Redfield to Redevelopment Libertyville, Illinois

67
Redfield to Redevelopment Libertyville, Illinois John Spoden, AICP, Director of Community Development, Village of Libertyville John McLinden, StreetScape Development, LLC

description

Redfield to Redevelopment Libertyville, Illinois. John Spoden , AICP, Director of Community Development, Village of Libertyville John McLinden , StreetScape Development, LLC. DEFINITIONS. Greenfield – development on previously undeveloped site - PowerPoint PPT Presentation

Transcript of Redfield to Redevelopment Libertyville, Illinois

Page 1: Redfield to Redevelopment Libertyville, Illinois

Redfield to

RedevelopmentLibertyville, Illinois

John Spoden, AICP, Director of Community Development, Village of Libertyville

John McLinden, StreetScape Development, LLC

Page 2: Redfield to Redevelopment Libertyville, Illinois

Greenfield – development on previously undeveloped site

Brownfield – development on environmentally challenged site

Redfield – development on foreclosed property

DEFINITIONS

Page 3: Redfield to Redevelopment Libertyville, Illinois

Libertyville, IL• Located 35 miles NW of Chicago at commuter rail stop

• Incorporated 1882

• Population 21,800

• Median household income $105,000

• Award-winning Main Street Community

BACKGROUND

Page 4: Redfield to Redevelopment Libertyville, Illinois

BACKGROUND

DO

WN

TO

WN

TRAIN STATION

3 MI TO INTERSTATE

SCHOOL STREET

Page 5: Redfield to Redevelopment Libertyville, Illinois

BACKGROUND

Page 6: Redfield to Redevelopment Libertyville, Illinois

BACKGROUND

Page 7: Redfield to Redevelopment Libertyville, Illinois

BACKGROUND

Page 8: Redfield to Redevelopment Libertyville, Illinois

• 1970s – Village of Libertyville identifies School Street as key future development site and commits to acquiring the 4 acre site

• 1976 – Village purchases first house

• 1976-2002 – Village systematically purchases each property as it comes on the market

• 2004 – Village issues RFP to nine pre-qualified developers to re-develop the site

• 2005 – Village selects developer based on concept of 31 Brownstones and 12 condos in the school building

• 2006 – Village approves original Planned Development

• 2007 – Construction begins on infrastructure and first 5-unit building

• 2008 – Village issues occupancy permits for first 5 units (4 of 5 sold)

• 2009 – Bank forecloses on property – a redfield is created

• 2009 – Village is approached by multiple developers about proposed concepts

BACKGROUND

Page 9: Redfield to Redevelopment Libertyville, Illinois

MOVING FORWARD - PRE-DEVELOPMENT

• January-September, 2009 – StreetScape Development, LLC envisions new development plan and gains Village support

Page 10: Redfield to Redevelopment Libertyville, Illinois

MOVING FORWARD - PRE-DEVELOPMENT

Page 11: Redfield to Redevelopment Libertyville, Illinois

The “Big Idea”

MOVING FORWARD - PRE-DEVELOPMENT

Page 12: Redfield to Redevelopment Libertyville, Illinois

Change development concept: townhomes

single-family homes

The “Big Idea”

MOVING FORWARD - PRE-DEVELOPMENT

Page 13: Redfield to Redevelopment Libertyville, Illinois

MOVING FORWARD - PRE-DEVELOPMENT

Page 14: Redfield to Redevelopment Libertyville, Illinois

MOVING FORWARD - PRE-DEVELOPMENT

Page 15: Redfield to Redevelopment Libertyville, Illinois

MOVING FORWARD - PRE-DEVELOPMENT

Page 16: Redfield to Redevelopment Libertyville, Illinois

MOVING FORWARD - PRE-DEVELOPMENT

Page 17: Redfield to Redevelopment Libertyville, Illinois

MOVING FORWARD - PRE-DEVELOPMENT

Page 18: Redfield to Redevelopment Libertyville, Illinois

MOVING FORWARD - PRE-DEVELOPMENT

Page 19: Redfield to Redevelopment Libertyville, Illinois

MOVING FORWARD - PRE-DEVELOPMENT

• January-September, 2009 – StreetScape Development, LLC envisions new development plan and gains Village support

Page 20: Redfield to Redevelopment Libertyville, Illinois

MOVING FORWARD - PRE-DEVELOPMENT

• January-September, 2009 – StreetScape Development, LLC envisions new development plan and gains Village support

• October, 2009 – StreetScape enters into purchase agreement with bank

Page 21: Redfield to Redevelopment Libertyville, Illinois

• January-September, 2009 – StreetScape Development, LLC envisions new development plan and gains Village support

• October, 2009 – StreetScape enters into purchase agreement with bank

• February, 2010 – StreetScape files to amend the Planned Development

MOVING FORWARD - PRE-DEVELOPMENT

Page 22: Redfield to Redevelopment Libertyville, Illinois

• January-September, 2009 – StreetScape Development, LLC envisions new development plan and gains Village support

• October, 2009 – StreetScape enters into purchase agreement with bank

• February, 2010 – StreetScape files to amend the Planned Development

• August, 2010 – Village approves the amended Planned Development

MOVING FORWARD - PRE-DEVELOPMENT

Page 23: Redfield to Redevelopment Libertyville, Illinois

• January-September, 2009 – StreetScape Development, LLC envisions new development plan and gains Village support

• October, 2009 – StreetScape enters into purchase agreement with bank

• February, 2010 – StreetScape files to amend the Planned Development

• August, 2010 – Village approves the amended Planned Development

• September, 2010 – StreetScape closes on the property

MOVING FORWARD - PRE-DEVELOPMENT

Page 24: Redfield to Redevelopment Libertyville, Illinois

September, 2010

CLOSING

Page 25: Redfield to Redevelopment Libertyville, Illinois

January, 2012

SCHOOL STREET AT PRESENT

Page 26: Redfield to Redevelopment Libertyville, Illinois

SCHOOL STREET AT PRESENT

Page 27: Redfield to Redevelopment Libertyville, Illinois

• Phase 1 pricing - $449,000 - $689,000

• Current pricing - $525,000 - $810,000

• 18%(+/-) price increase

• Sold without model home

• Ten closings to date (average - $628,673)

SCHOOL STREET AT PRESENT

Page 28: Redfield to Redevelopment Libertyville, Illinois

SCHOOL STREET AT PRESENT

Page 29: Redfield to Redevelopment Libertyville, Illinois

SCHOOL STREET AT PRESENT

Page 30: Redfield to Redevelopment Libertyville, Illinois

SCHOOL STREET AT PRESENT

Page 31: Redfield to Redevelopment Libertyville, Illinois

SCHOOL STREET AT PRESENT

Page 32: Redfield to Redevelopment Libertyville, Illinois

SCHOOL STREET AT PRESENT

Page 33: Redfield to Redevelopment Libertyville, Illinois

How was the project financed?

HOW DID WE DO IT?

Page 34: Redfield to Redevelopment Libertyville, Illinois

How was the project financed?

HOW DID WE DO IT?

• Purchase property with cash

Page 35: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?

How was the project financed?

• Purchase property with cash

• Investor requirements

Page 36: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?

How was the project financed?

• Purchase property with cash

• Investor requirements

• zoning approval

Page 37: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?

How was the project financed?

• Purchase property with cash

• Investor requirements

• zoning approval

• pre-sell 6 homes

Page 38: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?

How was the project financed?

• Purchase property with cash

• Investor requirements

• zoning approval

• pre-sell 6 homes

Page 39: Redfield to Redevelopment Libertyville, Illinois

• Purchase property with cash

• Investor requirements

• zoning approval

• pre-sell 6 homes

• Secure bank construction financing on

individual homes (same bank that

foreclosed on property)

HOW DID WE DO IT?

How was the project financed?

Page 40: Redfield to Redevelopment Libertyville, Illinois

Real Estate 101

HOW DID WE DO IT?

Page 41: Redfield to Redevelopment Libertyville, Illinois

Location, Location, Location

Real Estate 101

HOW DID WE DO IT?

Page 42: Redfield to Redevelopment Libertyville, Illinois

Real Estate 102

HOW DID WE DO IT?

Page 43: Redfield to Redevelopment Libertyville, Illinois

Marketing, Marketing, Marketing

Real Estate 102

HOW DID WE DO IT?

Page 44: Redfield to Redevelopment Libertyville, Illinois

Big Idea #2

HOW DID WE DO IT?

Page 45: Redfield to Redevelopment Libertyville, Illinois

Sarah Susanka and Not So Big

HOW DID WE DO IT?

Page 46: Redfield to Redevelopment Libertyville, Illinois

What’s the attraction of big?

HOW DID WE DO IT?Sarah Susanka and Not So Big

Page 47: Redfield to Redevelopment Libertyville, Illinois

It’s a quality, not a quantity!

The feeling of “Home”has almost nothing to do with size

HOW DID WE DO IT?Sarah Susanka and Not So Big

Page 48: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Sarah Susanka and Not So Big

Page 49: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Sarah Susanka and Not So Big

Page 50: Redfield to Redevelopment Libertyville, Illinois

Not So Big Showhouse

Grand Opening held November 19, 2011

Open 12 weekends for 10 hours per weekend

5,350 visitors to date

Average of 1 visitor every 1.3 minutes

HOW DID WE DO IT?Sarah Susanka and Not So Big

Page 51: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Selling Approach

Page 52: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Selling Approach

Page 53: Redfield to Redevelopment Libertyville, Illinois

Selling Approach

• Design Meeting #1 – “How do you live?”

• It’s personal

• A home is the ultimate Consumer Product

• Controlled customization

HOW DID WE DO IT?

Page 54: Redfield to Redevelopment Libertyville, Illinois

Retain top local Realtor

HOW DID WE DO IT?Marketing, Marketing, Marketing

Page 55: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Marketing, Marketing, Marketing

Page 56: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Marketing, Marketing, Marketing

Page 57: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Marketing, Marketing, Marketing

Page 58: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Marketing, Marketing, Marketing

PBS Nightly Business Report: Broken Developments / Redfield Sites

Page 59: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Marketing, Marketing, Marketing

Page 60: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Marketing, Marketing, Marketing

Page 61: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Marketing, Marketing, Marketing

Page 62: Redfield to Redevelopment Libertyville, Illinois

HOW DID WE DO IT?Marketing, Marketing, Marketing

Page 63: Redfield to Redevelopment Libertyville, Illinois

Marketing, Marketing, Marketing

HOW DID WE DO IT?

Page 64: Redfield to Redevelopment Libertyville, Illinois

WHY DID IT WORK?

• Public / Private Partnership

• Downtown Libertyville Location

• Emotional Connection / Selling Approach

• Create Great Product unlike anything else in the market

• Marketing, Marketing, Marketing

• Deliver the Ultimate Consumer Product

Page 65: Redfield to Redevelopment Libertyville, Illinois

WHAT’S NEXT?

SCHOOL STREET

Page 66: Redfield to Redevelopment Libertyville, Illinois

WHAT’S NEXT?

SCHOOL STREET

Page 67: Redfield to Redevelopment Libertyville, Illinois

QUESTIONS?