Reliability Management Group RMG Minneapolis, MN · Reliability Management Group RMG Minneapolis,...
Transcript of Reliability Management Group RMG Minneapolis, MN · Reliability Management Group RMG Minneapolis,...
David Noorani
Manager, Engineering, Maintenance and Reliability
Sinclair Wyoming Refining Company
Sinclair, Wyoming
Anthony V. Covato P.E.
Project Manager
Reliability Management Group RMG
Minneapolis, MN
Page 2
Although controls that are put into place during the
execution phase of a turnaround such as, Scope
Change Approval processes are a key element to
controlling scope creep, if they are not supported by
specific activities during the design and execution
phases of the turnaround they will be less than fully
effective.
Page 3
To minimize scope creep during the execution phase
of a turnaround requires three activities that must
occur during the planning and designing phases of the
turnaround;
• Development of a Turnaround Timeline that is
based on a Long Range Turnaround Plan
• Comprehensive Scope Development Process that
involves all stakeholders
• Detailed planning process that includes risk
analysis and mitigation planning
Page 4
• The minimum requirements in the development of
a turnaround timeline are:
• Identification of key milestones and due dates
for all pre and post turnaround activities
• A long range Turnaround Plan (7-10 Years)
that has been developed using a Strategic
Asset Management Plan
• A Timeline Management process that
establishes accountabilities and responsibilities
Page 5
Key Milestones and Due Dates
• Work Scope Defined (Scope Freeze)
• Project Planning Complete
• Health, Safety, Security and Environmental
(HSSE) Plans Complete
• Internal & External Staffing Plans Complete
• Parts and Material Delivery and Staging Plans
Complete
• Etc.
Page 6
4 Years 3 Years 2 Years
12 Months 11 Months 10 Months 9 Months 8 Months 7 Months 6 Months 5 Months 4 Months 3 Months 2 Months
6 mo < SS
4 Weeks 3 Weeks 2 Weeks 1 Week
Full TAR Team
On Site
4 wk < SS
Begin TAR Daily
Scheduling
1 wk < SS
Post
Week 1
Post
Week 2
Post
Week 3
Post
Week 4
Post
Week 5
Post
Week 6
Post
Week 7
Post
Week 8
Final TAR Cost, Scope
Attainment, Safety,
Contractor/Vendor Review
Reports Complete
All Equipment History Data
Entered into Maximo
Formal TAR Critique
Mtg. Held
Final TAR As Worked
Report Complete
4 wk > SF1 wk > SF
5 wk > SF
7 wk > SF
T/A Management Timeline Pre and Post T/A Activities
4 Year Cycle T/A
TAR
Execution
6 ½ mo < SS
At the conclusion of the Post TAR Activities the next scheduled TAR re-enters the timeline
Prepare T/A Scope
Document
46 mo. < T/A SS
T/A Scope Document
Annual Reviews
Annual Review
36/24/12 mo. < SS
T/A Project List
Complete
Detailed T/A Planning
Complete
Evaluate Unit Decon
Req.
External Staffing Plan
Complete
Internal Staffing Plan
Complete
HSSE Plan Complete
Detailed Engineering
Packages Complete
8 mo < SS
Budg/Scope/Sched
Reconciliation
T/A Master Project
Schedule Complete
Implement Scope
Approval Process
Matl Delv/Staging
Plan Complete
Finalize All Contract
Specifications
All Contract P.O.’s
Issued
T/A Scope Document
Final Approval
5 mo < SS
4 ½ mo < SS
4 mo < SS
3 mo < SS
8 mo < SS
24 mo. < SS
SS – Scheduled T/A Start Date
SF – Scheduled T/A Finish Date
Mo – Month
Wk – Week
< - Pre T/A
> - Post T/A
Page 7
Long Range Turnaround Plan
• Developed based on the Strategic Asset
Management Plan
• Should have a scheduled start date and
duration for all turnarounds for the next (7-10)
years
• Accuracy of schedule dates should be +/- 30
days, estimated budgets should be within +/-
25%
Page 8
T/A Timeline Management Process
• Defined and documented formal process to
manage all turnaround due dates for each
turnaround on the timeline
• Standing meetings at least monthly
• Defined roles, responsibilities and
accountability
• Mitigation procedures for milestones that
are behind schedule
Page 9
Purpose
Turnaround scope development is the activity of
clearly determining the objectives of a turnaround
and compiling a comprehensive, prioritized and
organized Work Breakdown Structure (WBS)
containing all work that must be completed to
achieve those objectives.
Page 10
Desired Characteristics
• Accurate scope development with complete work
orders for all work
• All work linked to a T/A objective
• Work identified early (for the next scheduled T/A
on an asset scope development should begin
during the current T/A on that asset)
• Standard format used to identify all work
Continued
Page 11
Desired Characteristics
• Identified work organized into a hierarchical driven
work breakdown structure (WBS)
• Identify 100% of all T/A work regardless of type of
work, the originating or performing organization ,
based on Post TAR, Inspection Reports, Risk
Assessment, etc.
• The T/A scope development process should identify
and sort work based on the basis of maintenance
activities and not on the basis of contracts required to
perform the work
Continued
Page 12
Desired Characteristics
• Scope development and planning activities driven
by a master scope document that is in a
standardized format for all T/A’s
• Objectives for each T/A are identified, quantified,
prioritized and measurable
• The T/A scope development process should
identify all work required to achieve the desired
asset profile
Continued
Page 13
Desired Characteristics
• The T/A scope development process should flag
long lead time items to facilitate the timely
delivery of all parts and materials
• All T/A work must meet the following criteria:
• Targets one or more of the T/A Objectives
• Work execution requires the asset to be out of
service
Continued
Page 15
Scope Document – Minimum Contents
• General Information Statement – Including a T/A
Purpose Statement and the T/A Objectives
• T/A Team Members and contact information
• Recommendations
• Assumptions
• Work Breakdown Structure (WBS)
• Pre T/A Equipment Testing Requirements
Continued
Page 16
Scope Document – Minimum Contents
• Standard Reoccurring Work List
• Capital Project List
• Capital Project Work List
• Mandatory Work List
• Corrective Work List
• Cost Estimates
• Budgetary Data
Continued
Page 17
Scope Document – Minimum Contents
• Internal Resource Plan
• External Resource Plan
• Special Tool and Equipment Requirements
• Master Project Schedule
• HSSE Plan
• Material Staging and Delivery Plan
• Risk Analysis and Mitigation Plans
• Summary Statement
Page 18
003
Define T/A
Standard Work
List
004
Define T/A Project
List
TAR Scope Document Process
001
Define T/A
Mandatory Work
List
002
Define Pre T/A
Equipment Testing
Requirements
007
Review Previous
T/A Final Report
008
Define T/A
Assumptions
006
Define T/A Work
Breakdown
Structure
005
Review T/A W.O.
Backlog Define
Corrective Work
List
009
Develop Initial T/A
Scope Document
010
Approve Initial
TAR Scope
Document
No
011
Initiate Detailed
Planning
012
Pre-T/A Scope
Document Review/
Revision
Yes
013
Perform
Scheduled Scope
Document
Reviews/Updates
014
Finalize Scope
Document
015
Approve Final
TAR Scope
Document
Yes
No
016
Implement Scope
Approval Process
Page 19
Detailed T/A planning should include an experience
based risk analysis and mitigation planning step
• This is not a statistical analysis but a subjective risk
analysis performed at the activity level of each job
by an experienced craftsman that has performed the
work
Page 20
• Requires the establishment of planning thresholds
that determine the degree of mitigation planning
that is required based on the acceptable level of risk
to T/A budget and schedule
• Used to identify the majority of discovery work
during the execution phase of the T/A and includes
detailed mitigation plans that can be merged into
the Master Project Schedule and executed
Page 21
Benefits of Risk Analysis and Mitigation Planning
• Decision making and approval process occurs prior
to T/A execution, reducing any schedule impacts
• Enables the acquisition of parts and materials that
result from identified discovery work, mitigating
schedule and costs related to expediting those parts
and materials
• Allows planning accuracy to improve since
contingencies are not built into T/A scope planning
Page 22
Requirements
• In order for risk analysis and mitigation planning to
be successful it does require that a very
comprehensive and robust planning process be in
place. This process must ensure that planning occurs
at a very detailed level
• Planning resources must be experienced and familiar
with the specific work scope, the accuracy of
subjective risk analysis is directly related to the
experience level of the planning resource
Page 23
Although risk analysis and mitigation planning is
labor resource intensive and requires a significant
investment in both time and money it is justified
since:
• Excluding project work typically 80% of all work
performed during a turnaround is repetitive in nature
• If planning is performed utilizing a comprehensive,
detailed planning process the bulk of the work related to
risk analysis and mitigation planning is performed once
and only reviewed and revising for future T/A’s
Page 24
006
Approve Job
Plans
T/A Planning Process
TJST-TAR Job Standard Template
001
Query TSJT
Library for
Applicable
TSJT's
Scope
Development
Process
002
Prepare Job
Plans For Non
Recurring Work
003
Convert Req.
TSJT to Job
Plans
004
Perform Risk
Analysis on Job
Plans
005
Prepare
Required
Mitigation Plans
007
Submit Job
Plans for
Merging Into
Master T/A Plan
Yes
No
008
Merge T/A Job
Plans In master
Plan
009
Prepare T/A
Standard Master
Sched Report
Templates
010
Reconcile T/A
Scope/Budget/
Schedule
012
Prepare Final
T/A Master
Schedule
011
T/A Scope
Approved
Scope Control
Approval
Process
013
Prepare Internal
Staffing Plan
015
Prepare External
Staffing Plan
017
Prepare Material
Delivery/Staging
Plan
014
Internal
Staffing Plan
Approval
016
External
Staffing Plan
Approval
018
Matl Delv/
Staging Plan
Approval
Purchasing
Process
019
Perform T/A
Master Schedule
Walkthrough
020
Revise T/A
Master Schedule
021
Obtain
Consensus On
Rev T/A Master
Schedule
022
Issue Final T/A
Master Schedule
023
Create T/A
Schedule/
Budget/Scope
Baselines
024
Modify T/A
Sched As Reqd
By Scope
Control Process
026
Create New T/A
Sched/Budg/
Scope Baselines
027
Track T/A
Measures
Against Current
Baselines
025
Mitigation Plan
Exists
No
Yes
No
No
No
Yes
Yes
No
Yes
Page 25
Scope Freeze
• Based on asset T/A cycle
• Set by the T/A Scheduled Start Date where (T/A SS)
is the turnaround scheduled start date (asset out of
service)
0-6 month cycle, Scope Freeze = T/A SS – 60 days
> 6 mo to 18 mo cycle, Scope Freeze = T/A SS – 90
Days
>18 mo to 36 mo cycle, Scope Freeze = T/A SS – 120
days
>36 mo – 72 mo cycle, Scope Freeze – T/A SS – 180
days
Page 26
Scope Freeze
• Once scope freeze is implemented through T/A
execution complete (asset returned to service) any
addition or deletion of scope from the T/A would
require following a formal defined scope approval
process
• Requires approvals at the same level as that
required to authorize the T/A expenditure, for any
scope changes that will impact schedule a high
level approval requirement should be defined.
Page 27
Scope Control Process Flow
001
New Work
Scope is
Identified
004
Mitigation
Plan Exists
No
Yes Yes
Yes
Yes
Fast Track Approval Process
003
Enter In Scope
Change
Request Log
Yes
005
Develop
Detailed Job
Package
006
Prepare Scope
Change
Request Pkg
007
Work Scope Is
Reviewed With
Mtc/Eng Mgr
008
Impacts T/A
Objective
No
009
Determine
Level Of
Approval Req
010
Submit Scope
Chg Req To
Ref Mgr
011
Fast Track
Appr. Req.
012
Fast Trk Appr
Criteria Met
013
Email Fast Trk
Scope Chg
Appr Req
014 Scope
Chg
Approved
015
Verbal
Notification To
Ref Mgr
Yes
016
Submit Scope
Chg Req For
Appr Routing
018
Ret Appr
Scope Chg Req
To Ref Mgr
017
Scope Chg.
Approved
019
Notify T/A
Mgr To Impl
Scope Chg
020
Merge New
Work Into T/A
Master Sched
No
Yes
022
Develop New
T/A Master
Sched Baseline
021
Mitigation
Plan Exists
023
Track Work As
Non
Attainment
Yes
No
024
Notify
Refinery Mgr
025
Place Work In
Ref Routine
Bklg
No
No
No
002
New Scope
Initial Review
No
Page 29
Author/Presenter: Anthony V. Covato PE
Professional Biography:
• Mr. Covato is a registered professional engineer with over forty years experience in power generation (fossil, hydro and nuclear) and project
management. He has retired after approximately thirty years of service with Allegheny Energy Incorporated. He is currently employed as a Project
Manager Outage/Turnaround Subject Matter Expert with the Reliability Management Group in Minneapolis, Minnesota. He has had several papers
published on process design and implementation of both routine and outage/turnaround work management process topics.
Company : Reliability Management Group RMG
Address: 350 West Burnsville Parkway
Burnsville, MN 55337
Phone Nos. Office: 952-882-8122
Cell: 724-322-4877
Email: [email protected]
Co-Author/Presenter: David Noorani
• Mr. Noorani is currently the Sinclair Wyoming Refinery Manager responsible for Maintenance/Tech Services and Engineering Departments. He has
over 37 years of experience in the refining industry. His work experience includes various managerial assignments with Texaco Inc., Aramco Saudia,
Shell Oil, Murphy Oil and the current Sinclair Oil Co. He has an extensive background in operations, maintenance, turnarounds, projects and
engineering.
Company : Sinclair Wyoming Refining Co.
Address: P.O. Box 77
Sinclair, WY, 82334
Phone Nos. Office: 307-328-3605
Cell: 504-232-0601
Email : [email protected]