Ray Goodfellow

download Ray Goodfellow

of 26

Transcript of Ray Goodfellow

  • 7/30/2019 Ray Goodfellow

    1/26

    Incorporating an Asset

    Integrity Program into the

    Design Stageof Projects

    Ray GoodfellowPangea Solutions IncMay 9, 2008

    [email protected]

    mailto:[email protected]:[email protected]
  • 7/30/2019 Ray Goodfellow

    2/26

    What is Asset Integrity Asset Integrity is an effective system for

    managing the integrity of equipment, piping andpipelines throughout the full lifecycle: design

    construction & installation operation

    maintenance, (repairs, alterations)

    integrity assessments

    decommissioning

    Developing and implementing an Asset Integrityprogram at the design stage supports lifecyclereliability and operability

  • 7/30/2019 Ray Goodfellow

    3/26

    What is Asset Integrity Regulatory Requirements (ABSA/CSA/EUB/)

    Pressure Equipment Integrity Management System(PEIMS)

    Pipeline Integrity Management Program

    Key elements include:Risk assessments

    Degradation Circuits

    Material selection

    Condition monitoring location (CML) selection Inspection, Mitigation, Monitoring

    Data management

    Training programs

  • 7/30/2019 Ray Goodfellow

    4/26

    What is Asset Integrity

    Typical Equipment within Scope: Boilers and heaters

    Pressure vessels (including Pressure relief devices)

    Pressure piping

    Tanks Non-pressure static equipment

    Non-pressure piping

    Pipelines

    Not in Scope Structural

    Rotating equipment

    Electrical

  • 7/30/2019 Ray Goodfellow

    5/26

    Overview

    Why:

    What is the value of incorporating Asset Integrity into

    the design stage of a project?

    How:

    What are the key activities at each stage of the

    project?

    Deliverables: What are the deliverables at each stage of the

    project?

  • 7/30/2019 Ray Goodfellow

    6/26

  • 7/30/2019 Ray Goodfellow

    7/26

    Why

    De-ethanizer overhead gas

    line

    erosion corrosion

    failure downstream of mixing

    point

    Humber Refinery Fire, Health Safety Executive (HSE) Report

    http://www.hse.gov.uk/offshore/information.htm\

    http://www.hse.gov.uk/offshore/information.htm/http://www.hse.gov.uk/offshore/information.htm/http://www.hse.gov.uk/offshore/information.htm/
  • 7/30/2019 Ray Goodfellow

    8/26

    Why incorporate Asset Integrity into

    the design stage of a project The goal of each project is to create a business asset

    that performs its intended function, is safe,environmentally sound and reliable. The project is expected to be executed within the planned cost

    and schedule

    * I cant emphasize enough that youve got to get this right.You got to get this right. Because when you finally lock thescope, youre stuck with it for 30, 40, 50 years, so you betternot have any regrets when you start building it and running itthat you didnt get it right

    ~Neil Camarta

    *Petro-Canada Investor Day: Fort HillsOil Sands Engine of Growth, Neil Camarta, Senior Vice-President, OilSands

  • 7/30/2019 Ray Goodfellow

    9/26

    You got to get this right

    Incorporate lifecycle asset integrity into the

    design

    Have a positive impact:

    for the project efficient project execution

    and optimize capital costs

    for the operation- improve reliability andoperability

  • 7/30/2019 Ray Goodfellow

    10/26

    Incorporate lifecycle asset integrity into

    the design Make well thought out

    decisions to meet project

    and operations objectives

    Good decisions include:

    Involving the right people

    Having a structured process

    to guide decision making

    Maintaining good

    documentation

  • 7/30/2019 Ray Goodfellow

    11/26

    Incorporate lifecycle asset integrity

    into the design Increased upfront engineering can:

    Support quality decisions regarding CAPEX (design

    mitigation) and OPEX (operational mitigation) Provide clarity and direction that reduces time in

    detailed engineering

    Reduce rework during fabrication and during

    operationsMeet operational reliability expectations for long term

    plant life

  • 7/30/2019 Ray Goodfellow

    12/26

    Trend in Industry

    Understanding of the importance ofincorporating Asset Integrity into the designstage is increasing due to serious failures in the

    refinery, petrochemical and pipeline industryMajor corporations now require risk assessments at

    the design stage.

    Regulator requires the effective systems formanaging the integrity of their pressure equipmentthroughout its full lifecycle which includes design,construction and installation.

  • 7/30/2019 Ray Goodfellow

    13/26

    How

    Incorporate asset integrity activities into key

    phases of the project

    Identify key project objectives, development phases,

    milestones and hold points Utilize defined processes (i.e. Risk Base Inspection)

    to make decisions

    Supply defined deliverables at each stage of the

    projectRecognize, understand, and quantify the impacts and

    values added from asset integrity activities

  • 7/30/2019 Ray Goodfellow

    14/26

    Key activities and deliverables at

    each stage of the project Companies have multi step project

    management processes

    1. Select Alternatives2. Front End Engineering

    3. Detailed Engineering

    4. Fabrication and Construction

    5. Commissioning6. Turn Over to operations

  • 7/30/2019 Ray Goodfellow

    15/26

    1. Select Alternatives

    Key ProcessesDesign Basis Risk Assessment

    Lessons Learned Study

    Key DeliverablesAsset Integrity design philosophy report

    Lessons learned report

    Technical work book with all supporting

    information. (dynamic document) The work book will form the basis of additional risk

    assessments and the integrity manuals for theoperating facilities

  • 7/30/2019 Ray Goodfellow

    16/26

    1. Select Alternatives Impact

    Business basis for integritymanagement strategy

    Risk based decisions thatconsider full asset lifecycle Design mitigation

    Alloys, coatings, equipmentdesign, process changes

    Operational mitigation Inhibition, process control,

    inspection, monitoring, run to

    failureAlternative selection considers

    potential degradationmechanisms and otherhazards

  • 7/30/2019 Ray Goodfellow

    17/26

    2. Front End Engineering Key Activities

    Risk Assessment

    Incorporate lessons learned

    Development/Updating of Standards

    Management of Change Key Deliverables

    Scope and budget includes asset integrity and QAwork

    Technical work book with all supporting information.

    New or revised specifications

    Documented basis of integrity related designdecisions

  • 7/30/2019 Ray Goodfellow

    18/26

    2. Front End Engineering

    Impact Scope and costs for integrity

    related work are included inproject budget

    Determine first plannedshutdown Equipment isolation and

    inspection plan

    Design mitigation

    i.e. select materials and designOperational mitigation

    i.e. select mitigation andmonitoring strategy

  • 7/30/2019 Ray Goodfellow

    19/26

    3. Detailed Engineering Key Processes

    Assessment of deviations from initial design Previous Risk Assessment methodology can be used

    Materials selection report and diagram (MSD) reviews

    P&ID reviews

    Development/Implementation of quality assurance program

    Key Deliverables

    Reports or recommendations on specific technical issues Equipment Integrity Manuals

    Based on technical work books

    Degradation circuits

    Document the basis of design decisions

    Incorporates information from reports or recommendations on specific

    technical issues Foundation of RBI and overall asset integrity program

    Incorporate EPC Information

    Condition Monitoring Location (CML) selection

    Corrosion monitoring locations

    QA issues

  • 7/30/2019 Ray Goodfellow

    20/26

    3. Detailed Engineering Impact

    Provide technical input atproject reviews, hold points,and milestones

    Capture the technical basisand rational behind material,mitigation, monitoring andinspection decisions Understanding the rational

    allows more effectivemanagement of future changes(personal and process)

    3D Modeling can be used forselection of CMLs, corrosionmonitoring locations, etc.

  • 7/30/2019 Ray Goodfellow

    21/26

    4. Fabrication and Construction

    Key ActivitiesQuality assurance and Quality control

    a key aspect of asset integrity

    Vendor audits and reviews

    Assessment of deviations from design

    Key Deliverables Updated equipment integrity manuals

    Baseline CML survey on critical equipment and pipingcompleted

    Start populating equipment data base

  • 7/30/2019 Ray Goodfellow

    22/26

    4. Fabrication and Construction

    Impact

    Final product

    meets design

    specifications

    Have base line

    data

  • 7/30/2019 Ray Goodfellow

    23/26

    5. Commissioning Key Activities

    Assessment of deviations from design

    Regulatory requirements prior to start up

    Plan for start up activities

    Key Deliverables Installation Inspections compete

    PSVs serviced

    Equipment integrity manual complete

    Equipment database is populated with new equipment

    Baseline TML complete on critical equipment and piping

    Complete training for critical tasks

  • 7/30/2019 Ray Goodfellow

    24/26

    5. Commissioning Impact

    All critical tasks have

    been completed prior

    to start up

    Installation inspections

    and PSV servicing Inhibition programs in

    place

    Monitoring programs in

    place

    Training on procedurescompleted

  • 7/30/2019 Ray Goodfellow

    25/26

    6. Hand Over to Operations

    Key Processes Training

    Key Deliverables Equipment Integrity Manuals

    Documentation of deviations from design

    Populated database

    Mitigation and monitoring planMaintenance planning

    Long term training program

  • 7/30/2019 Ray Goodfellow

    26/26

    6. Hand Over to Operations Impact

    A business asset that is safe, environmentally sound and reliable

    http://www.chemicals-technology.com/projects/safco/index.html