Regency Road to Pym Street Project PROJECT UPDATE CONTACT 1300 110 906 www.r2palliance.com.au [email protected] July 2020 Current works Works on the project are progressing well with stormwater drainage installation continuing along Regency Road, South Road and the North-South Motorway. These drainage works will be completed in August, weather permitting. The South Road surface roads are being constructed between Tait Street and Packard Avenue, and between Regency Road and the Regency Oval on the western side of South Road, and between Overland Road and Regency Road (next to Coopers Brewery) on the eastern side of South Road. Aerial photograph of the surface road being constructed along South Road, north of Regency Road These works require a temporary closure of some roads at their junction with South Road. Advance notice will be provided to local residents, and signage will also be in place to advise motorists of detours. Precast concrete panel noise walls are being constructed along South Road. They are 3.5 metres high and “woodland grey” in colour. Please visit the project website for more information about current works: https://r2palliance.com.au/construction/works- notifications. Noise wall installation along South Road, between Hotchkiss Crescent and Pym Street Upcoming works Heavy vehicle bypass road The R2P Project commenced survey works in June, for the new heavy vehicle bypass road into the Dudley Park Industrial Precinct. Construction works are expected to commence in late August, and works completed by the end of 2020, weather permitting. For more information on the heavy vehicle bypass road visit the project website to see the Fact Sheet: https://r2palliance.com.au/resources/publications.

Transcript of Regency Road to Pym Street Project...Regency Road to Pym Street Project PROJECT UPDATE Ju CONTACT...

Page 1: Regency Road to Pym Street Project...Regency Road to Pym Street Project PROJECT UPDATE Ju CONTACT 1300 110 906 info@r2palliance.com.au ly 2020 Changes to pedestrian access Pedestrian

Regency Road to Pym Street Project

PROJECT UPDATE

CONTACT

1300 110 906

www.r2palliance.com.au

[email protected]

July 2020

Current works Works on the project are progressing well with stormwater drainage installation continuing along Regency Road, South Road and the North-South Motorway. These drainage works will be completed in August, weather permitting.

The South Road surface roads are being constructed between Tait Street and Packard Avenue, and between Regency Road and the Regency Oval on the western side of South Road, and between Overland Road and Regency Road (next to Coopers Brewery) on the eastern side of South Road.

Aerial photograph of the surface road being constructed along South Road, north of Regency Road

These works require a temporary closure of some roads at their junction with South Road.

Advance notice will be provided to local residents, and signage will also be in place to advise motorists of detours.

Precast concrete panel noise walls are being constructed along South Road. They are 3.5 metres high and “woodland grey” in colour.

Please visit the project website for more information about current works: https://r2palliance.com.au/construction/works-notifications.

Noise wall installation along South Road, between Hotchkiss Crescent and Pym Street

Upcoming works Heavy vehicle bypass road

The R2P Project commenced survey works in June, for the new heavy vehicle bypass road into the Dudley Park Industrial Precinct. Construction works are expected to commence in late August, and works completed by the end of 2020, weather permitting.

For more information on the heavy vehicle bypass road visit the project website to see the Fact Sheet: https://r2palliance.com.au/resources/publications.

Page 2: Regency Road to Pym Street Project...Regency Road to Pym Street Project PROJECT UPDATE Ju CONTACT 1300 110 906 info@r2palliance.com.au ly 2020 Changes to pedestrian access Pedestrian

Regency Road to Pym Street Project

PROJECT UPDATE

CONTACT

1300 110 906

www.r2palliance.com.au

[email protected]

July 2020

Regency Road overpass

Bridge spans for the Regency Road overpass will be assembled ‘off site’ at the Polonia Reserve and then transported using Self Propelled Modular Transporters (SPMTs). Structures that support the bridge spans will be constructed at the South Road and Regency Road intersection. Overpass works will start in August.

For more information on the overpass, visit the project website to see the Fact Sheet: https://r2palliance.com.au/resources/publications.

Aerial photograph of the hardstand at the Polonia Reserve, where the Regency Road overpass bridge spans will be constructed ‘off site’

Second traffic switch The second traffic switch will occur in August. This will allow the commencement of works on South Road to construct the structures to support the Regency Road overpass. This switch will involve changes at Regency Road and Pym Street, as well as changes to bus routes and pedestrian crossings.

Temporary removal of right turns from South Road to Regency Road

To maintain the efficiency of the intersection and to minimise travel time impacts, from Saturday 8 August, right turns from South Road to Regency Road will be temporarily removed to assist traffic flow

through the intersection. Prior to removal of the right turns, two signalised U-turns will be created on South Road:

1. South of Hudson Avenue; and

2. North of Tikalara Street.

For details on the U-turns, see map: Use of the South Road U-turns.

Changes to Pym Street access

The final design for Pym Street will be left in and left out on both sides of South Road, with no east-west through movement. Vehicles will be required to travel along either Torrens Road or Regency Road or use the U-turn at Torrens Road to travel east-west.

In the final traffic configuration U-turns will be available on South Road at the intersection of Regency Road.

See map: Pym Street access changes.

Traffic switched onto surface roads

Also as part of the second traffic switch, the traffic will be switched to travel on the new surface roads, allowing for construction to occur in between the

north and south bound lanes.

Bus stop relocations

To accommodate the changes at Pym Street, bus routes that currently cross South Road at Pym Street (230, 232 and 232R), will be permanently re-routed.

New bus stops will be installed along the South Road surface roads. These stops will be moved slightly north or south, as construction works progress in the area.

Bus routes will change from the first service Monday, 10 August.

For more information, please see the insert: Bus Route Changes Fact Sheet.

Page 3: Regency Road to Pym Street Project...Regency Road to Pym Street Project PROJECT UPDATE Ju CONTACT 1300 110 906 info@r2palliance.com.au ly 2020 Changes to pedestrian access Pedestrian

Regency Road to Pym Street Project

PROJECT UPDATE

CONTACT

1300 110 906

www.r2palliance.com.au

[email protected]

July 2020

Changes to pedestrian access

Pedestrian access will alter when traffic is switched to travel along the new surface roads.

The South Road crossing, near Essex Crescent, will be removed in early August, and replaced with a new crossing at the U-turn near Hudson Avenue, operational from Monday, 10 August. The new pedestrian crossing is approximately 100 metres to the south of the existing crossing.

South Road pedestrian crossings at Regency Road and Pym Street will remain open.

Pedestrian access maps will be installed around the local area and added to the project website prior to the change.

Traffic management signage will be in place to guide pedestrians

Staging for the traffic switch

The traffic switch will happen over the weekend, starting on Friday, 7 August, through until Sunday, 9 August. Works will be undertaken continuously, as follows:

Friday 7 August, 7pm-6am: northbound traffic will

move to the new surface road (north of Regency Road) and the U-turn near Tikalara Street will be operational. Pym Street access will change to left in, and left out only on both sides of South Road.

Saturday 8 August, 6am-7pm: northbound traffic will move to the new surface road (south of Regency Road).

Bus users will continue to use their usual bus stops but may need to use the shuttle buses to access routes 230, 232, 232R, for more details contact Adelaide Metro https://www.adelaidemetro.com.au/.

Saturday 8 August, 7pm-6am: Southbound traffic will move to the new surface road (south of Regency Road). The U-turn facility near Hudson Avenue will be operational.

Removal of right turns from South Road into Regency Road and bus only hook-turns from the western side of Regency Road onto South Road southbound commence.

Between 10pm and 9am there will be a temporary closure of the southbound lanes on the North-South Motorway, between Grand Junction Road and Regency Road. See traffic restrictions section below for further details.

Sunday 9 August, 6am-7pm: The traffic switch will be completed. Bus users will be able to use their usual bus stops as per the details for Saturday.

Monday 10 August: Pedestrian crossing near

Hudson Avenue will be operational.

From first service on Monday bus passengers will need to use the new bus stops. For more information, please see the insert: Bus Route Changes Fact Sheet.

Traffic restrictions during the traffic switch

During the works there will be temporary lane and speed restrictions along South Road, Regency Road and Pym Street. There will also be a temporary closure of the southbound lanes on the North-South Motorway, between Grand Junction Road and

Page 4: Regency Road to Pym Street Project...Regency Road to Pym Street Project PROJECT UPDATE Ju CONTACT 1300 110 906 info@r2palliance.com.au ly 2020 Changes to pedestrian access Pedestrian

Regency Road to Pym Street Project

PROJECT UPDATE

CONTACT

1300 110 906

www.r2palliance.com.au

[email protected]

July 2020

Regency Road. This closure will take place on Saturday 8 August, between 9pm to 6am.

Advance notice signage will be in place to advise motorists of the upcoming closure, and signage will be in place to advise motorists of detours occurring during the closure. More details will be provided to local residents prior to works commencing.

Site Podium All latest news is available on the SitePodium App.

Visit the R2P Project website for details on how to download SitePodium: https://r2palliance.com.au/resources/sitepodium-app.

SitePodium can be downloaded on your smart phone

Community noticeboards Community noticeboards have been installed in the local area to provide project updates. The noticeboards are located at bus stops 14 and 16 on Pym Street, at the Hudson Avenue Reserve (at the intersection of Crossley Avenue) and on the fence at Polonia Reserve on Essex Crescent. The noticeboards at the bus stops will be relocated to the new bus stops on South Road after the August 2020 traffic switch.

Community noticeboard at bus stop 14 Pym Street

Cyclist access Please visit the project website for information about the current cyclist detours that will remain in place: https://r2palliance.com.au/construction/changes-to-access.

Support local business If you are a local business and would like your logo included on the R2P Project website, please email us via the details below with your logo and a link to your website or Facebook page.

Local businesses will remain open throughout construction and access will be maintained.

To view businesses in the project area please visit: https://r2palliance.com.au/business/supporting-local-business

COVID-19 update The R2P Project will continue to follow the South Australian Government restrictions to manage the risks of contracting COVID-19.

Page 5: Regency Road to Pym Street Project...Regency Road to Pym Street Project PROJECT UPDATE Ju CONTACT 1300 110 906 info@r2palliance.com.au ly 2020 Changes to pedestrian access Pedestrian

Regency Road to Pym Street Project

PROJECT UPDATE July 2020

CONTACT

1300 110 906

www.r2palliance.com.au

[email protected]

Use of the South Road U-turns

Two signalised U-turns will open on South Road prior to the temporary removal of the right turns at the intersection of South Road and Regency Road on the weekend of 7-9 August, weather permitting. The U-turns will be located:

1. south of Hudson Avenue;and

2. north of Tikalara Street.

Temporary U-turn

No right turn

Road permanently closed

LEGEND

Regency Road (from the west) to South Road

South Road (from the north) to Regency Road

South Road (from the south) to Regency Road

Regency Road (from the east) to South Road

Alternate routes

Work zone

Temporary U-turn

B-double vehicles will be required to use the U-turns at Days Road and Torrens Road.

Page 6: Regency Road to Pym Street Project...Regency Road to Pym Street Project PROJECT UPDATE Ju CONTACT 1300 110 906 info@r2palliance.com.au ly 2020 Changes to pedestrian access Pedestrian

Regency Road to Pym Street Project PROJECT UPDATE July 2020

CONTACT

1300 110 906

www.r2palliance.com.au

[email protected]

Pym Street access changes From 7pm Friday, 7 August, weather permitting, drivers will only be able to turn left in, and left out of Pym Street into South Road with no east-west through movement available.

Vehicles will be required to travel along either Torrens Road or Regency Road or use the U-turn facility at Torrens Road to travel east-west.

In the final traffic configuration of the R2P Project, U-turns will be available on South Road at the intersection of Regency Road.

No right turn

Road permanently closed

Construction zone

Westbound traffic route

Eastbound traffic route

Traffic movements

Pedestrian road crossing

Temporary U-turn and pedestrian

road crossing

HA

RR

ISON

RO

AD

REO

RO

AD

LEGEND