Report b Azman rqg qr gr gqreg
-
Upload
azman-anuar -
Category
Documents
-
view
224 -
download
2
description
Transcript of Report b Azman rqg qr gr gqreg
DEPARTMENT OF QUANTITY SURVERYING
FACULTY OF ARCHITECTURE, PLANNING & SURVEYING
REPORT B:
LABOUR COST
NAME : KHAIRUL AZMAN BIN ANUAR
MATRIX NO : 2013239324
GROUP : AP114 5F
INTRODUCTION
Construction and Manufacturing
OBJECTIVE
The objective of this report is:-
3.0 DEFINITION OF LABOUR
SOURCES OF LABOUR
The sources of labour in Malaysia can be divided into two categorized which is:
Sources of Labour
Local labour
Foreign labour
LABOUR CATEGORIES
SKILLED LABOUR
Skilled labourers are labourers who have certain skills in certain trades.
1) Bricklayer
2) Concreter
3) Masonry
4) Carpenter
5) Steel bar & welder
6) Plasterer
7) Pavior
8) Painter
9) Glazier
10) Plumber
11) Drain layer
12) Operator
13) Lorry driver
14) Bitumen worker
UNSKILLED LABOUR
The unskilled labourers have two categories:
i. Male
ii. Female
The rate for male unskilled labour is higher compared female unskilled labour. This is because
male unskilled labourers can do more work as compared female unskilled labour as they are
genetically more superior physically. The rate for unskilled labour (male) is a RM 50 to RM 65 while
the female is in between RM 45 to RM 60 per day.
Not only that, their rates depends on the task given to them whether they work under a foreman or
under a skilled labourer.
SUB-CONTRACT LABOUR
A subcontractor labour is a person or a company hired by a general contractor to
perform part of the work of a construction job and they do the specific work based on the
skills and expertise. The different of both sub contractorlabour and skilled labour can be seen
based on their different rate wages.
DIAGRAM 2.5 The diagram above shows 2 types of subcontractor
Domestic subcontractor
Nominated subcontractor
TYPES OF SUBCONTRACTOR
DOMESTIC NOMINATED
LABOUR BY TRADE
In the construction industry, labour is the important aspect for the contractor to ensure the
project is completed follow the plan. Labours can be divided into their own trades. There are
many trades can be found in the construction works. These trades are specified based on
their experienced and skilled in that works. The trade are:-
A) CONCRETER
The concreter is responsible in ensuring the concrete mixing for a building is
following the standard specification and they also responsible to ensure the
strength of the building the concrete test done.
B) BRICKLAYER
The bricklayer is expert in arrangement and bonding of bricks for the building
wall. They are expert in Flemish bond, English bond and stretcher bond.
Bricklayers build walls, chimneys and other structures from masonry units
such as brick, block, glass block or stone.
C) DRAIN LAYER
Drain layers are responsible for sewerage, sump, manhole and other things
concerning the sewerage system. It must be done perfectly to ensure that the
sewerage system in the building does not be in function when it is used.
The drain layer must be skillful in deciding the pitch for the drains and its
depth.
D) MASONRY
It is almost similar to bricklayer except the sizes of the bricks and stones are
different.The main purpose of the masonry is to prepare a rubble retaining wall,
arches, fair face, sundries and any masonry work such as lintel, jambs, and quoins.
Normally these works are done externally. These works must be done very carefully
as the main purpose of this is to make it look tidy and clean.
The skill that they must have is to properly arrange the stones and because of this,
they must know the installation inside out.
They must also prepare any shape required by the client or employer.
E) PLUMBER
A plumber is the trade that installs and connects pipes as there are many types of
pipes such as soil and waste pipe and service pipes.
The installation of cold-water pipes is included in the works of a plumber where the
work must follow the specifications of the provided drawings. After the work is done,
the plumber is to install pipes and equipments based on the layout plan. Examples of
the appliances used by this trade are auger, spanner, braces, bits, rules, blowtorches,
squares and electrical cutter.
F) CARPENTER
Carpenters in the construction industry are responsible for works concerning
woodwork such as window frame, installation of formwork, doorframe and
others.
G) PAINTER
This trade involved in paint work to external and internal surfaces like wall,
ceiling, frame, windows, doors and etc.Painter not just having the skill of
painting but also the knowledge of it. Painters first prepare the surface to be
covered, so that the paint will adhere properly. This may require removing the
old coat of paint by stripping, sanding, wire brushing, or water and abrasive
blasting.
H) BAR BENDER
Bar bender or also known as a steel bar bender is working by bending reinforcement
bars. Although reinforcement bar usually arrive ready to use, ironworkers from time to
time must cut bars with metal shears or acetylene torches, bend them by hand or
machine, or weld them with arc-welding equipment. They fasten the bars together by
tying wire around them using pliers. When reinforcing floors, ironworkers place
spacers under the bar to hold the bars off the deck. Some concrete is reinforced with
welded wire fabric.
I) ROOFER
In this trade, rooter is responsible to place the root finishes and the installation of the
trusses. The trusses must strong enough to support all load of the peaces or sheets
at rooting material. The bad installation might cause the leakage or bending. That’s
why, during the installation at the rooting material, the rooter must install it patiently
andfollow the manufacture’s instruction. It is important because the root is the top
element at building and open to the sunlight and rain.
J) PLASTERER
The role of a plasterer is to plaster the walls of building after the wall has been
constructed.
This work is normally carried out after the construction of the wall is completed and
the plaster is used to cover the brick wall for a smoother finish.
Special skills are needed to ensure that the plaster is laid out evenly. Floors and
ceilings are other examples of components that can be plastered.
Plastering works also include items such as ‘skirting’, ‘gutter’, ‘on cornices’, ‘curves’,
‘arches’, ‘column’ and ‘beam’.
The true purpose of plastering is actually to cover small spaces and holes in the wall,
floor or ceiling.
K) WELDER
Welder is involve in steel work where they will heat the steel until molten and
fused or soft enough to hammer or pressed together, the welder must wear
goggles for eye’s safety. They will use electrical power to heat the steel and
tie the reinforcement bar.
SCHEDULE RATES OF PRICE LABOUR PREPARED BY STATES
ITEM DESCRIPTION UNIT STATES
KUALA
LUMPUR
PAHANG PERAK TERENGGANU
1. GENERAL
LABOUR
DAY RM 60.00 RM 50.00 RM 50.00 RM 55.00
2. MASON DAY RM 85.00 RM 75.00 RM 95.00 RM 75.00
3. CARPENTER DAY RM 100.00 RM 80.00 RM 120.00 RM 80.00
4. JOINER DAY RM 100.00 RM 80.00 RM 120.00 RM 80.00
5. CONCRETER DAY RM 100.00 RM 70.00 RM 95.00 RM 75.00
6. STEEL BAR
BENDER
DAY RM 100.00 RM 80.00 RM 100.00 RM 80.00
7. PAINTER DAY RM 80.00 RM 70.00 RM 110.00 RM 75.00
8. PLASTERER DAY RM 80.00 RM 70.00 RM 120.00 RM 70.00
9. FITTER DAY RM 120.00 RM 80.00 RM 100.00 RM 60.00
10. WELDER DAY RM 85.00 RM 85.00 RM 100.00 RM 80.00
11. BRICKLAYER DAY RM 100.00 RM 75.00 RM 100.00 RM 75.00
GRAPH SHOWS PRICE LABOUR BY STATES
Chart above shows the distribution of labour rate between four difference region
which is Kuala Lumpur, Perak, Pahang and Terengganu. This three labour rate, priced on
2014 from 4 difference contractor which is Nine Hundred Builder Sdn. Bhd (Kuala Lumpur),
Teras Khidmat Niaga (Perak),Syarikat Yusof Yasin Sdn. Bhd (Terengganu) and Ijhraa Sdn.
Bhd.(Perak) .
From the figure , we can see that the labour prices at Perak are higher than labour
prices at Kuala Lumpur, Pahang and Terengganu for most of the trades. For example, the
labour price for a plasterer in Perak is RM120.00 while in Kuala Lumpur is RM 80.00,
Pahang and Terengganu are RM70.00 for both which it is lower than the price at Perak.
As a conclusion, the location of the project also affected the labour cost. Usually, the
price of labour in rural area is lower than in urban area. It is because the cost for living is
higher in the city. However, sometimes labour for project in a distant area is much higher to
cover overhead costs such as travel and communication.
FACTORS INFLUENCING THE LABOUR PRICES
Labour rate will change along with time. From analysis before we can see difference contractor will have several differences between their rates. This is due to below factors:
I. Location
The location of the project will influence labour prices. Examples, comparison between construction in cities and rural areas, most labour hired in city will get higher payment than labours working at rural areas. This is because, the cost of living in cities are much higher than rural areas and small town. Sometimes, labour rate can be higher when the location of the construction area is difficult to get labour.
II. High-risk project
The risky project will influence the price of labour. Workers generally receive higher
compensation when the task they must complete are more complex or difficult. It is because
the labours need to face the high-risk situation on site.As for the risk taken, the insurance
need to be cover the workers and highskill needed to handle a risky situation, as not many
labour is willing to take a big risk.
III. Competition among the contractors
There are many contractor companies in our construction industry. It is divided to a certain
level or class of contractors, followed by the reputation and experience of the contractors.
For the tender competition, contractors will tackle the client by offering them a lower rate for
labours. There is why the competition among the contractors also is the one of the factors
towards the labour rate.
IV. Labours market
Local labour cant fulfill domestic demands thus government allow foreign labour to be
imported to work as labour. In some situation foreign labour wage is much lower than the
local labours but their imported fees has being a big issued, thus many contractor use illegal
foreign worker to cut their wages expenses.
.
V. Size of projects
Sizes of projects also influence the labour price. For example, in multimillion projects the rate of labour usually expensive than smaller project depends on the difficulty of the projects as contractor want to avoid any losses if there is variance of works.
VI. Government policy
Malaysia Government by the Ministry of Human Resource has started that the labour rate for
the local labour must be higher than the foreign labours. The purpose of the policy is to
attract our local people to involve with the construction sectors. The policy also wants the
local labour to get the specialty. By this causes, it will be a different in the labour price rate in
the industry.
VII. Completion period
The completion period of a project could affect the labour price. The more time needed in
completion a project required the more cost on labour price. For those project which the
client want to complete in short period of time, the rates of labour will be increased. It is
because sometimes the labour will do extra work or overtime which require a payment.
VIII. Expertise
The labour cost is depends on their expertise and skills in performing a certain tasks. Skilled labour will get a higher amount of wages comparing with semi-skilled and unskilled labour. This is because skilled labour can perform their work perfectly and always do a complicated work such as bricklayer, carpenter, and others.
They have used all the energy to complete the work on times specified. Besides that, they have to work in night that is very risky and they are exposed with an accident. At least, the increasing of their rates will balance with their work. All these factors are considered to determine their rates