Reliability improvement project for blasthole drill...
Transcript of Reliability improvement project for blasthole drill...
Reliability improvement project for blasthole drill undercarriage
SKF Life Cycle Management Conference – Mining Presented by Darren Witt L&H Industrial 2014-10-09
1 The challenge
Mining Industry
Undercarriage Failures
Operating a common fleet of blasthole drills by a leading manufacturer, BHP Escondida Mine in Chile experienced frequent unplanned outages from undercarriage component failures: • Attachment hardware • Chain links
Mining Industry
Undercarriage Failures
Guarding Track Chain Pins
Mining Industry
Consequences
Downstream impacts: • Unit reliability was below Mine Plan estimates • Frequent inspections and re-tensioning of components was required • Repairs were difficult and time consuming • Low unit availability created an overall fleet capacity shortage • Negative impact to production schedules
2 The solution
Mining Industry
Cross-functional Team
L&H worked with mine personnel to identify the failure modes. • Mine team included:
– Drilling Superintendent – Engineering Superintendent – Maintenance Technical Lead – Engineering Technical Lead – Maintenance Engineer
• L&H Industrial team included: – Outside Salesman – L&H Chile Field Engineer – Product Line Manager – Chief Engineer – Design Engineer
Mining Industry
Adaptive Technology
• Adapted from excavators, the “bulldozer” undercarriage system was intentionally designed for a very aggressive, ground engaging, propel effort.
Mining Industry
New Challenges
• This ground engaging feature, exacerbated while propelling with the mast raised, results in extreme side loads when steering the drill.
Mining Industry
Solution
• To counter these effects, a low bearing pressure trackpad with less severe ground engagement was developed.
Mining Industry
Help it Turn
• To accommodate steering and side movement, the trackpad ends are “clipped”.
3 How did we implement it?
Mining Industry
Implementation
The Omega trackpad was designed to reduce the stress being transferred to the undercarriage system. • Design intent and conceptual models were shared with all
team members. • Omega trackpads are compatible with the OEM drive chain. • Standard mounting hardware was retained while
incorporating protection from the engagement surface.
4 Teamwork across life cycle stages
Mining Industry
Understand the Problems
The original specification from the mine was to provide a complete replacement undercarriage system; a significant impact to the design scope, manufacturing effort, costs, installation and commissioning requirements.
• Began by analyzing the effects • Developed “prototype” concepts
Mining Industry
Design Benefits
Design features reduced steering forces, minimizing inspection requirements and significantly reducing maintenance activities. Developing an efficient trackpad geometry resulted in manufacturing cost benefits. • Foundry operations are largely $$$/lb driven • Optimized for strength and material efficiency
5 The results
Mining Industry
Trials
After 1,000 hours of operation, the undercarriage system has performed exceptionally well. • No loose or broken trackpad mounting bolts • No failed drive chain links or trackpads • Preventative Maintenance frequency has been significantly reduced • Increased operational uptime • Drill positioning has improved, resulting in more efficient drilling
Mining Industry
Testing
A 6-month Test Procedure was developed to qualify the results • Improved reliability and availability • Increased drive chain life • Component failures • Wear rates • Associated component impacts
No adverse effects have been recorded to date.
6 The conclusion
Mining Industry
Successful Installation
Preliminary results of the Omega trackpad design and installation indicate operational reliability has been restored. • Involvement with the customer during the initial failure investigation accelerated our
learning curve. • Root cause discussion and information sharing identified the key failure modes. • Conceptual design reviews accelerated development of the prototype design. • Partial off-site assembly by L&H verified proper fit and alignment, thereby optimizing
installation and commissioning.
Mining Industry
Satisfied Customer
Teamwork and collaboration throughout the project led to a turnkey solution with in-service results in less than 12 months.