RECAPP Facility Evaluation Report - Alberta · Construction Year: 1983 Evaluation Date: July 5 2007...
Transcript of RECAPP Facility Evaluation Report - Alberta · Construction Year: 1983 Evaluation Date: July 5 2007...
Report run on: July 17, 2008 4:00 PM
RECAPP Facility Evaluation Report
Our Lady Of The Prairies Catholic Elementary School
B3241AEdmonton
Edmonton RCSSD #7
Report run on: July 17, 2008 4:00 PM Page 2 of 39
B3241ABuilding Id:
Our Lady Of The Prairies CathBuilding Name:
EdmontonLocation:17655 - 64 Avenue Address:
2,943.42Gross Area (sq. m): $6,415,103Replacement Cost:1983Construction Year:
Evaluation Date: July 5 2007
Asset Evolution Incorporated (AEI)Evaluation Company:
Mario PlastinaEvaluator Name:
Our Lady of the Prairies Catholic Elementary School is a one-storey school with a mechanical penthouse and a totalbuilding area of 2944 m2. The school was built in 1984 with an area of 2357m2. A cluster of six portables were added atthe west end of the school with a total area of 587m2. The age of the portables vary from 1982 to 2005. The one storey school comprised of several classrooms, a gymnasium, a library and a computer room. The 2007 student enrollment is 311 children.
General Summary:
Structural Summary:The foundations consist of cast-in-place concrete grade beams and spread footings. The original building has cast-in-placeconcrete slabs-on-grade with conventional steel reinforcement. The roof comprises of a metal roof deck with steel structuresupported by exterior & interior concrete walls. The structural walls and columns are concrete block walls or poured in placeconcrete. Overall the structural elements are in acceptable condition.
Envelope Summary:The exterior cladding consists primarily of brick with metal siding above the perimeter of the school. The exterior windowunits are aluminum frame with fixed and awning type units. The majority of the exterior doors are painted metal doorswith metal frames. The original roof covering is a built-up roof assembly. The roof is currently being replaced with an SBSroof assembly ( spring 2007) Overall, the envelope of the building is in acceptable condition.
Interior Summary:Sheet Vinyl is located throughout the corridors, computer room, ancillary room and classrooms. Ceramic tile is locatedthroughout the washrooms. The administration area, music room and library have a carpet floor finish. The gymnasiumarea has a parquet hardwood floor finish. The majority of the utility areas and mechanical rooms have a paint finish onthe concrete slab. The majority of the interior walls are painted concrete block walls. The majority of the school has asuspended 2'x4' acoustical tile ceiling. The steel structure is painted and exposed in the gymnasium. Overall, the interior finishes are in acceptable condition.
Mechanical Summary:There are no elevators in the building. A platform type stair lift provides handicap access to the raised floor level of room109 at the southeast corner of the school. There is also an overhead beam lift in the handicap accessible washroom. The building is heated by two gas fired glycol/hot water boilers which supply a glycol/hot water distribution system whichincludes finned tube radiation cabinets, two convectors, 13 unit heaters, six reheat coils and three air handling unitheating coils (the heating system was originally designed as a hot water system, but due to freezing problems the heattransfer fluid was changed to a glycol/water mixture). There are three air handling units which are mixed air systems;AS1 is the general supply unit for the west wing of the school, AS2 is the general supply unit for the east wing of theschool, and AS3 supplies the gymnasium. The fresh air supplied to the building by the air handling units is balanced bythe exhaust air flow from the air handling units and from approximately 13 sanitary and general exhaust fans. BuildingHVAC controls are pneumatic and the control air supply system includes two air compressors mounted on a receivertank and a refrigerated air dryer. There is a Building Management and Control System (BMCS) providing HVAC systemcontrol and monitoring functions (Andover model AC256M Plus).
9.22%5 year Facility Condition Index (FCI):
Facility Details Evaluation Details
Total Maintenance Events Next 5 years: $591,654
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Report run on: July 17, 2008 4:00 PM Page 3 of 39
There are two sets of boy's and girl's washrooms in the building. In addition, there are two individual staff washrooms, awashroom in the infirmary and a handicap accessible washroom. Standard washroom fixtures include floor mountedflush valve type toilets, counter mounted and wall mounted lavatories, and wall mounted flush valve type urinals. Otherplumbing fixtures in the building include drinking fountains in the corridors, a mop sink, a laundry tub, and stainless steelsinks in some of the classrooms, the kitchen, and in the staff room. Fire protection for the building consists of cabinet mounted and wall mounted fire extinguishers. No major mechanical equipment or systems require immediate replacement or upgrading, other than the Andoverbuilding automation system which is obsolete (difficulties have been reported in obtaining replacement parts). Overall,the building mechanical equipment and systems are in acceptable condition.
Electrical Summary:Our Lady of the Prairies School is fed with an incoming 120/208V three phase, 4 wire system from an EPCORpadmounted transformer, located on the school grounds. The main switchboard is rated at 800A, 120/208V. There is aMotor Control Centre and individual motor starters for the major mechanical equipment. The wiring in the building is typically standard wiring in conduit. The interior fluorescent lighting fixtures have T-12 lamps and magnetic ballasts. The exit lighting in the original buildingconsists of units with incandescent lamps. The emergency lighting is provided from emergency lighting battery packs.The exterior lighting consists of wall mounted H.P.S. Fixtures and some incandescent downlights in the canopies. The building is equipped with a Simplex 2001 fire alarm system. Detection and end devices include, smoke and heatdetectors, bells and pull stations. The various communications and security systems within the school include; a security system that monitors motiondetectors, a Telecor P.A. system and a Nitsuko telephone system. Data systems are installed within the school. It is recommended, as routine maintenance, that a program for annual examination of major electrical components beinstituted. Maintenance should include thermographic scans for hot spots and power shut down to allow examination ofinterior components for accumulated debris and signs of corrosion. Based on the condition of the electrical systems the following replacements are scheduled for replacement during theyears 2007 to 2011. - Replace the Simplex 2001 Fire Alarm system - Retrofit the exit signs - Replace the emergency lighting battery units Consideration should be given to upgrading the existing lighting with more energy efficient lighting and upgrading thelighting in the gymnasium. Overall the electrical components for Our Lady of the Prairies School are in acceptable condition.
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Condition Rating Performance1 - Critical Unsafe, high risk of injury or critical system failure.2 - Poor Does not meet requirements, has significant deficiencies. May have high operating/maintenance costs.
3 - Marginal Meets minimum requirements, has significant deficiencies. May have above average operating maintenance costs.4 - Acceptable Meets present requirements, minor deficiencies. Average operating/maintenance costs.
Rating Guide
5 - Good Meets all present requirements. No deficiencies.6 - Excellent As new/state of the art, meets present and foreseeable requirements.
Report run on: July 17, 2008 4:00 PM Page 4 of 39
A1010 Standard Foundations - 1983 Section*
A1030 Slab on Grade - 1983 Section*
B1010.01 Floor Structural Frame (Building Frame) - 1983 Section*
B1010.02 Structural Interior Walls Supporting Floors (or Roof) - 1983 Section*
B1010.09 Floor Construction Fireproofing - 1983 Section*
B1010.10 Floor Construction Firestopping - 1983 Section*
B1020.01 Roof Structural Frame - 1983 Section*
5 - Good
5 - Good
5 - Good
5 - Good
4 - Acceptable
4 - Acceptable
5 - Good
Rating
Rating
Rating
Rating
Rating
Rating
Rating
1983
1983
1983
1983
1983
1983
1983
Installed
Installed
Installed
Installed
Installed
Installed
Installed
100
100
100
100
50
50
100
Design Life
Design Life
Design Life
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Updated
Updated
Updated
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
S1 STRUCTURAL
The foundations consist of cast-in-place concrete grade beams and spread footings.
The building has cast-in-place concrete slabs-on-grade with conventional steel reinforcement.
Concrete structural flat slab supported by poured concrete & concrete block walls
Structural reinforced concrete block walls
Metal roof deck with steel structure supported by exterior & interior concrete walls.
Report run on: July 17, 2008 4:00 PM Page 5 of 39
B1020.06 Roof Construction Fireproofing - 1983 Section*
4 - AcceptableRating
1983Installed
50Design Life
JUL-07Updated
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Report run on: July 17, 2008 4:00 PM Page 6 of 39
B2010.01.02.01 Brick Masonry: Ext. Wall Skin - 1983 Section*
B2010.01.06.03 Metal Siding**
B2010.01.09 Expansion Control: Exterior Wall Skin - 1983 Section*
3 - Marginal
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
1983
1983
1983
Installed
Installed
Installed
75
40
75
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Repair - Displacement of brick wall on the NorthElevation
Replace Metal Siding Panels - 1983 Section
Repair
Lifecycle Replacement
2008
2023
$22,880
$160,160
Medium
Unassigned
The brick wall has shifted at the vertical brick joint along thenorth exterior wall
Concern:
Repair exterior brick wall.Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
S2 ENVELOPE
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
APR-08
APR-08
Brick is located around the lower portion of the exterior perimeter walls.
Painted metal siding is located on the upper portion of the exterior gym walls and above the brick assembly. Sloped metalsiding is located above each building entrance.
Expansion/control joints are located throughout the cladding assembly.
Shifted brick wall - North elevation
Report run on: July 17, 2008 4:00 PM Page 7 of 39
B2010.01.11 Joint Sealers (caulking): Ext. Wall - 1983 Section**
B2010.01.13 Paints (& Stains): Exterior Wall - 1983 Section**
B2010.03 Exterior Wall Vapor Retarders, Air Barriers, and Insulation - 1983 Section*
3 - Marginal
3 - Marginal
4 - Acceptable
Rating
Rating
Rating
1983
1983
1983
Installed
Installed
Installed
20
15
100
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Replace exterior joint sealant
Repaint exterior metal siding
Failure Replacement
Failure Replacement
2008
2008
$28,600
$34,320
Low
Low
The sealant around the exterior doors and windows is brittleand deteriorated.
The paint finish is worn and deteriorated.
Concern:
Concern:
Replace all joint sealant around doors and windows.
Repaint all exterior metal siding.
Recommendation:
Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
APR-08
APR-08
Sealant is located around all window, door and exterior cladding assemblies.
The metal siding located on the upper portion of the exterior gym walls and above the brick assembly is pre-finished withpaint.
Report run on: July 17, 2008 4:00 PM Page 8 of 39
B2010.06 Exterior Louvers, Grilles, and Screens - 1983 Section*
B2010.09 Exterior Soffits - 1983 Section*
B2020.01.01.02 Aluminum Windows (Glass & Frame)**
B2030.01.02 Steel-Framed Storefronts: Doors**
B3010.01 Deck Vapor Retarder and Insulation - 1983 Section*
4 - Acceptable
5 - Good
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
Rating
1983
1983
1983
1983
1983
Installed
Installed
Installed
Installed
Installed
50
50
40
30
25
Design Life
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Updated
Replace Aluminum Windows
Replace Entrance Doors - 1983 Section
Lifecycle Replacement
Lifecycle Replacement
2023
2013
$91,520
$50,336
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
APR-08
APR-08
Exterior metal louvres are located on the upper portion of the exterior walls.
The exterior soffits above each entrance has a painted exterior gypsum board finish.
The windows are aluminum frame double glazed operable awning units.
The majority of the entrance doors are painted metal doors in a painted steel frame. There are approximately 11 entrancedoors.
Report run on: July 17, 2008 4:00 PM Page 9 of 39
B3010.04.04 Modified Bituminous Membrane Roofing (SBS)**
B3020.02 Other Roofing Openings (Hatch,Vent, etc) - 1983 Section*
5 - Good
4 - Acceptable
Rating
Rating
2007
1983
Installed
Installed
25
25
Design Life
Design Life
JUL-07
JUL-07
Updated
Updated
Replace SBS roof assembly
Lifecycle Replacement 2032 $320,320 Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Type Year Cost Priority
Updated: APR-08
The original school had a built-up bituminous roofing assembly and has been replaced with an SBS roof system.
There is one metal roof hatch that provides access to the roof.
Report run on: July 17, 2008 4:00 PM Page 10 of 39
C1010.01.03 Unit Masonry Assemblies: Partitions -
C1010.01.07 Framed Partitions (Stud) -
C1010.05 Interior Windows - *
C1010.07 Interior Partition Firestopping - *
C1020.01 Interior Swinging Doors (& Hardware) - *
C1020.03 Interior Fire Doors - *
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
5 - Good
5 - Good
Rating
Rating
Rating
Rating
Rating
Rating
1983
1983
1983
1983
1983
1983
Installed
Installed
Installed
Installed
Installed
Installed
100
100
80
50
40
50
Design Life
Design Life
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Updated
Updated
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
S3 INTERIOR
Interior partitions typically consist of masonry block walls.
Interior partitions between classrooms are typically gypsum board partitions.
Fixed interior glazed windows with GWG are located in the general office area.
The interior swing doors generally consist of painted solid core wood doors in painted metal frames. Some of the utilityrooms & corridors are labeled indicating fire rated doors.
Fire doors are located in the common area corridors between the original building and the portable link. The majority of thedoors are rated and labeled.
Report run on: July 17, 2008 4:00 PM Page 11 of 39
C1030.01 Visual Display Boards - **
C1030.02 Fabricated Compartments(Toilets/Showers) - **
C1030.08 Interior Identifying Devices - *
C1030.10 Lockers**
5 - Good
4 - Acceptable
5 - Good
5 - Good
Rating
Rating
Rating
Rating
2006
1983
1983
2000
Installed
Installed
Installed
Installed
20
30
20
30
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Replace Visual Display Boards
Replace Toilets/Showers Stalls
Replace Metal Lockers
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
2026
2013
2030
$45,760
$16,016
$45,760
Unassigned
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Event:
Type
Type
Type
Year
Year
Year
Cost
Cost
Cost
Priority
Priority
Priority
Updated:
Updated:
Updated:
APR-08
APR-08
OCT-07
Tackboards and whiteboards are located in each classroom area.
Painted metal washroom stall partitions are located in each boy's & girls washroom.
The room number or room name is mounted on or above the interior doors.
Prefinished metal lockers are located in the main corridor.
Report run on: July 17, 2008 4:00 PM Page 12 of 39
C1030.12 Storage Shelving - *
C1030.14 Toilet, Bath, and Laundry Accessories - *
C2010 Stair Construction*
C2020.05 Resilient Stair Finishes**
C2020.08 Stair Railings and Balustrades*
C3010.06 Tile Wall Finishes - Ceramic tile**
5 - Good
4 - Acceptable
5 - Good
5 - Good
5 - Good
5 - Good
Rating
Rating
Rating
Rating
Rating
Rating
1983
1983
1983
1983
1983
1983
Installed
Installed
Installed
Installed
Installed
Installed
30
20
100
20
40
40
Design Life
Design Life
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Updated
Updated
Replace Ceramic Wall Tile
Lifecycle Replacement 2024 $17,160 Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Type Year Cost Priority
Updated: APR-08
Metal storage shelving throughout custodial utility rooms and staff supply rooms
The washrooms are equipped with typical washroom accessories: Paper towel dispensers, toilet paper dispensers, hand-soap dispensers, waste bins and mirrors.
The stairs leading to the mechanical room and music room are framed in wood construction.
The stairs leading to the mechanical room and music room are finished in rubber.
Painted steel handrails are provided at stairs to the music room and mechanical penthouse.
Ceramic wall tile is located in the boy's washroom areas.
Report run on: July 17, 2008 4:00 PM Page 13 of 39
C3010.09 Acoustical Wall Treatment - **
C3010.11 Interior Wall Painting - *
C3020.01.02 Paint Concrete Floor Finishes*
C3020.02 Tile Floor Finishes - **
5 - Good
4 - Acceptable
5 - Good
5 - Good
Rating
Rating
Rating
Rating
2006
1983
2000
1983
Installed
Installed
Installed
Installed
20
15
10
50
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Replace Acoustical Wall Treatment
Replace Ceramic Tile
Lifecycle Replacement
Lifecycle Replacement
2026
2033
$50,062
$40,040
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
APR-08
APR-08
Acoustical wall panels are located throughout the upper portion of the library and room 109.
The interior partitions throughout the school have a paint finish.
Painted/sealed concrete floors are located in the mechanical room and utility rooms.
Ceramic/Quarry floor tile is located in the washroom and vestibule areas
Report run on: July 17, 2008 4:00 PM Page 14 of 39
C3020.04 Wood Flooring**
C3020.07 Resilient Flooring - **
C3020.08 Carpet Flooring - **
C3030.06 Acoustic Ceiling Treatment (Susp.T-Bar) - **
4 - Acceptable
4 - Acceptable
5 - Good
5 - Good
Rating
Rating
Rating
Rating
1983
1983
2006
1983
Installed
Installed
Installed
Installed
30
20
15
25
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Replace hardwood flooring
Replace Sheet Vinyl
Replace Carpet Flooring
Replace Acoustic Ceiling Tiles (2200SM)
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
2013
2012
2016
2012
$62,920
$114,400
$13,728
$137,280
Unassigned
Unassigned
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Event:
Event:
Type
Type
Type
Type
Year
Year
Year
Year
Cost
Cost
Cost
Cost
Priority
Priority
Priority
Priority
Updated:
Updated:
Updated:
Updated:
APR-08
APR-08
APR-08
APR-08
Parquet hardwood flooring in located in the gymnasium.
Sheet vinyl is located throughout the majority of the classrooms and corridors. VCT is located in isolated areas.
Carpeting is located in the office areas, room 109 and library.
The majority of the ceilings have a 2'-0"x4'-0"suspended acoustical tile assembly.
Report run on: July 17, 2008 4:00 PM Page 15 of 39
C3030.07 Interior Ceiling Painting - *
D1010.02 Lifts**
5 - Good
4 - Acceptable
Rating
Rating
1983
2003
Installed
Installed
20
25
Design Life
Design Life
JUL-07
JUL-07
Updated
Updated
Replace Lifts in Music Room
Lifecycle Replacement 2028 $28,600 Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Type Year Cost Priority
Updated: OCT-07
All the gypsum board and exposed steel structures have a paint finish.
A lift is located in the music room.
Report run on: July 17, 2008 4:00 PM Page 16 of 39
D2010.04 Sinks - **
D2010.05 Showers - **
D2010.08 Drinking Fountains / Coolers - **
4 - Acceptable
5 - Good
4 - Acceptable
Rating
Rating
Rating
1983
1983
1983
Installed
Installed
Installed
30
30
35
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Replace ten sinks (in the janitor's closet, staffroom, kitchen and rooms 100, 102, 103, 104, 105,107 and 109)
Replace shower (located on the east side of thegymnasium)
Replace three drinking fountains (in the east, northand west corridors)
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
2013
2013
2018
$13,728
$4,004
$3,432
Unassigned
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
S4 MECHANICAL
Event:
Event:
Event:
Type
Type
Type
Year
Year
Year
Cost
Cost
Cost
Priority
Priority
Priority
Updated:
Updated:
Updated:
APR-08
APR-08
APR-08
There are approximately ten sinks in the building including a janitor's mop sink in the janitorial storage room, a laundry tubin room 107, and stainless steel general purpose sinks in the staff room, the kitchen and rooms 100, 102, 103, 104, 105and 109.
There is one shower stall located in a small room off the gymnasium on the east side.
There are approximately three drinking fountains in the building. The drinking fountains are generally wall mounted vitreouschina units and do not include coolers.
Report run on: July 17, 2008 4:00 PM Page 17 of 39
D2010.10 Washroom Fixtures (WC, Lav, Urnl) - Counter Mounted Lavatories**
D2010.10 Washroom Fixtures (WC, Lav, Urnl) - Toilets, Urinals and Wall Mounted Lavatories**
3 - Marginal
4 - Acceptable
Rating
Rating
1983
1983
Installed
Installed
35
35
Design Life
Design Life
JUL-07
JUL-07
Updated
Updated
Replace 17 counter mounted lavatories
Replace 35 washroom fixtures (approx. 25 toilets, 3wall mounted lavatories and 7 urinals)
Failure Replacement
Lifecycle Replacement
2009
2013
$32,032
$62,920
Low
Unassigned
The counter mounted lavatories are enameled steel and someof the lavatories are chipped.
Concern:
Replace the counter mounted enameled steel lavatories withcounter mounted stainless steel lavatories.
Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
SEP-07
APR-08
There are two sets of boy's and girl's washrooms in the building, one set on the north side of the gymnasium and one set onthe west side of the gymnasium. In addition, there are two staff washrooms, a washroom in the infirmary and a handicapaccessible washroom. Plumbing fixtures in the boy's and girl's washrooms include floor mounted flush valve type toilets,counter mounted enameled steel lavatories, and wall mounted flush valve type urinals. Plumbing fixtures in the staffwashrooms include floor mounted flush valve type toilets and counter mounted enameled steel lavatories. In the infirmarywashroom, there is a floor mounted flush valve type toilet and a wall mounted vitreous china lavatory, as well as a secondwall mounted vitreous china lavatory in the infirmary. In the handicap accessible washroom, there is a floor mounted flushvalve type toilet and a wall mounted vitreous china lavatory. There are a total of approximately 25 toilets, 20 lavatories (17counter mounted and three wall mounted), and seven urinals in the building.
There are two sets of boy's and girl's washrooms in the building, one set on the north side of the gymnasium and one set onthe west side of the gymnasium. In addition, there are two staff washrooms, a washroom in the infirmary and a handicapaccessible washroom. Plumbing fixtures in the boy's and girl's washrooms include floor mounted flush valve type toilets,counter mounted enameled steel lavatories, and wall mounted flush valve type urinals. Plumbing fixtures in the staffwashrooms include floor mounted flush valve type toilets and counter mounted enameled steel lavatories. In the infirmarywashroom, there is a floor mounted flush valve type toilet and a wall mounted vitreous china lavatory, as well as a secondwall mounted vitreous china lavatory in the infirmary. In the handicap accessible washroom, there is a floor mounted flushvalve type toilet and a wall mounted vitreous china lavatory. There are a total of approximately 25 toilets, 20 lavatories (17counter mounted and three wall mounted), and seven urinals in the building.
Consequences of Deferral:Poor washroom aesthetics and accelerated deterioration of theenameled steel lavatories.
Report run on: July 17, 2008 4:00 PM Page 18 of 39
D2020.01.01 Pipes and Tubes: Domestic Water - *
D2020.01.02 Valves: Domestic Water - **
D2020.01.03 Piping Specialties (Backflow Preventors) - **
4 - Acceptable
4 - Acceptable
3 - Marginal
Rating
Rating
Rating
1983
1983
1983
Installed
Installed
Installed
40
40
20
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Replace the domestic water distribution systemvalves
Install a backflow prevention device on thebuilding domestic water supply
Lifecycle Replacement
Code Upgrade
2023
2008
$25,740
$10,296
Unassigned
Low
Potential contamination of the municipal water supply causedby backflow from the building.
Concern:
Install a backflow prevention device on the building domesticwater supply.
Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
APR-08
OCT-07
The 100 mm diameter domestic water supply to the building enters the library on the north side of the building and isreduced to 50 mm diameter. From the library, the domestic water supply is routed through the ceiling space to the meterroom on the east side of the building where the water meter is located. Domestic water piping is generally copper withbrass valves, and fiberglass insulation is used to prevent heat loss and condensation.
Domestic water system valves include system isolation valves and fixture isolation valves. The domestic water systemvalves are generally brass.
There is no backflow prevention device on the domestic water supply to the building.
Report run on: July 17, 2008 4:00 PM Page 19 of 39
D2020.02.02 Plumbing Pumps: Domestic Water - **
D2020.02.06 Domestic Water Heaters - **
D2020.03 Water Supply Insulation: Domestic - *
D2030.01 Waste and Vent Piping - *
D2040.01 Rain Water Drainage Piping Systems - *
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
Rating
1983
1983
1983
1983
1983
Installed
Installed
Installed
Installed
Installed
20
20
40
50
50
Design Life
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Updated
Replace the DHW circulation pump P7
Replace the domestic hot water heater in thepenthouse mechanical room
Lifecycle Replacement
Lifecycle Replacement
2012
2012
$2,288
$4,576
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
APR-08
APR-08
There is a domestic hot water system circulation pump (P7) which maintains the domestic hot water loop at temperature.
A gas fired domestic hot water heater provides domestic hot water for the building sinks, lavatories and shower. The heateris a GSW model 3G75-270HAN with an input heating capacity of 243,000 Btu/h and a volume of 62 imperial gallons.
Where visible, the domestic water piping is insulated with fiberglass insulation to prevent heat loss and condensation.
Visible waste and vent piping is generally copper with some ABS plastic. Since the building is primarily on one level, mostof the waste piping is below grade and not visible. Larger diameter waste piping (buried) is probably cast iron. The sanitarydrain exiting the building is 150 mm diameter.
Standard roof drains (approximately 16) are used to provide storm water drainage of the roof areas. The storm waterdrainage piping appears to be cast iron. The storm sewer exiting the building is 375 mm diameter.
Report run on: July 17, 2008 4:00 PM Page 20 of 39
D2040.02.04 Roof Drains - *
D3010.02 Gas Supply Systems - *
D3020.02.01 Heating Boilers and Accessories: H.W. - Glycol**
D3020.02.02 Chimneys (&Comb. Air): H.W. Boiler - **
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
1983
1983
1983
1983
Installed
Installed
Installed
Installed
40
60
35
35
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Replace the two heating boilers in the penthousemechanical room
Replace the two boiler discharge stacks
Lifecycle Replacement
Lifecycle Replacement
2018
2013
$62,920
$13,156
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
APR-08
APR-08
Standard roof drains with metal strainers (approximately 16) are used to collect storm water from the roof areas.
The natural gas supply is underground to the building and the gas meter is located in the meter room on the east side of thebuilding. From the meter room, the gas piping to the mechanical penthouse and to the portables runs on the roof. Thenatural gas piping is steel.
The building was designed with a hot water heating system using two hot water boilers to provide hot water for the airhandling unit heating coils, the perimeter radiation cabinets, the reheat coils and the unit heaters. However, due to somefreezing problems, the hot water heating system was filled with a glycol/water mixture. The gas fired heating boilers areRaypak model 1630-WTD boilers with an input heating capacity of 1,630,000 Btu/h each.
The combustion gases from the two hot water boilers discharge through the roof of the mechanical penthouse in separatestacks.
Report run on: July 17, 2008 4:00 PM Page 21 of 39
D3020.02.03 Water Treatment: H. W. Boiler - *
D3040.01.01 Air Handling Units: Air Distribution - **
4 - Acceptable
4 - Acceptable
Rating
Rating
1983
1983
Installed
Installed
30
30
Design Life
Design Life
JUL-07
JUL-07
Updated
Updated
Refurbish the relief air, return air and fresh airdampers on air handling units AS1, AS2 and AS3located in the mechanical penthouse
Replace air handling units AS1, AS2 and AS3 inthe mechanical penthouse
Repair
Lifecycle Replacement
2008
2013
$17,160
$205,920
Medium
Unassigned
The dampers associated with each of the air handling units(relief or exhaust air dampers, return air dampers, and fresh airdampers) are reported to be deficient, in that they do notoperate smoothly or seal properly.
Concern:
Refurbish the air handling unit dampers and actuators.Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
OCT-07
APR-08
Water treatment for the closed loop glycol/hot water heating system consists of manual chemical addition via a pot feeder.In addition, make-up fluid (glycol/water mixture) for the closed loop heating system is premixed in a mixing tank for additionto the system expansion tank when necessary.
There are three constant volume air handling units located in the penthouse mechanical room. Air handling unit AS1 is thegeneral air handling unit for the west wing of the school and it includes a supply fan, a glycol/hot water heating coil, and afilter section. Air handling unit AS2 is the general air handling unit for the east wing of the school and it includes a supplyfan, a glycol/hot water heating coil, and a filter section. Air handling unit AS3 is the gymnasium air handling unit and itincludes supply fan, a glycol/hot water heating coil, and a filter section. All three air handling units are mixed air systemsproviding a mixture of return air and fresh air to the conditioned spaces. Each of the air handling units has an associatedheating coil circulation pump, humidifier and return air fan.
Consequences of Deferral:Poor ventilation system control, inadequate fresh air supply,building pressurization problems and potential coil freezing.
Report run on: July 17, 2008 4:00 PM Page 22 of 39
D3040.01.02 Fans: Air Distribution (Remote from AHU) - *
D3040.01.04 Ducts: Air Distribution - *
D3040.01.07 Air Outlets & Inlets:Air Distribution - *
D3040.03.01 Hot Water Distribution Systems - Glycol**
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
1983
1983
1983
1983
Installed
Installed
Installed
Installed
30
50
30
40
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Replace the glycol/hot water distribution system
Lifecycle Replacement 2023 $217,360 Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Type Year Cost Priority
Updated: APR-08
Air distribution fans other than the air handling unit supply fans include the three return air fans. Return air fan F1 isassociated with air handling unit AS1, return air fan F2 is associated with air handling unit AS2, and return air fan F3 isassociated with air handling unit AS3.
Air distribution ducts include the supply air and return air duct systems for the three air handling units AS1, AS2 and AS3.
Air outlets and inlets include supply air diffusers and return air grilles.
The original hot water heating system now uses a glycol/water mixture for the heat transfer fluid. The glycol/hot waterdistribution system includes all components of the closed loop heating system including piping, valves, piping insulation,piping specialties, circulation pumps, and expansion tanks. There are six hot water circulation pumps including three maincirculation pumps P1, P2 and P3 in the mechanical penthouse, and three coil circulation pumps in the mechanicalpenthouse for the three air handling units (P4 for AS1, P5 for AS2 and P6 for AS3) . The glycol/hot water loop expansiontank is an atmospheric type tank which is located in the mechanical penthouse.
Report run on: July 17, 2008 4:00 PM Page 23 of 39
D3040.04.01 Fans: Exhaust - **
D3040.04.03 Ducts: Exhaust - *
D3040.04.05 Air Outlets and Inlets: Exhaust - *
D3050.02 Air Coils - **
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
1983
1983
1983
1983
Installed
Installed
Installed
Installed
30
50
30
30
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Replace exhaust fans (approx. 13)
Replace three duct mounted hot water reheat coils(HC1 through HC6)
Lifecycle Replacement
Lifecycle Replacement
2013
2013
$27,456
$17,160
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
APR-08
APR-08
There are approximately 13 exhaust fans (F4 through F16) for the building including sanitary and general exhaust fans. Theexhaust fans are generally located in the ceiling space.
Exhaust duct systems include the collection and discharge ducts associated with the 13 exhaust fans.
Exhaust air inlets include the inlet grilles associated with the exhaust system collection ducts and exhaust outlets includethe exhaust system discharge louvres and gooseneck vents.
There are approximately six duct mounted glycol/hot water reheat coils (HC1 through HC6).
Report run on: July 17, 2008 4:00 PM Page 24 of 39
D3050.03 Humidifiers - **
D3050.05.01 Convectors**
D3050.05.03 Finned Tube Radiation - **
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
1983
1983
1983
Installed
Installed
Installed
25
40
40
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Replace the three air handling unit humidifiers(HU1, HU2 and HU3) located in the mechanicalpenthouse
Replace convectors FF1 and FF2 at the entrancevestibule between the school and the portables
Replace the perimeter finned tube radiationcabinets (approx. 200 m)
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
2012
2023
2023
$27,456
$4,576
$102,960
Unassigned
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Event:
Type
Type
Type
Year
Year
Year
Cost
Cost
Cost
Priority
Priority
Priority
Updated:
Updated:
Updated:
APR-08
OCT-07
APR-08
There are three Nortec steam humidifiers (HU1, HU2 and HU3), one for each air handling unit (AS1, AS2 and AS3). TheNortec model ES-400 humidifiers operate electrically and have a capacity of 10 kW.
There are two wall mounted glycol/hot water convectors (force flow units) which provide heating at the entrance vestibulebetween the school and the portables (FF1 and FF2).
The glycol/hot water heating system provides perimeter heating using finned tube radiation cabinets.
Report run on: July 17, 2008 4:00 PM Page 25 of 39
D3050.05.06 Unit Heaters**
D3060.02.02 Pneumatic Controls**
4 - Acceptable
4 - Acceptable
Rating
Rating
1983
1983
Installed
Installed
30
40
Design Life
Design Life
JUL-07
JUL-07
Updated
Updated
Replace the 13 unit heaters in the building
Refurbish the air handling unit heating coil controlvalve for AS1
Replace the HVAC system pneumatic controlsincluding the control air supply system
Lifecycle Replacement
Repair
Lifecycle Replacement
2013
2008
2023
$29,744
$2,288
$61,776
Unassigned
Low
Unassigned
The air handling unit heating coil control valve for AS1 isleaking, which will affect its performance and causeaccelerated deterioration.
Concern:
Refurbish the air handling unit heating coil control valve for AS1.Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Event:
Type
Type
Type
Year
Year
Year
Cost
Cost
Cost
Priority
Priority
Priority
Updated:
Updated:
Updated:
OCT-07
OCT-07
OCT-07
A total of approximately 13 glycol/hot water unit heaters (UH1 through UH13) are used for space heating in the building.Unit heaters are used in the building corridors and at the entrance vestibules, in the storage and meter rooms, in thegymnasium, and in the mechanical penthouse. One of the unit heaters in the mechanical penthouse (UH12) is used forpreheating combustion air.
The building HVAC system controls and actuators are primarily pneumatic. There is an Andover AC256M Plus BuildingManagement and Control System (BMCS) which provides control and monitoring functions, although the HVAC equipmentactuators and room thermostats are pneumatic. The control air supply system is located in the mechanical penthouse andconsists of two air compressors mounted on an air receiver tank with a wall mounted refrigerated air dryer. Pneumaticcontrols include control valves for the hydronic terminal units (approximately 40), control valves for the air handling unitheating coils (3), and damper actuators for the air handling units (approximately 9).
Report run on: July 17, 2008 4:00 PM Page 26 of 39
D3060.02.05 Building Systems Controls (BMCS, EMCS)**
D4030.01 Fire Extinguisher, Cabinets and Accessories - *
3 - Marginal
4 - Acceptable
Rating
Rating
1983
1983
Installed
Installed
20
30
Design Life
Design Life
JUL-07
JUL-07
Updated
Updated
Replace the Andover AC256M Plus BMCS to theAndover Continuum BMCS
Failure Replacement 2008 $62,920 Medium
The Andover AC256M Plus BMCS is obsolete and obtainingreplacement parts is difficult.
Concern:
Replace the Andover AC256M Plus BMCS to the AndoverContinuum BMCS
Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Type Year Cost Priority
Updated: JUL-07
The building is equipped with a central Building Management and Control System (Andover Controls model AC256M Plus),which provides control and monitoring functions for the HVAC equipment, although the HVAC equipment actuators androom thermostats are pneumatic.
Wall mounted and cabinet mounted fire extinguishers are located throughout the building.
Report run on: July 17, 2008 4:00 PM Page 27 of 39
D5010.03 Main Electrical Switchboards (Main Distribution)**
D5010.05 Electrical Branch Circuit Panelboards (Secondary Distribution)**
D5010.07.01 Switchboards, Panelboards, and Motor Control Centers**
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
1983
1983
1983
Installed
Installed
Installed
40
30
30
Design Life
Design Life
Design Life
JUL-07
JUL-07
APR-08
Updated
Updated
Updated
Replace Main Electrical Switchboard
Replace Branch Circuit Panelboards
Replace Motor Control Centre
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
2023
2013
2013
$46,205
$33,176
$18,304
Unassigned
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
S5 ELECTRICAL
Event:
Event:
Event:
Type
Type
Type
Year
Year
Year
Cost
Cost
Cost
Priority
Priority
Priority
Updated:
Updated:
Updated:
APR-08
APR-08
JUL-07
The main electrical switchboard is a Westinghouse switchboard rated at 120/208V, 3-phase, 4-wire. The switchboard hasan 800A main breaker and a distribution section with moulded case breakers feeding eight branch circuit panels, theportables and the M.C.C.. The main electrical switchboard is original equipment that was installed when the school wasconstructed. There is space within the switchboard for future breakers.
The majority of the electrical branch circuit panelboards are Westinghouse panels that appear to have been installed whenthe building was originally constructed. Eight panels are fed from the main switchboard.
A Klockner Moeller Motor Control Centre is located in the mechanical penthouse. The M.C.C. is a 3-section M.C.C. with 12starter units.
Report run on: July 17, 2008 4:00 PM Page 28 of 39
D5010.07.02 Motor Starters and Accessories**
D5020.01 Electrical Branch Wiring*
D5020.02.01 Lighting Accessories (Lighting Controls)*
D5020.02.02.02 Interior Florescent Fixtures**
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
1983
1983
1983
1983
Installed
Installed
Installed
Installed
30
50
30
30
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Replace Motor Starters
Replace Interior Florescent Fixtures
Lifecycle Replacement
Lifecycle Replacement
2013
2013
$4,009
$228,800
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
APR-08
APR-08
There are individual motor starters (K-M) and motor rated starter switches within the school.
The majority of the cabling is standard building wire in EMT conduit. Armoured cable has been provided, in selectedlocations, for final connections to mechanical and miscellaneous equipment.
Low voltage relays have been provided for the lighting. The low voltage relay cabinets are located adjacent to the lightingpanels.
The typical lighting within the school consists of wrap-around, two lamp fluorescent fixtures, surface mounted on the ceilingor recessed 1 ft. x 4 ft. fluorescent fixtures. Cubelight fluorescent fixtures are installed in the washrooms. The majority ofthe fluorescent lighting fixtures throughout the school have T12 lamps and magnetic ballasts. Classrooms 107, 108 and109 were renovated and recessed 2 ft. x 4 ft., 3-lamp, T8 fluorescent fixtures were installed.
Report run on: July 17, 2008 4:00 PM Page 29 of 39
D5020.02.02.03 Interior Metal Halide Fixture*
D5020.02.03.02 Emergency Lighting Battery Packs**
3 - Marginal
3 - Marginal
Rating
Rating
1983
1983
Installed
Installed
30
20
Design Life
Design Life
JUL-07
JUL-07
Updated
Updated
Program Functional Upgrade
Replace Emergency Lighting Battery Packs
Failure Replacement
Failure Replacement
2008
2008
$17,160
$11,440
Unassigned
Medium
The light levels in the gymnasium are low. The HID fixturesrequire time to reach full light output.
The emergency lighting battery packs are aged and may notoperate during an outage.
Concern:
Concern:
Replace existing metal halide lighting with T5 or T8 fluorescentlighting.
Replace emergency lighting battery units with new.
Recommendation:
Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
JUL-07
APR-08
The gymnasium is illuminated with 12 metal halide high bay fixtures, suspended from the ceiling. The lighting level in thegymnasium is low.
The emergency lighting in the building is provided by battery powered emergency lighting units and remote emergencylighting heads.
Consequences of Deferral:
Consequences of Deferral:
Poor quality lighting.
Life safety concern.
Aged emergency lighting battery unit.
Report run on: July 17, 2008 4:00 PM Page 30 of 39
D5020.02.03.03 Exit Signs*
D5020.03.01.01 Exterior Incandescent Fixtures*
D5020.03.01.04 Exterior H.P. Sodium Fixtures*
D5020.03.02 Lighting Accessories: Exterior (Lighting Controls)*
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
1983
1983
1983
1983
Installed
Installed
Installed
Installed
30
30
30
30
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Retrofit Exit Signs to LED Type
Energy Efficiency Upgrade 2008 $2,860 Unassigned
The incandescent lamps in the exit signs are inefficient andrequire frequent maintenance.
Concern:
Retrofit the existing exit signs with new LED lamps.Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Type Year Cost Priority
Updated: JUL-07
Exit signs are generally located to indicate building exits and egress routes to exits. The majority of the exit signs haveincandescent lamps.
Incandescent downlights with a wire guard have been provided in the canopies.
H.P.S. wallpack fixtures have been provided on the exterior walls.
A timer and contactor have been provided for exterior lighting control.
Consequences of Deferral:Increased energy and maintenance costs.
Report run on: July 17, 2008 4:00 PM Page 31 of 39
D5030.01 Detection and Fire Alarm**
D5030.02.02 Intrusion Detection**
D5030.03 Clock and Program Systems*
3 - Marginal
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
1983
1983
1990
Installed
Installed
Installed
25
25
25
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Replace Fire Alarm System
Replace Security System
Failure Replacement
Lifecycle Replacement
2009
2012
$51,480
$25,374
Medium
Unassigned
The Simplex fire alarm system is outdated. Replacement partsare not readily available.
Concern:
Replace existing fire alarm system with a new addressablesystem.
Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
JUL-07
APR-08
The fire alarm system control panel is a Simplex 2001 panel with 12 active zones and 8 spare zones. The control panel islocated in the electrical room and there is a remote annunciator at the main entrance to the school. The audible deviceswithin the school are typically 10" dia. Bells. Strobes have not been installed. Duct mounted smoke detection has beenprovided for the air handling equipment. The August 2006 fire alarm testing report indicated no problems with the fire alarmsystem.
The security system is a Partner Premier system model P-16128 with the main panel located in the janitor's room acrossfrom the kitchen. A security system keypad has been installed at the main entrance. PIR motion detectors have beenprovided throughout the school.
The clocks within the school are plug-in or battery operated clocks.
Consequences of Deferral:Life safety concern. Increased maintenance costs.
Aged Simplex fire alarm system.
Report run on: July 17, 2008 4:00 PM Page 32 of 39
D5030.04.01 Telephone Systems*
D5030.04.05 Local Area Network Systems*
D5030.05 Public Address and Music Systems**
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
1983
1998
2006
Installed
Installed
Installed
25
15
20
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Replace P.A. System
Lifecycle Replacement 2026 $10,436 Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Type Year Cost Priority
Updated: APR-08
The telephone system is a Nitsuko system. Nutec handsets are located in areas such as the general office. The maintelephone equipment is located in the main electrical room.
The data system server is located in the computer lab closet. Cat. 5 cables are used for the network wiring within theschool.
The public address system is a Telecor system. Return call switches have been provided in the classrooms. Speakers aretypically round, recessed ceiling mounted units. The console unit is located in the General Office workroom area.
Report run on: July 17, 2008 4:00 PM Page 33 of 39
E1090.07 Athletic, Recreational, and Therapeutic Equipment - *
E2010.02 Fixed Casework - **
E2010.03.01 Blinds**
E2010.03.06 Curtains and Drapes**
4 - Acceptable
5 - Good
5 - Good
4 - Acceptable
Rating
Rating
Rating
Rating
1983
1983
2000
1983
Installed
Installed
Installed
Installed
15
35
30
30
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Replace all Fixed Casework
Replace Roller Blinds
Replace curtains in isolated classrooms
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
2018
2030
2013
$171,600
$22,880
$8,008
Unassigned
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
S6 EQUIPMENT, FURNISHINGS AND SPECIAL CONSTRUCTION
Event:
Event:
Event:
Type
Type
Type
Year
Year
Year
Cost
Cost
Cost
Priority
Priority
Priority
Updated:
Updated:
Updated:
APR-08
APR-08
APR-08
Fixed & movable basketball hoops are located in the gymnasium. A climbing apparatus is located in the gymnasium.
Each classroom is equipped with custom wood open faced and/or painted cabinet units along the exterior wall. The staffroom has painted wood upper and lower cabinet units. The computer room has fixed counter-tops around the perimeter ofthe room. The library has fixed and moveable wood shelving casework. Glass display cabinets are located in the mainentrance area and in the corridors. The washrooms have plastic laminate counter tops.
Several windows have perforated roller blinds.
Several windows in the classrooms have curtains
Report run on: July 17, 2008 4:00 PM Page 34 of 39
E2020 Moveable Furnishings
F1010.02.04 Portable and Mobile Buildings - 193,194,195 & 196 & C17*
4 - Acceptable
4 - Acceptable
Rating
Rating
1983
1982
Installed
Installed
0
30
Design Life
Design Life
JUL-07
JUL-07
Updated
Updated
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Chairs, desks and tables are located in all the classrooms, science rooms, library and administration areas. Chairs &tables are typically storage in the gym storage area if lunch rooms are not provided.
Portables - 193, 194, 195, 196, C17 - Built in 1982 Structure: - Wood frame construction with concrete piles bearing on undisturbed soil. Envelope: - Cladding - A painted plywood sheathing skirt with vents is located at the base of the elevation. The exterior skin has apainted wood siding finish with wood framing construction. - Windows - The exterior windows are aluminum frame fixed and operable awning type windows with exterior metal securityscreens (original) - Roof Covering - The roof has a SBS (original) roof assembly. Interior: - Flooring - VCT flooring (1993) - Ceiling - 2'x4' Suspended Acoustical tile ceiling - Walls - Painted and /or vinyl covered gypsum board walls with either metal or wood wall construction. - Doors - Fire-rated steel door & frame assembly - Equipment - Whiteboards, tackboards, open wood shelving, wall mounted coat hooks & curtains. - Blinds - Horizontal metal blinds Mechanical: Portable heating is provided by a gas fired forced air furnace which provides a mixture of fresh air and return air to theconditioned space. Temperature control is independent and is typically provided by an analog or digital electric thermostat.Classroom portables do not have any plumbing. Portables are typically equipped with a fire extinguisher for fire protection.Exterior storm drainage for the portable consists of gutters and downspouts which discharge to grade. Mechanical elements within the portables were found to be in acceptable condition. Electrical: Each portable classroom is provided with a stablock panel (connected to the school electrical distribution system) thatprovides power for the individual classroom. The lighting fixture used within each portable classroom is typically a surfacemounted, T12, fluorescent, wrap-around fixture. Recessed round P.A. speakers, a telephone and a PIR motion detector aretypically provided in each portable classroom. The portables are connected to the school fire alarm system and havepullstations at the exits and heat detectors in the storage and furnace rooms. The electrical elements within the portables were found to be in acceptable condition.
Report run on: July 17, 2008 4:00 PM Page 35 of 39
F1010.02.04 Portable and Mobile Buildings - 236*
4 - AcceptableRating
1989Installed
30Design Life
JUL-07Updated
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Portable - 236 - Built in 1989 Structure: - Wood frame construction with concrete piles bearing on undisturbed soil. Envelope: - Cladding - A painted plywood sheathing skirt with vents is located at the base of the elevation. The exterior skin has apainted wood siding finish with wood framing construction. - Windows - The exterior windows are aluminum frame fixed and operable awning type windows with exterior metal securityscreens (original) - Roof Covering - The roof has a SBS (original) roof assembly. Interior: - Flooring - VCT flooring (1989) - Ceiling - 2'x4' Suspended Acoustical tile ceiling - Walls - Painted and /or vinyl covered gypsum board walls with either metal or wood wall construction. - Doors - Fire-rated steel door & frame assembly - Equipment - Whiteboards, tackboards, open wood shelving, wall mounted coat hooks & curtains. - Blinds - Horizontal metal blinds Mechanical: Portable heating is provided by a gas fired forced air furnace which provides a mixture of fresh air and return air to theconditioned space. Temperature control is independent and is typically provided by an analog or digital electric thermostat.Classroom portables do not have any plumbing. Portables are typically equipped with a fire extinguisher for fire protection.Exterior storm drainage for the portable consists of gutters and downspouts which discharge to grade. Mechanical elements within the portables were found to be in acceptable condition. Electrical: Each portable classroom is provided with a stablock panel (connected to the school electrical distribution system) thatprovides power for the individual classroom. The lighting fixture used within each portable classroom is typically a surfacemounted, T12, fluorescent, wrap-around fixture. Recessed round P.A. speakers, a telephone and a PIR motion detector aretypically provided in each portable classroom. The portables are connected to the school fire alarm system and havepullstations at the exits and heat detectors in the storage and furnace rooms. The electrical elements within the portables were found to be in acceptable condition.
Report run on: July 17, 2008 4:00 PM Page 36 of 39
F1010.02.04 Portable and Mobile Buildings - 280*
F2020.01 Asbestos - *
5 - Good
4 - Acceptable
Rating
Rating
2005
1983
Installed
Installed
30
0
Design Life
Design Life
JUL-07
JUL-07
Updated
Updated
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Portable - 280 - Built in 2005 Structure: - Wood frame construction with concrete piles bearing on undisturbed soil. Envelope: - Cladding - A painted plywood sheathing skirt with vents is located at the base of the elevation. The exterior skin has apainted wood siding finish with wood framing construction. - Windows - The exterior windows are aluminum frame fixed and operable awning type windows with exterior metal securityscreens (2005) - Roof Covering - The roof has a SBS (2005) roof assembly. Interior: - Flooring - VCT flooring - Ceiling - 2'x4' Suspended Acoustical tile ceiling - Walls - Painted and /or vinyl covered gypsum board walls with either metal or wood wall construction. - Doors - Fire-rated steel door & frame assembly - Equipment - Whiteboards, tackboards, open wood shelving, wall mounted coat hooks & curtains. - Blinds - Horizontal metal blinds Mechanical: Portable heating is provided by a gas fired forced air furnace which provides a mixture of fresh air and return air to theconditioned space. Temperature control is independent and is typically provided by an analog or digital electric thermostat.Classroom portables do not have any plumbing. Portables are typically equipped with a fire extinguisher for fire protection.Exterior storm drainage for the portable consists of gutters and downspouts which discharge to grade. Mechanical elements within the portables were found to be in acceptable condition. Electrical: Each portable classroom is provided with a stablock panel (connected to the school electrical distribution system) thatprovides power for the individual classroom. The lighting fixture used within each portable classroom is typically a surfacemounted, T12, fluorescent, wrap-around fixture. Recessed round P.A. speakers, a telephone and a PIR motion detector aretypically provided in each portable classroom. The portables are connected to the school fire alarm system and havepullstations at the exits and heat detectors in the storage and furnace rooms. The electrical elements within the portables were found to be in acceptable condition.
No asbestos known or reported.
Report run on: July 17, 2008 4:00 PM Page 37 of 39
F2020.04 Mould - *
F2020.09 Other Hazardous Materials - *
4 - Acceptable
4 - Acceptable
Rating
Rating
1983
1983
Installed
Installed
0
0
Design Life
Design Life
JUL-07
JUL-07
Updated
Updated
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
No mould known or reported.
No hazardous materials known or reported
Report run on: July 17, 2008 4:00 PM Page 38 of 39
K3020 Indoor Environment
K4010.01 Barrier Free Route: Parking to Entrance - *
K4010.02 Barrier Free Entrances - *
2 - Poor
4 - Acceptable
3 - Marginal
Rating
Rating
Rating
0
1983
1983
Installed
Installed
Installed
0
0
0
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Install local air conditioning for the computer room
Provided power operators for barrier free access atthe main entrance of the building.
Indoor Air Quality Upgrade
Barrier Free Access Upgrade
2008
2008
$13,728
$4,576
Low
Low
The computer room can get very warm since there is no airconditioning.
No automatic access is currently provided from any exteriorentrance doors.
Concern:
Concern:
Install local air conditioning for the computer room.
Provided power operators for barrier free access at the mainentrance of the building.
Recommendation:
Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
S8 FUNCTIONAL ASSESSMENT
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
JUL-07
JUL-07
The computer room does not have any air conditioning.
Barrier free access from the parking area to the main building entrance is provided on the east elevation.
No automatic door entrances are provided.
Report run on: July 17, 2008 4:00 PM Page 39 of 39
K4010.03 Barrier Free Interior Circulation - *
K4010.04 Barrier Free Washrooms - *
4 - Acceptable
3 - Marginal
Rating
Rating
1983
1983
Installed
Installed
0
0
Design Life
Design Life
JUL-07
JUL-07
Updated
Updated
Provide a unisex barrier free washroom
Barrier Free Access Upgrade 2008 $34,320 Low
The school does not have a barrier free washroom with currentbarrier free standards.
Concern:
Provide a unisex barrier free washroom Recommendation:
Edmonton - Our Lady Of The Prairies Catholic Elementary School (B3241A)
Event:
Type Year Cost Priority
Updated: OCT-07
Barrier free access is provided to most areas, including the music room
The washrooms do not fully comply with the current barrier free standards.
Report run on: July 18, 2008 1:59 PM
RECAPP Facility Evaluation Report
Our Lady Of The Prairies Catholic Elementary School
S3241Edmonton
Report run on: July 18, 2008 1:59 PM Page 2 of 6
S3241Building Id:
Our Lady Of The Prairies CathBuilding Name:
EdmontonLocation:Address:
0.00Gross Area (sq. m): $0Replacement Cost:0Construction Year:
Evaluation Date: May 7 2007
Asset Evolution Incorporated (AEI)Evaluation Company:
Mario PlastinaEvaluator Name:
The site of Our Lady of the Prairies Catholic Elementary School (2.60 hectares) includes an asphalt paved roadway &parking area accessible from 64th Avenue. A sodded playing field is located at the south end of the property. Grass,shrubs and trees are located along the south, west and east elevations of the school. An asphalt paved playground islocated at the south end of the school. Pedestrian concrete walkways are located at the main entrance (North Elevation).Asphalt walkways lead to secondary entrances & the portable areas. Site drainage appears to slope away from thebuilding with no problems indicated or observed. There is a cluster of 6 portables on site linked at the west elevation. Overall the site elements appeared to be in acceptable condition.
General Summary:
Structural Summary:
Envelope Summary:
Interior Summary:
Mechanical Summary:
Electrical Summary:
0%5 year Facility Condition Index (FCI):
Facility Details Evaluation Details
Total Maintenance Events Next 5 years: $143,000
Edmonton - Our Lady Of The Prairies Catholic Elementary School (S3241)
Condition Rating Performance1 - Critical Unsafe, high risk of injury or critical system failure.2 - Poor Does not meet requirements, has significant deficiencies. May have high operating/maintenance costs.
3 - Marginal Meets minimum requirements, has significant deficiencies. May have above average operating maintenance costs.4 - Acceptable Meets present requirements, minor deficiencies. Average operating/maintenance costs.
Rating Guide
5 - Good Meets all present requirements. No deficiencies.6 - Excellent As new/state of the art, meets present and foreseeable requirements.
Report run on: July 18, 2008 1:59 PM Page 3 of 6
G2010.02.02 Flexible Pavement Roadway (Asphalt) - **
G2020.02.02 Flexible Paving Parking Lots(Asphalt) - **
G2020.06.02 Parking Bumpers - *
G2020.06.03 Parking Lot Signs - *
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
1983
1983
1983
1983
Installed
Installed
Installed
Installed
25
25
25
25
Design Life
Design Life
Design Life
Design Life
JUL-07
OCT-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Replace Asphalt Paved Roadway - 300SM
Replace Asphalt Paving Parking Lot - 600SM
Lifecycle Replacement
Lifecycle Replacement
2012
2012
$28,600
$45,760
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (S3241)
S7 SITE
Event:
Event:
Type
Type
Year
Year
Cost
Cost
Priority
Priority
Updated:
Updated:
APR-08
APR-08
An asphalt paved roadway to the main parking areas is accessible from 64th Avenue located at the east end of the site.
The asphalt paved parking area on the east end of the site is accessible from 64th Avenue.
Painted wood parking bumpers are located at each parking stall.
Each parking bumper stall has a reference number.
Report run on: July 18, 2008 1:59 PM Page 4 of 6
G2030.02.02 Asphalt Pedestrain Pavement**
G2030.04 Rigid Pedestrian Pavement (Concrete) - **
G2040.03 Athletic and Recreational Surfaces - **
G2040.05 Site and Street Furnishings - *
4 - Acceptable
4 - Acceptable
5 - Good
4 - Acceptable
Rating
Rating
Rating
Rating
2000
1983
1983
1983
Installed
Installed
Installed
Installed
20
25
25
15
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Replace asphalt paved walkways
Replace poured in place concrete walkways
Replace Athletic and Recreational Surfaces
Lifecycle Replacement
Lifecycle Replacement
Lifecycle Replacement
2020
2012
2012
$17,160
$34,320
$34,320
Unassigned
Unassigned
Unassigned
Edmonton - Our Lady Of The Prairies Catholic Elementary School (S3241)
Event:
Event:
Event:
Type
Type
Type
Year
Year
Year
Cost
Cost
Cost
Priority
Priority
Priority
Updated:
Updated:
Updated:
APR-08
APR-08
APR-08
Asphalt paved walkways lead to the portables & secondary school entrances.
Poured in place concrete walkways lead to the main school entrances.
An asphalt paved playground & a sodded football / soccer field with goal posts is located at the south end of the property.The playgrounds are shared with the adjacent community centre.
Bicycle racks are located along the west end of the school. Basketball hoops are located adjacent to the asphalt pavedplayground along the south elevation of the school.
Report run on: July 18, 2008 1:59 PM Page 5 of 6
G2040.06 Exterior Signs - *
G2040.08 Flagpoles - *
G2050.04 Lawns and Grasses - *
G2050.05 Trees, Plants and Ground Covers - *
G3010.02 Site Domestic Water Distribution - *
G3020.01 Sanitary Sewage Collection - *
4 - Acceptable
4 - Acceptable
5 - Good
5 - Good
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
Rating
Rating
1983
1983
1983
1983
1983
1983
Installed
Installed
Installed
Installed
Installed
Installed
25
30
15
10
50
50
Design Life
Design Life
Design Life
Design Life
Design Life
Design Life
OCT-07
JUL-07
JUL-07
JUL-07
JUL-07
JUL-07
Updated
Updated
Updated
Updated
Updated
Updated
Edmonton - Our Lady Of The Prairies Catholic Elementary School (S3241)
Exterior wall-mounted signage is provided on the buildings main entrances. School signage is located on the north wall. Afree-standing signage panel is located at the north-east corner of the site.
A flagpole is located on the north end of the site, adjacent to the main entrance.
Grassed areas are located along the north and east sides of the school.
Small trees, shrubs and ground covered areas are located along the north side of the site.
The building domestic water supply comes from a domestic water mains on 64 Avenue. The 100 mm diameter domesticwater supply to the building enters the library on the north side of the building and is reduced to 50 mm diameter. From thelibrary, the domestic water supply is routed through the ceiling space to the meter room on the east side of the buildingwhere the water meter is located.
The 150 mm diameter building sanitary waste line discharges at the north side of the building to the 255 mm diametermunicipal sanitary sewer on 64 Avenue.
Report run on: July 18, 2008 1:59 PM Page 6 of 6
G3030.01 Storm Water Collection - *
G3060.01 Gas Distribution - *
G4010.02 Electrical Power Distribution Lines*
G4010.04 Car Plugs-ins - *
4 - Acceptable
4 - Acceptable
4 - Acceptable
4 - Acceptable
Rating
Rating
Rating
Rating
1983
1983
1983
0
Installed
Installed
Installed
Installed
50
50
50
25
Design Life
Design Life
Design Life
Design Life
JUL-07
JUL-07
OCT-07
OCT-07
Updated
Updated
Updated
Updated
Edmonton - Our Lady Of The Prairies Catholic Elementary School (S3241)
Storm water collected from the building roof areas is discharged through the 375 mm diameter building storm drainage lineat the north side of the building. The storm drainage line enters a manhole on the property and continues to the 1220 mmdiameter municipal sanitary sewer on 64 Avenue. There are four storm sewer catch basins on the site (two in the eastpaved parking area and two in the west grassed area) which also discharge to the storm sewer manhole on the north side ofthe building.
Natural gas is supplied to the building from a 100 mm diameter gas mains on 64 Avenue. The natural gas supply line runsunderground on the east side of the building to the meter room where the pressure reducing station and the gas meter arelocated. The original natural gas line which supplied the portables (since the portables were installed prior to the schoolbeing built) was located on the west side and this gas line was reportedly removed back to the property line when theschool was constructed.
The incoming hydro service to Our Lady of the Prairies School is a 120/208V, 3-phase, 4-wire service from an EPCORpadmounted transformer, located on the school grounds. The EPCOR meter is located in the main electrical room.
There are a total of 14 rail mounted weatherproof duplex receptacles for car plug-ins. The receptacles are controlled by acontactor in the electrical room.