Regional Water Supply Project (RWSP)
-
Upload
adria-brown -
Category
Documents
-
view
22 -
download
0
description
Transcript of Regional Water Supply Project (RWSP)
Regional Water Supply Project (RWSP)
Gary King, P.E., Engineering ManagerTodd Jordan, P.E., Project Engineer
Meeting Agenda1. Meeting Purpose2. Project Overview3. California Environmental
Quality Act (CEQA) Overview/Environmental Impact Report (EIR) Scoping
4. Comments
1. Meeting PurposeCEQA public
disclosure process1st Step = Notice of
Preparation (NOP)Goal: seek public
agency and stakeholder input on scope of the Environmental Impact Report
2. Project OverviewBackgroundPurpose and
ObjectivesNevada Irrigation
District (NID) Service Area
Proposed ProjectComponents
Parker Dam is not part of this project
Project Background2003 – 2005 Siting Study2008 – 2012 Planning and
Predesign, including Environmental Constraints Analysis
Project Purpose & ObjectivesProject Purpose
Provide treated water to the portion of the City of Lincoln which is within the Nevada Irrigation District (NID) boundary using NID water on NID lands.
Primary ObjectivesSupply potable water.Provide raw water storage for unexpected fluctuation,
variations in water quality, and water supply emergencies.Provide potable water storage to accommodate
anticipated diurnal demand fluctuations, fire protection, and emergencies.
Construct potable water facilities that meet or exceed California Department of Public Health (CDPH) drinking water standards.
Increase operational flexibility, redundancy, capacity and reliability.
Increase the reliability of the City’s treated water supply.
NID Service Area
NID Service Area In Placer County
Project Overview Proposed Linear Infrastructure
Project OverviewProposed Water Treatment Plant
Project OverviewProposed Raw Water Storage Reservoir
California Environmental Quality Act
OverviewProcessSchedulePublic NoticingNotice of
Preparation/EIR Scoping
CEQA OverviewCEQA is triggered by Discretionary Action of Public Agency (i.e. RWSP is subject to Approval by NID Board)Lead Agency = Nevada Irrigation
District Some of the Responsible Agencies are:
City of Lincoln, Placer County, California Department of Fish and Wildlife, California Air Resources Board, Regional Water Quality Control Board, Placer County, City of Lincoln and among many others.
CEQA ProcessPublic Participation is Encouraged (3 key Public Review Periods)
Notice of Preparation = 30 day public review period – August 15-September 19, 2014. All written comments must be received by
September 19, 2014 at 5pm.Draft Environmental Impact Report (EIR) = 45
day public review period and public hearing – Estimated to be June-July, 2015
Final EIR = 10 day public review period and public hearing – Estimated to be October, 2015
Public NoticingCEQA Requires one of the following for Public Noticing:
NID completed all three for this Notice of Preparation
Publish, Post, orDirect Mailing
CEQA Guidelines §15087
Published – 3 journals NID website
(www.nidwater.com)Posted Notices at:
Nevada Irrigation District Offices Nevada County Clerk Placer County Clerk Lincoln City Hall Nevada County
Library (both locations) Placer County Library (Auburn) City of Lincoln Library (Lincoln)
Direct Mailing to: 380 stakeholders
Notice of Preparation (NOP)EIR ScopingThe purpose of scoping is to help ensure comprehensive and
focused EIR with a firm basis for the decision-making process.NOP determine focus and content of EIR
Range of actions, alternatives, environmental effects, and mitigation measures
Allows elimination of issues if not pertinent to the final decision
Bring together and address: public concernsaffected agencies, other interested parties.
Public/Agency ID of Significant issues
EIR ScopeTo Include Assessments of: Aesthetic and Visual
Resources;Agriculture;Air Quality;Biological Aquatic and
Fisheries Resources;Biological Terrestrial
Resources;Cultural Resources;Geology and Soils;Greenhouse Gas
Emissions;
Hazardous Waste and Materials;
Hydrology and Water Quality;
Land Use;Noise;Population and Housing;Public Services and
Utilities;Recreation; andTransportation and Traffic.
Selection of AlternativesCEQA Guidelines §15126.6 -- Alternatives
should:Feasibly meet basic objectives of projectAvoid/substantially lessen significant effects
“Rule of Reason”Consider:
site suitability, economic viability, availability of infrastructure, General Plan consistency, etc.
Potential Project AlternativesAlternatives under consideration:
Alternatives w/in the ProjectAlternative Pipeline AlignmentsAlternate Raw Water Reservoir SiteAlternate WTP Site
Alternatives to the ProjectNo Project or Project DenialPCWA/Ophir Alternative Bear River Pump Station
Alternatives within the Project
PCWA/Ophir Alternative
Bear River Pump Station Alternative
Comments and Questions?Comments and Inputs WelcomeTo capture the intent and purpose of your
comments please complete a comment card or write NID at:
Lisa Francis Tassone, Board Secretary Nevada Irrigation District,
1036 West Main Street, Grass Valley, CA 95945E-mail: [email protected]
Project website: NIDregionalwatersupply.org NID website: www.nidwater.com
Project Components
Valley View WTP Site
Metering Station
Backup Water Supply
Big Hill Reservoir
Hydropower Site (typ)
Cross River Penstock
Raw Water Pipeline
49
Treated Water Pipeline
Treated Water Demand continued