Regional Rapid Transit System (RRTS) for National Capital...
Transcript of Regional Rapid Transit System (RRTS) for National Capital...
Regional Rapid Transit System (RRTS)forfor
National Capital Region
Rajeev MalhotraChief Regional PlannerChief Regional Planner
NATIONAL CAPITAL REGION PLANNING BOARD8th September, 2011
www ncrpb nic in
NATIONAL CAPITAL REGION PLANNING BOARD 1
www.ncrpb.nic.in
NCR: Constituent AreasNCR: Constituent Areas
(Area in sq kms) RP-2001 RP-2021
NCT-Delhi 1,483 1,483Haryana 13,413 13,413Haryana 13,413 13,413U.P. 10,853 10,853Rajasthan 4,493 7,829
Total 30,242 33,578
NCR area of 33,578 sq kms is– 1.06% of India’s area– 86.00% of Kerala – 75.90% of Haryana – 66.67% of Punjab
NCR area is almost 23 times that of NCT-Delhi (1,483 sq kms)( , q )
NCR area is more than the combined area of 3 States of Tripura, Nagaland and Sikkim (27 885 sq kms)
NATIONAL CAPITAL REGION PLANNING BOARD 2
Sikkim (27,885 sq kms)
NCR: Population DistributionNCR: Population DistributionPopulation Projection as per Regional Plan-2021 for NCR
YearPopulation (in Lakhs)
NCR Delhi Haryana Rajasthan U.P.
p j p g
2001 371.00 138.50 86.87 29.92 115.702011 486.19 179.90 117.55 37.91 150.832021 641.38 234.87 160.16 48.06 198.29
Urban-Rural Components of Population in NCR (1981-2001)Percent share (%) Rural, 43.61
1981 1991 2001
Urban NCR 45.87 50.23 56.39
R l NCR 54 13 49 77 43 61Rural NCR 54.13 49.77 43.61
Urban NCR* 24.53 29.39 34.47
Urban, 56.39
*Urban NCR excluding NCT-Delhi
NATIONAL CAPITAL REGION PLANNING BOARD 3
SubregionSubregion--wise Population of NCR wise Population of NCR
400.00
450.00
500.00
Sub-region Population (lakhs)
Year 2011 2011
200 00
250.00
300.00
350.00
198119912001
Year 2011Proposed
2011Actual
NCT-Delhi 179.90 167.53
Haryana 117.55 110.38
50.00
100.00
150.00
200.00 2011Rajasthan 37.91 36.72
UP 150.83 145.84
NCR 486.19 460.47
Sub-region/ Population (lakhs) Decadal Growth Rate (%) Share of Population (%)
0.00N C R N C T-D e lh i U t ta r P rades h H ary ana R a jas than
Sub region/ Population (lakhs) Decadal Growth Rate (%) Share of Population (%)
Year 1981 1991 2001 2011 1981-91 1991-01 2001-11 1981 1991 2001 2011
NCT-Delhi 62.20 94.21 138.51 167.53 51.45 47.02 20.96 31.28 34.43 37.33 36.38
Haryana 49.39 66.44 86.87 110.38 34.53 30.76 27.06 24.84 24.28 23.42 23.97
Rajasthan 17.56 22.97 29.93 36.72 30.82 30.31 22.75 8.83 8.39 8.06 7.97
Uttar Pradesh 69.69 90.02 115.70 145.84 29.17 28.53 26.05 35.05 32.9 31.19 31.67
NCR 198.83 273.63 371.00 460.47 37.62 35.59 24.12 100 100 100 100
NATIONAL CAPITAL REGION PLANNING BOARD 4
Regional Plan 2021: Aims and objectivesRegional Plan 2021: Aims and objectives
T t th d b l d d l t f th N ti l C it lTo promote growth and balanced development of the National CapitalRegion through
• Providing suitable economic base for future growth in identified regionalsettlements to absorb economic impulse of Delhi
P ti t i bl d l t• Promoting sustainable development
• Providing rational land use pattern
• Developing urban infrastructural facilities
• Providing efficient and cost effective rail and road based transportnetwork
• Minimizing adverse environmental impact
• Innovative methods of resource mobilization and attracting privateinvestments
NATIONAL CAPITAL REGION PLANNING BOARD 5
Regional Plan 2021: Thrust areasRegional Plan 2021: Thrust areas
• Development of Metro Centres and Regional Centres as powerful growthDevelopment of Metro Centres and Regional Centres as powerful growthnodes to attract major activities
• Provide regional transport linkages-Regional Rapid Transit SystemProvide regional transport linkages Regional Rapid Transit System(RRTS) and its interface with Delhi metro
• Construction of peripheral expressways and orbital rail corridor aroundConstruction of peripheral expressways and orbital rail corridor aroundDelhi
• Development of core urban infrastructure (transport power water supplyDevelopment of core urban infrastructure (transport, power, water supply,sewerage, drainage etc.) in NCR towns
• Facilitate development of the region’s economy through Model IndustrialFacilitate development of the region s economy through Model IndustrialEstates, Special Economic Zones etc. outside NCT-Delhi
• Development of counter-magnet areas outside NCR - Gwalior BareillyDevelopment of counter magnet areas outside NCR Gwalior, Bareilly,Kota, Hissar and Patiala, Ambala, Dehradun and Kanpur
• Public-private partnership
NATIONAL CAPITAL REGION PLANNING BOARD 6
Public private partnership
INTEGRATED TRANSPORT PLAN FOR NCRINTEGRATED TRANSPORT PLAN FOR NCR--20322032
NATIONAL CAPITAL REGION PLANNING BOARD 7
Integrated Transportation Plan for NCR• Board undertook the study on ‘Integrated Transportation Plan for NCR’ with
ti 2032perspective year 2032• Integrated Transportation Plan for NCR-2032 was approved by the Board
in its 31st meeting held on 11.11.09• Travel Pattern (Passenger Modes) : Study Indicates 11,07,043 passenger
modes crosses Delhi Borders in a day (year 2007)
I t l E t l (IE) 36 7% (O i i ithi NCTD)Internal-External (IE) : 36.7% (Origin within NCTD)External-Internal (EI) : 38.4% (Destination within NCTD)External-External (EE) : 22.9% (both O & D outside NCTD)
13.8 %22.9%
44.8 %36.7%
38 4%
GNCTD
41.4 %38.4%
NATIONAL CAPITAL REGION PLANNING BOARD 8
Integrated Transportation Plan for NCR
Mode-wise distribution of TripsMode Year - 2007 Year - 2032
Trips per % Trips per day %
Mode-wise distribution of Trips
Trips per day (Million)
% Trips per day (Million)
%
Bus 1.03 27.83 6.18 46.7Sub-urban Rail/ RRTS/ Regional MRTS
0.61 16.61 2.91 21.9
i)Sub-urban Rail/ RRTS 0 61 16 61 1 70 12 8i)Sub urban Rail/ RRTS 0.61 16.61 1.70 12.8
ii) Regional MRTS - - 1.21 9.1Auto-Rickshaw - - 0 66 5 0Auto-Rickshaw - - 0.66 5.0Car 1.12 31.90 2.22 16.72-Wheeler 0.87 23.57 1.28 9.62 Wheeler 0.87 23.57 1.28 9.6Total 3.63 100% 13.25 100%
NATIONAL CAPITAL REGION PLANNING BOARD 9
Integrated Transportation Plan for NCR
• The study was completed and the Transport Plan was approvedby the Board in its 31st meeting held on 11.11.09 which providesfor following componentsfor following components
Road SystemExpressways
Rail SystemNew Rail Lines
OthersLogistic HubsExpressways
National HighwaysState HighwaysOth R d
New Rail LinesRRTSMass Rapid Transit S t
Logistic HubsIntegrated Freight ComplexHi h F ilitiOther Roads
Bus SystemBus Fleet &
SystemAirports
International
Highway Facilities Centres
InfrastructureBus Terminals
Domestic
• It recommended prioritization of RRTS corridors
NATIONAL CAPITAL REGION PLANNING BOARD 10
Already 4-lane Highways
EXPRESSWAYS ALREADY PROPOSEDPANIPAT
Integrated Transportation Plan for NCRIntegrated Transportation Plan for NCR--2032: 2032: Road Network & AirportsRoad Network & AirportsNARAH
EXPRESSWAYS ALREADY PROPOSED
SONEPAT
KMP (Western Peripheral) Expressway
KGP (Eastern Peripheral) Expressway
GOHANA
NH24
TO BHIWANI
BAHADURGARH
KUNDLIROHTAK BAGHPATGhaziabad-Meerut (GM) Expressway
Yamuna ExpresswayGanga Expressway
MEERUT
GURGAON
NH24TO MURADABAD
South-West
NOIDA
HAPURGHAZIABAD
FARIDABAD
HARYANA UTTAR PRADESH
DELHINew Expressways
TRANSPORT PLAN PROPOSALSGULAOTHI
Up-gradation of Major HighwaysUp-gradation of Other Highways
JHAJJAR
BULANDSHAHR
REWARIGAUTAMBUDHNAGAR
KHURJABHIWADI
NH 71B
PALWAL
BALLABGARH
Up gradation of Other Highways
International Airport-Existing
AIRPORTS
HODALInternational Airport-Proposed
RAJASTHAN
ALWAR
NATIONAL CAPITAL REGION PLANNING BOARD 11
PANIPAT
Integrated Transportation Plan for NCRIntegrated Transportation Plan for NCR--2032: 2032: Rail NetworkRail Network
LEGEND
Existing Rail Network
MEERUT
BARAUT
SONEPAT
ROHTAKTO BHIWANIKUNDLI
RRTS Corridors- Proposed Under the Study
RRTS Corridors – Phase I
DMRC Corridors OperationalMEERUTKUNDLI
Jahangirpuri
HolambiKalan
RithalaBarwala
Mundka
BAHADURGARHBadli
Trinagar
W k i P IR P j t
DMRC Corridors -Under State Consideration
DMRC Corridors- Operational
U .P.
HARYANA JHAJJAR
TO MURADABADHAPURGHAZIABAD
Dwarka
S Lok
Okhla
Dilshad Gn.
Airport
R. Chowk.
Shahdara
ShivajiBridge
Badarpur
Dabur Chowk
Kirti nagar
Sec. 21
NOIDADELHI
Work in Progress- IR Projects
Survey in Progress- IR ProjectsSurvey Sanctioned – IR ProjectsInner Corridor- Proposed Under the Study
GURGAON
BULANDSHAHR
FARIDABAD
GAUTAMBUDHNAGAR
BHIWADI
REWARI
BALLABAGARH
S. Lok
New Rail Link
Inner Corridor Proposed Under the Study
DFC Corridor
KHURJA
PALWAL
NATIONAL CAPITAL REGION PLANNING BOARD 12
RAJASTHAN
ALWAR
12
• Logistic Hubs/ Inland Container
Inland Container Depots and DFCInland Container Depots and DFC
gDepots
Existing = 6– Existing = 6– Additional = 8– Total = 14
• Integrated Freight Complex
– In every Regional and Sub-regional Centres as part of city Master Plans
NATIONAL CAPITAL REGION PLANNING BOARD 13
REGIONAL RAPID TRANSIT SYSTEM (RRTS)REGIONAL RAPID TRANSIT SYSTEM (RRTS)
NATIONAL CAPITAL REGION PLANNING BOARD 14
Proposed RRTS Corridors Proposed RRTS Corridors
Sl. No. Corridor
1 Delhi – Sonipat - Panipat1 Delhi Sonipat Panipat
2 Delhi - Ghaziabad -Meerut
3 Delhi - Gurgaon – Rewari - Alwar
4 Delhi – Faridabad – Ballabgarh - Palwalg
5 Ghaziabad – Khurja
6 Delhi - Bahadurgarh - Rohtak
7 Ghaziabad-Hapurp
8 Delhi-Shahadra-Baraut
NATIONAL CAPITAL REGION PLANNING BOARD 15
Prioritization of RRTS CorridorsPrioritization of RRTS Corridors
Task Force met on 9.12.2009 and decided to take up following three Task Force met on 9.12.2009 and decided to take up following three RRTS corridors on priority for the study on Feasibility-cum-Detailed Project Report (DPR)
• Delhi-Gurgaon-Rewari-Alwar - 158 Km• Delhi-Sonepat-Panipat - 89 Km• Delhi-Ghaziabad-Meerut - 67 Km
Ministry of Urban Development Government of India is Financing theMinistry of Urban Development, Government of India is Financing the studyObjectives of the StudyObjectives of the StudyObjectives of the Study Objectives of the Study
To prepare Feasibility as well as Detailed Project Report (DPR) for theTo prepare Feasibility as well as Detailed Project Report (DPR) for the prioritized Regional Rapid Transit System (RRTS) Corridors
NATIONAL CAPITAL REGION PLANNING BOARD 16
PANIPAT
Regional Rapid Transit SystemRegional Rapid Transit System
LEGEND
Existing Rail Network
MEERUT
BARAUT
SONEPAT
ROHTAKTO BHIWANIKUNDLI
RRTS Corridors
RRTS Corridors – Phase IMEERUTKUNDLI
Jahangirpuri
HolambiKalan
RithalaBarwala
Mundka
BAHADURGARHBadli
Trinagar
U .P.
HARYANA JHAJJAR
TO MURADABADHAPURGHAZIABAD
Dwarka
S Lok
Okhla
Dilshad Gn.
Airport
R. Chowk.
Shahdara
ShivajiBridge
Badarpur
Dabur Chowk
Kirti nagar
Sec. 21
NOIDADELHI
GURGAON
BULANDSHAHR
FARIDABAD
GAUTAMBUDHNAGAR
BHIWADI
REWARI
BALLABAGARH
S. Lok
KHURJA
PALWAL
NATIONAL CAPITAL REGION PLANNING BOARD 17
RAJASTHAN
ALWAR
17
Regional Rapid Transit SystemRegional Rapid Transit System
• Feasibility Study-cum-DPR preparation in progress
• Combination of Elevated and Underground sections
• Broad Gauge
• Operating Speed of 160 km/ hr with acceleration of 1 0 m/ sec2Operating Speed of 160 km/ hr with acceleration of 1.0 m/ sec
• Automatic fare collection system
TOD b d f i l• TOD to be used to meet part of capital costs
• Land to be provided by respective State Governments
• Possibilities of PPP are under considered for implementation
• Other parameters are under finalisationp
NATIONAL CAPITAL REGION PLANNING BOARD 18
Progress of the StudyProgress of the StudySl. No. Corridor Consultant Reports submitted till date
1 Delhi-Gurgaon-Rewari-Alwar (158 km)
M/s. Urban Mass Transit Company Ltd., New Delhi
Inception Report, Existing Condition ReportTravel Demand Forecast ReportAlignment ReportAlignment Report
2 Delhi-Ghaziabad-Meerut (67 km)
M/s. Delhi Integrated Multi-Modal Transit System Limited, New
Inception Report, Existing Condition ReportTravel Demand Forecast ReportSystem Limited, New
DelhiTravel Demand Forecast Report Alignment Report
3 Delhi-Sonipat- Panipat(89 km)
M/s. Delhi Integrated Multi-Modal Transit
Inception Report, Existing Condition Report( )
System Limited, New Delhi
g pTravel Demand Forecast Report Alignment Report
• Alignment of all the three RRTS Corridors have been identified in consultationwith the State Governments and approved by the Task Force
• Specifications for RRTS are also finalisedp• Approval of the specifications by the Competent Authority has been conveyed to
the Consultants on 19.08.11• Feasibility report will be submitted by the Consultants next month
NATIONAL CAPITAL REGION PLANNING BOARD 19
• Feasibility report will be submitted by the Consultants next month
DelhiDelhi--SonepatSonepat--PanipatPanipat Corridor of RRTS Corridor of RRTS
NATIONAL CAPITAL REGION PLANNING BOARD 20
DelhiDelhi--SonepatSonepat--PanipatPanipat Corridor Corridor
P j t d T l D d P t i /d (i L kh)Projected Travel Demand - Passenger trips/day (in Lakh)
Length of Corridor : 103 km Cities proposed to be connected : Delhi (ISBT Kashmere Gate),
K dli M h l G S lkh d P i
NATIONAL CAPITAL REGION PLANNING BOARD 21
Kundli, Murthal, Gannur, Samalkha and Panipat
DelhiDelhi--SonepatSonepat--PanipatPanipat CorridorCorridor
Proposed Alignment
Legend
Proposed Alignment
Proposed Alignment
Existing Railway Line
National Highway
No. of Stations – 10
Total Length – 105 Km
NATIONAL CAPITAL REGION PLANNING BOARD 22
DelhiDelhi--SonepatSonepat--PanipatPanipat Corridor: Corridor: Station Locations & distances
Sr Stations Station Inter IndicativeSr. No
Stations Station location
Inter Station
Distance (KM)
Indicative Cumulative
Distance (KM)(KM) (KM)
1 Panipat Terminus and Depot At Grade 02 Panipat City Elevated 8.8 8.83 Samalkha Elevated 17 2 26 03 Samalkha Elevated 17.2 26.04 Gannaur (at NH1) Elevated 11.8 37.8
4(a) Gannaur Depot (along the spur) At Grade 6.0 43.85 Murthal (Sonepat) Elevated 12 6* 56 45 Murthal (Sonepat) Elevated 12.6 56.46 Rajeev Gandhi Education City
(Rai)Elevated 8.5 64.9
7 KMP Expressway interchange Elevated 4 2 69 17 KMP Expressway interchange Elevated 4.2 69.18 Kundli Border Elevated 6.5 75.69 Narela MMTC Elevated 6.9 82.510 Kashmere Gate Terminus Elevated 22 5 105 0**10 Kashmere Gate Terminus Elevated 22.5 105.0* distance from Gannaur Station at NH1 to Murthal** including spur length of 6KM (4 (a)Note : Final length shall be prepared based on topo surveys conducted along with Feasibility Report.
NATIONAL CAPITAL REGION PLANNING BOARD 23
Note : Final length shall be prepared based on topo surveys conducted along with Feasibility Report.
DelhiDelhi--GhaziabadGhaziabad--Meerut Corridor Meerut Corridor Projected Travel Demand - Passenger trips/day (in Lakh)
Length of Corridor : 90 km Length of Corridor : 90 km
Cities proposed to be connected : Nizamuddin Railway Station, Sahibabad,
Mohan Nagar Ghaziabad Murad Nagar Modi Nagar and Meerut
NATIONAL CAPITAL REGION PLANNING BOARD 25
Mohan Nagar, Ghaziabad, Murad Nagar, Modi Nagar and Meerut
DelhiDelhi--GhaziabadGhaziabad--Meerut CorridorMeerut CorridorProposed AlignmentProposed Alignment
No. of Stations - 17 Total Length - 90 Kmota e gt 90Elevated Length - 64 Km Underground Length - 26 Km
Anand Vihar Nizamuddin AlignmentAnand Vihar – Nizamuddin Alignment
T l L h 10 9Total Length - 10.79 KmElevated Length - 2.27 Km
Nizamuddin
NATIONAL CAPITAL REGION PLANNING BOARD 26
Km Underground Length- 8.52 Km
S No Stations U /G - Elevated Distance ( Km)
DelhiDelhi--GhaziabadGhaziabad--Meerut Corridor: Meerut Corridor: Station locations & distances( )
1 Delhi( Hazrat Nizamuddin) Underground 00.00
2 Delhi( Anand Vihar) Underground/2 km elevated 9.92
3 Sahibabad Elevated 6.44 Mohan Nagar Elevated 2.55 Ghaziabad Elevated 2.86 Guldhar Elevated 3.77 Duhai Elevated 4.28 Murad Nagar Elevated 6.99 Modi Nagar Elevated 9.8
10 Meerut South Elevated 8 410 Meerut South Elevated 8.411 Shatabdi Nagar Underground 7.312 Meerut Central ( HRS Chowk) Underground 3.513 Begum Pul Underground 3.1g g14 Meerut North( Pallavpuram) Elevated 7.7515 Modipuram Elevated 4.7
Total Route length 80.97Spur( Shatabdi Nagar- Shastri Nagar)Shatabdi Nagar Underground 00.00Hapur Road( Nauchandi Park) Underground 4.95
NATIONAL CAPITAL REGION PLANNING BOARD 27
Shastri Nagar( Medical College) Elevated 3.55
DelhiDelhi--GurgaonGurgaon--AlwarAlwar CorridorCorridorProjected Travel Demand - Passenger trips/day (in Lakh)
Length of Corridor : 188 km Length of Corridor : 188 km Cities proposed to be connected : Delhi (Kashmere gate ISBT),
Gurgaon, Manesar, Dharuhera, Bhiwadi, Rewari, Bawal, Shahjahanpur, Kh i h l d Al
NATIONAL CAPITAL REGION PLANNING BOARD 29
Khairthal and Alwar
ISBT-KG
DelhiDelhi--GurgaonGurgaon--AlwarAlwar CorridorCorridorFrom To Distance
(K )
Cumulative Distance
CYBR
NZMDWRK
(Kms) (Kms)ISBT (KG) New Delhi 3.50 3.50
New Delhi Nizamuddin 7.00 10.50
PNCH
Nizamuddin INA 5.00 15.50
INA Dhaula Kuan 4.50 20.00
Dhaula Kuan Mahipalpur 6.50 26.50
RWR
PNCH
BTK
Mahipalpur Cyber City 7.50 34.00
Cyber City Rajiv Chowk 7.50 41.50
Rajiv Chowk Manesar 13.00 54.50
SNB
BTK
Manesar Panchgaon 9.50 64.00
Panchgaon Dharuhera 13.00 77.00SNB
KRTL
Dharuhera BTK 9.00 86.00
BTK MBIR 15.00 101.00
MBIR Rewari 5.50 106.50 KRTLRewari Bawal 12.50 119.00
Bawal SNB 7.00 126.00
SNB Khairtal 29.50 155.50
NATIONAL CAPITAL REGION PLANNING BOARD 30
AWRKhairtal Alwar 24.50 180.00
DelhiDelhi--GurgaonGurgaon--AlwarAlwar Corridor: Selected Route in DelhiCorridor: Selected Route in Delhi
ISBT (KG)
NATIONAL CAPITAL REGION PLANNING BOARD 31
DelhiDelhi--GurgaonGurgaon--AlwarAlwar CorridorCorridor : Selected Route in Haryana: Selected Route in Haryana
NATIONAL CAPITAL REGION PLANNING BOARD 32
DelhiDelhi--GurgaonGurgaon--AlwarAlwar Corridor: Haryana/ RajasthanCorridor: Haryana/ Rajasthan
DFCDFC
DepotDFC
DFC
NATIONAL CAPITAL REGION PLANNING BOARD 33
Selected Route: Rajasthan
DelhiDelhi--GurgaonGurgaon--AlwarAlwar CorridorCorridor
Selected Route: Rajasthan
NATIONAL CAPITAL REGION PLANNING BOARD 34
Depot
Proposed Institutional Arrangement: National Capital Region Transport Corporation (NCRTC)National Capital Region Transport Corporation (NCRTC)
NATIONAL CAPITAL REGION PLANNING BOARD 35
• The National Capital Region Transport Corporation (NCRTC) has
National Capital Region Transport Corporation (NCRTC) National Capital Region Transport Corporation (NCRTC) p g p p ( )
been proposed as a wholly government owned company underCompanies Act 1956 under Ministry of Urban Development, withequity participation as given below:
Participants EquityParticipants EquityGovernment of IndiaMinistry of Urban Development/MoR : 45%y pNCR Planning Board : 5.0%State GovernmentsGovernment of NCT Delhi : 12.5%Government of Haryana : 12.5%Government of Rajasthan : 12.5%
Government of UP : 12.5%
NATIONAL CAPITAL REGION PLANNING BOARD 36
National Capital Region Transport Corporation (NCRTC) National Capital Region Transport Corporation (NCRTC)
• The Corporation will be responsible for over all development of• The Corporation will be responsible for over all development of Integrated Multi-Modal Transport System including Commuter Rail and feeder bus services for commuter in NCR
Present Status of Formation of NCRTC
• Draft EFC Note for setting up NCR Transport Corporation (NCRTC) hasg p p p ( )been circulated by the Ministry for comments
• MoU among NCR Constituent States, NCR Planning Board and MoUDsinged on 29.6.2011 to implement the project through NCRTC
• Appropriate debt: equity ratio will be formulated for implementation
• Sub-joint venture companies under umbrella company to implementeach RRTS corridor
• Inter-se contribution among the State Governments on the projects willbe decided by NCRTC
NATIONAL CAPITAL REGION PLANNING BOARD 37
SO O C SSO O C SSOME MAJOR ACHIEVEMENTSSOME MAJOR ACHIEVEMENTS
NATIONAL CAPITAL REGION PLANNING BOARD 39
Implementation of Regional PlanImplementation of Regional Plan : : AchievementsAchievements
P l ti th t f D lhi d d f 51 45% (1981 1991) t• Population growth rate of Delhi reduced from 51.45% (1981-1991) to47.02% (1991-2001) for the first time since independence. It further camedown to 20.96% during 2010-11 (as per 2011 Census provisional results)
• Percentage share of net-migrants in the decadal growth of population ofNCT-Delhi declined from 45.06% in 1961-1971 to 39.82% in 1991-2001
• Percentage share of migrants from NCR States to NCT-Delhi declined from65.76% in 1981-1991 to 57.09% in 1991-200165.76% in 1981 1991 to 57.09% in 1991 2001
• Number of out-migrants increased from 2.82 lakhs in the decade 1981-91 to4 58 lakhs in decade 1991-20014.58 lakhs in decade 1991-2001.
• In the decade 1991-2001, the in-migration including inter-district migration torest of NCR was 24 55 lakhs and to Delhi was 21 02 lakhsrest of NCR was 24.55 lakhs and to Delhi was 21.02 lakhs.
NATIONAL CAPITAL REGION PLANNING BOARD 40
Achievements at a GlanceAchievements at a Glance
Declining rate of population growth of NCT-Delhi
52.93 5351.45
47.0250
60
31.28 30.0234.55
30.75 27.06
28.1129.17
28.53 26.0527.43
26 2329.7 30.3
35.338.1 37.62
35.59
24 12
30
40
wth
rate
(%)
22.2526.23
22.7520.96
24.12
10
20Gro
w
01971 1981 1991 2001 2011*
Haryana UP Rajasthan NCT NCR
NATIONAL CAPITAL REGION PLANNING BOARD 41
• Up-gradation of National Highways converging at Delhi [NH1,NH2, NH8,
Implementation of Regional Plan : Achievements Implementation of Regional Plan : Achievements p g g y g g [ , , ,
(NH10), NH24 & NH58] to 4-lane divided carriage way carried out
• Up-gradation of about 580 km of Outer Grid roads & Inner Grid roads in NCRas per the policies of RP-2001 have been carried out.
• Peripheral Expressway (Western & Eastern) around Delhi is underconstruction.
• Construction of Delhi-Meerut Expressway to be taken up by M/o RoadT t Shi i & Hi h d NHDP VI P ti f d t il dTransport, Shipping & Highways under NHDP-VI. Preparation of detailedproject report is in progress.
• Mass Commuter System for Delhi in the form of Delhi Metro Rail has been• Mass Commuter System for Delhi in the form of Delhi Metro Rail has beenconstructed and is in operation.
• Delhi Metro Rail been has been proposed to extend to five out of six CNCR• Delhi Metro Rail been has been proposed to extend to five out of six CNCRtowns. Delhi-Noida, Delhi-Gurgaon & Delhi-Ghaziabad Lines have beencommissioned. Delhi-Faridabad corridor have been agreed by the Ministry.
NATIONAL CAPITAL REGION PLANNING BOARD 42
• Participating states prepared 28 Master/Development Plans and 25 more
Achievements of Implementation of Regional Plan Achievements of Implementation of Regional Plan
• Participating states prepared 28 Master/Development Plans and 25 moreMaster/Development Plans are under preparation for various towns in NCR
• Board provided financial assistance to the State Governments & theirpimplementing agencies for 263 infrastructure development projects throughlong term soft loan/low interest rate up to 75% of the estimated cost (Rs.18008 crore)18008 crore).
• Loan amount of Rs. 7988 crore was sanctioned & Rs. 5815 crore released.
• Projects financed related to drinking water supply sewerage & sewageProjects financed related to drinking water supply, sewerage & sewagetreatment, Development of industrial estates, Rural water supply schemes,roads, residential sectors, commercial areas, power generation,transmission & distribution etctransmission & distribution, etc.
• Education City – Kundli, Sampla, and Samalkha in Haryana Sub-region andShahjhanpur-Neemrana-Behror in Rajasthan Sub-region are new townshipsj p j g pproposed and are at various stages of planning.
NATIONAL CAPITAL REGION PLANNING BOARD 43
SubregionSubregion--wise Population of NCR wise Population of NCR
350
400
450
500
)200
250
300
350
pula
tion
(lakh
s
50
100
150
200Po
p
0NCT-Delhi Haryana Rajasthan Uttar Pradesh NCR
Sub-regions
P d A t lProposed Actual
Sub-region Population 2011 (lakhs)Proposed Actual
NCT Delhi 179 9 167 53NCT-Delhi 179.9 167.53Haryana 117.55 110.38Rajasthan 37.91 36.72Uttar Pradesh 150.83 145.84NCR 486 19 460 47
NATIONAL CAPITAL REGION PLANNING BOARD 44
NCR 486.19 460.47