    Student: Costiuc Elena

    Group:3304

  • 7/27/2019 Reabilitare Elena

    2/20

    The "National Theatre" was built between 1891-1896, on the

    former City Hall of Iasi, after the plans of architects Felner and

    Helmer.

  • 7/27/2019 Reabilitare Elena

    3/20

    Old building of the National Theater in Iasi

    (Copou) built in 1846 and destroyed by the fire

    in 1888

    http://ro.wikipedia.org/wiki/Imagine:TNI_1846.jpg
  • 7/27/2019 Reabilitare Elena

    4/20

  • 7/27/2019 Reabilitare Elena

    5/20

    Building 1

    The structure is made of bearing masonry, slabs of brick and steel profiles, with the area

    from the second floor having concrete between the steel profiles.

    Foundations are continuous under the bearing walls made of stone with hydraulic lime,with consolidated areas through concrete.

  • 7/27/2019 Reabilitare Elena

    6/20

    Building 2

    The structure is made of

    frames of monolith

    reinforced concrete with

    reinforced concrete slabs.

  • 7/27/2019 Reabilitare Elena

    7/20

    Building 3(4)

    The structure is made of bearing masonry with monolith reinforced

    concrete slabs and the foundations are continuous under the bearing

    walls, made of concrete.

  • 7/27/2019 Reabilitare Elena

    8/20

    Technical Expertise

    -Water infiltration from melting snow

    The spectacle hall during the winter is heated with hot air making the temperature of

    the bridge to climb up to 18-20 degrees. In these conditions the roof sheet allows

    rapid melting of snow and water flows into the collecting gutter.

    The sewerage no longer being maintained doesn't have any connection to the drain

    pipe. Thus a part of the water flows on the walls.

    Solutions:

    - Ensuring the flow of rain water goes directly into the sewerage system;

    - Remaking the thermal insulation with mattresses of mineral wool in the polyethylene

    sheeting;

  • 7/27/2019 Reabilitare Elena

    9/20

  • 7/27/2019 Reabilitare Elena

    10/20

    The first

    renovation was

    plastered over the

    old plaster with

    mortar whichcaused cracks in

    the new plaster.

    Solutions:

    -decopertation of old plasters(affected by dampness or rain water) and

    adjacent areas of drain pipes, closing the cracks with mortar by injection of

    the cracked walls and restoring plasters in marble dust with 100% white

    cement and coloring areas under slab facades of the project .

  • 7/27/2019 Reabilitare Elena

    11/20

    Exfoliations, cracks, detachmentseven falling of the stairsin the

    posterior and lateral facades. The lateral facades are not usually plastered

    (as in this case) because during the winter waters from snow infiltrate, freeze

    and provoke cracks.

    All stairs from the outside and those of stone from the main entrance from the

    theatre and from the entrances and secondary accesses are affected (stairs and

    parapets).

  • 7/27/2019 Reabilitare Elena

    12/20

    Solutions:- At the stairs from the secondary accesses will be recovered all the steps with

    mosaic stone, white marble and the walls (just like the plaster of socket).

    -The access stairs are mainly from stone and will be repaired by plastie and

    the parapets with decorative motives will be cleaned and treated like other

    elements of stone of the theatre.

  • 7/27/2019 Reabilitare Elena

    13/20

    Fractures between the socle and the ornamental columns

    from the facades due to soil settlement

  • 7/27/2019 Reabilitare Elena

    14/20

  • 7/27/2019 Reabilitare Elena

    15/20

    Removing the stone socle

    Deterioration of the stone foundation and the bricks by crumbling and

    crushing due to chemical processes between them and silicate brought in to

    strengthen its land under a constant humidity and raising the walls by capillarity.

    Solutions:

    - We tried to introduce sodium silicate for removing the salts from the soil;

    -Hot plasters with perlite (type Dinu Moraru);

    -Above the floor were executed holes and the solution with peruse was introduced .

  • 7/27/2019 Reabilitare Elena

    16/20

    Achieving holes in the foundation for the

    inserting of solution with peruse

  • 7/27/2019 Reabilitare Elena

    17/20

    Attempting the method with solution of

    peruse

  • 7/27/2019 Reabilitare Elena

    18/20

    Replacing the socle stone with concrete socle.

  • 7/27/2019 Reabilitare Elena

    19/20

    Deterioration of exterior joinery ; inclined large cracks and vertically to

    headers.

    Solutions:

    - There will be recovered the windows from the basement and holes will be done in the

    areas with windows formerly recovered;

    - The windows of the old building will be unmounted and replaced with new ones after

    the initial model;- All the inferior horizontal parts of the windows will be repaired.

  • 7/27/2019 Reabilitare Elena

    20/20

    In the rehabilitation and

    consolidation works we must

    keep the architectural details

    after the initial model.