Reliabilty Project
Transcript of Reliabilty Project
-
8/3/2019 Reliabilty Project
1/19
Course Project PresentationCourse Project Presentationonon
Factors of Safety and Reliability inFactors of Safety and Reliability inGeotechnical EngineeringGeotechnical Engineering
Presented byPresented by
Kamal Kant JainKamal Kant Jain
-
8/3/2019 Reliabilty Project
2/19
IntroductionIntroductionBasic Tools of Reliability AnalysisBasic Tools of Reliability Analysis
Geotechnical Applications of ProbabilisticGeotechnical Applications of Probabilistic
Methods and Reliability AnalysisMethods and Reliability AnalysisExample:Example: Retaining Wall StabilityRetaining Wall Stability
ConclusionsConclusions
Outline of presentationOutline of presentation
-
8/3/2019 Reliabilty Project
3/19
-
8/3/2019 Reliabilty Project
4/19
Factors of safety in Geotechnical EngineeringFactors of safety in Geotechnical Engineering
Based on experienceBased on experience
Dont depend on degree of uncertainty involvedDont depend on degree of uncertainty involved
Present status of use of Reliability theory inPresent status of use of Reliability theory inGeotechnical EngineeringGeotechnical EngineeringInvolves terms and concepts that are not much familiar toInvolves terms and concepts that are not much familiar to
most of the geotechnical engineersmost of the geotechnical engineers
Perception that it would require more data time, and effortPerception that it would require more data time, and effort
Is not used extensivelyIs not used extensively
-
8/3/2019 Reliabilty Project
5/19
-
8/3/2019 Reliabilty Project
6/19
1) Normal Variables
M R Q!
M R Q! Q Q Q
2 2 2
2M R Q R QRQ
! VW W W W W
2) Lognormal Variables
Reliability Index1
1
QF !
WProbability of failure fP ! *F
= CDF of Standard Normal Variate*
/
ln ln ln
F R Q
F R Q
!
!
2
ln ln
1ln
2F F F
Q ! Q W
2 2
ln ln(1 )FF V! W
Direct Reliability Analysis
-
8/3/2019 Reliabilty Project
7/19
Distributions other than normal or lognormal
arise often in practice like
Gamma distribution
Extreme Type distributions
Poisson
-
8/3/2019 Reliabilty Project
8/19
-
8/3/2019 Reliabilty Project
9/19
Monte Carlo Simulation
1 2 3
1 2 3
( , , ... )
, , ...
n
n
i
ifM fx x x x
x x x x are uncorrelated random variables with
known distribution type, then we generate a large
numberofrandom data points for each ofx using
tables and spreadsheets
!
and determine parameters of
M us ingdata obtained
-
8/3/2019 Reliabilty Project
10/19
Event Trees
Describe logical interactions among a complex set of events,
conditions, physical parameters and states
Start with an initiating event and consider no logical difference
between an event and a condition
Proceed with set of exhaustive and exclusive events that could
follow and each event is associated with conditional probability
Proceed along each path to evaluate the next outcomes, and
so on and so forth
At the end of the any stage of tree, the probability of each
outcome is simply the product of the conditional probabilities of
preceding events and conditions
-
8/3/2019 Reliabilty Project
11/19
-
8/3/2019 Reliabilty Project
12/19
Geotechnical Applications of
Probabilistic Methods
Studies of Safety of Dams, Dikes, andEmbankments
Probabilistic Seismic Hazard Analysis
Limit State Design or Load and ResistanceFactor
Nuclear Waste Repositories
Mining
Analysis of Retaining Wall Stability
-
8/3/2019 Reliabilty Project
13/19
FIG. 1 : Cantilever Retaining Wall with Silty Sand Backfill
(Source
:J. Michael Duncan. (2000), Factors of Safety andReliability in Geotechnical Engineering)
Example: Retaining Wall StabilityExample: Retaining Wall Stability
Cantilever
retaining wall
Compacted silty
sand backfill
Concrete footing
built on a layerof silty sand
Backfill drained
to prevent build
up of waterpressure behind
the wall
-
8/3/2019 Reliabilty Project
14/19
Factor of Safety (FoS) against SlidingFactor of Safety (FoS) against Sliding
tanss
W
EF
H
!
W= Weight of wall and backfill over the heel of the wall (lb/ft or kN/m)
tanH = Tangent of friction angle between base of wall and sand
E= Earth pressure force on vertical plane through heel of wall (lb/ft or kN/m)
-
8/3/2019 Reliabilty Project
15/19
HCV= Highest conceivable value of the parameter
LCV= Lowest conceivable value of the parameter
Steps involved in estimation ofFoSSteps involved in estimation ofFoS
Estimate the standard deviations of the
quantities involved In equation
1) Computation from data :
2
i
= 1
x x
NW
2) Computation from published values :
V=
Coefficient of variation
( )*( )V xW !
3) Computation from three sigma rule :( - )
6
HCV LCVW !
-
8/3/2019 Reliabilty Project
16/19
Estimation of the standard deviation and theEstimation of the standard deviation and the
coefficient of variation of the factor of safetycoefficient of variation of the factor of safety
22 2 2
31 2 4
2 2 2 2F
F
F
MLV
F F F F
FV
W
W
(( ( ( !
!
;F F Fiii ( !
4) Graphical three sigma rule may also be used for
estimation of standard deviation
/
iF !Where Factor of safety calculated with the value of the
ith parameter increased / decreased by one
standard deviation from its best estimate value
-
8/3/2019 Reliabilty Project
17/19
FMLV = Most likely value of factor of safety, computed using
best estimate values for all of the parameters.
Finding probability of failure and the reliability
of the factor of safety
Assuming that factor of safety follows a lognormal distribution :
2
ln 2
ln1
ln(1 )
MLVF
V
VF
!
lnF = lognormal reliability index
V= coefficient of variation of
factor of safetyFMLV = most likely value of
factor of safety
-
8/3/2019 Reliabilty Project
18/19
ConclusionsConclusions
-
8/3/2019 Reliabilty Project
19/19
Thank you