Replace Motor Mol Pump DP-1A

3
WORK PACKAGE Doc No.: ...../WP-DQC/0472A/XI/11 OPERATIONAL TECHNICAL MAINTENANCE PHE - ONWJ WO MAXIMO No. : .............. Job Description : Replace Motor & Pump DP-1A.( Mol Pump ) Duration period : 03 Nov – 08 Nov 2011 Location : BRAVO F/S RISK WARNING CAUTION DANGER Electricity , High pressure. Drop object Secure the Pump before is begun, Inspect lifting tools before lifting process I. MATERIAL REQUIRED STATUS 1. Pump Assy Hand Carried Send by Boat, 2 Nov 2011 2. Electric Motor Hand Carried Send by Boat, 2 Nov 2011 II. EQUIPMENT / TOOLS REQUIRED STATUS 1. COMSISIONING TOOL…. Hand Carry, Send by Boat, 2. Web Sling ……..………….... Ready at F/S. Send by Boat, 3. ………………………......……. Ready at F/S Send by Boat III. SUPPORTING 1. SOP …………………………. IV. MAN POWER 1. YUSUF AGIL……………………… MCU (Nop-02-2012 ) sea Survival (Jul-17-2012) 2. YAYA PANCA………………..…… MCU (Agst-23-2012) Sea Survival (Agst-02-2013) 3. KASMURI..............………………… MCU (Mar-15-2012) Sea Survival (Sep-21-2014) V. JOB SQUENCE REPLACE MOL PUMP DP-1A 1. PREPARE PERMIT 2. ISOLASI ENERGY. 3. PULL OUT PUMP AND MOTOR 4. INSTALL NEW CASING AND LEVELING. 5. TEST LEAK, SOLO RUN MOTOR 6. PERFORMANCE TEST PUMP 7. HOUSE KEEPING

description

FFFFF

Transcript of Replace Motor Mol Pump DP-1A

Page 1: Replace Motor Mol Pump DP-1A

WORK PACKAGEDoc No.: ...../WP-DQC/0472A/XI/11

OPERATIONAL TECHNICAL MAINTENANCE PHE - ONWJWO MAXIMO No. : .............. Job Description : Replace Motor & Pump DP-1A.( Mol Pump ) Duration period : 03 Nov – 08 Nov 2011Location : BRAVO F/S

RISK WARNING CAUTION DANGER

Electricity , High pressure. Drop object Secure the Pump before is begun, Inspect lifting tools before lifting process

I. MATERIAL REQUIRED STATUS1. Pump Assy Hand Carried Send by Boat, 2 Nov 20112. Electric Motor Hand Carried Send by Boat, 2 Nov 2011

II. EQUIPMENT / TOOLS REQUIRED STATUS1. COMSISIONING TOOL…. Hand Carry, Send by Boat, 2. Web Sling ……..………….... Ready at F/S. Send by Boat, 3. ………………………......……. Ready at F/S Send by Boat

III. SUPPORTING1. SOP ………………………….

IV. MAN POWER1. YUSUF AGIL……………………… MCU (Nop-02-2012 ) sea Survival (Jul-17-2012)

2. YAYA PANCA………………..…… MCU (Agst-23-2012) Sea Survival (Agst-02-2013)

3. KASMURI..............………………… MCU (Mar-15-2012) Sea Survival (Sep-21-2014)

V. JOB SQUENCEREPLACE MOL PUMP DP-1A 1. PREPARE PERMIT 2. ISOLASI ENERGY.3. PULL OUT PUMP AND MOTOR 4. INSTALL NEW CASING AND LEVELING.5. TEST LEAK, SOLO RUN MOTOR 6. PERFORMANCE TEST PUMP7. HOUSE KEEPING

VI. JOB COMPLETION

………… (hand over on job completion from contractor to PHE Operation Reps.) ..……

I hereby inform that all job preparations for above jobs have been completed and the jobs can be performed safely.

Prepared by, Approved by, Endorsed by,

( SIGIT M..) ( SAIFUDDIN HAQ ) (………..RONALD F……..)Contractor Planner/Engineer Contractor Lead/Coordinator PHE ONWJ .

Page 2: Replace Motor Mol Pump DP-1A

JOB COMPLETION ACCEPTANCECERTIFICATE

The undersigning has certified and accepted that the following jobs:

Replace Mol Pump DP-1A ……………….WO NO .................

has been satisfactory ……..completed……. by …….Duraquipt

Cemerlang……

PHE Area Authority

Notes/Comments: ………………………………..

Name (Caps) :

Signed : Date : _________________

PHE Superintendent/OIM

Notes/Comments: ………………………………..

Name (Caps) :

Signed : Date : ________________