Regulations Handbook-DEWA

download Regulations Handbook-DEWA

of 93

description

COnstruction of UG Electrical cables/ OHL

Transcript of Regulations Handbook-DEWA

  • First Edition 2013Issued ByTransmission Maintenance DepartmentTransmission Power DivisionDubai Electricity and Water Authority

  • HAND BOOKon EHV Over Head Line &Under Ground Cable Protective Regulations

  • 4 DEWA Hand Book

    TABLE OF CONTENTS

  • 5EHV Over Head Line & Under Ground Cable Protective Regulations

  • 6 DEWA Hand Book

    Dubai is one of the renowned cities within the Gulf countries, as well as internationally, for business, security & tourism, which is becoming one of the modern citiy of the world. Therefore, reliability of Electricity becomes one of the basic requirements for modernization.

    Electricity is one of the basic needs, for the human beings health, education, business, agriculture, transportation, communication, industrialization & etc. This is to be considered a measuring parameter of the citizens living standard, industrialization and economic growth for a country. The mentioned parameters will affect, if there is shortage of electricity or frequent failure, due to any reasons.

    Transmission lines are the backbone of electricity network which transmit power from generating stations to distribution system, for supplying power to the customer.

    DEWA 400 / 132kV OHL & Cable lines are in open fields and passing through desert / hilly terrain, urban areas and crossing roads / bridge / underpass / canals & utility services etc.

    The risk of damages due to contractors are very high, due to Possible unauthorized and unsafe construction activities in the vicinity of the lines. In the following consequences, it may lead to partial or full blackout in the Emirates of Dubai, if there are any damages with lines.

    To achieve Dubai governments vision of supplying uninterrupted electricity, to our valuable customer(s) and to promote development activities, we feel it is quiet essential & noteworthy, sharing the information which is of vital importance with contractor / consultant & utility depts about DEWA protective rules & regulations to protect Transmission lines from unwanted damages.

    Nevertheless, this handbook will streamline DEWAs regulations, to the contractor in the implementation of works safety, quality near the Extg. Transmission lines, which will in turn support the purpose of the contractors time & cost, which generally gets affected due to unprofessional work practices.

    This handbook will help the contractor / consultant & utility depts, with the information about the NOC requirements, DEWA Protective Rules & Regulations to work in the vicinity of OHL & Cables lines, to avoid the unexpected damage to Transmission lines & human injury / death.

    We hope contractor / consultant / utility departments & private parties will follow DEWA protective rules & regulations and cooperate to achieve Dubai governments vision of uninterrupted electricity supply, in the Emirates of Dubai.

    Transmission Maintenance Dept

    PREFACE

  • TRANSMISSION LINES &ACCESSORIES

    CHAPTER 1

  • 8TRANSMISSION LINES & ACCESSORIES

    DEWA Hand Book

    1.1 Types Of Cables

    a. 400kV XLPE Cable

    b. 132kV XLPE Cable

    c. 132kV Oil Filled Cable

    a) Voltage wise underground cable are of 02 types 400 & 132kV.

    b) Construction wise Underground Power Cables are of 02 types:

    1. XLPE (Fig a & b)2. Oil Filled (Fig c)

    Note:Power cables cannot be detected by cable detector, when it is under shutdown/out of service.

  • 9EHV Over Head Line & Under Ground Cable Protective Regulations

    e. Cross Section of Pilot cabled. Fiber Optic Cable

    Communication cable is based on construction & function 02 types as under:

    1. Fiber Optic Cable (Fig d) 2. Pilot Cable (Fig e)

    Note:F.O & Pilot Cables cannot be detected by cable detector, even under live condition.

  • 10

    TRANSMISSION LINES & ACCESSORIES

    DEWA Hand Book

    1.2 Types Of Transmission Over Head Towers

    a. 400kV Over Head Transmission Tower

    c. 400 / 132kV Gantry Tower

    b. 400kV Tubular Monopole Tower

    d. 132kV Steel Lattice (Double Circuit Tower)

    Double Circuit Single Circuit

    Voltage wise Overhead Lines are of 02 types 400 & 132kV.Construction wise Overhead Lines are of 02 types -

    1. Tubular Monopole Tower 400kV 2. Steel Lattice 400kV, 132kV & Gantry

  • 11EHV Over Head Line & Under Ground Cable Protective Regulations

    1.3 Installation Methods

    a. 400kV Cable Tunnel

    (Cable Installation method in Precast Culvert)

    400 & 132kV Cables are laid by the following methods:a) 400kV cable laid in Tunnelb) 132kV cable laid in concrete troughc) 132kV cable laid in 50cm trough in congested area

    d) 132kV FO cable laid in 50cm troughe) 132kV Power & FO cable laid in PVC ductsf) 132kV Power/Pilot & FO cable laid in directly buried

    condition

  • 12

    TRANSMISSION LINES & ACCESSORIES

    DEWA Hand Book

    b. 132kV Cable laying in Concrete trough

    132kV Cable Laying In Trough

  • 13EHV Over Head Line & Under Ground Cable Protective Regulations

    c. 132kV Cable laying in 50cm trough in Congested Area

    132kV & Fibre Opticcable in 50cm Wide Trough in Congested Area Due to Inadiquate Space

  • 14

    TRANSMISSION LINES & ACCESSORIES

    DEWA Hand Book

    d. 132kV FO Cable laying in 50cm trough

    132kV F.O Cable Laying In 50cm Wide Trough

  • 15EHV Over Head Line & Under Ground Cable Protective Regulations

    e. 132kV cable power / FO cable laying through PVC ducts

    (132kV Power / Fo Cable Laying Through Duct (with 10 Ducts)(Open Cut Method for unmade Area)

  • 16

    TRANSMISSION LINES & ACCESSORIES

    DEWA Hand Book

    f. 132kV Cable Power / pilot / fo cable in directly buried

    Cable Laying Method Directly Buried 132kV Power / Pilot / F.O. Cable

  • 17EHV Over Head Line & Under Ground Cable Protective Regulations

    Typical Trench Details for Directly Buried 132kV F.O. Cable

  • 18

    TRANSMISSION LINES & ACCESSORIES

    DEWA Hand Book

    Typical Trench Details for Directly Buried 132kV Pilot Cable

  • 19EHV Over Head Line & Under Ground Cable Protective Regulations

    1.4 AccessoriesA. Cable Accessories1.4.1 Cable Joints & TerminationsCable joint and termination is the integral part of the Transmission under ground lines system as a whole.

    1.4.1 A 132kV Cable joint location

    Location of 132kV cable Joint bay installation with identification route marker

    Note: Joint is a weak point in transmission cable system. The joint area to be maintained and protected properly to ensure reliability of power supply.

    Power cable joint normally enclosed in 2.4 meter wide concrete trough. Few Transition joints are enclosed in UG Manholes and joint location is identified with red & white route markers for all type of installation.

    1.4.2 Earth Link BoxesThis is one of the accessories for the transmission system used for easy access to cable sheath test.

    1.4.2 A Types of installation of link boxa. Vertical mounted b. Flush mounted (Underground)

    1.4.3 Cable Route Marker (Power, Fiber Optic, or Pilot) Cablesa. This is used for cable route identification and it helps

    to indicate the presence of Transmission cable in subject area. There are two types of installation of route markers

    1. Surface / pole mounted (Figure: 1.4.6) 2. Flush mounted (Figure: 1.4.7)

    b. Surface / Pole type route marker is installed for direct buried or cable trough under any un-paved area.

    c. Flush type cable route marker (Concrete) is installed for direct buried or cable trough under any paved area, road way, parking etc with suitable marking for straight and angle run, cable joint etc.

    d. All type of route markers should be installed 50 Meters interval for straight route.

  • 20

    TRANSMISSION LINES & ACCESSORIES

    DEWA Hand Book

    1.4.4 Vertical mounted link box with steel bollard Protection

    1.4.5 Vertical mounted link box with steel crash barrier protection in road side

    1.4.6 Surface / pole type route marker installed in every 50 m interval

    1.4.7 Flush type route marker at paved areas

  • 21EHV Over Head Line & Under Ground Cable Protective Regulations

    1.4.8 Installation of Permanent Height limit gantry at road crossing tower location

    1.4.9 Installation of Permanent Height limit gantry at road crossing tower location

    B. Overhead Line Accessories

  • 22 DEWA Hand Book

    1.4.10 Installation of no parking Sign board at OHL to restrict the vehicle movement / parking in OHL corridor

    1.4.11 Installation of no dumping Sign board at OHL to restrict the dumping of waste materials in OHL corridor

    TRANSMISSION LINES & ACCESSORIES

  • HAZARDOUS FACTORS WHILE WORKING NEAR TRANSMISSION LINES

    CHAPTER 2

  • HAZARDOUS FACTORS WHILE WORKING NEAR TRANSMISSION LINES

    24 DEWA Hand Book

    Most common hazard is damage to the EHV Transmission lines due to contractors unsafe construction activities:

    a) Works within & around the Transmission Lines without obtaining NOC, violation of NOC condition & Method statement.

    b) Works without verification / Identification of the underground cables.c) Works without verification / checking clearance of the Overhead lines.d) Usage of machinery for excavation over / in the close vicinity of Transmission lines.

    2.1 Hazardous Factors Of The Line Damages

  • 25EHV Over Head Line & Under Ground Cable Protective Regulations

    2.2 Hazard Levels

    Sl.No. Hazards Hazardslevel

    a Works within & around the Transmission Lines without obtaining NOC, violation of NOC condition & Method statement

    High

    b Works without verification / confirmation of the under ground cables. High

    c Works without verification / checking of the Overhead lines. High

    d Usage of machinery for excavation over / in the close vicinity of Transmission lines

    High

  • 26 DEWA Hand Book

    2.3 Precautionary Measures To Eliminate The Hazards

    Sl.No. Precautionary measures Hazardslevel

    a Contractor works within & around the Transmission lines to be allowed with valid NOC & following all NOC conditions / method statement.

    Low

    b All under ground cables should be identified & protect at the work areas. Low

    c OHL clearance shall be confirmed & height limit gantry shall be provided to work under OHL.

    Low

    d Ensure manual excavation over / in the close vicinity of the Transmission lines. Low

    HAZARDOUS FACTORS WHILE WORKING NEAR TRANSMISSION LINES

  • NOC FOR CONSTRUCTION WORKSCHAPTER 3

  • 28 DEWA Hand Book

    NOC FOR CONSTRUCTION WORKS

    3.1 General Provisions3.1.1 Definitions

    No Objection Certificate is usually abbreviated as NOC and defined as a written permission issued by Infrastructure Information and Permit / Connection service Department of DEWA to any desiring to carry out the proposed construction as indicated on the submitted and approved Drawings.

    3.1.2 Purpose Issuance of NOC prior to construction works provide first line of protection to all existing DEWAs assets from proposed construction, as it contents sets of regulatory requirements, protective rules, precautionary measures, engineering construction standards, etc that require clear understanding of every constructors for adherence.

    3.1.3 ScopeThe extent of application of approved NOC are those areas within or in close proximity to the transmission line networks (400 / 132kV Over Head Line and underground cables)

    3.2 Type Of NOCs3.2.1 Design NOC

    Design NOC is a permission given to consultant to proceed to the proposed project as indicated on the Tender Design Drawing which indicates the approximate locations and clearance of all the existing transmission underground cables and overhead lines.

    3.2.2 Trial Pit NOCTrial Pit NOC is a permission given to contractor to proceed digging-in the number of Trial Pits based on the proposed scope of work limit demarcated on the site as directed by the Patrolling Staff.

    A. Purpose of Trial PitTo confirm the real identification and exact location of existing utilitys assets in relation to proposed construction works and to be the only parameters used in the evaluation and approval of the subsequent Construction NOC.

    B. Requirements for Trial Pit Preparationa. Trial Pit digging should only be initiated with

    the supervision of DEWAs representative (TLM-Patrolling). According to the scope of work, Trial Pit location will be marked by the supervisor.

    b. The required supervision specified in above should be requested by using DEWA work supervision request format and FAX to DEWA, threet (03) days before to start of any digging works. (Annex 3.1.1)

    c. Trial Pit is a trench made across and over the suspected location of underground cable, trough, joint, etc. (Figure: 3.1.2)

    d. Trial Pit should only be dig manually by hand to ensure that the buried unconfirmed location of cables may not be penetrated and unaware. (Figure: 3.1.3)

    e. Trial Pit Checklist should be satisfied before initiation of digging Trial Pit. (Annex 3.1.1)

  • 29EHV Over Head Line & Under Ground Cable Protective Regulations

    Annexure 3.1.1 - Trial Pit Work supervision request

  • 30 DEWA Hand Book

    NOC FOR CONSTRUCTION WORKS

    Annexure 3.1.1 - Trial Pit check List

  • 31EHV Over Head Line & Under Ground Cable Protective Regulations

  • 32 DEWA Hand Book

    NOC FOR CONSTRUCTION WORKS

    Fig 3.1.2 Locating 132kV cable through Trial Pit. Fig 3.1.3 Manual excavation for Trial Pit.

    Fig 3.1.4 Trail pit verification.

    Locating the service by referring the NOC Manual excavation for trial pit to trace the service

    C. Trial Pit VerificationAfter exposing all existing cables, troughs, joints, etc. DEWAs representative (TLP-Supervisor) to be confirming the exact location of the cables, depth and clearance from the proposed scope of work limit.

    Such confirmation should be written and signed by the same Supervisor. The Contractor should submit the verified trial pit details along with construction NOC

    Special Cases:1. In case of 132kV cable not found (HDD area), DEWA

    supervisor will write in the verification, that cable is not found at x meter depth.

    2. Additionally, coordinates from As-Built drg. can be provided for trial pits.

    3. Sensor method can be used for identification of 132kV cable.

  • 33EHV Over Head Line & Under Ground Cable Protective Regulations

    D. OHL Clearance verificationTo confirm the horizontal and vertical clearance details from the proposed scope of work limit to the OHL to be identified as per the demarcation. Such confirmation should be written and signed by the TLP supervisor. The Contractor should submit the verified OHL clearance details along with construction NOC, if the proposed work within the vicinity of the OHLs.

    3.2.3 Construction NOC.Construction NOC is a permission given to Contractor to proceed the proposed construction works as indicated on accompanying shop drawing.

    3.2.4 Revalidation or Renewal of Expired Construction NOC

    a. Whenever, the six (6) months life span or validity of the issued Construction NOC may be insufficient for completion of any project, the NOC holder should submit application for Revalidation to DEWA II & P or CS Dept. as two weeks before the date of expiration to ensure that there may have a valid NOC at all times.

    3.3 Requirements For The Application Of NOCA. Road work

    a. Proposed scope of work drawing to be submitted in scale (1:1000) with DLTM coordinates incorporating the Existing 400 / 132kV OHL / cable route, circuit names, cable joint / link box location, clearance from the

    proposed road edge to the cable / trough edge, OHL Horizontal and vertical clearance from the proposed road, Horizontal clearance from the tower foundation to the road edge.

    b. Clearance details from the proposed bridge, ramp, and side wall of ramp, bridge pillar/ pier, and underpass to the transmission lines, crossing and protection details to be submitted.

    c. ROW Cross section details.d. Details of OHL tower protection (crash

    barrier) Height limit gantry, fencing details, access from the proposed road to the OHL corridor (If the proposed road is close / crossing to the OHL corridor).

    e. If the proposed road is over the existing 132kV cable / trough, Length of the cable protection, spare duct details with ends coordinates to be shown to the drawing.

    f. The proposed road / road widening over the existing duct bank, edge of the proposed road to the existing cable duct bank edge to be shown. If the duct bank is extended details and ends coordinates to be provided.

    g. If the Proposed road edge is close to the cable joint / link box locations, 4 corners coordinates of the joint box, Horizontal clearance from the joint / link box to the road edge to be shown to the drawing.

    h. If any utility services / diversions included in the proposed road work contract, clearance details of the services, (Water, Drainage, storm water, Irrigation pipelines Etc., Etisalat duct, Electricity HV and LV) Crossing details, Protection details to be submitted.

  • 34 DEWA Hand Book

    NOC FOR CONSTRUCTION WORKS

    i. If any landscaping work included under the road project within the vicinity of the existing 400 / 132kV OHL / cable services those details to be submitted.

    j. Clearance from the road signal post, street light poles to the existing 400 / 132kV OHL / cable to be provided.

    k. If the 132kV Cable diversions / OHL rising included under the road contract, detailed drawing to be submitted.

    l. Access to the substation to be shown to the drawing. (If the proposed road close to the substation).

    m. TLP staff verified Cable / OHL clearance details.n. If any additional information required other

    than the above to be provided.

    B. Installation of Electrical cable / trougha. Proposed scope of work drawing to be

    submitted in scale (1:1000) with DLTM coordinates incorporating the Existing 400 / 132kV OHL / cable route, circuit names, and cable joint / link box location.

    b. Clearance from the proposed scope of work / excavation edge to the 132 / 400kV cable / trough edge and Horizontal and vertical clearance from the OHL to the proposed scope of work, Horizontal clearance from the tower foundation to the excavation edge.

    c. ROW cross section details.d. Method statement, crossing details, cable /

    trough protection details.e. Clearance details of equipment / machinery to

    be submitted along with method of statement, if the works are near / close to the OHL.

    f. Details of tower protection (crash barrier) temporary height limit gantry, etc. safety arrangement to be provided if the works are close to the OHL.

    g. Underground structural works details like cable joint / duct bank.

    h. Clearance from the existing joint location to the proposed joint lotion for LILO / Existing cable diversion works.

    i. TLP staff verified Cable / OHL clearance details.

    j. If any additional information required other than the above to be provided.

    C. Installation of Pipelines.a. Posed scope of work drawing shall be

    furnished in details such as Main pipe, PVC duct for control cables, RTU, Valve chamber Etc. to be submitted in scale (1:1000) with DLTM coordinates incorporating the Existing drawing route, circuit names, cable joint / link box location.

    b. Clearance from the proposed scope of work / excavation edge to the 132 / 400kV cable / trough edge and Horizontal and vertical clearance from the OHL to the proposed scope of work, Horizontal clearance from the tower foundation to the excavation edge.

    c. ROW cross section details.d. Method statement, crossing details, cable /

    trough protection details.e. Clearance details of equipment / machinery

    to be submitted along with method of statement, if the works are near / close to the OHL.

  • 35EHV Over Head Line & Under Ground Cable Protective Regulations

    f. Details of tower protection (crash barrier) temporary height limit gantry, etc. safety arrangement to be provided if the works are close to the OHL.

    g. Underground structural works details like manholes, pumping stations and chambers etc shall be submitted along with method of statement.

    h. TLP staff verified Cable / OHL clearance details.

    i. If any additional information required other than the above to be provided.

    D. Construction of building, Boundary walls, Temporary fencing and interlocking.

    a. Proposed plot details / affection plan.b. Scope of work details / setting out plan

    including the access details. If the access to the plot / building is over the existing cable routes, shall be protected with additional protection slab and spare ducts. Detailed drawing for protection / spare ducts shall be provided.

    c. Clearance from the plot limit / Depth of excavation / shoring / anchoring / fencing details along with existing 400 / 132kV OHL / cable clearance.

    d. Fencing details (only see through if cable enclosed).

    e. Undertaking that no materials, no cabins, construction and materials on cable reservations.

    f. Undertaking for interlock tiles, gardening, pavement, asphalt etc. (that the owner will allow DEWA at any time access and

    reinstatement will be done by them).g. TLP staff verified Cable / OHL clearance

    details.h. If any additional information required other

    than the above to be provided.

    E. NDRC / Thrust Boring / Micro tunneling / Pipe jacking

    a. Proposed scope of work drawing plan view to be submitted in scale (1:1000) with DLTM coordinates of entry and exit pits incorporating the Existing 132 / 400kV cable / OHL route, circuit names, cable joint / link box location (if any).

    b. Longitudinal section of proposed scope of work location indicating the existing 400 / 132kV cables, clearance from the bottom of the trough and the clearance from entry and exit pit to the existing cables.

    c. Horizontal and vertical clearance from the OHL to the proposed scope of work, Horizontal clearance from the tower foundation to the excavation edge.

    d. Clearance details of equipment / machinery to be submitted along with method of statement, if the works are near / close to the OHL.

    e. Details of tower protection (crash barrier) temporary height limit gantry, etc. safety arrangement to be provided if the works are close to the OHL.

    f. Sheet piling protection details (If required).g. TLP staff verified Cable / OHL clearance

    details.

  • 36 DEWA Hand Book

    NOC FOR CONSTRUCTION WORKS

    h. If any additional information required other than the above to be provided.

    F. Etisalat / Du Duct / Chamber Installationa. Proposed scope of work drawing to be

    submitted in scale (1:1000) with DLTM coordinates incorporating the Existing 400 / 132kV OHL / cable route, circuit names, and cable joint / link box location.

    b. Clearance from the proposed scope of work / excavation edge to the 132 / 400kV cable / trough edge and Horizontal and vertical clearance from the OHL to the proposed scope of work, Horizontal clearance from the tower foundation to the excavation edge.

    c. ROW cross section details.d. Method statement, crossing details, cable /

    trough protection details.e. Clearance details of equipment / machinery

    to be submitted along with method of statement, if the works are near / close to the OHL.

    f. Details of tower protection (crash barrier) temporary height limit gantry, etc. safety arrangement to be provided if the works are close to the OHL.

    g. Clearance details of chamber and installation details.

    h. TLP staff verified Cable / OHL clearance details.

    i. If any additional information required other than the above to be provided.

    G. Other Miscellaneous works. (Sign board, bore holes, Piling etc.)

    a. Proposed scope of work drawing to be submitted in scale (1:1000) with DLTM coordinates incorporating the Existing 132 / 400kV cable / OHL route, circuit names, cable joint / link box location if any within the proposed working area.

    b. Clearance from the proposed scope of work / excavation / piling to the 132 / 400kV cable / trough edge and Horizontal and vertical clearance from the OHL to the proposed scope of work, Horizontal clearance from the tower foundation to the excavation edge.

    c. ROW cross section details.d. Method statement for the proposed work.e. Clearance details of equipment / machinery

    to be submitted along with method of statement, if the works are near / close to the OHL.

    f. Details of tower protection (crash barrier) temporary height limit gantry, etc. safety arrangement to be provided if the works are close to the OHL.

    g. TLP staff verified Cable / OHL clearance details.

    h. If any additional information required other than the above to be provided.

    H. Revalidation or Renewal of Expired Construction NOC.

    a. NOC holder should submit application for revalidation to extend its validity period to another 6 months.

    b. Expired NOC can be revalidated in several times so long as submitted with acceptable reasons.

  • 37EHV Over Head Line & Under Ground Cable Protective Regulations

    c. The original TLM stamped drawing of expired NOC and all its accompanying drawings and method statement should be submitted while applying for revalidation.

    d. Drawing showing the part of completed works and the remaining works which should be the work scope of the Revalidated NOC should be submitted.

    e. Application for NOC renewal should be submitted as early as two weeks before the date of expiration to ensure that there may have a valid NOC at all times.

    I. Requirements of Project completion certificate

    This is to confirm by DEWA that the contractor has completed the work as per the Issued NOC drawing / s and Method of statement. In general, the following documents / details are required to submit for completion certificate and As Built drawing approval.a. Full set of the Construction NOC drawing

    / shop drawing / Diversion drawings Etc. issued by DEWA (TLM) for the full project / contract area to be submitted along with the as built drawing and all those works details included in the As built drawing within the vicinity of the existing 400 / 132kV OHL / cable area.

    b. As built drawing submitted in scale (1:1000) incorporating the Existing 400 / 132kV OHL / cable route, circuit names, cable joint / link

    box location, clearance from the proposed scope of work to the cable / trough edge, OHL Horizontal and vertical clearance from the proposed work, Horizontal clearance from the tower foundation.

    c. Clearance details from the proposed bridge, ramp, and side wall of ramp, bridge pillar / pier, and underpass to the existing 132 / 400kV cable and crossing details, cable protection details to be submitted.

    d. Details of OHL tower protection (crash barrier) Height limit gantry, fencing details, access from the proposed road to the OHL corridor (If the proposed road is close / crossing to the OHL corridor).

    e. Access to the substation to be shown to the drawing (If the proposed road close to the substation)

    f. If the proposed road is over the existing 400 / 132kV cable / trough, Length of the cable protection, spare duct details with ends coordinates to be shown to the drawing.

    g. The proposed road / road widening over the existing duct bank, edge of the proposed road to the existing cable duct bank edge to be shown. If the duct bank is extended details and ends coordinates to be provided.

    h. If the Proposed road edge is close to the cable joint / link box locations, 4 corners coordinates of the joint box, Horizontal clearance from the joint / link box to the road edge to be shown to the drawing.

    i. If any utility services / diversions included in the proposed road work contract, clearance

  • 38 DEWA Hand Book

    NOC FOR CONSTRUCTION WORKS

    details of the services, (Water, Drainage, storm water, Irrigation pipelines Etc., Etisalat duct, Electricity HV and LV) Crossing details, Protection details to be submitted.

    j. If any landscaping work included under the road project within the vicinity of the existing 400 / 132kV OHL / cable services those details to be submitted.

    k. Clearance from the road signal post, street light poles to the existing 400 / 132kV OHL / cable to be provided.

    l. If the 132kV Cable diversions / OHL raising included under the road contract, Separate As built drawing to be submitted as per DEWA standard.(Standard requirements list attached).

    m. The contractor and the consultant make sure that back filling works over the existing cable route where the construction related works carried out over / within the vicinity of the 400 / 132kV OHL / cable area and route markers displaced / removed / damaged during the work execution are replaced.(If any)

    n. Joint site inspection from TLM personnel may be required to confirm the above details provided.

    o. Note:-If any work carried out without DEWA NOC or Violation of DEWA NOC conditions during the work execution, such cases the clearance certificate may be not issued.

    J. Requirements of as built drawings for 400 / 132kV OHL rising / Cable diversions a. Clearance from the B / L / ROW / Road edge

    to the cable diversion to be marked on the drawing.

    b. Cross section details of services crossing i.e. mainly for water and other pressure pipe line crossings, Existing 132kV cable crossing, Road crossing etc. to be provided.

    c. Copy of RTA NOC to be attached with the Final as Built Drawing along with ROW cross section.

    d. Duct bank / Drilling portion including length and GPS coordinates.

    e. Directional Drilling profile details with GPS co ordinates (Separately for each drilling).

    f. Cable schedule showing the section wise route length.

    g. Pilot / F.O cable joint location marked with GPS coordinates and detailed section.

    h. Cable route layout inside the substation (if any).

    i. Updated substation layout showing new 132kV cable route along with existing (If any).

    j. Single line drawing showing cable in duct bank area / protection with Inter lock tile / Directly buried area.

    k. Cable diversion contract No., Cable manufacture name, Cable test report, Data of cable laid, Cable type and size, No. Of cables, Distance between cable centre to centre and cable circuit Name.

    l. Cable joint details i.e. Coordinates (Four corners), Joint type, Jointer name and date, Joint Manufacture name.

    m. Spare Duct details. Duct coordinates, No. Of ways / layers, Duct inspection checklist

  • 39EHV Over Head Line & Under Ground Cable Protective Regulations

    (Signed by DEWA Inspector), Type of duct (road cutting / drilling), Extended duct / split duct details (If any).

    n. Type of proposed OHL Tower, Test report, Technical specifications, Plan, Elevation, Cross section of the tower with dimensions, insulator and other used component for the proposed tower to be provided.

    o. Profile drawings including the nearest existing OHL to the proposed OHLs to be submitted.

    p. Horizontal clearance from the proposed road edge to the proposed tower foundation / tower protection barrier edge.

    q. Vertical clearance details from the proposed road level to the lowest OHL conductor (After raising the tower).

    r. Existing and proposed Tower Nos., distance between either sides of the existing towers to the proposed the tower(s).

    s. Access road to the proposed tower location.

  • 40 DEWA Hand Book

    NOC FOR CONSTRUCTION WORKS3.4 Transmission Line Maintenance NOC ConditionsA. 400 / 132Kv Cables

  • 41EHV Over Head Line & Under Ground Cable Protective Regulations

    B. 400 / 132kV Over Head Lines

  • 42 DEWA Hand Book

    3.5 Submission Of ApplicationSubmission of Applications: - All the NOC applications are submitted through Senior Manager. Infrastructure Information and Permit Dept. (II&P) / Senior Manager Connection Services Dept. (CS)

    Contact details

    To Senior Manager Senior Manager Senior Manager

    Dept. Infrastructure information & permit

    Dept.

    Connection services Dept.

    Transmission Line Maint. Dept.

    Location DEWA Head office DEWA Hudaiba office DEWA Hudaiba office

    P.B.No. 564 564 564

    Emirates. Dubai Dubai Dubai

    Tel. 04-3072603 04-5066445 04-5066826 / 827

    Fax. 04-3245545 04-5066793 04-3984655

    Note: No any NOC applications directly received by TLM Office.

    NOC FOR CONSTRUCTION WORKS

  • PROTECTIVE REGULATIONS & PRECAUTIONARY MEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    CHAPTER 4

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    44 DEWA Hand Book

    75cm

    DANGER132kV LIVE CABLE

    BELOW

    20cm

    15cm

    Rear view

    Front view

    75cm

    Rear view

    Front view

    DANGER132kV LIVE CABLE

    BELOW

    20cm

    15cm

    DANGER132kV LIVE CABLE

    BELOW

    20cm

    15cm

    DANGER132kV LIVE CABLE

    BELOW

    20cm

    15cm

    4.1 Infrastructure WorksA. In the vicinity of existing 400 / 132kV Cable1. Identification & Barricading: Existing Transmission lines in the vicinity & within the proposed working area

    to be identified by trial pits. Danger sign board needs to be fixed and barricading entire cable route, before starting the work at site. - Figure: 4.1.1, 4.1.2, 4.1.3

    Danger Sign Boad

    Fig 4.1.1: Cable identification by Trial pitFig 4.1.2 Danger Sign Board To Be Provided After Identification Of 400 / 132kV Cable At Work

    Fig 4.1.3: Danger sign board and barrication at work area

  • 45EHV Over Head Line & Under Ground Cable Protective Regulations

    2. No Machinery Excavation: Machinery, construction equipment / excavator / Vehicles etc. are not allowed to work / move or park over the cable route and use of heavy vibratory compaction is prohibited. If any particular locations are required to cross over the Extg.cables, then that portion separate NOC to be obtained & cable route to be protected for the crossing area. Only Manual excavation is allowed. Figure: 4.1.4

    3. Separate Noc criteria: No construction of road or services where joints & link boxes exit and joint bay access to be available at all times. If any activity within this area, separate NOC to be obtained.

    4. Miscellan\eous installations: Streetlight poles, crash barriers, road signboards, excessive filling on cable cor ridor are prohibited. Only grass / shrubs allowed in cable corridor. Trees should be 5.0 m. away. Figure: 4.1.5

    5. Cable protection: Shifting / slewing or exposing of cables will not be permitted without NOC explicit written permission. Exposed cable to be protected in wooden box after wrapping with hessian cloth and supported properly. Figure: 4.2.2 - (Pg) & 4.2.3 (Pg)

    6. Road construction: Carriageway is not allowed to run longitudinally over 132kV Power, Fiber Optic, and Pilot Cables. Existing cables / Trough coming under / along the proposed road to be diverted and abandoned portion of the cable / trough to be removed. Steel protection barrier to be provided for Link boxes in the vicinity of Road. A new trough design is used for Asphalt Road (carriage way) by replacing the Existing Protection slab with heavy duty slab. Figure: 1.4.4 (Pg.21) and Figure: 4.1.6 (pg 48)

    7. Road crossing: New Carriageway and Service Road are allowed to cross over the existing Transmission lines if the following additional protections are provided:

    Fig 4.1.4: No machinery excavation over / vicinity of cable route

    Fig 4.1.5: Trees should be 5m away from cable route

    5 Meter away from cable route

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    46 DEWA Hand Book

    7.1 132kV Power, Fiber Optic, and Pilot Cables in trougha. Provide (3m x 1m x 0.3m) Pre cast Reinforced Concrete Class 40 / 20 Protection Slab over the trough. Extending

    1mtr from the road edge. Figure: 4.1.6, 4.1.7

    Protection Slab Details For Road Construction On Top Of The 132kV Trough

    / Cable

    New Trough Design for Asphalt carriage way

    Fig 4.1.6: 132kV Trough Protection for Road crossing Works

  • 47EHV Over Head Line & Under Ground Cable Protective Regulations

    8. New service Road: New Service Road is allowed to run longitudinally over Fiber Optic or Pilot Cables if the following requirements and additional protections / spare duct are met and provided respectively:

    a. Providing the depth of existing Fiber Optic or Pilot Cables is not less than 1.0 meter below the ground and protection tiles are installed over the cables. Figure: 4.1.8.

    b. Providing Cable Joint Box outside the proposed service road, otherwise, it should be made inside approved type of manhole.

    b. Protection Slab should be extended along the width of the proposed road and extended at least one meter from the edge of each side of the road.

    c. Provide 4 x 150mm dia spare ducts inside the trough and terminate the spare ducts to both ends of protection slab, for future use, without disturbing the surface of the road.

    7.2 132kV directly buried power / pilot / F.O cablesa. Each of the existing cable should be encased by new

    150 mm dia (split duct) and all ducts plus two spare ducts should be encased by concrete to be called as Concrete Duct Bank. Figure: 4.1.8

    b. There concrete duct bank should extend at least one meter away, from edges of the proposed road.

    Fig 4.1.7 : 132kV trough protection forroad works

    Protection Slab Over 132kV Trough(3Mx1m, 0.30 M)

    Fig 4.1.8: Direct buried cable pilot / F.O cable protection by split duct and surround concrete with spare duct

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    48 DEWA Hand Book

    Protection Slab Details For Road Construction On Top Of The 132kV Trough / Cable

    Fig 4.1.9 Protection details for tiling on top of 132kV cable trough

    9. Parking installation: Parking (Asphalted or Interlocking Tiles) is allowed above the existing 132kV cables in trough or direct buried Fiber optic / Pilot Cables and the following requirements and additional protections should be met and provided respectively.

    a. Providing of protection / spare duct as shown in the Figure: 4.1.8 & 4.1.9.

    b. No part of parking area should be constructed over underground cable joint and flush type Link box.

    c. Flush type cable route marker should be installed over the cable route at maximum interval of 50 meters for straight cable run. Figure: 1.4.7 (Pg 21)

    10. Road widening: Existing protection & spare ducts to be extended to the proposed road widening / crossing area. New spare ducts (end to end) to be provided, if not possible and maintain minimum 1.0 meter either side of the proposed road edge. Figure: 4.1.10

  • 49EHV Over Head Line & Under Ground Cable Protective Regulations

    Protection Slab Details For Road Widening On Top Of The 132kV Trough / Cable

    Fig 4.1.10 - 132kV trough protection for road widening

    11. No Blocking of Access: Entrance to DEWA substation and access to DEWA Corridor should not be blocked for the new project / work by any means temporary or permanently

    12. Backfilling: Backfilling of transmission cable route to be carried out as per DEWA standard. Backfilling materials / excavated soil or any other materials which is used for placement of buried pipe shall not be left at the site. The stored / dumped materials or soil shall be disposed immediately and the site shall

    be cleaned before demobilization. Figure: 4.1.11, 4.1.12, 4.1.13

    13. Route markers: Route markers should not be displaced / destroyed (will be charged) and to be replaced / reinstated in the same place / position after after completion of the work with pole or flush type & tiled area to be provided with flush type route marker. after completion of the works - Figure: 1.4.6, 1.4.7 (Pg 21)

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    50 DEWA Hand Book

    Fig 4.1.11 Placing of cable Protection tiles during backfilling

    Fig 4.1.12 Placing of electrical warning tape during backfilling

    14. As built drawings: As built drawing showing cable, joint / Link box position installation to the permanent structures or land marks, to be provided after finishing the project.

    Back Filling In Progress

    CBCH-INDS pilot finally back filled CBCH-INDS pilot finally back filled

    Fig 4.1.13 Providing of route marker after backfilling

  • 51EHV Over Head Line & Under Ground Cable Protective Regulations

    B. In the vicinity of Existing 400 / 132kV OHL1. Height limit gantries: Installation of temporary height limit gantries about 5.5 - 6 m from ground level, at all

    machinery (shovel / Crane) working locations, along with Danger sign boards. Figure: 4.1.14, 4.1.15

    Fig 4.1.14 - Temporary Height limit gantry under OHL At machinery working locations

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    52 DEWA Hand Book

    Fig 4.1.15

  • 53EHV Over Head Line & Under Ground Cable Protective Regulations

    2. Crash barrier: Temporary concrete crash barriers need to be installed around nearby tower foundation

    Fig 4.1.16

    Concrete barrier protection for tower foundation

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    54 DEWA Hand Book

    Minimum Horizontal Clearence From 400 / 132kV OHL Tower Foundation To The Edge Of The Road, When The Line & The Road Is Running In Parallel

    3. Horizontal clearance: Minimum horizontal clearance of about 40m and 30m from tower concrete foundation to edge of road and bridge to be ensured for 400kV and 132kV OHL respectively.

    Fig 4.1.17

  • 55EHV Over Head Line & Under Ground Cable Protective Regulations

    Minimum Vertical Clearence From Bottom Conductor of 400 / 132kV O / H Line To The Top Of The Road Level For High Way / Secondary Road (considering a maximum conductor temperature of 80 degree Celsius)

    4. Vertical Clearance: Minimum vertical clearance of about 16.5 and 15m to be ensured from the lowest conductor to the finished road level for 400kV and 132kV OHL respectively.

    Fig 4.1.18

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    56 DEWA Hand Book

    8. Removal of unwanted material: Leftover / Waste / debris materials should be removed from the OHL Corridor, after the completion of work.

    5. Permanent Crash Barrier: Permanent steel Crash barrier need to be provided, if the horizontal clearance from the Tower concrete foundation to the edge of the road / bridge is less than 40 m and 25 m for dual carriage way and service roads respectively.

    Fig 4.1.19 Permanent steel crash barrier for Tower foundation protection

    Fig 4.1.21 Scaffolding provided at road crossing during Tower erection

    Tower Foundation LegSteel Crash Barrier

    6. Permanent Height limit gantry: Permanent heights limit Gantry of about 5.5 - 6 m from the finished road level to be provided at the road crossing tower locations, at both sides of the road (Dual Carriageway and service roads). Figure: 1.4.9 (Pg 23)

    7. Access Road: DEWAs Access road must be repaired by the contractor, if damaged.

    9. Parking of vehicle: Parking of Light / Heavy Vehicle within the OHL corridor is prohibited.

    10. Scaffolding protection: Scaffolding to be provided for road crossing, during Tower Construction activities Figure: 4.1.21

  • 57EHV Over Head Line & Under Ground Cable Protective Regulations

    4.2 Installation Of New Cables / Trough Of All Voltage LevelsA. In the vicinity of existing 400 / 132kV Cable1. Existing cable identification: Existing Transmission

    lines to be identified in the vicinity of new cable installation area, by trial pit and fix danger sign board along the cable route & area to be barricaded, before starting the work at site. Figure: 4.1.1, 4.1.2, 4.1.3 (Pg no - 44)

    2. No Machinery Excavation: Machinery, construction equipment / excavator / Vehicles etc. are not

    allowed to work / move or park over the cable route and use of heavy vibratory compaction is prohibited.If any particular locations are required to cross over the Extg.cables, then that portion separate NOC to be obtained & cable route to be protected for the crossing area. Only Manual excavation is allowed. Figure: 4.1.4 (Pg no - 45)

    3. Service clearance: Minimum clearances of services such as cables, pipes and ducts etc. to be 1 (one) Meter away and 500 mm above / below and no services lay on top of the troughs.

    Fig 4.2.1 Minimum clearance requirement for utility line crossing

    Minimum Horizontal Clearence For 11kV / 33kV / Etisalat / DU Duct and Pipe Laying With Parallel 132kV Cable In Trough

    Minimum Vertical Clearence For 11kV / 33kV / Etisalat / DU Duct Laying With Crossing 132kV

    Cable In Trough

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    58 DEWA Hand Book

    Profile - Directonal Drilling

    4. Parallel installation: New cable installation is not allowed to run parallel exactly above or below the existing 132kV cables and troughs, irrespective of any vertical clearance but allowed besides (adjacent), provided the clearances should be complied as per the approved NOC.

    5. Crossing over: New cable crossing over the Existing trough is not allowed. All crossing shall be underneath of the trough except joint area through HDD only (Fig 4.2.5)

    6. Any crossing of new 132kV / 11kV cables above Existing direct buried Transmission cable, existing cable to be protected by spilt duct and surround concrete with spare duct to ensure that no load will be transferred to the cables. (Figure: 4.1.8 - Pg 47). While crossing below the existing direct buried Transmission cable, affected cable should be protected in splict duct / wooden coffin box and supported with cross beam & vertical steel angle / nylon rope. (Figure: 4.2.2 & 4.2.3)

    Fig 4.2.5 Directional drilling

  • 59EHV Over Head Line & Under Ground Cable Protective Regulations

    Typical Protection for Single Group Of 132kV Oil File Filled Cables

    Fig 4.2.2 Protection of direct buried oil filled cable inside wooden box with supporting

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    60 DEWA Hand Book

    7. Crossing under trough: 132kV trough / direct buried cable to be protected as per approved method while installation of duct bank by open cut method (if trench width exceeds 1.5 m) underneath of cable trough of 6 m length. (Figure: 4.2.4)

    8. GPS coordinates: For crossing existing 132kV cable by HDD Method all existing Transmission services to be identified by trial pit. HDD entry / exit pit location shall be marked by GPS coordinates and shall be verified by DEWA-TLP supervisor during T.P verification & before starting the construction work.

    9. Diversion / LILO cable length: New cable length for existing cable diversion & LILO should not be less than 100m from joint to joint or joint to cable termination at GIS.

    Fig 4.2.3 Protection of direct buried cable with supporting structure

    Fig 4.2.4 Protection of 132kV trough by H-beam method for utility corssings

    10. Entrance: Entrance to DEWA substation and access to DEWA corridor should not be blocked for the proposed project / work by any means temporary or permanently

    11. Backfilling: Backfilling of transmission cable route to be carried out as per DEWA standard Backfilling materials or any other materials to have been used for placement. The excess materials or soil shall be disposed immediately and that site shall be cleaned before the shift to next site. (Figure: 4.1.11, 4.1.12, 4.1.13 - Pg 50)

    12. Route markers: Route markers should not be displaced / destroyed (will be charged) and to be replaced / reinstated in the same place / position after after completion of the work with pole or flush type& tiled area to be provided with flush type route marker. after completion of the works Figure: 1.4.6, 1.4.7 (Pg no - 21)

    Direct Buried FO / Pilot cable protection by split duct & supporting structure

  • 61EHV Over Head Line & Under Ground Cable Protective Regulations

    5.0mtr.

    EXISTING G.L

    PROP. TRENCH EXCAVATION

    EDGE OF THE EXCAVATION

    1. Height limit gantries: Installation of temporary height limit gantries about 5.5 - 6 m from ground level, at all machinery (shovel / Crane) working locations, along with Danger sign boards. (Figure: 4.1.14, 4.1.15 - Pg 51 & 52)

    2. Crash barrier: Temporary concrete crash barriers need to be installed around nearby tower foundation. (Figure: 4.1.16) Pg 53

    3. Excavation clearance: Minimum horizontal distance of 5m to be ensured for any excavations near the concrete foundation of the tower. (Figure: 4.2.6)

    4. Sheet piling: Sheet piling or sand bags to be provided, while excavating near the tower foundation to avoid collapse of sand. (Figure: 4.2.7)

    5. Earth conductor protection: Tower foundation earth conductor to be protected, while excavating near the tower foundation.

    6. Access Road: DEWA patrolling access road must be repaired by the contractor, if damaged.

    7. Removal of Waste materials: Leftover / Waste / debris materials should be removed from the OHL Corridor, after the completion of work.

    B. In the close vicinity of Existing 400 / 132kV OHL8. Parking of vehicle: Parking of Light / Heavy Vehicle

    within the OHL corridor is prohibited.

    Fig 4.2.6 - Minimum horizontal clearance requirement for excavations near tower foundation

    Minimum Horizontal Clearence From 132 / 400kV / O / H Line Tower To Prop. Trench Excavaion

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    62 DEWA Hand Book

    Fig 4.2.7 Sheet piling provided for tower foundation

  • 63EHV Over Head Line & Under Ground Cable Protective Regulations

    4.3 Installation of pipelines (Pressurized water / Gas / Irrigation / Fuel / Chilled water pipe lines works & Gravity lines such as drainage, storm water line, sewerage)

    A. In the vicinity of existing 400 / 132kV Cable1. Existing cable identification: Existing Transmission

    lines to be identified in the vicinity of new cable installation area, by trial pit and fix danger sign board along the cable route & area to be barricaded, before starting the work at site. Figure: 4.1.1, 4.1.2, 4.1.3 (Pg no - 44)

    2. No Machinery Excavation: Machinery, construction equipment / excavator / Vehicles etc. are not allowed to work / move or park over the cable route and use of heavy vibratory compaction is prohibited.If any particular locations are required to cross over the Extg.cables, then that portion separate NOC to be obtained & cable route to be protected for the crossing area. Only Manual excavation is allowed. Figure: 4.1.4 (Pg no - 45)

    3. Service clearance: Minimum clearances of pressurized water / Irrigation to be 03 meter (minimum) away and 500 mm above / below and no services lay on top of the troughs. Figure: 4.2.1 (Pg no - 57)

    4. DEWA Corridor: Any construction / structures in DEWA corridor, i.e. RTU, manholes, gullies etc. are prohibited

    5. Deep Excavation: Any deep excavation close proximity of the cable / trough should be provided with steel sheet piling / protection with de-watering arrangement along the cable route, after providing method of statement. (Figure: 4.3.1)

    6. Substation Access: Entrance to DEWA substation and access to DEWA corridor should not be blocked for the proposed project / work by any means temporary or permanently

    7. Cable shifting / slewing: Shifting / slewing or exposing of cables will not be permitted without NOC explicit written permission. Exposed cable to be protected in wooden box / split duct after wrapping with hessian cloth and supported properly. (Fig.4.2.2 & 4.2.3 - Pg 59 & 60)

    132kV cable trough supported by H beam

    132kV cable corridor (protected by sheet

    piling from collapsing)

    Fig 4.3.1 Sheet piling protection for 132kV cable from trench collapse

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    64 DEWA Hand Book

    8. Steel sleeve protection: Installation of High pressure line crossing below of the 132kV cable.Pipe line need to be provided by suitable steel sleeve to prevent pipeline breakage impact. (Figure: 4.3.2)

    Fig 4.3.2 Steel sleeve provided for high pressure pipeline crossing 132kV cable

    Steel sleeve for high pressure pipeline crossing

    9. Trough protection: While laying of steel sleeve / pipe line underneath of trough for crossing by open cut method, 132kV cable trough to be supported with suitable steel supports Figure: 4.2.4 (Pg no 60)

    10. Cable protection: While laying of pipe under the existing direct buried Transmission cable, affected cable should be protected and supported Figure: 4.2.2 & 4.2.3 (Pg no 59 & 60)

    11. Parallel installation: New pipeline installation is not allowed to run parallel exactly above or below the existing 132kV cables and troughs, irrespective of any vertical clearance but allowed besides (adjacent), provided the clearances should be complied as per the approved NOC.

    12. Trough cover opening: Crossing of pressurized pipe line above the cable trough is not allowed as this will obstruct opening of trough cover.

    13. Backfilling: Backfilling of transmission cable route to be carried out as per DEWA standard. Backfilling materials or any other materials to have been used for placement. The excess materials or soil shall be disposed immediately and that site shall be cleaned before the shift to next site.Figure: 4.1.11, 4.1.12, 4.1.13 (Pg no. 50)

    14. Route markers: Route markers should not be displaced / destroyed (will be charged) and to be replaced / reinstated in the same place / position after after completion of the work with pole or flush type& tiled area to be provided with flush type route marker. after completion of the works Figure: 1.4.6, 1.4.7 (Pg no. 21)

  • 65EHV Over Head Line & Under Ground Cable Protective Regulations

    B. In the vicinity of Existing 400 / 132kV OHL1. Height limit gantries: Installation of temporary

    height limit gantries about 5.5 - 6 m from ground level, at all machinery (shovel / Crane) working locations, along with Danger sign boards. (Figure: 4.1.14, 4.1.15 - Pg no 51 & 52)

    2. Crash barrier: Temporary concrete crash barriers need to be installed around nearby tower foundation. (Figure: 4.1.16 - Pg 53)

    3. Excavation clearance: Minimum horizontal distance of 5m to be ensured for any excavations near the concrete foundation of the tower. (Figure: 4.2.6) Pg 61

    4. Sheet piling: Sheet piling or sand bags to be provided, while excavating near the tower foundation to avoid collapse of sand. (Figure: 4.2.7) Pg 62

    5. Earth conductor protection: Tower foundation earth conductor to be protected, while excavating near the tower foundation.

    6. Access road: DEWA patrolling access road must be repaired by the contractor, if damaged.

    7. Removal of unwanted materials: Leftover / Waste / debris materials should be removed from the OHL Corridor, after the completion of work.

    8. Parking of vehicle: Parking of Light / Heavy Vehicle over or beneath the Transmission services (Cable / OHL) corridor is prohibited.

    9. Sand dumping: Dumping of sand within Transmission (OHL / Cable) Corridor is prohibited.

    10. Horizontal clearance for pipe line:

    10.1 A minimum horizontal clearance of 25m from tower foundation to be ensured, for laying any proposed me tallic pipe services at a nominal diameter less than 150mm, as per DEWA Technical specification.

    10.2 A minimum horizontal clearance of 50m from tower foundation to be ensured, for laying any proposed metallic pipe services at a nominal diameter between 180 - 450mm, as per DEWA Technical specification.

    10.3 A minimum horizontal clearance of 100m from tower foundation to be ensured, for laying any proposed metallic pipe services at a nominal diameter more than 450mm, as per DEWA Technical specification

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    66 DEWA Hand Book

    4.4 Construction Of Buildings, Boundary Wall, Temporary Fencing And InterlockingA. In the vicinity of existing 400 / 132kV Cable1. Existing cable identification: Existing Transmission

    lines to be identified in the vicinity of new cable installation area, by trial pit and fix danger sign board along the cable route & area to be barricaded, before starting the work at site. Figure: 4.1.1, 4.1.2, 4.1.3 (Pg no - 44)

    2. No Machinery Excavation: Machinery, construction equipment / excavator / Vehicles etc. are not allowed to work / move or park over the cable route and use of heavy vibratory compaction is prohibited. If any particular locations are required to cross over the Extg.cables, then that portion separate NOC to be obtained & cable route to be protected for the crossing area. Only Manual excavation is allowed. Figure: 4.1.4 (Pg no - 45)

    3. Undertaking: DEWA reserves the right to excavate the garden / grass / tiled area and road without intimation thia in case of emergency. Owners for tiling / gardening / landscaping work etc. should give an undertaking before commencement of the work. Trees should be 5.0 M away. NOC in this regard to be obtained. Figure: 4.1.5 (Pg no - 45)

    4. Enclosing by fence: Cable corridor should not be enclosed by fence and if the corridor is inside boundary of project area, then should not be used as a storage of excavated / construction materials, equipments, site offices, parking area Etc. Figure: 4.4.1

    5. Access Road: Access road to the building necessary protection to be made for the existing cable route as per the approved NOC.

    6. Shoring / Anchoring: Shoring / Anchoring should be minimum 2.0 M away from the existing cable / Trough edge. Figure: 4.4.2

    Fig 4.4.1 Transmission cable (400kV, 132kV)route should not be enclosed by fence and no storage of any material over cable corridor

    Fence not enclosing the cable route

  • 67EHV Over Head Line & Under Ground Cable Protective Regulations

    Fig 4.4.2 Transmission cable route should be protected from shoring

    Shoring Section Details

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    68 DEWA Hand Book

    B. In the vicinity of Existing 400 / 132kV OHL

    No Building Constructions Allowed Within DEWA Transmission OHL Corridor

    Fig 4.4.3 Prohibition of building construction within DEWA OHL Corridor

    1. Construction works inside corridor: Construction of building & any other activities are not allowed within DEWA OHL Corridor. OHL corridor shall be confirmed from TLMD NOC center. (Figure: 4.4.3)

    2. Miscellaneous works inside corridor: Shoring / walls / Fence / Interlocking are not allowed within OHL corridor. OHL corridor shall be confirmed from TLMD NOC center.

    3. Access Road: DEWA access road along the line not to be disturbed or damaged.

    4. Vehicle parking: Heavy machinery, vehicle or other equipment are not allowed to park under / near the overhead line.

    5. Height limit gantry: Temporary height limit gantry to be installed, in case vehicles and equipment require to pass / approach the OHLs.

    Note: Width of the OHL corridor varies from one to another tower location.20m - Minimum horizontal

    clearance from 400kV outer conductor

    15m - Minimum horizontal clearance from 132kV outer conductor

  • 69EHV Over Head Line & Under Ground Cable Protective Regulations

    4.5 Drilling / Boring / Anchoring / Micro tunneling / Piling / NDRC works (wherever applicable)A. In the vicinity of existing 400 / 132kV Cable1. Existing cable identification: Existing Transmission

    lines to be identified in the vicinity of new cable installation area, by trial pit and fix danger sign board along the cable route & area to be barricaded, before starting the work at site. Figure: 4.1.1, 4.1.2, 4.1.3 (Pg no - 44)

    2. NOC / Method statement: All drilling related works to be carried out as per construction NOC and method statement.

    3. Prior intimation: Prior intimation to be given to DEWA 3 days advance prior to start the work and works to be carried out in the presence of DEWA TLP supervisor. (Format attached Pg.no - 31)

    4. No Machinery Excavation: Machinery, construction equipment / excavator / Vehicles etc. are not allowed to work / move or park over the cable route and use of heavy vibratory compaction is prohibited. If any particular locations are required to cross over the Extg.cables, then that portion separate NOC to be obtained & cable route to be protected for the crossing area. Only Manual excavation is allowed. Figure: 4.1.4 (Pg no- 45)

    5. GPS coordinate: NDRC works such as Micro tunneling / Thrust boring / Pipe jacking / Directional drilling and Piling / boring will be approved only after all the services and clearances have been identified and verified with coordinates. Method statement and shop drawing to be approved by DEWA before execution of the work. Drilling location to be ensured as per the approved profile and coordinates before starting the work by Transmission Line Patrolling supervisor.

    6. Clearance: Micro tunneling / Thrust boring / Directional drilling should have a minimum vertical clearance of 2.0m from the bottom of the cable / trough and the horizontal clearance of 2.0m from the edge of the cable / trough to the entry / exit pit. Drilling profile to be approved by DEWA TLMD.

    7. Trough protection: While laying of steel sleeve / pipe line underneath of trough for crossing by open cut method, 132kV cable trough to be supported with suitable steel supports Figure: 4.2.4 (Pg no 60)

    8. Entry / Exit pit: While making entry / Exit pit close to 132kV cable for for drilling,132kV cable to be protected by sheet piling. (Figure: 4.5.1)

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    70 DEWA Hand Book

    Fig 4.5.1 Transmission cable to be protected by sheet pilling during microtunnelling

    132kV cable corridor / trough

    B. In the vicinity of Existing 400 / 132kV OHL1. Height limit gantries: Installation of temporary

    height limit gantries about 5.5 - 6 m from ground level, at all machinery (shovel / Crane) working locations, along with Danger sign boards. (Figure: 4.1.14, 4.1.15 - Pg no 51 & 52)

    2. Crash barrier: Temporary concrete crash barriers need to be installed around nearby tower foundation. (Figure: 4.1.16 - Pg 53)

    3. Excavation clearance: Minimum horizontal distance of 5m to be ensured for any excavations near the concrete foundation of the tower. (Figure: 4.2.6) Pg 61

    4. Sheet piling: Sheet piling or sand bags to be provided, while excavating near the tower foundation to avoid collapse of sand. (Figure: 4.2.7) Pg 62

    5. Earth conductor protection: Tower foundation earth conductor to be protected, while excavating near the tower foundation.

    6. Access road: DEWA patrolling access road must be repaired by the contractor, if damaged.

    7. Removal of unwanted materials: Leftover / Waste / debris materials should be removed from the OHL Corridor, after the completion of work.

    8. Parking of vehicle: Parking of Light / Heavy Vehicle over or beneath the Transmission services (Cable / OHL) corridor is prohibited.

  • 71EHV Over Head Line & Under Ground Cable Protective Regulations

    4.6 Telecommunication services such as Etisalat / Du (services /duct laying)A. In the vicinity of existing 400 / 132kV Cable1. Existing cable identification: Existing Transmission

    lines to be identified in the vicinity of new cable installation area, by trial pit and fix danger sign board along the cable route & area to be barricaded, before starting the work at site. (Figure: 4.1.1, 4.1.2, 4.1.3 - Pg no - 44)

    2. No Machinery Excavation: Machinery, construction equipment / excavator / Vehicles etc. are not allowed to work / move or park over the cable route and use of heavy vibratory compaction is prohibited. If any particular locations are required to cross over the Extg.cables, then that portion separate NOC to be obtained & cable route to be protected for the crossing area. Only Manual excavation is allowed. (Figure: 4.1.4 - Pg no - 45)

    3. Minimum clearances: Minimum clearances of services such as cables, pipes and ducts etc. to be 1 (one) Meter away and 500 mm above / below and no services lay on top of the troughs.Figure: 4.2.1 (Pg no - 57)

    4. Parallel installation: New cable installation is not allowed to run parallel exactly above or below the existing 132kV cables and troughs, irrespective of any vertical clearance but allowed besides (adjacent), provided the clearances should be complied as per the approved NOC

    5. Trough cover opening: Crossing of pressurized pipe line above the cable trough is not allowed as this will obstruct opening of trough cover.

    6. Cable crossing protection: Any crossing of duct bank above Existing direct buried Transmission cable existing cable to be protected by spilt duct and surround concrete with spare duct to ensure that no load will be transferred to the cables. Figure: 4.1.8 (Pg no - 47)

    7. Crossing of new Duct bank: While crossing of new duct bank below the existing direct buried Transmission cable, said cable should be protected and supported. (Figure: 4.2.2 & 4.2.3) (Pg no - 59 & 60)

    8. Cable protection for open cut method: Existing 132kV trough / direct buried cable to be protected as per approved method while installation of duct bank by open cut method (if trench width exceeds 1.5m) underneath of cable trough of 6 m length. Figure: 4.2.4 (Pg no - 60)

    9. Service verification: All services to be identified by trial pit if duct laying by HDD method. GPS coordinates to be provided for TP locations & entry / exit pit for the drilling. Before starting the drilling works, the coordinates shown in the approved NOC for entry / exit pit & trial pit locations to be confirmed by TLP supervisor.

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    72 DEWA Hand Book

    4. Sheet piling: Sheet piling or sand bags to be provided, while excavating near the tower foundation to avoid collapse of sand. (Figure: 4.2.7) Pg 62

    5. Earth conductor protection: Tower foundation earth conductor to be protected, while excavating near the tower foundation.

    6. Access road: DEWA patrolling access road must be repaired by the contractor, if damaged.

    7. Removal of unwanted materials: Leftover / Waste / debris materials should be removed from the OHL Corridor, after the completion of work.

    8. Parking of vehicle: Parking of Light / Heavy Vehicle over or beneath the Transmission services (Cable / OHL) corridor is prohibited.

    10. Entrance: Entrance to DEWA substation and access to DEWA corridor should not be blocked for the proposed project / work by any means temporary or permanently.

    11. Backfilling: Backfilling of transmission cable route to be carried out as per DEWA standard. Backfilling materials or any other materials to have been used for placement. The excess materials or soil shall be disposed immediately and that site shall be cleaned before the shift to next site. (Figure: 4.1.11, 4.1.12, 4.1.13 - Pg no 50)

    12. Route markers: Route markers should not be displaced / destroyed (will be charged) and to be replaced / reinstated in the same place / position after after completion of the work with pole or flush type& tiled area to be provided with flush type route marker. after completion of the works (Figure: 1.4.6, 1.4.7- Pg no - 21)

    B. In the vicinity of Existing 400 / 132kV OHL1. Excavations near Tower foundations: Minimum

    horizontal distance of 5m to be ensured for any excavations near the concrete foundation of the tower. Figure: 4.2.6 (Pg no - 61)

    2. Height limit gantries: Installation of temporary height limit gantries about 5.5 - 6 m from ground level, at all machinery (shovel / Crane) working locations, along with Danger sign boards. (Figure: 4.1.14, 4.1.15 - Pg no 51 & 52)

    3. Crash barrier: Temporary concrete crash barriers need to be installed around nearby tower foundation. (Figure: 4.1.16 - Pg 53)

  • 73EHV Over Head Line & Under Ground Cable Protective Regulations

    4.7 Miscellaneous Construction Works (Sign Board, Lighting Pole, Bore Holes, Piling, Parking Area, Tree Plantation Etc)A. In the vicinity of Existing 400 / 132kV Cable1. Existing cable identification: Existing Transmission

    lines to be identified in the vicinity of new cable installation area, by trial pit and fix danger sign board along the cable route & area to be barricaded, before starting the work at site. (Figure: 4.1.1, 4.1.2, 4.1.3 - Pg no - 44)

    2. No Machinery Excavation: Machinery, construction equipment / excavator / Vehicles etc. are not allowed to work / move or park over the cable route and use of heavy vibratory compaction is prohibited. If any particular locations are required to cross over the Extg.cables, then that portion separate NOC to be obtained & cable route to be protected for the crossing area. Only Manual excavation is allowed. (Figure: 4.1.4 - Pg no - 45)

    3. Prohibited installations: Any streetlight poles, crash barriers, road signboards installation over the Transmission cable are prohibited.

    4. Bore holes and piling works: Bore holes and piling works will be approved only after all the services and clearances have been identified and verified with coordinates. Method statement and shop drawing to be approved by DEWA before execution of the work. Drilling location to be ensured as per the approved profile and coordinates before starting the work by Transmission Line Patrolling supervisor.

  • PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

    74 DEWA Hand Book

    Note: Width of the OHL corridor varies from one to another tower location.No Tree Plantation Allowed Inside DEWA Transmission OHL Corridor

    B. In the vicinity of Existing 400 / 132kV OHL1 Tree Plantation: No tree plantation is allowed within the OHL corridor. (Figure: 4.7.1)

    Fig 4.7.1 Prohibition of tree plantation within DEWA OHL corridor

  • 75EHV Over Head Line & Under Ground Cable Protective Regulations

    Fig 4.7.2

    Minimum Clearance requirement for Lighting Pole Installation from OHL conductor

    2 Lighting pole and Sign board installations:a) Height limit gantries: Installation of temporary

    height limit gantries about 5.5 - 6 m from ground

    level, at all machinery (shovel / Crane) working locations, along with Danger sign boards. (Figure: 4.1.14, 4.1.15 - Pg no 51 & 52)

  • 76 DEWA Hand Book

    b) Crash barrier: Temporary concrete crash barriers need to be installed around nearby tower foundation. (Figure: 4.1.16 - Pg 53)

    c) Excavations near Tower foundations: Minimum horizontal distance of 5m to be ensured for any excavations near the concrete foundation of the tower. (Figure: 4.2.6 - Pg 61)

    d) Minimum vertical clearance: Any poles / structure erected in the vicinity of OHL should have minimum falling clearance of 6.0 / 5.0 meter for 400 / 132kV lines. (Figure: 4.7.2)

    e) Access road: DEWA patrolling access road must be repaired by the contractor, if damaged.

    f) Removal of unwanted materials: Leftover / Waste / debris materials should be removed from the OHL Corridor, after the completion of work.

    g) Parking of vehicle: Parking of Light / Heavy Vehicle over or beneath the Transmission services (Cable / OHL) corridor is prohibited.

    3 Construction parking:

    a. Parking area construction is not allowed within DEWA Transmission OHL Corridor. OHL Corridor details shall be confirmed from TMD NOC center.

    b. DEWA patrolling access road must be repaired by the contractor, if damaged.

    c. Leftover / Waste / debris materials should be removed from the OHL Corridor, after the completion of work.

    d. Parking of Light / Heavy Vehicle within the OHL corridor is prohibited.

    PROTECTIVE REGULATIONS & PRECAUTIONARYMEASURES FOR THE PROTECTION OF TRANSMISSION LINES

  • IMPLEMENTATION OF NOC CONDITIONS & PRECAUTIONARY MEASURES

    CHAPTER 5

  • IMPLEMENTATION OF NOC CONDITIONS & PRECAUTIONARY MEASURES

    78 DEWA Hand Book

    To ensure implementation of all the provisions of Protective Regulations of this Handbook during execution of any activities near or within the vicinity of the existing OHL and UG Cable corridors.

    5.1 Patrolling Patrolling of all existing OHL / cable routes is carried out in a scheduled frequency to monitor the DEWAs Transmission lines network from damages & third party violations by observing, reporting & preventive actions.

    5.1.1 Routine PatrollingDEWAs Transmission Networks / Grids are divided into number of patrolling zones of which each zone should be patrolled twice a day.

    5.1.2 Emergency PatrollingThis type of patrol should be conducted as requested to specific area where damaged / tripping has occurred or where transmission facilities needs special attention or priority actions to minimize or prevent the possibility of damage.

    5.1.3 Intensive PatrollingThis type of patrol is acted upon the request from concerned parties to exert additional attention (extra patrol) to specific circuit on the

    following reasons: To ensure healthiness of the remaining cables / lines in Ring network feeder, if any one or more of the Ring network feeder is / are shut down for repair and maintenance or s requested for approved purposes.

    5.1.4 Special PatrollingThis type of patrol is acted upon the request from concerned parties to exert additional attention (extra patrol) to specific circuit on the following reasons:To ensure healthiness of all transmission lines / cables supplying substation that is to serve important occassions / VVIP visit to the emirates.

    5.2 Precommission InspectionThis type of Inspection is conducted in response to the request for joint inspection of completed project. This will ensure that all installed components of transmission system were installed according to the DEWAs Standards.

    5.3 Contractors Work SupervisionTLM directly supervise the execution of all construction activities near or in vicinity with line / cable corridor to ensure that such work executions are in accordance with the provisions of NOC & Method statement. The following types of supervision should be scheduled suitable to the kinds of work requirements. (Pls refer Annexure-3.1.1 Pg 22)

  • 79EHV Over Head Line & Under Ground Cable Protective Regulations

    5.3.1 WorkSupervision RequestAll works near or in vicinity of OHL / UG Cables corridor, if with relevant NOC, should only be executed under direct supervision of TLMs Standby Site Supervisor. The service of Standby Site Supervisor will be obtained through the following requirements: A. The Work Supervision Request Form should

    be obtained from TLM Patrolling Section of DEWA or Patrolling & NOC Staff at site and should be appropriately completed.

    B. Submission of completed Forms a. The completed forms should be submitted

    within three (3) working days, before commencement of the proposed works, through TLM Patrolling FAX No. (04) 3984655.

    b. Alternatively, for priority actions, the contractor should submit the completed form with the required attachment personally, one day before to commencement of work, to the office of TLM Patrolling & NOC Section.

    5.3.2 Area Site Supervision

    5.3.3 Critical Site SupervisionAny work execution near or in vicinity of OHL / UG cables corridor which likely needs special actions to protect the lines by additional cable protection in coordination with contractors / consultant or utility dept & for which requires more time.

    5.4 Site Instruction NoticeDuring patrolling, the patroller checks the contractors work site & if any non-critical violations are found, then Site instruction notice is issued to contractor for correcting immediately. If contractor does not take necessary action, further the patroller will issue Notice to stop work.(Format attached Figure: 5.4)

  • IMPLEMENTATION OF NOC CONDITIONS & PRECAUTIONARY MEASURES

    80 DEWA Hand Book

    Figure: 5.4 - Site instruction Note

  • 81EHV Over Head Line & Under Ground Cable Protective Regulations

    5.5 Notice to Stop WorkDuring patrolling, the patroller checks the contractors work site, NOC documents & implementation of NOC conditions. In case, any of the criteria is not met, then the patroller will issue the Notice to stop work & immediately leave the contractors site, without waiting for further compliance from the contractor, to complete his patrolling, based on the landmark. Black points will be provided to the contractor based on the violation types under each Notice to stop work received by the contractor. (Format attached Figure: 5.5)

    Figure: 5.5 - Notice to stop work

  • 82 DEWA Hand Book

    5.6 Awareness Tool Box talkAwareness TBT is conducted by DEWA TLM Engineer to contractors Engineer, safety Engineer, supervisor, machine operators at site to create awareness about the safety precautionary measures to avoid lines abnormality or damages. (Format attached Figure: 5.6)

    Figure: 5.6 - Tool Box talk format

    IMPLEMENTATION OF NOC CONDITIONS & PRECAUTIONARY MEASURES

  • ACTIONS AGAINST VIOLATORS CHAPTER 6

  • 84 DEWA Hand Book

    ACTIONS AGAINST VIOLATORS

    6.1 Legal RequirementsLegal action and penalty shall be imposed to the contractor for Cable damage as per Dubai Govt. Local Act No. 2 / 1994.

    6.2 Black Points SystemA System Implemented by DEWA as a Preventive measure to monitor & control the contractors, from performing violations of issued Nocs & its conditions at site, which will lead to damage of the DEWAS Transmission lines network.

  • 85EHV Over Head Line & Under Ground Cable Protective Regulations

    Categories And Actions6.2.1.1 Action Against Contractor Damaging 132kV Power / Pilot / Fo Cables

    The table - 6A shows the Actions taken against Contractors damaging the 132kV Power / Pilot / FO cables, falling under two categories.Category A - First time Damage within a year periodCategory B - Second time Damage within a year period

    6.2.1.2 Action Against The Contractor Who Contravene The Utilities Protective Regulations

    The table - 6B shows the Actions taken against Contractors who violate the NOC & its conditions related to protective regulations.Category A - Contractors receiving 20 points, to the violated projectCategory B - Contractors receiving 35 points, to the violated projectCategory C - Contractors receiving 50 points, to the violated project

  • 86 DEWA Hand Book

    ACTIONS AGAINST VIOLATORS

    Table 6A

  • 87EHV Over Head Line & Under Ground Cable Protective Regulations

    Table 6B

  • 88 DEWA Hand Book

    a. Action is taken against contractor pertaining to Category A, as per Table 6B.

    b. Contractors works are stopped in locations wherever Notice to stop work was issued & new NOC issuance or suspension of issued NOC done.

    c. Concerned utility / dept should take necessary actions against the contractor against the performed violations.

    d. Action plan for safe construction works in the close vicinity of the of Extg. Trans.lines neds to be prepared by contractor & submitted to TLM-LP for approval.

    e. CVs of Project manager, Project Engineer & Site supervisor to be submitted for TLM-LP approval.

    f. Undertaking letter shall be provided that all terms & conditions of issued NOC & method statement are understood & followed by Project Manager / Site Engineer.

    g. After the contractor submits all the above documents, TLM-LP will review and approve the same.

    h. The Contractor will resume the works after necessary clearance from TLM-LP.

    i. Similar procedural action will be taken in accordance with the category - B & C, if the contractor falls in those categories.

    j. Except that in category B, The contractor shall replace Safty Engineer and site supervisor of the project.

    k. In category C, the contractor shall replace The project Engineer, Safty engineer and site supervisor of the project.

    6.2.3 Procedure Of Accruing Black Points & Action Taken By TLM

    Contractor performs violation at site repeatedly & accumulates say 20 points, as per the violations of NOC conditions & protective regulations.

    ACTIONS AGAINST VIOLATORS

  • SERVICES PROVIDED BY TLMCHAPTER 7

  • 90 DEWA Hand Book

    SERVICES PROVIDED BY TLM

    7.1 Trial pit / OHL Verification & Supervision:To verify the clearance & geographic details of the transmission lines (Cable & OHL) & accessories from the proposed scope of works for NOC applications, trasmission Lines maintenance-Patrolling unit is providing the following services to the valued customers (constractor, consultant & other utilities) in the Emirates of Dubai.

    7.1.1 Prior Intimation, Supervision for trial pit work & verification for the trial pit : DEWA Work supervision / Verification request format duly filled to be sent to DEWA 03 working days in advance by a) applying direct with DEWA TLM-TLP office, 4th floor, DEWA customer service building, Hudaiba office (During DEWA office hours 7:30am to 2:30pm) b) by fax no 04-3984655 and c) by email [email protected], sample attached in page no.31.

    7.1.2 Telephonic confirmation: To be done with concerned DEWA Engineer, after sending fax or email to ensure the

    availability of DEWA supervisor on the requested date, by the telephone numbers 04-5066670 / 04-5066680.

    7.1.3 Work Hours: Works should be carried out during DEWA working hours only. Special approval to be obtained for emergency and very urgent works with justification to work beyond working hours.

    7.2 Construction Work Supervision:To provide supervisor during the construction activities in the vicinity of 400 / 132kV OHL / Cable lines or in DEWA Corridor to give advice for safe guard & protection methods:

    7.2.1 Prior Intimation, supervision for OHL / Cable lines protection works: DEWA Work supervision request format duly filled to be sent to DEWA 3 working days advance by a) applying direct with DEWA TLM-TLP office, 4th floor, DEWA customer service building, Hudaiba office (During DEWA office hours 7:30am to 2:30pm) b) by fax no 04-3984655 and c) by email [email protected], sample attached in page no.31.

    7.2.2 Telephonic confirmation: To be done with concerned DEWA Engineer, after sending fax or email to ensure the availability of DEWA supervisor on the requested date, by the telephone numbers 04-5066670 / 04-5066680.

    7.2.3 Work Hours: Works should be carried out during DEWA working hours only. Special approval to be obtained for emergency and very urgent works with justification to work beyond working hours.

    For clarification about services completion time & followup in English / Arabic, you can contact us on the following telephone numbers : 04 5066670 / 04 5066680.

  • 91EHV Over Head Line & Under Ground Cable Protective Regulations

    Moreover, we are providing Awareness Training to contractors Staff to improve their safety skills to work in the vicinity of 400 / 132kV OHL / cable lines and being certified from our end.

    In this Hand Book, are explained the following items in different chapters in order to protect the existing 400 / 132kV Transmission Lines network as below:1. Transmission Lines & Accessories2. Hazardous factors while working near Transmission Lines 3. NOC for construction works 4. Protective Regulations & precautionary measures for the protection of Transmission Lines5. Implementation of NOC conditions & precautionary measures 6. Legal Actions against violators

    The above items will helps all contractors, consultant, utility depts & private parties for proceeding NOC application, with proper method statement for safe construction works in & around the transmission lines.

    Furthermore, all concern parties will get general / technical knowledge about the transmission OHL & Cable lines and safety precautionary measures to avoid unwanted damages.

    All are welcome for Queries, clarifications and suggestion if any.

    We hope contractor, consultant, utility departments & private parties will follow DEWA protective rules & regulations, for the uninterrupted electricity supply, in the Emirates of Dubai.

  • 92 DEWA Hand Book

    SERVICES PROVIDED BY TLM

    CS Connection Services

    DM Dubai Municipality

    F.R.L Finished Road Level

    F.O Fibre Optic

    GIS Geographical Information System

    GPS Global Positioning System

    HDD Horizontal Directional Drilling

    II & P Infrastructure Information & Permits

    LILO Loop in Loop out

    NDRC Non Disruptive Road Crossing

    List Of Abbreviations

    NOC No Objection Certificate

    OHL Over head Line

    OPGW Optical Ground Wire

    R.C.C Reinforced Cement Concrete

    R.O.W Right Of Way

    R T A Road Transport Authority

    TMD Transmission Maintenance Department

    TP Trial Pit

    UG Under Ground

    TLM-LP Transmission Lines Maintenance - Lines Patrolling

  • 93EHV Over Head Line & Under Ground Cable Protective Regulations

    For any clarification related to any information mentioned in the Hand Book, please send your queries / comments to the following contact details:

    Tel : 04 322 1507 / 04 322 1519

    Fax : 04 398 4655

    Email : [email protected]

    Website : www.dewa.gov.ae

    Contact Us