RECYCLING OF WASTEWATER
IN URBAN SECTOR AS
DEMAND MANAGEMENT
TOOL Dr. U. D. Kulkarni
Chairman Indian Water Works Association Aurangabad Centre
Earlier worked as Associate Professor in Civil Engineering
SGGS Institute of Engineering and Technology Nanded
9-8-2016
UDK Nanded 1
Water Issues in Urban areas
9-8-2016 UDK Nanded
2
Water scarcity
Water conflict
Long distance transport-National Water Policy
ULB unable to provide water
Population density – high rise buildings
Stress on infrastructure
Sustainability
9-8-2016 UDK Nanded
3
Technology- affordable, flexible, people centric,
behaviour aspects
Resources - enough
Economics- willingness to pay on continuous basis
Dynamic situation- changing scenario
Water governance- UNESCO publication
Water
9-8-2016 UDK Nanded
4
Demand management
Demand side management
Variable pricing
Why reuse, recycling in urban sector?
WATER BALANCE PER DAY BASIS DURING NON-MONSOON SEASON
Total water requirement = 704
Treated sewage available for recycling = 242 [Treated sewage from STP of building 3 & ( building 4 (wing A,B, C, D, E,F & G)].
After recycling treated sewage for gardening (61) and flushing (117) [Treated sewage would be used for flushing requirement for building 3 & ( building 4 (wing A,B, C, D, E,F & G)]
Hence Net water requirement = 526 Source: From M.C.G.M and Tanker water of potable quality
Reduction in Net water Demand = 25 %
9-8-2016 UDK Nanded
5
All quantities are in KLD
Building 1,2,3 (A & B)
Gardening
= 61
Sewage: 287
Domestic
= 221 Flushing
= 110
61
Swimming pool =
4
From Tanker water of
potable quality= 4 From M.C.G.M
= 166
Sewage: 218
Treatment in STP
(** Available for recycling 196)
Domestic
= 166
Flushing
= 85
85
Bldg No 4 (A,B, C, D, E,F & G)
Excess 50 shall be disposed to
municipal sewer line To municipal sewer line
Building 3C
Sewage: 52
Treatment in STP
(** Available for recycling 46)
Domestic
= 25 Flushing
= 32
Excess 14 shall be disposed to
municipal sewer line
32
From M.C.G.M
= 25
From M.C.G.M
= 331
Capacity 240 KL
Techno. Moving Bed Bio-Reactor (MBBR) Technology
Details MBBR is based on the fixed film attached growth biological system. The moving media provided is small circular ring with
Polypropylene (PP) media will be provided in the tank for bacterial slime growth on its surface.
Primary treatment:
Bar Screen
Oil & Grease Trap
Raw Collection tank
Raw Sewage Transfer
pumps
Secondary treatment:
MBBR Bioreactor
Secondary Clarifier/Settling
Sludge Dewatering System-
(Filter press)
Tertiary treatment:
Filter feed tank
Pressure Sand Filter
Activated Carbon
Filter
UV system
Outlet
Characteristic pH : 6.5 to 7.5, Total Suspended Solids : <10 mg/lit., Chemical Oxygen Demand (COD) :
<30,mg/lit. Biological Oxygen Demand (BOD) : <10 mg/lit., Oil & Grease : <5 mg/lit.
TECHNICAL DETAILS OF STP
BAR
SCREEN
OIL &
GREASE
TRAP
RAW
COLLECTION
TANK
AERATION
TANK
(MBBR)
SECONDAR
Y
CLARIFIER
/SETTLING
FILTER
FEED TANK
PSF ACF UV SYSTEM
TREATED
WATER
TANK
RAW WASTEWATER
TRANSFER PUMP
SLUDGE RECYCLE
PUMP
FILTER
PRESS EXCESS SLUDGE
FLUSHING &
GARDENING
FILTER
FEED
PUMP 9-8-2016 UDK Nanded
6
WATER BALANCE PER DAY BASIS DURING MONSOON SEASON
Total water requirement = 643
Treated sewage available for recycling = 242 [Treated sewage from STP of building 3 & ( building 4 (wing A,B, C, D, E,F & G)].
After recycling treated sewage for flushing (117)
[Treated sewage would be used for flushing requirement
From RWH = 33 Hence Net water requirement = 493 Source: From M.C.G.M and Tanker water of potable quality
Reduction in Net water Demand = 23 %
Ref.:
Criteria For Occupancy Load : National Building Code (NBC) -2005 – Part 4, Page 27, Occupant Load
Criteria For Water Requirement : National Building Code (NBC) -2005 – Part 9, Page 19, Water Requirement
9-8-2016 UDK Nanded
7
All quantities are in KLD
Building 1,2,3 (A & B)
Sewage: 287
Domestic
= 221 Flushing
= 110
Sewage
Swimming pool =
4
From M.C.G.M.: 133
RWH: 33
Sewage: 218
Treatment in STP
(** Available for recycling 196)
Domestic
= 166
Flushing
= 85
85
Bldg No 4 (A,B, C, D, E,F &G)
Excess 111 shall be disposed to
municipal sewer line To municipal sewer line
Building 3C
Sewage: 52
Treatment in STP
(** Available for recycling 46)
Domestic
= 25 Flushing
= 32
Sewage
Excess 14 shall be disposed to
municipal sewer line
32
From M.C.G.M
= 25 From M.C.G.M = 331
From Tanker water of
potable quality= 4
Cases from Thane, Palghar, Vasai
9-8-2016 UDK Nanded
8
Project proponent has to ensure source of water
Drainage arrangement
Vasai-Virar population 11 lac
New project population 0.9 lac
Rs 70 million STP- Recycling is to the tune of 35%
Impact on water source and sewer line?
ULB is not ready to accept their wastewater in the
drain, sewer line is not ready
Cases from Thane, Palghar, Vasai
9-8-2016 UDK Nanded
9
Temghar (Bhivandi)
500 KLD STP, Rs 12.5 million cost, Phytorid
technology+ MBBR Rs 8 million
Rs 30 lac O&M annual
Nalla nearby BOD 250 ppm
Treated sewage BOD 10 ppm
Dilution
Recycling is to the tune of 35%
Cases from Thane, Palghar, Vasai
9-8-2016 UDK Nanded
10
Nilemore- Magnum home project in Vasai Virar MC
Nearby nalla 90 ppm BOD
No sewer line
BOD of treated sewage 10ppm
After recycling excess discharged in nalla
Recycling is to the tune of 35%
Cases from Thane, Palghar, Vasai
9-8-2016 UDK Nanded
11
Ultratech project 605 KLD, population 8337
Palghar Municipal council
Small ULB can not sustain such project
Conditional permission
Recycling to the tune of 30-35%
Cases from Thane- Shahapur
9-8-2016 UDK Nanded
12
Village Malegaon can not sustain big projects
Deepjyoti real estate
Conditional permission –water infrastructure to be
developed/strengthened by PP
345 row houses, 220 KLD supply, 230 KLD STP
Recycling 50%
Excess sewage where to discharge?
IT park in Airoli
9-8-2016 UDK Nanded
13
Reliable Tech Park
237629 sq m. Water requirement 1105 KLD
Recycling 610 KLD, Net reqirement 495 KLD
Demand reduction 55%
It is in MIDC
Treated sewage BOD less than 10 ppm
It can be used in MIDC industrial use, cooling
requirement
9-8-2016 UDK Nanded
14
Newa Bhakti Knowledge City
MIDC, Airoli, District-Navi Mumbai.
The total water requirement of
the project will be 510 m3/day.
The water supply will be received
from MIDC.
The fresh water requirement will
be reduced by the recycling of
450 m3/day.
Individual water meters for shops, offices and flats
in each Financial, IT & residential buildings.
9-8-2016
15
UDK Nanded
Water balance diagram Newa Bhakti Knowledge City
9-8-2016 UDK Nanded
16
Water balance
9-8-2016 UDK Nanded
17
Dry Season Wet Season
Total water budget 510 510
Fresh water requirement 342 342
Human contact 342 342
Non-human contact 168 168
Gardening 28 14
Vehicle washing 6 6
HVAC make up 247 247
Losses (total) & sludge 65 65
Sewage generation 459 459
Treated water 450 450
Water recycled 450 435
Excess to drain 0 15
% recycled 88 85
Treated wastewater reuse
9-8-2016 UDK Nanded
18
Treated water reuse
Sr. Treated water reuse Dry season
Quantity (m3/day) Wet season
Quantity (m3/day)
1. Flushing 168 168
2. Gardening 28 14
3. Vehicle washing 6 6
4. HVAC make up 247 247
STP area 460 m2
STP capacity 460 m3/day
Rain Water Harvesting as tool
Project
proponents are
doing RWH to
satisfy the
requirement.
View point
Look at it as
demand
management tool
9-8-2016
19
UDK Nanded
Rain water harvesting:
Rainwater harvesting can serve as a solution to the water problem in the
area during water crises by capturing the runoff. Rainwater harvesting helps in utilizing the primary source of water and prevents the runoff from
going into sewer or storm drains, thereby serving a dual purpose: making water available for future use and reducing the load on treatment plants.
9-8-2016 UDK Nanded 20
Table 2.12: Size of RWH Tanks
Type of building Size of RWH
Financial 205 m3/day
IT 420 m3/day
Residential 152 m3/day
Total 777 m3/day
New techniques
9-8-2016 UDK Nanded
21
Demand Side Management
Water Demand Management
NEWater project in Singapore
Now SCE is partnering with BWSSB for reuse project
SCE contribution 756890 SGD, BWSSB contribution 263346 SGD in Bangalore
Water leakage manual- WHO, IWWA
Learning lesson from leaders
9-8-2016 UDK Nanded
22
CH2M Water Industry Award 2015: www.siwi.org
Long story 1965 to 2015
Research for public acceptance
Technology improvement
Stakeholder participation
9-8-2016 UDK Nanded
23
PP will maintain for 5 years
Corpus fund for 5 years
There after residents have to take responsibility
Sustainable management of STP for reuse and recycling
Per person O&M annual cost around Rs 1500
Maintenance of STP is the solution- Implementation, Monitoring, Regular Reports, Improving technologies in response to feedback, people centric
Suggestions
9-8-2016 UDK Nanded
24
Demand management
Research in wastewater treatment
Wastewater as alternative source of water
Central Govt- schemes integrated proposal for water and wastewater together
Encouragement to PP
Publish case studies to replicate, like Suryapet
Reduce stress on natural resources/environment
Sustainable solution