOKINGHAM
T1,2,3
T4
T5
SouthallHanwell
West Ealing
Ealing BroadwayWest
Drayton Hayes & Harlington Acton
Main LineTottenham Court Road Canary
WharfAbbey Wood
Custom House
Bond Street
Forest Gate
Manor Park
Seven Kings
Paddington
Farringdon
Iver
Heathrow
LangleySlough
BurnhamTaplow
Maidenhead
Reading
Twyford
Whitechapel
Woolwich
IlfordGoodmayes
Chadwell Heath Gidea
Park
Harold Wood
Romford
Brentwood
Shenfield
Maryland
Stratford
Liverpool Street
Surface line
Tunnel
Portal (tunnel entrance and exit)
DistrictOverground
Hammersmith& City
CentralJubilee
Hammersmith& City
MetropolitanCircle
LutonGatwick
DLRCentralNorthern
DistrictCentral
OvergroundDLRJubileeCentral
Hammersmith& CityBakerloo
Circle
District NorthernCentral
Stansted
Hammersmith& City
Southend
MetropolitanCircle
PiccadillyHeathrow
DLRDLR
DLRJubilee
Surface line
Tunnel
Portal (tunnel entrance and exit)
National Rail connection
Airport connection
Airports not on the Crossrail route - to travel to these airports passengers will need to travel on other connecting rail services. Step-free travel is possible but assistance will be required to get on and o� some trains. Travel from Luton Airport Parkway Station to Luton Airport is via an accessible bus.
Route Map Showing rail and air connectionsRoute Map
Source: Crossrail Limited, Regional Map. Available at: www.crossrail.co.uk/route/maps/
Figure 1 Crossrail regional map
A memorandum on the Crossrail programme What is Crossrail? 8
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Introduction History of the Crossrail project
Elizabeth line services
History of the Crossrail project
Crossrail has a long history. In 1974 and 1980, feasibility studies concluded that it would be too costly a scheme to build and in 1994 a private members bill to build Crossrail was defeated. The current incarnation of Crossrail goes back to 2002, when the newly formed Cross London Rail Links (which became Crossrail Ltd in 2009) assessed the feasibility of the scheme again, after the Strategic Rail Authority
recommended that new rail links should be built across London to relieve existing and forecast overcrowding and to reduce congestion on the rail network between east and west. Legislation required to build the railway gained Royal Assent in 2008 in the form of the Crossrail Act. Construction started in 2009 on the first Crossrail site, Canary Wharf station.
Figure 2 Crossrail development timeline
1974 and 1980 2000 20102007 20141991 2001 20112008 20151994 2005 20122009 2017
1991
First Crossrail Bill (private) introduced
1994
Crossrail Bill defeated in the Commons
2002
Cross London Rail Links established to assess feasibility and develop the business case for Crossrail
2012
Tunnelling starts
Jul 2014
TfL awards contracts to operate Crossrail services to MTR
May 2015
Tunnelling completes and TfL takes over services between Shenfield and Liverpool Street
2005
Crossrail Bill introduced
2008
Crossrail Bill gains Royal Assent
2009
Cross London Rail links renamed ‘Crossrail Limited’. In May, work starts on Canary Wharf station
2011
Crossrail Limited passes ‘Review Point 4’ to gain autonomy to deliver the programme. This was the final point at which sponsors could pull out
Source: National Audit Offi ce analysis of departmental information
1974 and 1980
Two feasibility studies (1974 and 1980) conclude that Crossrail would be too costly a project to approve. The proposed scheme becomes known as ‘Crossrail’ for the first time
2000
Government commissions the Strategic Rail Authority to examine options for relieving congestion on London’s rail network. The Authority recommends that the Crossrail programme be developed
2007
The Department and TfL agree a funding package of £15.9 billion for Crossrail, including £2.3 billion financed by Network Rail
2010
As part of the 2010 Spending Review, government and TfL agreed to reduce the funding package by more than £1 billion, from £15.9 billion to £14.8 billion
Jun 2017
Services between Shenfield and Liverpool Street commence, although a month later than planned
Feb 2014
TfL awards contracts to design, build and maintain a fleet of trains
A memorandum on the Crossrail programme What is Crossrail? 9
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Introduction History of the Crossrail project
Elizabeth line services
Elizabeth line services
When Crossrail is complete and fully open, passengers will have access to a large number of new services for travelling between east and west. Figure 3 summarises the promised peak-time service frequency.
Figure 3Planned Elizabeth line services at peak times
Section of the railway Examples of service frequency at peak times
Central section 24 trains an hour between Paddington and Whitechapel stations
Eastern section 12 trains an hour between Shenfi eld and central London; an additional four trains an hour will run between Gidea Park and Liverpool Street main-line station
South-eastern section 12 trains an hour between Abbey Wood and Canary Wharf, and central London
Western section 6 trains an hour between Maidenhead and central London
4 trains an hour between Reading and central London
4 trains an hour between Heathrow Terminals 2, 3 and 4 and central London
2 trains an hour between Heathrow Terminals 2, 3 and 5 and central London
Source: Crossrail Ltd
A memorandum on the Crossrail programme Why are the government and TfL building Crossrail? 10
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Increasing capacity and reducing congestion
Improving connectivity Government and TfL projections of the benefits of Crossrail
Increasing capacity and reducing congestion
One of the main objectives of Crossrail – and central to the business case for the programme – is the need to increase capacity on the underground and main-line rail network in London to meet future demand, thereby reducing congestion on some of the most overcrowded lines on the London Underground network. According to Crossrail Ltd’s website, Crossrail will increase capacity on the rail network in central London by around 10%.
In 2010, the Crossrail business case forecast that London’s population would continue to grow, with nearly 1.3 million additional people living in London and 750,000 new jobs being created between 2010 and 2031, and that annual growth in demand for peak-time public transport would increase to around 1.5% a year. At that time, Crossrail Ltd estimated that Crossrail would carry around 200,000 people each day during the morning peak.
Figures 4a and 4b shown on the right, which are taken from the 2010 business case, show that Crossrail Ltd was forecasting that the introduction of Crossrail services to the network could result in peak-time reductions in overcrowding of between 20% and 60% on the Bakerloo, Central, District and Jubilee lines of the London Underground as well as reductions in overcrowding on the national rail network.
Source: Crossrail business case, July 2010. Available at: https://webarchive.nationalarchives.gov.uk/20120215100250/http:/assets.dft.gov.uk/publications/crossrail-business-case-update/crossrail-business-case-update-summary-report-july-2011.pdf
Figure 4aLondon Underground crowding changes with Crossrail 2026
Source: Crossrail business case, July 2010. Available at: https://webarchive.nationalarchives.gov.uk/20120215100250/http:/assets.dft.gov.uk/publications/crossrail-business-case-update/crossrail-business-case-update-summary-report-july-2011.pdf
Figure 4bRail crowding changes with Crossrail 2026
Crossrail business case Summary report
The transport case for Crossrail6
Figure ETube Crowding Changes with Crossrail 2026
Figure FRail Crowding Changes with Crossrail 2026
Over 10%
0% to 10%0% to -10%-10% to -30%
Over -30%
2026 LUL crowding di�erence
This schematic map does not include all details of the network
Woolwich Arsenal
Amersham
Watford
Moor Park
Walthamstow Central
Harrow & Wealdstone
South Ruislip
West Ruislip
Stanmore
Edgware High Barnet CockfostersEpping
UpminsterNotting Hill Gate
North ActonPaddington
Finsbury Park
King's Cross
CanaryWharf
LiverpoolStreet
OxfordCircus
Charing Cross
Holborn
Euston
Morden
Brixton
Stratford
LondonBridge
Blackfriars
Bank
Waterloo
Stockwell
VictoriaEarl’sCourt
Hammersmith
Willesden Jct
Lewisham
Beckton
Ealing Broadway
Wimbledon
Richmond
Heathrow
Uxbridge
Barking
Green Park
Mill Hill East
Woodford
Over 10%
0% to 10%0% to -10%-10% to -30%
Over -30%
2026 National Rail crowding di�erence
This schematic map does not include all details of the network
A memorandum on the Crossrail programme Why are the government and TfL building Crossrail? 11
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Increasing capacity and reducing congestion
Improving connectivity Government and TfL projections of the benefits of Crossrail
Improving connectivity
Improving connectivity was one of Crossrail’s main objectives. When the railway is fully open and all services are running – the timing for which is not yet clear – Crossrail will provide a direct link between London’s existing major employment centres, including Heathrow, the City of Westminster and the West End (Paddington and Bond Street), the City of London (Farringdon and Liverpool Street) and Canary Wharf. Crossrail has interchanges with most London Underground lines, the Docklands Light Railway, and the London Overground, as well as main-line stations including Stratford, Woolwich, Paddington and a number of stations on the Great Western and Great Eastern main lines.
§ Check before you travel§ Services to/from some stations are subject to variation. Please search ‘TfL stations’ for full details.
Riverboat services
Trams
Emirates Air Line
Metropolitan
Victoria
Circle
Central
Bakerloo
DLR
Piccadilly
Waterloo & City
Jubilee
Hammersmith & City
Northern
District
District open at weekendsand on some public holidays
Emirates Air Line
London Overground
Victoria Coach Station
Transport for London This diagram is an evolution of the original design conceived in 1931 by Harry Beck · DRAFT based on July 2017 specifications
National Rail
Airport
Interchange stations
Step-free access from street to platform
Step-free access from street to train
Elizabeth
The Elizabeth line - December 2019
River Thames
Regent’s Park
GoodgeStreet
Bayswater
Warren Street
Aldgate
RussellSquare
High Street Kensington
Old Street
Green Park
BakerStreet
NottingHill Gate
Victoria
Mansion House
Temple
TowerHill
Westminster
PiccadillyCircus
CharingCross
Holborn
Tower Gateway
Monument
Leicester SquareSt. Paul’s
Hyde Park Corner
Knightsbridge
Angel
Queensway
Marble Arch
SouthKensington
SloaneSquare
Covent Garden
Great PortlandStreet
BankChancery Lane
LancasterGateHolland
Park
Cannon Street
Fenchurch Street
GloucesterRoad St. James’s
Park
EustonSquare
EdgwareRoad
EdgwareRoad
Embankment
Blackfriars
King’s CrossSt. Pancras
Marylebone
Watford High Street
Watford Junction
Bushey
Carpenders Park
Hatch End
North Wembley
South Kenton
Kenton
Wembley Central
Kensal Green
Queen’s Park
Stonebridge Park
Bethnal Green
Cambridge Heath
London Fields
Harlesden
Willesden Junction
Headstone Lane
Harrow &Wealdstone
Kilburn Park
Warwick Avenue
Maida Vale
Euston
New Cross Gate
Imperial Wharf
West Croydon
ClaphamJunction
Crystal Palace Norwood Junction
Sydenham
Forest Hill
Anerley
Penge West
Honor Oak Park
Brockley
Wapping
New Cross
Queens RoadPeckham
Peckham Rye
Denmark Hill
Surrey Quays
WandsworthRoad
Rotherhithe
ShoreditchHigh Street
Haggerston
Hoxton
Shepherd’sBush
Shadwell
CanadaWater
Fulham Broadway
West Brompton
Parsons Green
Putney Bridge
East Putney
Southfields
Wimbledon Park
Wimbledon
Kensington(Olympia)
AldgateEast
BethnalGreen Mile End
Dalston Kingsland
HackneyWick
Homerton
HackneyCentral
Rectory Road
HackneyDowns
Theydon Bois
Epping
Debden
Loughton
Buckhurst Hill
Leytonstone
Wood StreetBruce Grove
White Hart Lane
Silver Street
Edmonton Green
Southbury
Turkey Street
Theobalds Grove
CheshuntEnfield Town
StamfordHill
Bush Hill Park
Highams Park
Chingford
Leyton
Woodford
South Woodford
Snaresbrook
Hainault
Fairlop
Barkingside
Newbury Park
RodingValley
GrangeHill
Chigwell
Redbridge
GantsHill
Wanstead
Dalston Junction
Canonbury
Stepney Green
SevenSisters
Highbury &Islington
TottenhamHale
WalthamstowCentral
Clapton
St. James Street
Stoke Newington
Dagenham East
Dagenham Heathway
Becontree
Upney
Upminster
Upminster Bridge
Hornchurch
Elm Park
HarringayGreenLanes
WansteadPark
LeytonstoneHigh Road
LeytonMidland Road
Emerson Park
South Tottenham
Blackhorse Road
Barking
East Ham
Plaistow
Upton Park
Upper Holloway
Crouch Hill
GospelOak
BowChurch
West Ham
BowRoad
Bromley-by-Bow
Island Gardens
Greenwich
Deptford Bridge
South Quay
Crossharbour
Mudchute
Heron Quays
West India Quay
Elverson Road
Devons Road
Langdon Park
All Saints
Canary Wharf
Cutty Sark for Maritime Greenwich
Lewisham
EmiratesGreenwichPeninsula
Westferry Blackwall
CanningTown
PoplarLimehouse EastIndia
StratfordInternational
Star Lane
NorthGreenwich
Oakwood
Cockfosters
Southgate
Arnos Grove
Bounds Green
Turnpike Lane
Wood Green
Manor House
FinsburyPark
Arsenal
KentishTown West
Holloway Road
Caledonian Road
Mill Hill East
Edgware
Burnt Oak
Colindale
Hendon Central
Brent Cross
Golders Green
Hampstead
Belsize Park
Chalk Farm
Camden Town
High Barnet
Totteridge & Whetstone
Woodside Park
West Finchley
Finchley Central
East Finchley
Highgate
Archway
Tufnell Park
Kentish Town
MorningtonCrescent
CamdenRoad
CaledonianRoad &
Barnsbury
Amersham
Chorleywood
Rickmansworth
Chalfont &Latimer
Chesham
Moor Park
Croxley
Watford
Northwood
Northwood Hills
Pinner
North Harrow
Harrow-on-the-Hill
Northwick Park
Preston Road
Wembley ParkRayners Lane
Stanmore
Canons Park
Queensbury
Kingsbury
Neasden
Dollis Hill
Willesden Green
Swiss Cottage
Kilburn
West Hampstead
Finchley Road
WestHarrow
IckenhamUxbridge
Hillingdon Ruislip
Ruislip Manor
Eastcote
St. John’s Wood
Northfields
Boston Manor
SouthEaling
Osterley
Hounslow Central
Hounslow East
Hounslow West
Hatton Cross
Perivale
Hanger Lane
Ruislip Gardens
South Ruislip
Greenford
Northolt
South Harrow
Sudbury Hill
Sudbury Town
Alperton
Park Royal
North Ealing
West Ruislip
Ealing Common
Gunnersbury
Kew Gardens
Richmond
Acton Town
ChiswickPark
TurnhamGreen
StamfordBrook
RavenscourtPark
WestKensington
BaronsCourt
Earl’sCourt
Shepherd’sBush Market
Goldhawk Road
Hammersmith
Wood Lane
WhiteCity
Finchley Road& Frognal
KensalRise
BrondesburyPark
Brondesbury
Kilburn High Road
South Hampstead
WestActon
NorthActon
EastActon
Southwark
Waterloo
London Bridge Bermondsey
Vauxhall
Lambeth NorthPimlico
Stockwell
Brixton
Elephant & Castle
Oval
Kennington
Borough
Clapham North
Clapham High Street
Clapham Common
Clapham South
Balham
Tooting Bec
Tooting Broadway
Colliers Wood
South Wimbledon
Morden
LadbrokeGrove
Latimer Road
Royal Oak
Westbourne Park
PuddingMill Lane
Acton Central
South Acton
HampsteadHeath
Stratford High Street
Abbey Road
WoodgrangePark
WalthamstowQueen’s Road
Oxford Circus
Paddington
West Silvertown
EmiratesRoyal Docks
PontoonDock
LondonCity Airport
WoolwichArsenal
King George V
Prince Regent
Royal Albert
Beckton Park
Cyprus
Beckton
Gallions Reach
RoyalVictoria
Romford
Farringdon
BondStreet
Moorgate
LiverpoolStreet
TottenhamCourt Road
Paddington WhitechapelActon
Main Line
Stratford
Custom House for ExCeL
Abbey Wood
Woolwich
WestDrayton
Slough
Burnham
Twyford
Reading
Maidenhead
Ilford
Goodmayes
Chadwell Heath
Gidea Park
Harold Wood
Shenfield
Brentwood
Seven Kings
Maryland
Manor Park
Forest Gate
Iver
Langley
Taplow
WestEaling
Southall
HanwellHayes &
Harlington
EalingBroadway
Barbican
HeathrowTerminal 5
HeathrowTerminal 4
HeathrowTerminals 2 & 3
Source: Crossrail route map. Available at: www.crossrail.co.uk/route/maps/
Figure 5Crossrail (the Elizabeth line) as it will appear on the London Underground map
A memorandum on the Crossrail programme Why are the government and TfL building Crossrail? 12
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Increasing capacity and reducing congestion
Improving connectivity Government and TfL projections of the benefits of Crossrail
Government and TfL projections of the benefits of Crossrail
The benefit–cost ratio in the latest 2011 update of the business case was 1.97. This means every £1 invested in Crossrail would achieve £1.97 of benefits to the economy. The assessed benefits of Crossrail in the economic appraisal of the programme are shorter journey times and less congestion. This is within the Department’s definition of ‘medium’ value for money, a range of 1.5 to 2. The benefit–cost ratio increases to £3.10 of benefits for every £1 of investment in Crossrail if estimated wider economic benefits are included. Crossrail Ltd has not updated the business case since 2011.
The business case states that Crossrail will bring about a wide range of additional economic and social benefits. For example:
• The Elizabeth line will bring 1.5 million more people within a 45-minute commute of the existing major employment centres of the West End, the City and Canary Wharf (up from 5 million currently), and make major international gateways like London Heathrow more accessible.
• Crossrail will support up to 14,000 construction jobs and 1,000 jobs operating and maintaining the railway once complete.
A memorandum on the Crossrail programme Who is paying for Crossrail? 13
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
The Crossrail funding and financing model
How the funding position has changed
The Crossrail funding and financing model
Crossrailtotal,
£17,570m
DfT direct funding (original), £4,960m
Loan from DfT to GLA, £1,300m
Loan from DfT to TfL (contingency), £750m
City of London Corporation committed funding, £250m
DfT additional funding (July 18), £150m
HAL, £70mNR financing for work on existing network, £2,300mVoluntary funding from London
businesses, £100m
DfT additional funding for NR, £290m
Contribution from GLA, £100mTfL direct funding (original), £1,900m
Business rate supplement, borrowing and direct contribution, £4,100m
Sale of surplus land and property, £550m
Community infrastructure levy, £300mDeveloper
contributions, £300m
TfL additional funding (July 18), £150m
Figure 6 Breakdown of contributions to the Crossrail funding package of £17.6 billion
Notes
1 Cost in £ millions, includes £750 million contingency loan announced in December 2018. Excludes the cost of the rolling stock and depot.
2 GLA = Greater London Authority; DfT = Department for Transport, TfL = Transport for London; NR = Network Rail; HAL = Heathrow Airport Limited.
3 Precise levels of funding from some sources, such as sale of surplus land and property may be subject to change.
Source: National Audit Offi ce analysis of departmental information
A memorandum on the Crossrail programme Who is paying for Crossrail? 14
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
The Crossrail funding and financing model
How the funding position has changed
How the funding position has changed
Funding for the project has increased by £2.8 billion to £17.6 billion
In 2007 the government announced a funding package from project sponsors of £15.9 billion for the infrastructure elements of the project, including improvements to the existing network to be delivered by Network Rail.
In 2010 project sponsors reduced available funding to £14.8 billion to reflect savings identified and revised cost estimates.
Reflecting cost pressures, in July 2018 the Department announced that project sponsors had agreed an additional £590 million of funding, bringing the overall funding to £15.4 billion.
Reflecting delays and further cost increases, in December 2018 the Department announced that it would loan £1.3 billion to the Greater London Authority (GLA). The GLA intend to repay this loan via London’s Business Rate Supplement and from the Community Infrastructure Levy. In addition the Department announced a £750 million loan could be made available to Transport for London (TfL) as additional contingency. The GLA has also agreed to make an additional cash contribution of £100 million. The total funding package for the infrastructure project is now £17.6 billion. The final cost of the programme is not yet known.
The upfront capital cost of rolling stock and depot is around £1 billion. The capital cost of the trains was funded directly by TfL and is outside the main funding package shown in Figure 7. In January 2018, TfL announced its intention to sell the rolling stock and to lease it back from the buyer, in order to release capital to invest in the enhancement of other tube lines. This transaction has not yet been concluded.
2007 2010 Jul 2018 Dec 2018
15.9 14.8 15.4 17.6
0
2
4
6
8
10
12
14
16
18
20
Figure 7Funding package
£ billion
Funding package (£bn)
Source: National Audit Office analysis of departmental information
A memorandum on the Crossrail programme Who is delivering Crossrail? 15
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
The governance and delivery structure
Crossrail Ltd Crossrail Ltd, previous Board
Issues identified with governance and information on the programme
How governance and delivery works
Network Rail
Delivering work on existing network
Rail for London (part of TfL)
Responsible for the rolling stock contract and the contract with the private sector operator of the railway
Suppliers and partners
Delivery
Sponsor oversight Department for Transport (DfT)
Programme sponsor and funder
Joint Sponsor Board
Monthly forum for sponsors to receive updates on, and challenge the Crossrail Ltd executive on, programme progress Four members (two from TfL and two from DfT – including one at director general level); rotating chair
Joint Sponsor Team
Supports the Sponsor Board – made up of representatives from TfL and DfT
Transport for London (TfL)
Programme sponsor and funder, and responsible for operating Elizabeth line services
Crossrail Project Representative (Jacobs)
Embedded in CRL. Reports on progress to sponsor team and carries out specific investigations at sponsors’ request
Reports to
Organisational oversight
Supplier
Informal reporting
Partners
Crossrail Ltd (CRL) Board
Independently chaired; TfL and DfT non-executive representatives; three executive-members (chief executive officer, chief financial officer, deputy chief executive officer); non-executives including chair and deputy
Construction and systems contractors Rolling stock contractor
(Bombardier)
Operator
(MTR Crossrail)
Figure 8 The governance and delivery structure
Source: National Audit Offi ce analysis of departmental information
Crossrail Ltd
Wholly-owned subsidiary of TfL, set up to deliver the programme. Overall responsibility for programme integration and delivery of the operational railway
Post publication this page was found to contain an error which has been corrected (Please find Published Correction Slip)
A memorandum on the Crossrail programme Who is delivering Crossrail? 16
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
The governance and delivery structure
Crossrail Ltd Crossrail Ltd, previous Board
Issues identified with governance and information on the programme
How governance and delivery works
How governance and delivery works
Sponsor oversight
The Department and TfL are jointly sponsoring the Crossrail project. A number of agreements formalise delivery and governance arrangements:
• An agreement between the Department and TfL, which sets out the respective responsibilities of the two sponsors and how the programme will be governed.
• A Project Development Agreement between the Department, TfL and Crossrail Ltd, which defines Crossrail Ltd’s overall responsibility for successful delivery of Crossrail, including construction, integrating the programme and making preparations for operating the railway. The project development agreement did not state how sponsors would gain assurance about Crossrail Ltd’s readiness to move to the operational phase of the programme.
• A protocol between Network Rail and Crossrail Ltd sets out Network Rail’s responsibilities for delivering the surface elements of the route.
A joint sponsor board oversees the programme and meets monthly to discuss progress on the programme. A joint sponsor team supports the sponsor Board, and is made up of staff from TfL and the Department. The Project Representative (P-Rep) is a team of engineers and project management specialists from engineering firm Jacobs that is contracted by the sponsors to provide support and advice to the sponsor team and sponsor board. It reviews and provides commentary on Crossrail Ltd’s regular progress reports, as well as carrying out focused reviews of particular aspects of the programme.
In the project development agreement, the sponsors and Crossrail Ltd agreed a set of ‘intervention points’ to encourage Crossrail Ltd to keep its own direct costs within available funding, and set out actions sponsors could take in the event that forecast costs increased above specified thresholds. Crossrail Ltd’s forecast costs breached the first two intervention points in November 2015 and June 2017 respectively, which resulted in sponsors seeking assurance that Crossrail Ltd could bring costs under control.
The project formally breached the final intervention point in May 2018. At this stage, TfL could have required the Department to take ownership of Crossrail Ltd and either wind-up or continue with the project. In the event, sponsors decided not to take this option, but sought further assurances from Crossrail Ltd that it could bring costs under control.
1/2
A memorandum on the Crossrail programme Who is delivering Crossrail? 17
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
The governance and delivery structure
Crossrail Ltd Crossrail Ltd, previous Board
Issues identified with governance and information on the programme
How governance and delivery works
How governance and delivery works
Delivery
Crossrail Ltd is a company wholly owned by TfL that is responsible for delivering the programme, from building the line and stations, through to integrating systems and providing an operational railway. The main governance body overseeing delivery of the programme is the Crossrail Ltd Board. Sponsors’ oversight of the programme has been through appointed non-executive members of the Board and through discussions with the Crossrail Executive at the Sponsor Board. The Crossrail Board does not report to the sponsor Board.
The Crossrail delivery model, which involves the establishment of a separate delivery body, was previously used on the programme to develop the Olympic Park (now the Queen Elizabeth Olympic Park) in Newham, east London, and to construct the venues required for the 2012 London Olympic and Paralympic Games. This model is now being used on, for example, High Speed 2. The Crossrail model differs from the Olympics and High Speed 2 in that the Olympic Delivery Authority was, and High Speed 2 Ltd is, a non-departmental public body sponsored by government departments, and chief executive officers who are/were also accounting officers.
Crossrail Ltd earned autonomy from the sponsors to deliver the programme – meaning that it had, for example, authority to award major contracts – by passing four review points between July 2008 and April 2011. In our January 2014 report on Crossrail we recommended that the Department should finalise its plans for the development of governance arrangements as appropriate for the transition from construction to operation.
Suppliers
Crossrail is being delivered through contracts between Crossrail Ltd and a range of private sector suppliers, including programme delivery partners, Bechtel and Transcend (a consortium of AECOM, CH2M Hill and Nichols Group), Siemens, and other joint ventures from firms including Alstom, Costain, Skanska and Balfour-Beatty. These main contractors have contracts with other suppliers for the supply of services, materials and components of the railway. The contract to design, build and maintain the trains is between TfL and Bombardier Transportation.
Although Network Rail is a public sector body sponsored by the Department, on the Crossrail programme it functions as a partner to Crossrail Ltd, funded directly by the Department, with its responsibilities set out in the protocol agreement between Network Rail and Crossrail Ltd.
2/2
A memorandum on the Crossrail programme Who is delivering Crossrail? 18
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
The governance and delivery structure
Crossrail Ltd Crossrail Ltd, previous Board
Issues identified with governance and information on the programme
How governance and delivery works
Crossrail Ltd
There were significant changes to the executive team and board during 2018 to strengthen Crossrail Ltd’s capabilities:
• The Crossrail Board approved the appointment of a new executive management team during late 2018. The sponsors also approved the appointment of the chair and chief executive.
• Crossrail Ltd’s current Board of Directors is chaired by Tony Meggs, previously the Chief Executive of the Infrastructure and Projects Authority, following the resignation of Sir Terry Morgan in December 2018.
• The new Chief Executive, Mark Wild, was previously a non-executive member of the Crossrail Board and has been appointed on secondment from his role as Managing Director of London Underground.
• Three members of Crossrail’s Board have been with the project for more than one year (Figure 9).
The sponsors have increased their representation on Crossrail Ltd’s Board to increase scrutiny and support transition to operations:
• The Board now includes two non-executive directors nominated by the Department.
• TfL now has two appointed non-executive nominees on the Board.
• Up to mid-2018, each sponsor only had one nominated non-executive member on the Board.
Chairman
Tony Meggs(from 14 Jan 2019)
Deputy Chief Executive
Chris Sexton(from 1 Apr 2018)
Chief Finance Officer
David Hendry(from 10 Nov 2018)
Non-ExecutiveTfL nominee
Dr Nelson Ogunshakin(from 1 Jul 2018)
Non-ExecutiveIndependent
Phil Gaffney(from 2011)
Non-ExecutiveDepartment
nominee
Robert Jennings CBE
(from 2009)
Non-ExecutiveDepartment
nominee
Andy Pitt(from 1 Jul 2018)
Chief Executive
Mark Wild(from 19 Nov 2018)
Previously TfL nominee
Deputy ChairmanIndependent
Nick Raynsford(from 14 Jan 2019)
Non-ExecutiveTfL nominee
Anne McMeel(from 1 July 2018)
Figure 9Crossrail Ltd Board of Directors at February 2019
Note
1 The Chief Executive, Deputy Chief Executive and Chief Finance Offi cer are executive members of the board.
Source: Crossrail Ltd
Board member for less than one year
Board member for more than one year
A memorandum on the Crossrail programme Who is delivering Crossrail? 19
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
The governance and delivery structure
Crossrail Ltd Crossrail Ltd, previous Board
Issues identified with governance and information on the programme
How governance and delivery works
Crossrail Ltd, previous Board
Figure 10 Crossrail Ltd Board of Directors at 31 March 2018
Chairman
Sir Terry Morgan(until 5 Dec 2018)
Non-ExecutiveIndependent
Phil Gaffney (from 2011)
Chief Executive
Andrew Wolstenholme (to 31 Mar 2018)
Non-ExecutiveDepartment nominee
Robert Jennings CBE (from 2009)
Programme Director
Simon Wright (Chief Executive from Apr to Nov 2018)
Non-Executive (SID)
Terry Hill (until 30 Jun 2018)
Non-Executive
Michael Cassidy (until 30 Jun 2018)
Finance Director
Mathew Duncan (until 9 Nov 2018)
Non-Executive
Pam Alexander (until 30 Jun 2018)
Non-ExecutiveTfL nominee
Mark Wild (from Sep 2016) Chief Executive since 19 Nov 2018
Remuneration in 2017-18 Salary Performance related pay for 2016-17
Compensation for loss of employment
Benefits in kind Total remuneration (excluding pension contributions)
Total remuneration (excluding pension contributions)
2017-18 2017-18 2017-18 2017-18 2017-18 2016-17
(£000) (£000) (£000) (£000) (£000) (£000)
Andrew Wolstenholme, Chief Executive 477 160 98 2 736 946
Simon Wright, Programme Director 329 106 – 2 436 494
Sir Terry Morgan, Non-Executive Chairman 250 – – 2 252 252
Mathew Duncan, Finance Director 247 112 – 2 361 270
Note1 The sponsor agreement, to which the Department and TfL are parties, sets out the Remuneration Principles governing the remuneration and benefi ts package which applies to all members of the Crossrail Ltd Board. The Crossrail Ltd Remuneration Committee
develops the Remuneration Framework, consistent with the Remuneration Principles. TfL approves the Remuneration Framework and ensures that the Secretary of State is provided with the approved Framework promptly. The Secretary of State may object to any part of the Remuneration Framework or a specifi c remuneration and benefi ts package which is not consistent with the Remuneration Principles and TfL shall take appropriate action to ensure that the inconsistency is addressed. The remuneration and benefi ts package of the executive directors of Crossrail Ltd and the chair and chief executive offi cer of Crossrail Ltd is determined by the Crossrail Ltd Remuneration Committee in accordance with the Remuneration Framework and in consultation with TfL.
Source: Transport for London Annual Report and Statement of Accounts, 2017-18
Remains a Board member
No longer a Board member
Crossrail Ltd senior remuneration
Post publication this page was found to contain an error which has been corrected (Please find Published Correction Slip)
A memorandum on the Crossrail programme Who is delivering Crossrail? 20
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
The governance and delivery structure
Crossrail Ltd Crossrail Ltd, previous Board
Issues identified with governance and information on the programme
How governance and delivery works
Issues identified with governance and information on the programme
Figure 11The Department and TfL commissioned KPMG to perform three reviews of the programme
Review Purpose
Financial and commercial(published January 2019)
Available at: http://content.tfl .gov.uk/fi nancial-and-commercial-redacted.pdf
To establish the extent to which Crossrail Ltd’s fi nancial modelling refl ects the true state of the fi nances of the programme. It was a high-level assessment and did not include detailed analysis of the programme schedule or remaining works. It found that based on this information, it expected the programme to need between £1.6 billion and £2 billion more to complete the programme, including the additional £300 million announced in July 2018.
The sponsors used this work to determine the revised funding package, and the amount the Department would loan the Greater London Assembly and TfL.
Governance (published January 2019)
Available at: http://content.tfl .gov.uk/governance-redacted.pdf
To assess how governance and oversight of the programme had been working, and to make recommendations for improvement. It examined the relationship between the sponsors and Crossrail Ltd, and information coming to the Crossrail Board and on to the sponsors. It found that:
• Reporting within, and by, Crossrail Ltd was neither timely, nor suffi ciently clear, as to the impacts and magnitude of the range of probable consequences of issues within the programme.
• Crossrail has taken action to update governance arrangements to refl ect the changing nature of the programme. For example, Crossrail Ltd has created the Elizabeth line Strategic Steering Group. However, the revised governance arrangements have not suffi ciently refl ected the changing balance between construction, systems, integration and operational readiness activities.
• The Project Representative reported many of the key issues and risks to achieving the December 2018 opening date for the central section, but did not provide an assessment of the potential or likely impact on the opening date. KPMG found that the Project Representative did not adequately challenge Crossrail Ltd in its assumptions that it could recover delays, but this is not necessarily the view of sponsors.
• There was a much-reduced level of internal scrutiny during 2017-18 and 2018-19, as the Crossrail Board continued with its plans to reduce central resources. This included reduced internal audit coverage and disbanding the Crossrail Limited Audit Committee in July 2018 and the reallocation of its responsibilities.
The sponsors are considering what actions to take as a result of the review.
Timeline of events To validate the Department’s timeline of events between November 2017 when the explosion at Pudding Mill Lane occurred, and October 2018. The fi rst phase of this work confi rmed that the Department’s timeline was largely consistent with source documents. A second phase is now underway to produce a more detailed timeline of events. Sponsors plan to publish this work once the second phase is complete.
Source: KPMG reviews
A memorandum on the Crossrail programme How is Crossrail being delivered? 21
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
The main component parts of the programme
Integration of a complex programme
The main component parts of the programme
The Crossrail programme has the following main components:
Tunnels
The 26 miles of Crossrail tunnels were created by eight tunnel-boring machines, each lowered into a series of shafts along the route. The machines cut their way beneath London with precision, removing spoil and creating the main structure of tunnels as they went.
Systemwide track and electrification
Once the tunnels had been built, concrete slab track and the steel railway itself could be laid, as well as the overhead lines required to provide power to the trains, and the systems needed to operate the railway.
Stations
The Crossrail programme required the construction of 10 new stations; seven of them below ground in the central section and three on the existing network. The programme also included the enhancement of 31 existing stations. Each station platform is around 240 metres long to accommodate the 200-metre-long, nine-carriage trains. A range of complex IT systems support management of the stations, including keeping passengers safe, and ensuring that they can move efficiently through the stations.
Trains and depots
In February 2014, TfL awarded the contract to design, build and maintain the trains that will run on the Elizabeth line (including a maintenance depot). The new Class 345 trains have new systems to provide passengers with information. Passengers are able to walk through the train from carriage to carriage and each train is designed to carry 1,500 passengers.
Railway operations
In July 2014, TfL awarded a concession contract to Mass Transit Railway (MTR), a transport operating company based in Hong Kong, to operate Elizabeth line services. MTR Crossrail began running services on the eastern section of the railway in May 2015 and has a contract to operate services for eight years, with an option to extend to 10 years.
Post publication this page was found to contain an error which has been corrected (Please find Published Correction Slip)
A memorandum on the Crossrail programme How is Crossrail being delivered? 22
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
The main component parts of the programme
Integration of a complex programme
Integration of a complex programme
The design of the programme involves a number of complex elements.
The trains
Crossrail’s new Class 345 trains are the first of a new class of train involving new systems and software. They will be run with nine carriages and will be nearly twice the length of a tube train, and are designed to carry 1,500 passengers.
Signalling
The Crossrail trains will use an on-board Train Control and Management System (TCMS) to integrate information from a range of signalling systems to maintain safe and effective operations. The nature of the Crossrail route, which runs on both the existing national network and a new section of underground railway will use three separate signalling systems: Train Protection Warning System (TPWS), which is used on the mainline sections of the railway and is focused on ensuring safe operation of the railway; and two separate systems – Communication Based Train Control (CBTC) and European Train Control System (ETCS) – which use technology on the trackside and train to identify the position of trains and issue instructions to both maintain safety and enable the railway to operate with shorter distances between trains to increase overall capacity. The safe and efficient operation of Crossrail services depends on the TCMS software being able to switch between these three systems as the trains move from one part of the route to another. This transition between signalling systems has not been used in this way before on the UK’s railways. Figure 12 shows which signalling systems are being used on which sections of the railway.
Operational systems
To maintain safe and efficient management of stations, Crossrail will use Supervisory Control and Data Acquisition (SCADA) software. These systems require data collection sensors to be installed in stations to enable key systems such as on-platform sliding doors, lifts and escalators to be monitored effectively.
Stations
A number of the stations on the Crossrail route have been designed to a high architectural specification. Examples of complex design features include the roof and ceiling of the ticket hall at Farringdon station and the extensive use of a large steel and glass canopy at Paddington station to bring in natural light.
Mark Wild, Crossrail Ltd Chief Executive, has stated that integrating the stations into the new railway and into the wider London underground and national rail network is a significant undertaking. There are around 60,000 different elements that must be integrated for the stations to operate effectively. TfL would usually undertake this activity once a year. Crossrail Ltd is developing its schedule and approach to do this for 10 stations in a compressed timeframe.
1/2
A memorandum on the Crossrail programme How is Crossrail being delivered? 23
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
The main component parts of the programme
Integration of a complex programme
Integration of a complex programme 2/2
Train Protection Warning System (TPWS)
European Train Control System L2 (ETCS L2)
Communication Based Train Control (CBTC)
Train Protection Warning SystemTrain Protection Warning System European Train Control System L2
Communication Based Train ControlEuropean Train Control System L2
To Reading
Taplow
Stratford
Burnham
Maryland Chadwell Heath
Langley
Manor Park
Gidea Park Brentwood
West Drayton
Seven Kings
West Ealing
Acton Mainline
Bond Street
Tottenham Court Road
Liverpool Street
Farringdon Custom House
WoolwichCanary Wharf
Whitechapel
Southall
Slough
Forest Gate
Iver
Ilford
Hayes &Harlington
Goodmayes
Ealing Broadway
HaroldWood
Hanwell
Romford
MAIDENHEAD
SHENFIELD
HEATHROW
PADDINGTON(Main)
PADDINGTON(Low Level)
ABBEY WOOD
Note
1 TPWS will be used from Reading to Paddington until ETCS is fi tted on the Great Western main line.
Source: Crossrail Ltd
Figure 12 Signalling systems on the Crossrail route
A memorandum on the Crossrail programme When will Crossrail be complete and open? 24
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Events leading to the announcement of delays
Progress against the timetable for opening the railway
Remaining work
Events leading to the announcement of delays
From late 2017, cost pressures escalated, eventually causing costs to exceed the revised £14.8 billion funding agreed by sponsors in 2010.
Risks to the schedule began to materialise. First there were delays to the train software, and then delays to the testing of the trains in the tunnels. Crossrail produced a revised schedule to allow testing while construction and fit out continued, but in August 2018 it was decided that the December 2018 deadline for opening the central section could not be met. 2017 2018
Jun 2017
Crossrail raises concerns with sponsors regarding uncertainty of timely development of on-board signalling and train control management software.
Crossrail reports that costs have breached Intervention Point 1, triggering a drawdown of funds from a Transport for London (TfL) Contingency Fund of £600 million.
Mar 2018
Crossrail produces a revised opening schedule, stating that December 2018 is still achievable, but increasingly challenging.
Crossrail reports that costs have breached Intervention Point 2.
Aug 2018
Crossrail Ltd raises an Adverse Event Notice to Sponsors, stating the delay to the central section from December 2018 to Autumn 2019.
Dec 2018
Interim findings of the KPMG report, state that Crossrail’s works could cost £1.6 billion – £2 billion more than expected, including £300 million announced in July.
The Department announces loans of £1.3 billion to the Greater London Authority (GLA) and £750 million to TfL as contingency. The GLA makes £100 million contribution. This financing incorporates the £350 million announced in October.
Crossrail announces that it can no longer commit to the Autumn 2019 date.
Oct 2018
Rail Minister announces a further £350 million of interim financing will be made available to Crossrail.
May 2018
Stage 2 opening partially achieved. TfL Started running 2 class 345 trains per hour from Paddington to Hayes and Harlington, rather than 4 class 345 trains per hour to Heathrow as planned.
Jul 2018
Rail Minister announces £590 million additional funding, of which £300 million was provided jointly by the Department and TfL to Crossrail Ltd, and £290 million by the Department to Network Rail.
Nov 2017
Failure of transformer equipment at Pudding Mill Lane delays start of train testing by 3 months. Crossrail begins to develop a new schedule for the programme to account for this.
Figure 13Recent events on the Crossrail programme
Source: National Audit Offi ce analysis of departmental information
A memorandum on the Crossrail programme When will Crossrail be complete and open? 25
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Events leading to the announcement of delays
Progress against the timetable for opening the railway
Remaining work
Progress against the timetable for opening the railway
The Department and TfL originally planned for the central section of the railway to start running from December 2018. In 2010, sponsors decided to stagger the opening of the railway by opening the railway in sections and introducing services in a phased way. This was in order to reduce risks – and therefore reduce the costs allocated to risks – associated with opening the railway ‘all at once’.
As Figure 14 on the right shows, Crossrail Ltd did not open the full, planned services for stages 1 and 2 on time, and it remains unclear when stages 3, 4 and 5 will open. New class 345 Bombardier trains are in use between Shenfield and Liverpool Street as part of the opening of stage 1 services, but are not yet in use between Heathrow and Paddington as had been planned. This is because the software required to use the ETCS signalling system that is on the line into Heathrow has not yet been successfully implemented and tested.
Project sponsors have agreed a concession arrangement with Mass Transit Railway (MTR) to operate the new railway. MTR are paid a performance-related fee for operating the railway, with TfL retaining revenues. Because of the delays to opening the railway, TfL’s revenues will not start to increase significantly until stage 5 is complete and full end-to-end journeys through central London are possible. TfL’s December 2018 business plan states that its revenues could be around £600 million lower than expected as a result of delays to the opening of Crossrail services. Because Crossrail Ltd and sponsors have not yet confirmed the opening dates for stages 3, 4 and 5, these estimates remain uncertain.
Crossrail Ltd is currently developing a new schedule for the programme.
Figure 14Current plans for introducing new Elizabeth line services
Stage Description Target date Actual/forecast delivery
1 Liverpool Street (main line) to Shenfield May 2017 June 2017
2 Heathrow to Paddington (main line) May 2018 Stage 2 opening partially achieved in May 2018. Two Class 345 trains per hour are running from Paddington to Hayes and Harlington, rather than four trains per hour to Heathrow as planned. The Department currently expects four trains per hour to be running by December 2019
3 Paddington (Crossrail) to Abbey Wood – using new Class 345 trains with 15 trains per hour
December 2018 Unknown
4 Paddington (Crossrail) to Shenfield – using new Class 345 trains with 12 trains per hour
May 2019 Unknown – dependent on stage 3
5 Full east–west service with 24 trains per hour in each direction
December 2019 Unknown – dependent on stage 3. There are currently plans to introduce some Crossrail services between the existing Paddington station and Reading from December 2019
Source: National Audit Offi ce analysis of departmental information
A memorandum on the Crossrail programme When will Crossrail be complete and open? 26
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Events leading to the announcement of delays
Progress against the timetable for opening the railway
Remaining work
Remaining work
There remains significant work to complete in key areas: the construction and fit-out of the tunnels and stations; and the testing of the signalling and other systems.
Construction and fit-out of the tunnels and stations:
• Work to fit-out tunnels with, for example, cabling and equipment needed to support signalling systems is not yet complete.
• Stations are in different states of completion and there is still significant work to be completed. Bond Street and Whitechapel stations have caused particular problems. Stations are not required to be fully completed in order for some services to start running but opening the railway without stopping at some unfinished stations will delay passengers receiving the full benefits of the railway, and significant further construction work could continue to delay testing.
Testing of the signalling and other systems:
• This includes the lineside signalling systems, the signalling equipment on the trains, as well as the station systems that remotely monitor and control systems, for example, ventilation.
• The software and infrastructure required to operate the complex signalling systems on trains and at the trackside has been significantly delayed. These systems are critical for the safe and efficient operations of services.
• Crossrail Ltd is adopting an incremental approach to the testing of trains running through tunnels, gradually increasing the number of trains tested on the central section, before beginning testing across the entire line. Crossrail Ltd does not yet know how long this testing will take.
Trial running and preparing for operations:
• Once the signalling and safety systems are complete and full testing has been carried out, the railway will be ready to be commissioned and handed over to the operator to begin trial running. This process allows operators to test how the service will work in practice, and refine areas such as passenger management, and how to address delays and faults when they occur.
A memorandum on the Crossrail programme Previous examinations of Crossrail by PAC and the NAO 27
What is Crossrail?Introduction to this guide Key facts Summary
Why are the government and TfL building Crossrail?
Who is paying for Crossrail?
Who is delivering Crossrail?
How is Crossrail being delivered?
When will Crossrail be complete and open?
Previous examinations of Crossrail by PAC and the NAO
Previous examinations of Crossrail by PAC and the NAO
Relevant reports and transcripts of the Committee of Public Accounts (PAC)
Crossrail, Eighth Report of Session 2014-15, Session 2014-15, HC 574, July 2014 . Available at: www.parliament.uk/business/committees/committees-a-z/commons-select/public-accounts-committee/news/report-crossrail/
Oral evidence, Rail Franchising in the UK, HC 689, February 2018 . Available at: http://data.parliament.uk/writtenevidence/committeeevidence.svc/evidencedocument/public-accounts-committee/rail-franchising-in-the-uk/oral/79138.pdf
Oral evidence, Department for Transport: Implementation of Brexit, HC 1657, October 2018 . Available at: http://data.parliament.uk/writtenevidence/committeeevidence.svc/evidencedocument/public-accounts-committee/department-for-transport-implementation-of-brexit/oral/92048.pdf
Oral evidence, Rail management and disruption, HC 1793, December 2018 . Available at: http://data.parliament.uk/writtenevidence/committeeevidence.svc/evidencedocument/public-accounts-committee/rail-franchising/oral/93794.pdf
Relevant report of the National Audit Office (NAO)
Crossrail, Session 2013-14, HC 965, January 2014. Available at: www.nao.org.uk/report/crossrail-3/
Report by the Comptroller and Auditor General
A memorandum on the Crossrail programmeHC 1924 Session 2017–2019
ISBN 9781786042439
Ordered by the House of Commons to be printed on 25 February 2019
CORRECTION
On page 15 of the memorandum: We propose changing the wording describing the role of the Joint Sponsor Board in the governance diagram on page 15 from:
Monthly forum sponsors to receive updates on, and challenge, programme progress
to:
Monthly forum for sponsors to receive updates on, and challenge the Crossrail Ltd executive on, programme progress
This then makes it clear that the Crossrail exec attends sponsor board and is challenged on progress. We also propose including a solid red arrow on the right hand side of the diagram from the box ‘Crossrail Ltd’ to the box ‘Joint Sponsor Board’.
See the corrected Figure 8 overleaf.
BACK
Net
wo
rk R
ail
Del
iver
ing
wor
k on
exi
stin
g ne
twor
k
Rai
l fo
r L
on
do
n (p
art
of
TfL
)
Res
pons
ible
for
the
rolli
ng s
tock
con
trac
t and
the
cont
ract
with
th
e pr
ivat
e se
ctor
ope
rato
r of
the
railw
ay
Su
pp
liers
an
d
par
tner
s
Del
iver
y
Sp
on
sor
ove
rsig
ht
Dep
artm
ent
for
Tran
spo
rt (D
fT)
Pro
gram
me
spon
sor
and
fund
er
Join
t S
po
nso
r B
oar
d
Mon
thly
foru
m fo
r sp
onso
rs to
rec
eive
upd
ates
on,
and
cha
lleng
e th
e C
ross
rail
Ltd
exec
utiv
e on
, pro
gram
me
prog
ress
Fo
ur m
embe
rs (t
wo
from
TfL
and
tw
o fr
om D
fT –
incl
udin
g on
e at
dire
ctor
gen
eral
leve
l); r
otat
ing
chai
r
Join
t S
po
nso
r Te
am
Sup
port
s th
e S
pons
or B
oard
– m
ade
up o
f re
pres
enta
tives
from
TfL
and
DfT
Tran
spo
rt f
or
Lo
nd
on
(TfL
)
Pro
gram
me
spon
sor
and
fund
er, a
nd r
espo
nsib
le fo
r op
erat
ing
Eliz
abet
h lin
e se
rvic
es
Cro
ssra
il P
roje
ct R
epre
sen
tati
ve (J
aco
bs)
Em
bedd
ed in
CR
L. R
epor
ts o
n pr
ogre
ss to
spo
nsor
team
an
d ca
rrie
s ou
t spe
cific
inve
stig
atio
ns a
t spo
nsor
s’ r
eque
st
Rep
orts
to
Org
anis
atio
nal
over
sigh
t
Sup
plie
r
Info
rmal
rep
ortin
g
Par
tner
s
Cro
ssra
il Lt
d (C
RL)
Bo
ard
Inde
pend
ently
cha
ired;
TfL
and
DfT
non
-exe
cutiv
e re
pres
enta
tives
; thr
ee e
xecu
tive-
mem
bers
(chi
ef e
xecu
tive
offic
er, c
hief
fina
ncia
l offi
cer,
depu
ty c
hief
exe
cutiv
e of
ficer
); no
n-ex
ecut
ives
incl
udin
g ch
air
and
depu
ty
Co
nst
ruct
ion
and
sys
tem
s co
ntr
acto
rs R
olli
ng
sto
ck c
on
trac
tor
(Bom
bard
ier)
Op
erat
or
(MTR
Cro
ssra
il)
Fig
ure
8 T
he g
over
nanc
e an
d de
liver
y st
ruct
ure
Sou
rce:
Nat
iona
l Aud
it O
ffi ce
ana
lysi
s of
dep
artm
enta
l inf
orm
atio
n
Cro
ssra
il Lt
d
Who
lly-o
wne
d su
bsid
iary
of T
fL, s
et u
p to
del
iver
the
prog
ram
me.
O
vera
ll re
spon
sibi
lity
for
prog
ram
me
inte
grat
ion
and
deliv
ery
of th
e op
erat
iona
l rai
lway
BA
CK
Net
wo
rk R
ail
Del
iver
ing
wor
k on
exi
stin
g ne
twor
k
Rai
l fo
r L
on
do
n (p
art
of
TfL
)
Res
pons
ible
for
the
rolli
ng s
tock
con
trac
t and
the
cont
ract
with
th
e pr
ivat
e se
ctor
ope
rato
r of
the
railw
ay
Su
pp
liers
an
d
par
tner
s
Del
iver
y
Sp
on
sor
ove
rsig
ht
Dep
artm
ent
for
Tran
spo
rt (D
fT)
Pro
gram
me
spon
sor
and
fund
er
Join
t S
po
nso
r B
oar
d
Mon
thly
foru
m fo
r sp
onso
rs to
rec
eive
upd
ates
on,
and
cha
lleng
e th
e C
ross
rail
Ltd
exec
utiv
e on
, pro
gram
me
prog
ress
Fo
ur m
embe
rs (t
wo
from
TfL
and
tw
o fr
om D
fT –
incl
udin
g on
e at
dire
ctor
gen
eral
leve
l); r
otat
ing
chai
r
Join
t S
po
nso
r Te
am
Sup
port
s th
e S
pons
or B
oard
– m
ade
up o
f re
pres
enta
tives
from
TfL
and
DfT
Tran
spo
rt f
or
Lo
nd
on
(TfL
)
Pro
gram
me
spon
sor
and
fund
er, a
nd r
espo
nsib
le fo
r op
erat
ing
Eliz
abet
h lin
e se
rvic
es
Cro
ssra
il P
roje
ct R
epre
sen
tati
ve (J
aco
bs)
Em
bedd
ed in
CR
L. R
epor
ts o
n pr
ogre
ss to
spo
nsor
team
an
d ca
rrie
s ou
t spe
cific
inve
stig
atio
ns a
t spo
nsor
s’ r
eque
st
Rep
orts
to
Org
anis
atio
nal
over
sigh
t
Sup
plie
r
Info
rmal
rep
ortin
g
Par
tner
s
Cro
ssra
il Lt
d (C
RL)
Bo
ard
Inde
pend
ently
cha
ired;
TfL
and
DfT
non
-exe
cutiv
e re
pres
enta
tives
; thr
ee e
xecu
tive-
mem
bers
(chi
ef e
xecu
tive
offic
er, c
hief
fina
ncia
l offi
cer,
depu
ty c
hief
exe
cutiv
e of
ficer
); no
n-ex
ecut
ives
incl
udin
g ch
air
and
depu
ty
Co
nst
ruct
ion
and
sys
tem
s co
ntr
acto
rs R
olli
ng
sto
ck c
on
trac
tor
(Bom
bard
ier)
Op
erat
or
(MTR
Cro
ssra
il)
Fig
ure
8 T
he g
over
nanc
e an
d de
liver
y st
ruct
ure
Sou
rce:
Nat
iona
l Aud
it O
ffi ce
ana
lysi
s of
dep
artm
enta
l inf
orm
atio
n
Cro
ssra
il Lt
d
Who
lly-o
wne
d su
bsid
iary
of T
fL, s
et u
p to
del
iver
the
prog
ram
me.
O
vera
ll re
spon
sibi
lity
for
prog
ram
me
inte
grat
ion
and
deliv
ery
of th
e op
erat
iona
l rai
lway
BA
CK
On page 21 of the memorandum: We also propose changing the date when MTR Crossrail started running services on the eastern section of the line on page 21 from:
MTR Crossrail began running services on the eastern section of the railway in June 2017
to:
MTR Crossrail began running services on the eastern section of the railway in May 2015
The corrected paragrah should read
Railway operations
In July 2014, TfL awarded a concession contract to Mass Transit Railway (MTR), a transport operating company based in Hong Kong, to operate Elizabeth line services. MTR Crossrail began running services on the eastern section of the railway in May 2015 and has a contract to operate services for eight years, with an option to extend to 10 years.
On page 19 of the memorandum: We also propose changing the date the finance director was no longer a board member, from:
Finance Director Mathew Duncan (until 19 November 2018)
to:
Finance Director Mathew Duncan (until 9 November 2018)
See the corrected Figure 10 overleaf.
007232-001 | February 2019
BACK
Fig
ure
10
Cro
ssra
il Lt
d B
oard
of D
irect
ors
at 3
1 M
arch
201
8
Ch
airm
an
Sir
Terr
y M
orga
n(u
ntil
5 D
ec 2
018)
No
n-E
xecu
tive
Ind
epen
den
t
Phi
l Gaf
fney
(fro
m 2
011)
Ch
ief
Exe
cuti
ve
And
rew
Wol
sten
holm
e (to
31
Mar
201
8)
No
n-E
xecu
tive
Dep
artm
ent n
omin
ee
Rob
ert J
enni
ngs
CB
E (f
rom
200
9)
Pro
gra
mm
e D
irec
tor
Sim
on W
right
(Chi
ef E
xecu
tive
from
Ap
r to
Nov
201
8)
No
n-E
xecu
tive
(SID
)
Terr
y H
ill (u
ntil
30 J
un 2
018)
No
n-E
xecu
tive
Mic
hael
Cas
sid
y (u
ntil
30 J
un 2
018)
Fin
ance
Dir
ecto
r
Mat
hew
Dun
can
(unt
il 9
Nov
201
8)
No
n-E
xecu
tive
Pam
Ale
xand
er (u
ntil
30 J
un 2
018)
No
n-E
xecu
tive
TfL
nom
inee
Mar
k W
ild (f
rom
Sep
201
6)
Chi
ef E
xecu
tive
sinc
e 19
Nov
201
8
Rem
uner
atio
n in
201
7-18
Sal
ary
Per
form
ance
rel
ated
p
ay fo
r 20
16-1
7C
om
pen
satio
n fo
r lo
ss o
f em
plo
ymen
tB
enef
its in
kin
dTo
tal r
emun
erat
ion
(exc
lud
ing
pen
sio
n co
ntri
but
ions
)To
tal r
emun
erat
ion
(exc
lud
ing
pen
sio
n co
ntri
but
ions
)
2017
-18
2017
-18
2017
-18
2017
-18
2017
-18
2016
-17
(£0
00)
(£0
00)
(£0
00)
(£0
00)
(£0
00)
(£0
00)
And
rew
Wol
sten
holm
e, C
hief
Exe
cutiv
e47
7 16
0 98
2
736
946
Sim
on W
right
, Pro
gram
me
Dire
ctor
329
106
–2
436
494
Sir
Terr
y M
orga
n, N
on-E
xecu
tive
Cha
irman
250
––
225
2 25
2
Mat
hew
Dun
can,
Fin
ance
Dire
ctor
247
112
–2
361
270
No
te1
The
spon
sor
agre
emen
t, to
whi
ch th
e D
epar
tmen
t and
TfL
are
par
ties,
set
s ou
t the
Rem
uner
atio
n P
rinci
ple
s go
vern
ing
the
rem
uner
atio
n an
d b
enefi
ts p
acka
ge w
hich
ap
plie
s to
all
mem
ber
s of
the
Cro
ssra
il Lt
d B
oard
. The
Cro
ssra
il Lt
d R
emun
erat
ion
Com
mitt
ee
dev
elop
s th
e R
emun
erat
ion
Fram
ewor
k, c
onsi
sten
t with
the
Rem
uner
atio
n P
rinci
ple
s. T
fL a
pp
rove
s th
e R
emun
erat
ion
Fram
ewor
k an
d en
sure
s th
at th
e S
ecre
tary
of S
tate
is p
rovi
ded
with
the
app
rove
d Fr
amew
ork
pro
mpt
ly. T
he S
ecre
tary
of S
tate
may
ob
ject
to
any
par
t of t
he R
emun
erat
ion
Fram
ewor
k or
a s
pec
ifi c
rem
uner
atio
n an
d b
enefi
ts p
acka
ge w
hich
is n
ot c
onsi
sten
t with
the
Rem
uner
atio
n P
rinci
ple
s an
d Tf
L sh
all t
ake
app
rop
riate
act
ion
to e
nsur
e th
at th
e in
cons
iste
ncy
is a
dd
ress
ed. T
he r
emun
erat
ion
and
ben
efi ts
p
acka
ge o
f the
exe
cutiv
e d
irect
ors
of C
ross
rail
Ltd
and
the
chai
r an
d ch
ief e
xecu
tive
offi c
er o
f Cro
ssra
il Lt
d is
det
erm
ined
by
the
Cro
ssra
il Lt
d R
emun
erat
ion
Com
mitt
ee in
acc
ord
ance
with
the
Rem
uner
atio
n Fr
amew
ork
and
in c
onsu
ltatio
n w
ith T
fL.
Sou
rce:
Tra
nsp
ort f
or L
ond
on A
nnua
l Rep
ort a
nd S
tate
men
t of A
ccou
nts,
201
7-18
Rem
ains
a B
oard
mem
ber
No
long
er a
Boa
rd m
embe
r
Cro
ssra
il Lt
d s
enio
r re
mu
ner
atio
n
BA
CK
This report has been printed on Evolution Digital Satin and contains material sourced from responsibly managed and sustainable forests certified in accordance with the FSC (Forest Stewardship Council).
The wood pulp is totally recyclable and acid-free. Our printers also have full ISO 14001 environmental accreditation, which ensures that they have effective procedures in place to manage waste and practices that may affect the environment.
£10.00
9 781786 042439
ISBN 978-1-78604-243-9
Design and Production by NAO External Relations DP Ref: 007232-001
You have reached the end of this document