RBI Embedded within Maximo
Jarret Reeves - Asset Integrity Systems Product Manager How technology and innovation drive optimisation AND safety.
Lloyd’s Register Energy - Offshore Europe 2015
Asset Intensive Industry Goals
To achieve • Safe operations • Profit and ROI • Balance long/short decisions • Sustainability • Regulatory
To improve • Improve uptime • Asset longevity • Safety and Risk Management • Improve yield • Cost control
Lloyd’s Register Energy - Offshore Europe 2015
WHY RBI? The right insights, to make the right decisions, to keep assets “under control” (operating within set boundaries for business performance, safety, and compliance) at all times
Lloyd’s Register Energy - Offshore Europe 2015
Reduce unplanned downtime
Reduce failures, specifically HSE and catastrophic ones
Aging plant with unknowns
Balance long range improvements with quick wins
WHY RBI?
Lloyd’s Register Energy - Offshore Europe 2015
Challenges with existing Risk Approaches
Typically look backwards at failures vs. predicting and mitigating. Narrow view. What you’re doing now, how do we get you to world class?
Lack engineering expertise in-house; start from scratch with reliability models every time
Ability to close the loop between recommended actions and actual performance
Lloyd’s Register Energy - Offshore Europe 2015
Challenges with existing Risk Approaches
Lloyd’s Register Energy - Offshore Europe 2015
Compliance Manager
Embedded within
Root Cause
Analysis
Predictive Modeling
Reliability Centered
Maintenance
Industry Libraries
Lloyd’s Register Energy - Offshore Europe 2015
Introducing RBI Embedded within
Why we’re a good fit and position to address these challeng
We’ve done this before
• First to make integrated RBI system, often ahead of standards
• Existing RBI and APM Software (RBMI, strEAM+ and Optimizer)
• Innovative library approach accelerates time to value 50-80%
Lloyd’s Register Energy - Offshore Europe 2015
Publishing models to customers EAM
Internet
Customer A
(Maximo)
Customer B
(SAP)
Customer C
Standalone
LR
Library Manager
Publishing Models • Version and manage models via meta data • Model development takes weeks, not years • Current Models include Fixed Equipment,
Pipe, Relief Devices, Instrumentation, subsea jacketed structures, and rotating
• More models in the works
Lloyd’s Register Energy - Offshore Europe 2015
Stored in and performed in Maximo throughout asset life cycle
Design
In-Service
Construction
Decommission Risk-Based
RBI
RCM
Optimize
Time-Based
Run to Fail
CM’s
PM’s
MOC
Spares
Plan
Work Order
Job Plan/ Details
Execute
Inspection
Maintenance
Telemetry
Analyze
Failure/RCA
NCR
Compliance
Trending
Condition-Based
Asset Management Strategy
Safety
Work pack
Improve
Maximo
LR Modules
Broadsword
FMEA
Libraries
SME
Lloyd’s Register Energy - Offshore Europe 2015
Risk provides a sustainable solution over time
Time
Risk
Acceptable Limits
Traditional Approach The cost and effort to manage risk increases significantly over time
Decrease effort/cost, increasing knowledge
Plan
Do
Check
Update
Plan
Do
Check
Update
Lloyd’s Register Energy - Offshore Europe 2015
The Financial Case
EAM
RBI
Inspection Management
RCM
As-Is • Disparate Systems • Costly Integration • Redundant or Missing
information • Not connecting workgroups • Engineering knowledge
erosion
Lloyd’s Register Energy - Offshore Europe 2015
The Financial Case
Maximo
Analysis
Inspection Management
RBI To-Be • Leverage EAM investments • Single Data Source • Strategic and Tactical
decision making • Right information to the right
person • Knowledge retention
Lloyd’s Register Energy - Offshore Europe 2015
The Safety Case…..
What if you could • Quantify your HSE risk… • Predict failures… • Focus resources… • Continuous improvement… • In your EAM system…
Lloyd’s Register Energy - Offshore Europe 2015
Demonstration of RBI, PM’s and Work Orders…..
Design
In-Service
Construction
Decommission Risk-Based
RBI
RCM
Optimize
Time-Based
Run to Fail
CM’s
PM’s
MOC
Spares
Plan
Work Order
Job Plan/ Details
Execute
Inspection
Maintenance
Telemetry
Analyze
Failure/RCA
NCR
Compliance
Trending
Condition-Based
Asset Management Strategy
Safety
Work pack
Improve
Maximo
LR Modules
Broadsword
FMEA
Libraries
SME
Lloyd’s Register Energy - Offshore Europe 2015
Sample RBI embedded within Maximo
Lloyd’s Register Energy - Offshore Europe 2015
Sample RBI embedded within Maximo – Internal Corrosion
Lloyd’s Register Energy - Offshore Europe 2015
Sample RBI – Qualitative model
Lloyd’s Register Energy - Offshore Europe 2015
Sample RBI – Qualitative continued
Lloyd’s Register Energy - Offshore Europe 2015
Mitigating the risk (recommendations)
Auto calculation of due dates (frequency + last
activity date)
Lloyd’s Register Energy - Offshore Europe 2015
Realizing the mitigations to work orders (PM’s in Maximo)
Lloyd’s Register Energy - Offshore Europe 2015
Summary
• Proven approach with preconfigured models, though customers can developer their own
Time to Value
• Predictive models • Optimal life performance of the asset
Focus limited resources on most important items
• Leverage existing EAM investments • Reduce cost of ownership
Integrated processes that generate maximum
Lloyd’s Register Energy - Offshore Europe 2015
Question and Answer
Lloyd’s Register and variants of it are trading names of Lloyd’s Register Group Limited, its subsidiaries and affiliates. Copyright © Lloyd’s Register Energy. 2015. A member of the Lloyd’s Register group.