Relay Coordination of over Current Relay in Presence of DG ... · approach involves the...
Transcript of Relay Coordination of over Current Relay in Presence of DG ... · approach involves the...
IJSRD - International Journal for Scientific Research & Development| Vol. 6, Issue 02, 2018 | ISSN (online): 2321-0613
All rights reserved by www.ijsrd.com 3358
Relay Coordination of over Current Relay in Presence of DG System
using FCL
Pushpa Bhatiya1 Shruti Khatri2
1,2Department of Electrical Engineering 1,2Vadodara Institute of Engineering and Research, Vadodara, India
Abstract— In the Power System presence of Distributed
generation (DG) is one of attractive phenomena. With the
presence of DG units in distribution system, its function
would generally be changed and it would variously be
affected by DGs. When DGs are introduced into the power
system, the value and direction of both system’s power flow
in normal operation and short circuit current under fault
condition are changed results the disturbance to relay
coordination. In this, GA-NLP approach is presented to solve
the directional over current relay coordination problem,
which arises from installing DG in distribution system. This
approach involves the implementation of Fault Current
Limiter (FCL) to limit the DG fault current. In this thesis,
simulation of 3-bus and 9-bus system is implemented in
ETAP software. The optimum value of time multiplier setting
(TMS) and plug setting (PS) are found by using MATLAB
Optimization toolbox.
Key words: Genetic Algorithm (GA); Nonlinear
Programming (NLP); Overcurrent Relay Coordination; Time
Multiplier Setting (TMS); Plug Setting (PS), Fault Current
Limiter (FCL)
I. INTRODUCTION
OVERCURRENT relays have been widely used as an
economic alternative option for the protection of transmission
and distribution system [1]. To diminish the power outages
care should be taken that backup relays should work
efficiently and chances of their mal-operation should be
avoided. Hence coordination in case of overcurrent relays is
a matter of major. Overcurrent relay must be efficient enough
to provide protection to the affected primary zones. In case if
the primary protection fails to clear the fault, the back-up
protection should instigate tripping. Each protection relay
needs to be coordinated with the relays protecting the
neighboring equipment thereby making the overall protection
coordination complicated [2].
Distributed generation (DG) presence in power
systems is one of the attractive phenomena in power industry.
With the presence of DG units in distribution systems, its
function would generally be changed and it would variously
be affected by these units. One of the most important effects
of these units is on distribution systems protection. Since the
number of DG units not only can be varied but also has a great
deal of wide spread, Distribution systems protective devices
manner is completely changed with the presence of
distributed generation[3]. DG units are electrical energy
sources which are connected to distribution systems and in
comparison with the large scale power stations, have the
lower generation capacity and also have a lower starting cost.
II. PROBLEM FORMULATION
The coordination problem of overcurrent relays is an
optimization problem, where the sum of the operating times
of the relays of the system is to be reduced,
min Z= ∑ Wi . ti,k (i=1 to m) (1)
Where,
m- number of relays;
Wi- operating time of the relay;
ti,k - weight assigned for operating time of the relay.
As the lines are short and are of approximately equal
length, weight is equal for operating times of all the relays.
The purpose of reducing the total operating times of relays is
to be achieved under five sets of constraints, as discussed
below.[4.]
A. Constraint Set I—Coordination Criteria
The backup relay should operate only in case if the primary
relay fails to provide protection and causes maloperation.
The operating time of primary relay decides
minimum operating time of backup relay. The sum of
operating time of CB associated with primary relay, and the
overshoot time is called the coordination time interval (CTI).
If Rj is the primary relay for fault at k, and Ri is backup relay
for the same fault, then the coordination constraint can be
stated as –
ti,k – tj,k ≥ Δt (2)
Where,
ti,k - operating time of the primary relay, Rj
tj,k - operating time of the backup relay, Ri
B. Constraint Set II—Bounds on Relay Operating Time
Relay needs minimum time for operation. The constraint
imposed due to time related restriction on the operating time
of relays can be stated as –
ti,min ≤ ti.k ≤ ti,max (3)
Where,
ti,min - minimum operating time of relay at i
ti,max - maximum operating time of the relay at i
C. Constraint Set III—Bounds on the TMS ofRelays
Relays directly affect the operating time of relays, which puts
bounds on of relays. It can be stated as
TMSi,min ≤ TMSi.k ≤ TMSi,max (4)
Where,
TMSi,min - minimum value of relay;
TMSi,max - maximum value of relay.
D. Constraint Set IV—Bounds on the PS of Relays
The bounds on PS of relays can be stated as
PSi,min ≤ PSi.k ≤ PSi,max (5)
PSi,min - minimum value of PS on relay;
PSi,max - maximum value of PS on relay.
Relay Coordination of over Current Relay in Presence of DG System using FCL
(IJSRD/Vol. 6/Issue 02/2018/910)
All rights reserved by www.ijsrd.com 3359
E. Constraint Set V—Relay Characteristics
A nonlinear and popular overcurrent relay characteristic
function is as below-
top =(λ.TMS) / ((Irelay / PS)γ - 1) (6)
Where,
top- relay operating time;
Irelay – current through coil of relay.
III. APPLICATION OF HYBRID GA-NLP APPROACH TO RELAY
COORDINATION OPTIMIZATION
The problem of optimum coordination of OCRs is formulated
as NLPP. After formulation of the problem, few generations
of GA are used to determine the TMS and PS of OCRs and
Xfcl of fault current limiter. These values are then used as
initial choice in NLP method, which gives the global
optimum solution[2].
A. Finding Initial Solution Using GA
For applying GA technique to find the initial solution, the
problem is first converted into unconstrained optimization
problem. As the objective function, coordination constraints
and operating time constraints are written using the relay
characteristics, the relay characteristic constraint gets
automatically incorporated in the objective function,
coordination constraints and operating time constraints. The
constraints due to bounds on TMS and PS and Xfcl are taken
care of by defining the lower and upper limit of the variables
representing TMS and PS of relays and Xfcl, respectively, in
the GA program[2]. The constraints due to operating time of
relays, and the constraint due to coordination criteria, and the
constraint due to FCL are included in the objective function
using penalty method and thus the problem gets converted
into an unconstrained optimization problem[2]. Number of
bits to represent each parameter is decided and then a
population of suitable number of chromosomes is generated
randomly. The value of variables in each chromosome is
bounded by lower and upper limits, as described above. After
this, the iterations (generations) of GA are started. The
population is passed through the fitness function (objective
function). Then the population is sorted according to fitness.
As the objective function is of minimization type the
chromosome giving minimum value is most fit chromosome.
This chromosome has been treated as elite chromosome. The
chromosomes with higher _tness value survive (reproduced
in the next generation) and are called parent chromosomes.
These are used for mating. Pairs of parent chromosomes are
made for mating. Using the pairs of parent chromosome,
crossover is performed. For each pair the crossover site is
selected randomly. One pair (two parent chromosomes)
generates two offsprings after crossover. All the parent
chromosomes and all offsprings are placed together to form
the population for the next generation. The same population
size is maintained in all generations. The "mutation" is
applied after crossover. The number of mutations to be
performed is decided by mutation rate, which is one of the
GA parameter to be supplied at the beginning of the program.
For each mutation the chromosome is selected randomly (if
selected chromosome is elite then mutation is not performed
on this chromosome and another chromosome is selected).
The bit to be mutated is selected randomly from the
chromosome and is replaced by its complement. At this point,
an iteration of GA is complete. As, in this paper, the stopping
criteria has been considered as number of iteration of GA, the
process is stopped after performing pre-specified number of
iterations. The elite chromosome, at this stage, gives the
result[2].
B. Finding Final (Optimum) Solution Using NLP
The function available in MATLAB optimization toolbox, to
solve a constrained nonlinear optimization problem, can be
used to find the global optimum solution of the relay
coordination problem. The results obtained, after performing
prespecified number of iterations of GA, are taken as the
initial values of variables while applying NLP method. The
lower and upper bounds of variables (TMS and PS of OCRs),
are decided as per the mentioned constraints. The objective
function and the constraints (relay operating time constraints,
and coordination constraints), are defined in two different
function files. These functions are called in the main program
where the MATLAB optimization toolbox function is used to
give the optimum solution[2].
IV. SYSTEM INFORMATION
A. Three bus system without DG
The Hybrid GA -NLP method was tested for three bus system
as shown in fig 1. In this, eight relays have been considered
as numerical relay with standard IDMT characteristics. A
multi loop distribution system with 3-buses, and 8 relays, as
shown in fig.1 was considered.
Bus 1 is receiving the power, which has been
represented by a source of 25 MVA, 11 kV with a source
impedance of (0+j0.25)p.u. Base MVA is 25 MVA and base
kV is 11 kV. Lines between bus-1 and bus-2, and line
between bus-2 and bus-3 have an impedance of ( 0+j0.3) p.u.
Line between bus-1 and bus-3 has an impedance of (0+j0.6)
p.u. The overcurrent relays (OCRs) are numbered as 1 to 8.
B. System information with DG
The Hybrid GA -NLP method was tested for three bus with
DG system as shown in fig 2.In this eight relays have been
considered as numerical relay with standard IDMT
characteristics. A multi loop distribution system with 3-buses,
and 8 relays, as shown in fig 2 was considered.
Fig. 1: Single line diagram of three bus system
Relay Coordination of over Current Relay in Presence of DG System using FCL
(IJSRD/Vol. 6/Issue 02/2018/910)
All rights reserved by www.ijsrd.com 3360
Fig. 2: Single line diagram of three bus system with DG
Bus 1 is receiving the power, which has been
represented by a source of 25 MVA, 11 kV with a source
impedance of (0+j0.25)p.u. Base MVA is 25 MVA and base
kV is 11 kV. Lines between bus-1 and bus-2, and line
between bus-2 and bus-3 have an impedance of ( 0+j0.3) p.u.
Line between bus-1 and bus-3 has an impedance of (0+j0.6)
p.u. The overcurrent relays (OCRs) are numbered as 1 to 8.
Five wind generators are connected on bus 2 and rating of
each is 2.3 MW.
V. SIMULATION RESULTS OF THREE BUS SYSTEM
The proposed method was tested for the three bus system with
the help of different optimization method like genetic
algorithm, NLP and Hybrid GA-NLP. Short circuit Analysis
of three bus (with DG and without DG) system have been
done using E-TAP software. MATLAB optimization toolbox
function is used to get the optimum solution.
Table 1: Maximum load current and maximum fault current
(without DG)
Table 2: Values of TMS and PS for relays using GA
(without DG)
Table 3: Values of TMS and PS for relays using NLP
(without DG)
Table 4: Values of TMS and PS for relays using hybrid GA-
NLP (without DG)
Relay Coordination of over Current Relay in Presence of DG System using FCL
(IJSRD/Vol. 6/Issue 02/2018/910)
All rights reserved by www.ijsrd.com 3361
Table 5: Maximum load current and maximum fault current
(with DG)
Table 6: Values of TMS and PS for relays using GA (with
DG)
Table 7: Values of TMS and PS for relays using NLP (with
DG)
Table 8: Values of TMS and PS for relays using hybrid GA-
NLP (with DG)
VI. CONCLUSION
The values of TMS and PS for each relay of the three bus and
nine bus distribution system without DG using only genetic
algorithm technique were not optimal. Optimization
terminated and no feasible solution found using NLP method
for the same system. By using hybrid GA-NLP method a
feasible solution is achieved with minimum objective
function value. CTI was maintained between primary and
backup relay pairs. The operating time of all the relays were
minimized using Hybrid GANLP approach and at the same
time coordination was maintained. The values of TMS and
PS for each relay and XFCL of the three bus distribution
system with DG using only genetic algorithm technique were
not optimal. Optimization terminated and no feasible solution
found using NLP method for the same system. The optimal
values of TMS and PS and XFCL for 3-bus distribution
system with DG were found using hybrid GA-NLP approach
and CTI was maintained between primary and backup relay
pairs. The operating time of all the relays were minimized
using Hybrid GA-NLP approach and at the same time
coordination was maintained.
VII. FUTURE SCOPE OF WORK
There are some recommendations for further study in this
topic:
Used different types of relays such as directional
overcurrent relay, earth fault protection and others. Some
distribution system used different types of relay like
earth fault relay and directional overcurrent relay. The
different types of relay can be used to compare the
operating time at different setting of relays.
Combined all the protection system for distribution
system and transmission system. For transmission
system, the protection that applied was different with
distribution system. So, if distribution and transmission
system was combined, we should get the different setting
and coordination according to the system.
The further research suggested is the development of the
total intelligent protection system that is adaptive to all
Relay Coordination of over Current Relay in Presence of DG System using FCL
(IJSRD/Vol. 6/Issue 02/2018/910)
All rights reserved by www.ijsrd.com 3362
system conditions. Two major areas are improvement on
optimization method and real-time coordination and
adaptive grading margin.
REFERENCES
[1] Prashant Prabhakar Bedekar,Sudhir Ramkrishna
Bhide,”Optimum Coordination of Directional
overcurrent relays using the Hybrid GA-NLP
Approach”,IEEE Transactions on Power
delivery,vol.26,No.1,January 2011.
[2] A. J. Urdaneta, N. Ramon, and L. G. P. Jimenez,
“Optimal coordination of directional relays in
interconnected power system,” IEEE Trans. Power Del.,
vol. 3, no. 3, pp. 903–911, Jul. 1988.
[3] H. Zeienldin, E. F. El-Saadany, and M. A. Salama, “A
novel problem formulation for directional overcurrent
relay coordination,” in Proc. Large Engineering Systems
Conf. Power Engineering, Halifax, NS, Canada, 2004,
pp. 48–52.
[4] B. Chattopadhyay, M. S. Sachdev, and T. S. Sidhu, “An
online relay coordination algorithm for adaptive
protection using linear programming technique,” IEEE
Trans. Power Del., vol. 11, no. 1, pp. 165–173, Jan. 1996.
[5] H. A. Abhyaneh, M. Al-Dabbagh, H. K. Karegar, S. H.
H. Sadeghi, and R. A. J. Khan, “A new optimal approach
for coordination of directional overcurrent relays in
interconnected power system,” IEEE Trans. Power Del.,
vol. 18, no. 2, pp. 430–435, Apr. 2003.
[6] S. K. Bhattacharya and S. K. Goswami, “Distribution
network reconfiguration considering protection
coordination constraints,” Elect. Power Compon. Syst.,
vol. 36, pp. 1150–1165, 2008.
[7] C. W. So and K. K. Li, “Overcurrent relay coordination
by evolutionary programming,” Elect. Power Syst. Res.,
vol. 53, pp. 83–90, 2000.
[8] F. Razavi, H. A. Abyaneh, M. Al-Dabbagh, R.
Mohammadi, and H. Torkaman, “A new comprehensive
genetic algorithm method for optimal overcurrent relays
coordination,” Elect. Power Syst. Res., vol. 78, pp. 713–
72, 2008.
[9] K. T. Lai, and K. Y. Fung, “Application of genetic
algorithm to overcurrent relay grading coordination,” in
Proc. 4th Int. Conf. Advances in Power System Control,
Operation and Management, Hong Kong, China, 1997,
pp. 283–287.
[10] K. A. Waleed, N. H. Zeineldin, “Optimal protection
coordination for microgrids with grid connected and
islanded capability”, IEEE Trans. Ind. Electronis., vol.
60,no.4, pp. 16681677, Apr. 2013.
[11] S. A. Soman, Lectures on Power System Protection
module 4 & 5.[Online]. Available:
www.cdeep.iitb.ac.in/NPTEL
[12] Bhuvanesh Oza, Nirmalkumar Nair, Rashesh Mehta,
Vijay Makwana, "Power System Protection and
Switchgear" Tata McGraw Hill Education Private
limited,New Delhi, 2010.pp 1-50, 175-270.
[13] N.P.Padhy”Artificial intelligence and intelligent
systems” 1st edition;2005,pp.459-505.