Page 1: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

REGION 4 - MOBILITY PRESENTATION

3-7-2018

Page 2: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

PROJECTS TO DISCUSS

1. I-84: Swanson Canyon – Arlington (K20274)

• 2019 Construction Work Zone Impacts

2. ORS 366.215 Impacts

• US97: Bend – Spring Creek Hill VSL (K19260)

• I-84: Hood River EB & US97 @ Biggs Jct SB VMS

(K20860)

3. Local Jurisdiction TSP Updates

• City of Sisters

• City of Madras

2

Page 3: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

I-84: Swanson Canyon – Arlington (K20274)

Scope - pavement preservation between MP 125-138.

Construction in 2019

MP 125.50 – 132.00 (6.5 miles)

- 3” grind, 5” inlay/overlay

MP 132.00 – 137.78 (5.8 miles)

- Left (“A”) Lane - 5” grind, 8” inlay/overlay

- Right (“B”) Lane – 3” grind, 5” inlay/overlay

Traffic Analysis – single lane conditions remain below

delay thresholds except during Memorial Day and Labor

Day weekends.

3

Page 4: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

I-84: Swanson Canyon – Arlington (K20274)

Traffic Control Alternatives

1. Single Lane Closures $500K

– 14.5’ – 19’ horizontal clearance, likely nighttime

2. Temporary Crossover w/ Concrete Barrier $1.8M

– 18’ horizontal clearance, 24-hour restriction

– Exposure while placing barrier (12.5 miles)

3. Temporary Crossover w/ Plastic Drums $700K

– 17.5’ horizontal clearance, 24-hour restriction

– 19’ horizontal clearance at start/end

– Speed Reduction to 45mph

– See attachment “TZ_K20274_ Misc_04.pdf”

4

Page 5: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Scope - design of weather responsive Variable Speed

Limit system on US97 from Lava Butte (MP 143) to Spring

Creek Hill (MP 244). Project is not funded for construction.

ORS366.215 Impacts – cantilever mounted Variable

Message Signs and Variable Speed Signs will encroach

over the roadway. Current design calls for 18’-0” vertical

clearance.

See following pages

for site locations

5

Page 6: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Bend – LaPine

Site 1: MP 143.68 Southbound

Site 6: MP 152.75 Northbound

Site 7: MP 153.50 Southbound

Site14: MP 164.17 Northbound

Chemult – Spring Creek Hill

Site 15: MP 204.10 Southbound

Site 22: MP 212.98 Northbound

Site 23: MP 213.29 Southbound

Site 28: MP 227.66 Northbound

Site 29: MP 227.86 Southbound

Site 32: MP 243.22 Northbound

6

Page 7: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Site 1 – US97 MP 143.68 Southbound

Designed Vertical Clearance: 18’-0”

7

Page 8: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Site 6 – US97 MP 152.75 Northbound

Designed Vertical Clearance: 18’-0”

8

Page 9: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Site 7 – US97 MP 153.50 Southbound

Designed Vertical Clearance: 18’-0”

9

Page 10: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Site 14 – US97 MP 164.17 Northbound

Designed Vertical Clearance: 18’-0”

10

Page 11: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Site 15 – US97 MP 204.10 Southbound

Designed Vertical Clearance: 18’-0”

11

Page 12: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Site 22 – US97 MP 212.98 Northbound

Designed Vertical Clearance: 18’-0”

12

Page 13: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Site 23 – US97 MP 213.29 Southbound

Designed Vertical Clearance: 18’-0”

13

Page 14: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Site 28 – US97 MP 227.66 Northbound

Designed Vertical Clearance: 18’-0”

14

Page 15: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Site 29 – US97 MP 227.86 Southbound

Designed Vertical Clearance: 18’-0”

15

Page 16: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

US97: Bend – Spring Creek Hill VSL (K19260)

Site 32 – US97 MP 243.22 Northbound

Designed Vertical Clearance: 18’-0”

16

Page 17: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

I-84: Hood River EB & US97 @ Biggs Jct SB VMS (K20860)

Scope – Design and installation of two Variable Message

Signs (VMSs); one on I-84 Hood River Eastbound (MP63.04)

and one on US97 @ Biggs Junction Southbound (MP TBD).

ORS366.215 Impacts – cantilever mounted VMSs will

encroach over the roadway. The current design is

proposing 18’-0” to 19’-0” vertical clearance.

17

Page 18: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

I-84: Hood River EB & US97 @ Biggs Jct SB VMS (K20860)

I-84 at MP 63.04± Eastbound VMS

18

Located near the Westcliff Dr. Overcrossing Structure

Proposed Vertical Clearance: 18’-0” to 19’-0”

• Centered over the skip line

• Placed behind guardrail

Visual Concept of VMS

Page 19: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

I-84: Hood River EB & US97 @ Biggs Jct SB VMS (K20860)

I-84 at MP 63.04± Eastbound VMS: Existing Structures

19

To the East: Exit 63 (MP 63.78)Sign Truss Bridge (#09199A)

Existing Vertical Clearances

• Right Lane = 18’-1”

• Left Lane = 17’-8”

Google Maps August 2016

To the West: Exit 62 (MP 62.05)Bridge Structure #09017

Existing Vertical Clearances

• EB Right Lane = 16’-9”

• EB Left Lane = 16’-0”

• Diamond Interchange

Google Maps August 2016

Page 20: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

I-84: Hood River EB & US97 @ Biggs Jct SB VMS (K20860)

US97 at Biggs Jct Southbound VMS

20

Existing NB VMS

• Will be located within MP 0.07 to MP 0.21 on US 97 (Sherman Hwy #042)

• Proposed Vertical Clearance: 18’-0” to 19’-0”• US97: Biggs Jct. - Spanish Hollow & Trout Creek Project (K19075) will continue

extending the southbound acceleration lane ½ mile south of Interchange (2018)

Cantilever VMS located within this area

(similar to I-84 Hood River EB)

Page 21: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

I-84: Hood River EB & US97 @ Biggs Jct SB VMS (K20860)

US97 at Biggs Jct Southbound VMS: Existing Structures

21

Google Maps November 2015

Google Maps August 2016

To the North: Biggs Jct Int (MP 0.04)Traffic Signal

Existing Vertical Clearances

• Right Lane = 18’-6”

• Left Lane = 18’-7”

To the South: Wasco Intchg (MP 14.73)Bridge Structure #13548

Existing Vertical Clearances

• Right Lane = 17’-9”

• Left Lane = 18’-1”

• Diamond Interchange – could go “up

and over” ramps

Page 22: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

City of Sisters TSP Update

GOAL: Improve highway operations on the east side of the city and

improve the highway alternate route (Barclay and Locust) for all

users, including freight.

PLANNING GOAL TO IMPLEMENTATION:

1. Identify Funding (not there yet)

2. Intersection Traffic Control Study (Alternatives Analysis)

3. Stakeholder Outreach & Design

4. Construction

22

Source: Sisters TSP Refinement (KAI)

Page 23: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

City of Sisters TSP Update

NEAR TERM IMPROVEMENT US20 at Locust – Mini Roundabout

Single Lane approaches

Designed so that all loads are accommodated

23

Source: Sisters TSP Refinement (KAI)

CONCEPT ONLY

Page 24: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

City of Sisters TSP Update

LONG TERM IMPROVEMENTS

1. Potential Roundabout US20 and Locust

24

Source: Sisters TSP Refinement (KAI)

CONCEPT ONLY CONCEPT ONLY CONCEPT ONLY

Page 25: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

City of Sisters TSP Update

2. Potential Roundabout US20 and OR126

25

Source: Sisters TSP Refinement (KAI)

CONCEPT ONLY

Page 26: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

City of Madras TSP Update

SOUTH MADRAS CONCEPT AREA:

Three lane highway (US97) without signals or roundabouts. In the

future, lands to the east and west of the highway will compete with

high demand on the highway.

STEPS TO IMPLEMENTATION:

1. Identify Funding (not there yet)

2. Intersection Traffic Control Study (Alternatives Analysis)

3. Stakeholder Outreach & Design

4. Construction

26

Page 27: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

City of Madras TSP Update

NEAR TERM IMPROVEMENT ALTERNATIVES FOR CONSIDERATION

Intersection Improvements at primary connections to US97

(Fairgrounds Road and Hall Road)

• ROUNDABOUT – highway volumes likely require multilane

– Mobility benefits (v/c, delay)

– Safety benefits (reduced crashes)

– Aesthetic Benefits

27

Page 28: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

City of Madras TSP Update

• JUG-HANDLE

– Restrict left and right turn movements at an intersection

– Two phase (more efficient) signalized intersection

– Turn movements served by “jug-handles”

28

Source: Google Maps

Page 29: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

City of Madras TSP Update

• MEDIAN U-TURN

» Restrict left-turns at main intersection

» Two phase (more efficient) signalized intersection

» Provide U-Turn downstream of intersection

29

Source: FHWA Median U-Turn

Information Guide

Page 30: REGION 4 - MOBILITY PRESENTATION 3-7-2018 Document... · REGION 4 - MOBILITY PRESENTATION 3-7-2018. PROJECTS TO DISCUSS 1. I-84: Swanson Canyon –Arlington (K20274) ... Google Maps

City of Madras TSP Update

• Restricted Crossing Median U-Turn

– Restrict minor street through volumes

» Served by turning right and then using the downstream u-turn

– Allow major street left-turns

Want to Know More? http://www.madrastsp.com/30

Source: FHWA Median U-Turn Information Guide