Recent cross-wiring issue and implication

for circuits protection 

Bozhidar Panev TE-MPE-CP 14.04.2011

Page 2: Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP 14.04.2011.

Short chronology of the event from 07.04.2011 • FPA during pre-cycle on RB.A45 at 07:12:09.270

• Energy was extracted without problems. Current in main circuit – 2349A

• The origin of the trip was found:– DQQDC board_A detected: U_HTS = 3mV and open the

quench loop. U_RES in the same moment was ~20mV (threshold 100mV)

• The new feature recently introduced in main current lead protection units toggles detector boards (every 25s) allowing to record U_HTS and U_RES also for the redundant channel (board_B)

Page 3: Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP 14.04.2011.

Short chronology of the event from 07.04.2011 • Unusual behavior has been pointed out between board A

and B in respect of U_HTS.

• Both two boards were checked through QPS Test Mode, simulating a voltage rise on the HTS and/or Resistive part

• Correct performance observed of board A and B

• Analysis of the event’s data and results from Test Mode bring the conclusion of abnormal behavior of U_HTS concerning board_B– Eventual short in the cable or inverted pins (Hypothesis

of Reiner)– Giorgio also assured no errors found between PE and

cold part of leads during ELQA campaign

Page 4: Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP 14.04.2011.

U_HTS Signals for CL3 and CL4

A

B

A

BA

B

A

W r o n g b e h a v i o r o f U _ H T Sm e a s u r e d b y b o a r d B

E x c e l l e n t p r f o r m a n c eo f b o a r d _ A ( t h r e s h o l d 3 m V )

Page 5: Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP 14.04.2011.

What was wrong?• Intervention in the Tunnel to check the cabling and discover what

was wrong• Cable patch - correct• The Error was found in connector P60 of cable between QPS crate

and Proximity cable patch. Pin 15(EE22) and 16(EE42) were inverted.

Page 6: Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP 14.04.2011.

What was measured?

Page 7: Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP 14.04.2011.

Verification for correct wiring of 13kA circuits (RB,RQD,RQF)

• Due to the available acquisition data from boards A and B. It became possible to check by TIMBER the rest RB, RQD/F circuits for swapped pins.

• The only what was necessary to be done was take a look and check how U_HTS and U_RES behave during the rump.

U_HTSBoard_A

I_MEASU_HTSBoard_B

Page 8: Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP 14.04.2011.

U_HTS Signals for CL3 and CL4 of DFLAS.7L5

• Normal behavior of U_HTS of CL3

• U_HTS stay flat during the rump - indication for problem

Page 9: Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP 14.04.2011.

Verification for correct wiring of all IPDs, IPQs and ITs circuits – 08th of April

• A dedicated PNO.a7 which does unbalanced powering was carried out over all IPQs.

• As no automatic swap between boards. The test has been done twice. Once at board_A and second at board_B.

• For IPDs and ITs a manual rump was done.

• Difficulties that were found:– When tried to switch to board_B, some B_board did

not give power permit (13 circuits). It has required a local power-cycle.

– The analysis of U_HTS signals

Page 10: Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP 14.04.2011.

Criteria for correct wiring of IPQs, IPDs and ITs

• Resistive part of leads during asymmetric powering of RQ.8R1

• HTS part of leads during asymmetric powering of RQ.8R1

• Verification of U_RES and U_HTS for all IPDs, IPQS, ITs– Done for board A and B

Page 11: Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP 14.04.2011.

Conclusion 8th of April

• On Thu 7th of April all 13kA circuits were checked for correct wiring.

• On Fri 8th April all IPDs, IPQs, ITs also pased verification.

• 600A were not checked because its were checked by QPS team before with a correct procedure and dedicated tester – all tests are documented

• Green light for powering has been given