Rate Analysis
-
Upload
nehal-shah -
Category
Documents
-
view
15 -
download
4
Transcript of Rate Analysis
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.1.01
Cu.m
For 10 Cum
[A] Materials --- --- ---
[B] Labours Skilled Nos. --- 150 --- Unskilled Nos. 5 90 450.00
Total labour rate 450.00
[C] Water + electric @ 2% of A+B --- --- 9.00
[D] Tools, Equipments & plants @ 2% A+B --- --- 9.00
[E] Scaffolding @ 2% A+B --- --- ----
[F] Profit & overhead @ 15% of A+B+C+D --- --- 70.2
Total cost 538.20
Unit Rate 54
Checked by:
Name of the Project: Vrajnandan Bunglows
Excavation for foundation up to 1.5 M depth including sorting out and stacking of useful materials, removing of grass or plants, and disposing of the excavated stuff up to 50 M. lead. In ordinary soil.
Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.1.03
Cu.m
For 10 Cum
[A] Materials --- --- ---
[B] Labours Skilled Nos. --- 150 --- Unskilled Nos. 2.6 90 234.00
Total labour rate 234.00
[C] Water + electric @ 2% of A+B --- --- 4.68
[D] Tools, Equipments & plants @ 2% A+B --- --- 4.68
[E] Scaffolding @ 2% A+B --- --- ----
[F] Profit & overhead @ 15% of A+B+C+D --- --- 36.504
Total cost 279.86
Unit Rate 28
Name of the Project: Vrajnandan Bunglows
Filling available excavated earth (including rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm. in depth consoladating each deposited layer by ramming and watering.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.1.04
Cu.m
For 10 Cum
[A] Materials --- --- ---
[B] Labours Skilled Nos. --- 150 --- Unskilled Nos. 2.5 90 225.00
Total labour rate 225.00
[C] Water + electric @ 2% of A+B --- --- 4.50
[D] Tools, Equipments & plants @ 2% A+B --- --- 4.50
[E] Scaffolding @ 2% A+B --- --- ----
[F] Profit & overhead @ 15% of A+B+C+D --- --- 35.1
Total cost 269.10
Unit Rate 27
Name of the Project: Vrajnandan Bunglows
Filling in plinth with sand under floors including watering ramming, consolidating and dressing etc. comp.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Item Item Description Unit Quantity Rate AmountNo.1.02
Cu.m
For 10 Cum
[A] Materials --- --- ---
[B] Labours Skilled Nos. --- 150 --- Unskilled Nos. 2 90 180.00
Total labour rate 180.00
[C] Water + electric @ 2% of A+B --- --- 3.60
[D] Tools, Equipments & plants @ 2% A+B --- --- 3.60
[E] Scaffolding @ 2% A+B --- --- ----
[F] Profit & overhead @ 15% of A+B+C+D --- --- 28.08
Total cost 215.28
Unit Rate 22
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
Filling in excavated trenches with sand under B.B.C.C. including watering ramming, consolidating and dressing etc. comp.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.3.01
Cu.m
For 10 Cum
[A] Materials
Bricks Nos. 4314 2.10 9059.40
Cement Bags 12.14 200.00 2428.00
Sand cu.m. 2.74 142.00 389.08
Total material rate 11876.48
[B] Labours Skilled Nos. 8.2 150.00 1230.00 Unskilled Nos. 18 90.00 1620.00
Total labour rate 2850.00
[C] Water + electric @ 2% of A+B --- --- 294.53
[D] Tools, Equipments & plants @ 2% A+B --- --- 294.53
[E] Scaffolding @ 2% A+B --- --- 294.53
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2341.51032
Total cost 17951.58 Rs
Unit Rate 1795 Rs/Cum
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
Brick work using common brunt clay building bricks having crusing strength not less than 35 Kg/S.cm. in foundation and plinth in cement mortar 1:4 (1cement : 4 fine sand), Conventional
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculation for rate analysis for Brick work for 10 Cum
[A] Materials1. Bricks Total No= 10 / (0.24 X 0.125 X 0.085) = 3921.56 10% Wastage=3922 x 1.1= 4314 bricks
2. Cement Wet Mortar =
= 2.22 + 5% Wastage = 2.33 cu.m.
Dry Mortar = 2.33 x 1.25 (25% Shrinkage Factor) = 2.91 cu.m
Cement =
3. Sand Sand
= 2.49 + 10% Wastage = 2.74 cu.m.
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
10×[ (0.24×0.125×0 . 085 )−(0 .23×0.115×0 .075 ) ]0 . 24×0 . 125×0 .085
2.917
=0. 416+2%Wastage
=0 .420 .0345
=12 .41Bags
=2 .91×67
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.3.02
Cu.m
For 10 Cum
[A] Materials
Bricks Nos. 4314 2.10 9059.40
Cement Bags 12.14 200.00 2428.00
Sand cu.m. 2.74 142.00 389.08
Total material rate 11876.48
[B] Labours Skilled Nos. 9.8 150.00 1470.00 Unskilled Nos. 21.3 90.00 1917.00
Total labour rate 3387.00
[C] Water + electric @ 2% of A+B --- --- 305.27
[D] Tools, Equipments & plants @ 2% A+B --- --- 305.27
[E] Scaffolding @ 2% A+B --- --- 305.27
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2426.89332
Total cost 18606.18 Rs
Unit Rate 1861 Rs/Cum
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
Brick work using common brunt clay building bricks having crusing strength not less than 35 Kg/S.cm. for Ground floor in cement mortar 1:4 (1cement : 4 fine sand), Conventional
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.3.03
Sq.m
For 10 Sqm
[A] Materials
Bricks Nos. 539 2.10 1131.90
Cement Bags 1.38 200.00 276.00
Sand cu.m. 0.20 142.00 28.40
Total material rate 1436.30
[B] Labours Skilled Nos. 1.3 150.00 195.00 Unskilled Nos. 2.5 90.00 225.00
Total labour rate 420.00
[C] Water + electric @ 2% of A+B --- --- 37.13
[D] Tools, Equipments & plants @ 2% A+B --- --- 37.13
[E] Scaffolding @ 2% A+B --- --- 37.13
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 295.1517
Total cost 2262.83 Rs
Unit Rate 226 Rs/Sqm
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
Half brick masonary in common brunt clay building bricks having crushing strength not less than 35 Kg./Sq.cm. in cement mortar 1:3 (1 Cement : 3 coarse sand) in Ground floor., Conventional
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculation for rate analysis for Brick work for 10 Sqm
[A] Materials1. Bricks Bricks = 0.24 x 0.085 = 0.0204 = 10 / 0.0204 = 490.20 = 490.20 + 10% Wastage = 539 Bricks
2. Cement Wet Mortar = [10 - (490 x 0.23 x 0.075)] x 0.115 = 0.18 + 5% Wastage = 0.19 cu.m. Dry Mortar = 0.19 x 1.25 (25% Shrinkage Factor) = 0.24 cu.m.
Cement = 0.24 / 4 = 0.048 + 2% Wastage = 1.38 Bags
3. Sand Qty = 0.24 x 3 /4 = 0.18 + 10% Wastage = 0.20 cu.m.
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.3.04
Cu.m
For 10 Cum
[A] Materials
Bricks Nos. 4314 2.10 9059.40
Cement Bags 12.14 200.00 2428.00
Sand cu.m. 2.74 142.00 389.08
Total material rate 11876.48
[B] Labours Skilled Nos. 9.8 150.00 1470.00 Unskilled Nos. 21.3 90.00 1917.00 10% extre labour for rise 338.70
Total labour rate 3725.70
[C] Water + electric @ 2% of A+B --- --- 312.04
[D] Tools, Equipments & plants @ 2% A+B --- --- 312.04
[E] Scaffolding @ 2% A+B --- --- 312.04
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2480.74662
Total cost 19019.06 Rs
Unit Rate 1902 Rs/Cum
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
Brick work using common brunt clay building bricks having crusing strength not less than 35 Kg/S.cm. for First floor in cement mortar 1:4 (1cement : 4 fine sand), Conventional
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.3.05
Sq.m
For 10 Sqm
[A] Materials
Bricks Nos. 539 2.10 1131.90
Cement Bags 1.38 200.00 276.00
Sand cu.m. 0.20 142.00 28.40
Total material rate 1436.30
[B] Labours Skilled Nos. 1.3 150.00 195.00 Unskilled Nos. 2.5 90.00 225.00
10% extra labour for rise 42.00Total labour rate 462.00
[C] Water + electric @ 2% of A+B --- --- 37.97
[D] Tools, Equipments & plants @ 2% A+B --- --- 37.97
[E] Scaffolding @ 2% A+B --- --- 37.97
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 301.8297
Total cost 2314.03 Rs
Unit Rate 231 Rs/Sqm
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
Half brick masonary in common brunt clay building bricks having crushing strength not less than 35 Kg./Sq.cm. in cement mortar 1:3 (1 Cement : 3 coarse sand) in First floor., Conventional
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.3.06
Cu.m
For 10 Cum
[A] Materials
Bricks Nos. 4314 2.10 9059.40
Cement Bags 12.14 200.00 2428.00
Sand cu.m. 2.74 142.00 389.08
Total material rate 11876.48
[B] Labours Skilled Nos. 9.8 150.00 1470.00 Unskilled Nos. 21.3 90.00 1917.00 20% extre labour for rise 677.40
Total labour rate 4064.40
[C] Water + electric @ 2% of A+B --- --- 318.82
[D] Tools, Equipments & plants @ 2% A+B --- --- 318.82
[E] Scaffolding @ 2% A+B --- --- 318.82
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2534.59992
Total cost 19431.93 Rs
Unit Rate 1943 Rs/Cum
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
Brick work using common brunt clay building bricks having crusing strength not less than 35 Kg/S.cm. for tarrace in cement mortar 1:4 (1cement : 4 fine sand), Conventional
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.3.07
Sq.m
For 10 Sqm
[A] Materials
Bricks Nos. 539 2.10 1131.90
Cement Bags 1.38 200.00 276.00
Sand cu.m. 0.20 142.00 28.40
Total material rate 1436.30
[B] Labours Skilled Nos. 1.3 150.00 195.00 Unskilled Nos. 2.5 90.00 225.00
20% extra labour for rise 84.00Total labour rate 504.00
[C] Water + electric @ 2% of A+B --- --- 38.81
[D] Tools, Equipments & plants @ 2% A+B --- --- 38.81
[E] Scaffolding @ 2% A+B --- --- 38.81
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 308.5077
Total cost 2365.23 Rs
Unit Rate 237 Rs/Sqm
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
Half brick masonary in common brunt clay building bricks having crushing strength not less than 35 Kg./Sq.cm. in cement mortar 1:3 (1 Cement : 3 coarse sand) in Tarrace., Conventional
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.2.01
Cu.m
For 10 Cum
[A] Materials
Cement Bags 36.31 200.00 7262.00
Sand Cum 5.14 142.00 729.88
Brick bats Cum 10.28 175.00 1799.00
Total material rate 9790.88
[B] Labours Skilled Nos. 3.10 150.00 465.00 Unskilled Nos. 23.30 90.00 2097.00
Total labour rate 2562.00
[C] Water + electric @ 2% of A+B --- --- 247.06
[D] Tools, Equipments & plants @ 2% A+B --- --- 247.06
[E] Scaffolding @ 2% A+B --- --- ----
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1927.05
Total cost 14774.04
Unit Rate 1477
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
Providing and laying brick bat cement concrete 1:5:10 (1 Cement : 5 Course sand : 10 hand broken bricks) including ramming, curing complete
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculation for rate analysis for BBCC for 10 Cum
[A] Materials
1. Cement Wet Mix = 10cu.m.
Dry Mix = 15.2 cu.m. (52% Shrinkage Factor)
Cement = 15.2 / 13 = 1.17 / 0.0345 = 35.60 Bags +2% Wastage = 36.31 Bags
2. Sand Qty = (15.2 x 4) / 13 = 4.67 + 10% Wastage = 5.14 cu.m.
3. Brick bats Brick bats = (15.2 x 8) / 13 = 9.35 + 10% Wastage = 10.28 cu.m.
Checked by:
Name of the Project: Vrajnandan Bunglows
Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.2.03
Cu.m
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 2.50 150.00 375.00 Unskilled Nos. 29.00 90.00 2610.00
Total labour rate 2985.00
[C] Water + electric @ 2% of A+B --- --- 457.58
[D] Tools, Equipments & plants @ 2% A+B --- --- 457.58 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 457.58
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3616.34
Total cost 28047.87
Unit Rate 2805
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete 1:1.5:3 (1 Cement : 1.5 Course sand : 3 broken stone aggregate 40 m.m nominal size) including compcting and curing, excluding cost of form work and reinforcement complete in coping and plinth beem
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculation for rate analysis for RCC for 10 Cum
[A] Materials
1. Cement Wet Mix = 10cu.m.
Dry Mix = 15.2 cu.m. (52% Shrinkage Factor) = 15.5 cu.m. (2% Wastage)
Cement = 15.5 / 5.5 = 2.82 + 2% Wastage = 2.88 / 0.0345 = 81.35 bags
2. Sand Qty = (15.5 x 1.5) / 5.5 = 4.23 + 10% Wastage = 4.65 cu.m.
Coarse Aggregates = (15.5 x 3) / 5.5 = 8.46 cu.m. = 10.28 cu.m.
3. Grit Grit (33%) = 8.46 x 0.33 = 2.62 +5% Wastage = 2.96 cu.m.
4. Kapchi Kapchi = 8.46 x 0.67 = 5.64 + 5% Wastage = 5.93 cu.m.
Checked by:
Name of the Project: Vrajnandan Bunglows
Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.03 Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 3.90 150.00 585.00 Unskilled Nos. 39.40 90.00 3546.00
Total labour rate 4131.00
[C] Water + electric @ 2% of A+B --- --- 480.50
[D] Tools, Equipments & plants @ 2% A+B --- --- 480.50 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 480.50
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3846.94
Total cost 29493.23
Unit Rate 2949
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for column including curing etc. complete excluding formwork and reinforcement below plinth lvl.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.04
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 3.00 150.00 450.00 Unskilled Nos. 30.00 90.00 2700.00
Total labour rate 3150.00
[C] Water + electric @ 2% of A+B --- --- 460.88
[D] Tools, Equipments & plants @ 2% A+B --- --- 460.88 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 460.88
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3690.96
Total cost 28297.39
Unit Rate 2830
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for coping and for plinth beam including curing etc. complete excluding formwork and reinforcement for above plinth lvl. and below GF slab.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.05
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 4.70 150.00 705.00 Unskilled Nos. 43.10 90.00 3879.00
Total labour rate 4584.00
[C] Water + electric @ 2% of A+B --- --- 489.56
[D] Tools, Equipments & plants @ 2% A+B --- --- 489.56 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 489.56
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3918.97
Total cost 30045.44
Unit Rate 3005
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg 20mm down size) for column including curing etc. complete excluding formwork and reinforcement for above plinth upto GF slab.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.06
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 4.60 150.00 690.00 Unskilled Nos. 39.10 90.00 3519.00
Total labour rate 4209.00
[C] Water + electric @ 2% of A+B --- --- 482.06
[D] Tools, Equipments & plants @ 2% A+B --- --- 482.06 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 482.06
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3859.35
Total cost 29588.31
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3(1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for lintel bend and chajja slab including curing etc. complete excluding formwork and reinforcement for above plinth and upto GF slab.
Unit Rate 2959
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.3.07
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 4.10 150.00 615.00 Unskilled Nos. 38.10 90.00 3429.00
Total labour rate 4044.00
[C] Water + electric @ 2% of A+B --- --- 478.76
[D] Tools, Equipments & plants @ 2% A+B --- --- 478.76 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 478.76
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3833.11
Total cost 29387.18
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for beam including curing etc. complete excluding formwork and reinforcement for above plinth and upto GF slab.
Unit Rate 2939
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.3.08
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 5.10 150.00 765.00 Unskilled Nos. 51.10 90.00 4599.00
Total labour rate 5364.00
[C] Water + electric @ 2% of A+B --- --- 505.16
[D] Tools, Equipments & plants @ 2% A+B --- --- 505.16 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 505.16
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 4042.99
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for stair case including curing etc. complete excluding formwork and reinforcement for above plinth and below GF slab.
Total cost 30996.26
Unit Rate 3100
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.09
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 5.00 150.00 750.00 Unskilled Nos. 30.10 90.00 2709.00
Total labour rate 3459.00
[C] Water + electric @ 2% of A+B --- --- 467.06
[D] Tools, Equipments & plants @ 2% A+B --- --- 467.06 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 467.06
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3740.0952
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for slab including curing etc. complete excluding cost of formwork and reinforcement for above plinth and below GF slab.
Total cost 28674.06
Unit Rate 2867
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.10
Cum
For 10 Cum
[A] Materials
Cement Bags 36.31 200.00 7262.00
Sand Cum 5.14 142.00 729.88
Brick bats Cum 10.28 175.00 1799.00
Total material rate 9790.88
[B] Labours Skilled Nos. 3.10 150.00 465.00 Unskilled Nos. 23.30 90.00 2097.00 10% extra for rise 256.20
Total labour rate 2818.20
[C] Water + electric @ 2% of A+B --- --- 252.18
[D] Tools, Equipments & plants @ 2% A+B --- --- 252.18
[E] Scaffolding @ 2% A+B --- --- 56.54
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2290.05
Total cost 15460.03
Name of the Project: Vrajnandan Bunglows
Providing and laying BBCC in 1:4:8 (1-cement, 4-fine agg. 8-brick bat) including curing, ramming etc. complete for above GF slab below FF slab.
Unit Rate 1546
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.11
Cum
For 10 Cum
[A] Materials
Cement Bags 65.55 200.00 13110.00
Sand Cum 4.88 142.00 692.96
Sinder Cum 9.55 500.00 4775.00
Total material rate 18577.96
[B] Labours Skilled Nos. 3.10 150.00 465.00 Unskilled Nos. 23.30 90.00 2097.00 10% extra for rise 256.20
Total labour rate 2818.20
[C] Water + electric @ 2% of A+B --- --- 427.92
[D] Tools, Equipments & plants @ 2% A+B --- --- 427.92
[E] Scaffolding @ 2% A+B --- --- 55.80
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3660.72
Total cost 25968.53
Name of the Project: Vrajnandan Bunglows
Providing and sinder concrete in 1:2:4 for sunk slab filling including curing etc. complete above GF slab below FF slab.
Unit Rate 2597
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculation for rate analysis for Sinder concerte for 10 Cum
[A] Materials
1. Cement Wet Mix = 10cu.m.
Dry Mix = 15.2 cu.m. (52% Shrinkage Factor)
Cement = 15.2 / 7 = 2.21 / 0.0345 = 64.26 Bags +2% Wastage = 65.55 Bags
2. Sand Qty = (15.2 x 2) / 7 = 4.34 + 10% Wastage = 4.88 cu.m.
3. Sinder Brick bats = (15.2 x 4) / 7 = 8.68 + 10% Wastage = 9.55 cu.m.
Name of the Project: Vrajnandan Bunglows
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.3.12
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 4.70 150.00 705.00 Unskilled Nos. 43.10 90.00 3879.00 10% extra for rise 458.40
Total labour rate 5042.40
[C] Water + electric @ 2% of A+B --- --- 498.72
[D] Tools, Equipments & plants @ 2% A+B --- --- 498.72
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg 20mm down size) for column including curing etc. complete excluding formwork and reinforcement for above GF slab & upto FF slab.
Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 498.72
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3991.86
Total cost 30604.23
Unit Rate 3060
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.13
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 4.60 150.00 690.00 Unskilled Nos. 39.10 90.00 3519.00 10% extra for rise 420.90
Total labour rate 4629.90
[C] Water + electric @ 2% of A+B --- --- 490.47
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for lintel bend and chajja above including curing etc. complete excluding formwork and reinforcement for above GF slab upto FF slab.
[D] Tools, Equipments & plants @ 2% A+B --- --- 490.47 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 490.47
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3926.27
Total cost 30101.39
Unit Rate 3010
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.14
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 5.10 150.00 765.00 Unskilled Nos. 51.10 90.00 4599.00 10 % extra for rise 536.40
Total labour rate 5900.40
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for stair case including curing etc. complete excluding formwork and reinforcement for above GF slab upto FF slab.
[C] Water + electric @ 2% of A+B --- --- 515.88
[D] Tools, Equipments & plants @ 2% A+B --- --- 515.88 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 515.88
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 4128.28
Total cost 31650
Unit Rate 3165.01
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.3.15
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 5.30 150.00 795.00 Unskilled Nos. 53.00 90.00 4770.00 10 % extra for rise 556.50
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for concrete fins including curing etc. complete excluding formwork and reinforcement for above GF slab upto FF slab.
Total labour rate 6121.50
[C] Water + electric @ 2% of A+B --- --- 520.31
[D] Tools, Equipments & plants @ 2% A+B --- --- 520.31 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 520.31
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 4163.43
Total cost 31919.65
Unit Rate 3192
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.3.16
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 4.10 150.00 615.00 Unskilled Nos. 38.10 90.00 3429.00
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for beam including curing etc. complete excluding formwork and reinforcement for above GF slab and upto FF slab.
Total labour rate 4044.00
[C] Water + electric @ 2% of A+B --- --- 478.76
[D] Tools, Equipments & plants @ 2% A+B --- --- 478.76 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 478.76
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3833.11
Total cost 29387.18
Unit Rate 2939
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.3.17
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 5.00 150.00 750.00
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for slab including curing etc. complete excluding formwork and reinforcement for above GF upto FF slab.
Unskilled Nos. 30.10 90.00 2709.00Total labour rate 3459.00
[C] Water + electric @ 2% of A+B --- --- 467.06
[D] Tools, Equipments & plants @ 2% A+B --- --- 467.06 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 467.06
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3740.0952
Total cost 28674.06
Unit Rate 2867
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.3.18
Cum
For 10 Cum
[A] Materials
Cement Bags 36.31 200.00 7262.00
Sand Cum 5.14 142.00 729.88
Brick bats Cum 10.28 175.00 1799.00
Total material rate 9790.88
[B] Labours Skilled Nos. 3.10 150.00 465.00 Unskilled Nos. 23.30 90.00 2097.00 20% extra for rise 512.40
Name of the Project: Vrajnandan Bunglows
Providing and laying BBCC in 1:4:8 (1-cement, 4-fine agg. 8-brick bat) including curing, ramming etc. complete for above FF slab and upto SF slab.
Total labour rate 3074.40
[C] Water + electric @ 2% of A+B --- --- 257.31
[D] Tools, Equipments & plants @ 2% A+B --- --- 257.31
[E] Scaffolding @ 2% A+B --- --- 257.31
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2045.58
Total cost 15682.78
Unit Rate 1568
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.19
Cum
For 10 Cum
[A] Materials
Cement Bags 65.55 200.00 13110.00
Sand Cum 4.88 142.00 692.96
Sinder Cum 9.55 500.00 4775.00
Total material rate 18577.96
[B] Labours Skilled Nos. 3.10 150.00 465.00 Unskilled Nos. 23.30 90.00 2097.00 20% extra for rise 512.40
Name of the Project: Vrajnandan Bunglows
Providing and sinder concrete in 1:2:4 for sunk slab filling including curing etc. complete above FF slab and upto SF slab.
Total labour rate 3074.40
[C] Water + electric @ 2% of A+B --- --- 433.05
[D] Tools, Equipments & plants @ 2% A+B --- --- 433.05
[E] Scaffolding @ 2% A+B --- --- 433.05
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3442.73
Total cost 26394.23
Unit Rate 2639
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.20
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement,
1.5-fine agg. 3- coarse agg 20mm down size) for column including curing etc.
complete excluding formwork and reinforcement for above FF slab and
upto SF slab.
Total material rate 19893.80
[B] Labours Skilled Nos. 4.70 150.00 705.00 Unskilled Nos. 43.10 90.00 3879.00 20% extra for rise 916.80
Total labour rate 5500.80
[C] Water + electric @ 2% of A+B --- --- 507.89
[D] Tools, Equipments & plants @ 2% A+B --- --- 507.89 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 507.89
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 4064.74
Total cost 31163.02
Unit Rate 3116
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.21
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg.) for lintel bend and chajja including curing etc. complete excluding formwork and reinforcement for above FF slab and upto SF slab.
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 4.60 150.00 690.00 Unskilled Nos. 39.10 90.00 3519.00 20% extra for rise 841.80
Total labour rate 5050.80
[C] Water + electric @ 2% of A+B --- --- 498.89
[D] Tools, Equipments & plants @ 2% A+B --- --- 498.89 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 498.89
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3993.19
Total cost 30614.47
Unit Rate 3061
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.22
Cum
For 10 Cum
[A] Materials
Cement Bags 81.35 200.00 16270.00
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for beam including curing etc. complete excluding formwork and reinforcement for above FF slab & upto SF slab.
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 4.10 150.00 615.00 Unskilled Nos. 38.10 90.00 3429.00 20% extra for rise 808.80
Total labour rate 4852.80
[C] Water + electric @ 2% of A+B --- --- 494.93
[D] Tools, Equipments & plants @ 2% A+B --- --- 494.93 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 494.93
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3961.71
Total cost 30373.11
Unit Rate 3037
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.23
Cum
For 10 Cum
[A] Materials
Name of the Project: Vrajnandan Bunglows
Providing and laying reinforced cement concrete in 1:1.5:3 (1-cement, 1.5-fine agg. 3- coarse agg. 20mm down size) for slab including curing etc. complete excluding formwork and reinforcement for above FF slab upto SF slab.
Cement Bags 81.35 200.00 16270.00
Sand Cum 4.65 142.00 660.30
Grit (10mm. Down Size) Cum 2.96 300.00 888.00
Kapchi (20mm. Down Size) Cum 5.93 350.00 2075.50
Total material rate 19893.80
[B] Labours Skilled Nos. 5.00 150.00 750.00 Unskilled Nos. 30.10 90.00 2709.00 20% extra for rise 691.80
Total labour rate 4150.80
[C] Water + electric @ 2% of A+B --- --- 480.89
[D] Tools, Equipments & plants @ 2% A+B --- --- 480.89 Mixer Machine (On Rent) 120.00 Needle Vibrator 60.00
[E] Scaffolding @ 2% A+B --- --- 480.89
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 3850.0914
Total cost 29517.37
Unit Rate 2952
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculation for rate analysis for BBCC for 10 Cum
Dry Mix = 15.2 cu.m. (52% Shrinkage Factor)
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculation for rate analysis for RCC for 10 Cum
Dry Mix = 15.2 cu.m. (52% Shrinkage Factor)
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculation for rate analysis for Sinder concerte for 10 Cum
Dry Mix = 15.2 cu.m. (52% Shrinkage Factor)
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
For 10 Cum
Rs
Rs/Cum
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.01
Sq.m
For 1.5 Sqm
[A] Materials 12mm ply wood BWR grade Sqm 1.8 485 58.20 (divided by 15 - no of repetitions) Wooden battens Cum 0.04 12350 32.93 (divided by 15 - no of repetitions) Nails kg 0.25 40 10 Binding wire kg 0.25 35 8.75 Deshuttering oil Lit 0.15 15 2.25
Total material rate 112.13
[B] Labours Skilled 0.2 150 30 Unskilled 0.2 90 18
Total labour rate 48.00
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 3.20
[E] Profit & overhead 24.50
Total cost 187.84
Unit Rate 125
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for plinth beam and coping below plinth upto 1.5m depth.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.03
Sq.m
For 0.72 Sqm footing
[A] Materials 12mm ply wood BWR grade Sqm 0.8 485 25.87 (divided by 15 - no of repetitions) Wooden battens Cum 0.02 12350 18.53 (divided by 15 - no of repetitions) Nails kg 0.1 40 4 Binding wire kg 0.12 35 4.2 Deshuttering oil Lit 0.1 15 1.5
Total material rate 54.09
[B] Labours Skilled 0.1 150 15 Unskilled 0.1 90 9
Total labour rate 24.00
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 1.56
[E] Profit & overhead 11.95
Total cost 91.60
Unit Rate 127
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for padetal of column below plinth.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculation for rate analysis for 0.72 Sqm footing
Materials1. 12mm plywood Length=2 x (1.2+1.2+0.03) =4.86 (here 0.3 is for thickness of ply for both sides) Q=4.86 x 0.15=0.729 SqmTotal =0.729+10% wastage=0.8 Sqm
2. Battens Q=4.86 x 0.075 x 0.05=0.018 Cum Q=4 x 0.5 x 0.050 x 0.025=0.0025 CumTotal = 0.0205 + 10% wastage = 0.02253. Nails For first use for 10 Sqm= 5kg For other 15 uses= 1 Kg / every use Total weight= 20 Kg for 10 Sqm for 16 uses Total weight per Sqm per use = 20/10 x 16 = 0.125 Kg / Sqm Total weight for 0.72 Sqm=0.1 Kg
4. Binding Wire Assume 0.1 kg 5. Deshuttering oil Assume 0.1 Lit.
Name of the Project: Vrajnandan Bunglows
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.02
Sq.m
Rate analysis for 3.84 Sqm
[A] Materials 12mm ply wood BWR grade Sqm 4.38 485 141.62 (divided by 15 - no of repetitions) Wooden battens Cum 0.06 12350 52.69 (divided by 15 - no of repetitions) Props Nos. 6 50 15.00 (divided by 20 - no of repetitions) Nails kg 0.38 40 15.2 Binding wire kg 0.4 35 14 Deshuttering oil Lit 0.25 15 3.75 Shakanja Nos. 4 40 3.2
Total material rate 242.26
[B] Labours Skilled 0.96 150 144 Unskilled 0.77 90 69.3
Total labour rate 213.30
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 9.11
[E] Profit & overhead 69.70
Total cost 534.38
Unit Rate 139
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for column below plinth.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis for 3.84 Sqm of column formwork
Materials1. 12mm plywood Q= 2 x 0.35 x 2.4 =1.68 Q=2 x (0.45 + 0.03) x 2.4=2.30 (here 0.3 is for thickness of ply for both sides)Total =3.98+10% wastage=4.38
2. Battens Vertical Q=10 x 0.075 x 0.025 x 2.4=0.045 Horizontal Q=2 x 3 x 0.075 x 0.025 x 0.50=0.0056 Q=2 x 3 x 0.075 x 0.025 x 0.35=0.0039 Q=2 x 4 x 0.25 x 0.075 x 0.025 =0.0038 (L=0.480-0.075-0.075-0.075=0.255) Q=2 x 4 x 0.2 x 0.075 x 0.020 =0.0024 (L=0.350-0.075-0.075=0.2) Total=0.0157Total=0.061 + 5% wastage=0.064
3. Props 6 Nos.
4. Nails For first use for 10 Sqm= 5kg For other 15 uses= 1 Kg / every use Total weight= 20 Kg for 10 Sqm for 16 uses Total weight per Sqm per use = 20/10 x 16 = 0.125 Kg / Sqm Total weight for 3.84 Sqm=0.48 Kg
5. Binding Wire Assume 0.5 kg 6. Deshuttering oil
Name of the Project: Vrajnandan Bunglows
Assume 0.5 Lit.
7. Shakanja Total 6 Nos.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.04
Sq.m
Rate analysis for 3.84 Sqm
[A] Materials 12mm ply wood BWR grade Sqm 4.38 485 141.62 (divided by 15 - no of repetitions) Wooden battens Cum 0.06 12350 52.69 (divided by 15 - no of repetitions) Props Nos. 6 50 15.00 (divided by 20 - no of repetitions) Nails kg 0.38 40 15.2 Binding wire kg 0.4 35 14 Deshuttering oil Lit 0.25 15 3.75 Shakanja Nos. 4 40 3.2
Total material rate 242.26
[B] Labours Skilled 1 150 150 Unskilled 0.9 90 81
Total labour rate 231.00
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 9.47
[E] Profit & overhead 72.41
Total cost 555.14
Unit Rate 145
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for column above plinth and upto Ground Floor slab.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.05
Sq.m
Rate analysis for 2.99 Sqm
[A] Materials 12mm ply wood BWR grade Sqm 3.61 485.00 116.72 (divided by 15 - no of repetitions) Wood Cum 0.02 12350.00 15.89 (divided by 15 - no of repetitions) Props Nos. 3 50.00 7.50 (divided by 20 - no of repetitions) Nails kg 0.5 40.00 20.00 Binding wire kg 0.5 35.00 17.50 Deshuttering oil Lit 0.4 15.00 6.00
Total material rate 183.61
[B] Labours Skilled 0.80 150 120 Unskilled 0.69 90 62.1
Total labour rate 182.10
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 7.31
[E] Profit & overhead 55.95
Total cost 428.98
Unit Rate 143
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for lintel and chajja above plinth and upto Ground Floor slab lvl.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis for 3.84 Sqm of column formwork
Materials1. 12mm plywood For sides 2 x 0.25 x 5=2.5 Sqm For bottom = 1.3 x 0.23 = 0.3 Sqm For bottom= 0.46 x 1.76 = 0.81 Sqm Total = 3.61 Sqm
2. Wood Qty = (5+ 0.46) x 2 x 0.025 x 0.050 =0.0136 Qty = 2 x 1.76 x 0.025 x 0.05=0.004 Total =0.0193
Name of the Project: Vrajnandan Bunglows
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.12.02
Sq.m
Rate analysis for 4.06 Sqm
[A] Materials 12mm ply wood BWR grade Sqm 4.59 485.00 148.41 (divided by 15 - no of repetitions) Wood Cum 0.04 12350.00 30.46 (divided by 15 - no of repetitions) Props Nos. 10 50.00 25.00 (divided by 20 - no of repetitions) Nails kg 0.5 40.00 20.00 Binding wire kg 0.5 35.00 17.50 Deshuttering oil Lit 0.4 15.00 6.00
Total material rate 247.37
[B] Labours Skilled 1.22 150 183 Unskilled 0.69 90 62.1
Total labour rate 245.10
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 9.85
[E] Profit & overhead 75.35
Total cost 577.67
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for Stair case from G.F. to F.F.
Unit Rate 142
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis for 3.84 Sqm of column formwork
Materials1. 12mm plywood For Decking: Inclined Length = 1.54 m Q= 0.915 x 1.54 =1.41 Sqm Landing = 0.915 x 0.665 m Q= 0.915 x 0.665 =0.84 Sqm
For Risers: Nos - 5 (0.180 x 0.915) Q= 5 x 0.915 x 0.18 = 0.82 Sqm
For Strings: Flight Length = 1.54 m (.34 x 1.54) Nos. - 2 Q= 2 x 1.54 x 0.34 = 1.09 Sqm Landing = 1.14 x 0.125 m (Sides - 2) Q= 2 x 1.14 x 0.125 = 0.28 Sqm For Winder Side a (0.915 x 0.23) 0.915+.030 = 0.945 Q= 0.945 x 0.23 = 0.22 Sqm For Winder Side b (0.915 x 0.16) Q= 0.915 x 0.18 = 0.16 Sqm Total = 4.59 + 5% Wastage = 4.81 Sqm
Name of the Project: Vrajnandan Bunglows
PROJECTION
WAIST SLAB
DUE TO WINDER
OF FLIGHT 2
FLIGHT 1
230 18
0
WINDER (BRICK
900
1250
MASONRY)WAIST SLAB
250
180
STEPS
LANDING
665
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.06
Sq.m
For 1.98 Sqm beam formwork
[A] Materials 12mm ply wood BWR grade Sqm 1.677 485 54.22 (divided by 15 - no of repetitions) Wooden battens Cum 0.07 12350 53.52 (divided by 15 - no of repetitions) Props Nos 5 50 12.5 Nails kg 0.25 40 10 Binding wire kg 0.2 35 7 Deshuttering oil Lit 0.2 15 3 Shankaja Nos 5 40 4
Total material rate 140.24
[B] Labours Skilled 0.59 150 88.5 Unskilled 0.4 90 36
Total labour rate 124.50
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 5.29
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for beam at Ground Floor slab.
[E] Profit & overhead 40.51
Total cost 310.54
Unit Rate 157
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculation for rate analysis for 1.98 Sqm beam formwork
Materials1. 12mm plywood Length=2 x (0.28+0.025) x 2.5=1.525 (here 0.025 is for thickness of ply for both sides)
Total =1.525+10% wastage=1.677 Sqm
2. Battens Bottom=0.025 x 0.230 x2.5=0.0144 Cum Sides=2 x 2 x 0.075 x 0.050 x 2.5=0.0375 Cum Sides=2 x 6 x 0.130 x 0.050 x 0.025=0.00195 Cum T head= 5 x 0.3 x 0.075 x 0.05=0.0056 CumTotal = 0.0594 + 10% wastage = 0.065 Cum
3. Props Total Nos. 5
4. Nails For first use for 10 Sqm= 5kg For other 15 uses= 1 Kg / every use Total weight= 20 Kg for 10 Sqm for 16 uses Total weight per Sqm per use = 20/10 x 16 = 0.125 Kg / Sqm Total weight for 1.975 Sqm=0.25
Name of the Project: Vrajnandan Bunglows
5. Binding Wire Assume 0.2 kg 6. Deshuttering oil Assume 0.2 Lit.
7. Shankaja Total No 5
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.07
Sq.m
For 12.8 Sqm
[A] Materials Shuttering plate Nos. 23.7 300 203.14 (divided by 35 - no of repetitions) Wooden battens Cum 0.16 12350 130.09 (divided by 15 - no of repetitions) Props Nos. 42 50 140.00 (divided by 15 - no of repetitions) Nails kg 1.6 40 64 Binding wire kg 1.5 35 52.5 Deshuttering oil Lit 2 15 30
Total material rate 619.73
[B] Labours Skilled 2.94 150 441 Unskilled 2.56 90 230.4
Total labour rate 671.40
[C] Water + electric @ 2% of A+B 0.00
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for Ground Floor slab.
[D] Tools, Equipments & plants @ 2% A+B 25.82
[E] Profit & overhead @ 15% of A+B+C+D 197.54
Total cost 1514.49
Unit Rate 118
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculation for 12.8 Sqm
[A] Materials1. Shuttering plate Area of 1 plate= 0.9 x 0.6=0.54 Sqm No of Shuttering plates= 12.8/0.54 = 23.7 Nos
2. Battens Total No= 4/0.9 = 5+1=6 Nos Total volume= 6 x 3.2 x 0.1 x 0.075 = 0.144 Material wastage 10% = 0.144 x 1.1 = 0.158
3. Props Total Nos.= 42 Nos
4. Nails For first use for 10 Sqm= 5kg For other 15 uses= 1 Kg / every use Total weight= 20 Kg for 10 Sqm for 16 uses Total weight per Sqm per use = 20/10 x 16 = 0.125 Kg / Sqm Total weight for 12.8 Sqm=1.6 Kg
5. Binding Wire Assume 1.5 Kg for 12.8 Sqm slab formwork
Name of the Project: Vrajnandan Bunglows
6. Deshuttering Oil Assume 2 Lit. for 12.8 Sqm formwork
[B] Labours Skilled 0.23 / Sqm Unskilled 0.2/ Sqm Total Skilled = 0.23 x 12.8= 2.94 Total Unskilled = 0.23 x 12.8= 2.54
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.08
Sq.m
Rate analysis for 3.84 Sqm
[A] Materials 12mm ply wood BWR grade Sqm 4.38 485 141.62 (divided by 15 - no of repetitions) Wooden battens Cum 0.06 12350 52.69 (divided by 15 - no of repetitions) Props Nos. 6 50 15.00 (divided by 20 - no of repetitions) Nails kg 0.38 40 15.2 Binding wire kg 0.4 35 14 Deshuttering oil Lit 0.25 15 3.75 Shakanja Nos. 4 40 3.2
Total material rate 242.26
[B] Labours Skilled 1 150 150 Unskilled 0.9 90 81
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for stub column of First Floor.
10% extra for rise 23.1Total labour rate 254.10
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 9.93
[E] Profit & overhead 75.94
Total cost 582.23
Unit Rate 152
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.09
Sq.m
Rate analysis for 2.99 Sqm
[A] Materials 12mm ply wood BWR grade Sqm 3.61 485.00 116.72 (divided by 15 - no of repetitions) Wood Cum 0.02 12350.00 15.89 (divided by 15 - no of repetitions) Props Nos. 3 50.00 7.50 (divided by 20 - no of repetitions) Nails kg 0.5 40.00 20.00 Binding wire kg 0.5 35.00 17.50 Deshuttering oil Lit 0.4 15.00 6.00
Total material rate 183.61
[B] Labours Skilled 0.80 150 120
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for lintel and chajja at First Floor Lintel Level.
Unskilled 0.69 90 62.1 10 % extra for rise 18.21
Total labour rate 200.31
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 7.68
[E] Profit & overhead 58.74
Total cost 450.34
Unit Rate 151
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.14
Sq.m
Rate analysis for 3.84 Sqm
[A] Materials 12mm ply wood BWR grade Sqm 4.38 485 141.62 (divided by 15 - no of repetitions) Wooden battens Cum 0.06 12350 52.69 (divided by 15 - no of repetitions) Props Nos. 6 50 15.00 (divided by 20 - no of repetitions) Nails kg 0.38 40 15.2 Binding wire kg 0.4 35 14 Deshuttering oil Lit 0.25 15 3.75 Shakanja Nos. 4 40 3.2
Total material rate 242.26
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for Sloping Roof at First Floor Lintel slab.
[B] Labours Skilled 1.2 150 180 Unskilled 1.1 90 99 10% extra for rise 27.9
Total labour rate 306.90
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 10.98
[E] Profit & overhead 84.02
Total cost 644.17
Unit Rate 168
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.10
Sq.m
For 1.98 Sqm beam formwork
[A] Materials 12mm ply wood BWR grade Sqm 1.677 485 54.22 (divided by 15 - no of repetitions) Wooden battens Cum 0.07 12350 53.52 (divided by 15 - no of repetitions) Props Nos 5 50 12.5 Nails kg 0.25 40 10 Binding wire kg 0.2 35 7 Deshuttering oil Lit 0.2 15 3 Shankaja Nos 5 40 4
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for beams First Floor slab level.
Total material rate 140.24
[B] Labours Skilled 0.59 150 88.5 Unskilled 0.4 90 36 10% extra for rise 12.45
Total labour rate 136.95
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 5.54
[E] Profit & overhead 42.41
Total cost 325.14
Unit Rate 164
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.4.11
Sq.m
For 12.8 Sqm
[A] Materials Shuttering plate Nos. 23.7 300 203.14 (divided by 35 - no of repetitions) Wooden battens Cum 0.16 12350 130.09 (divided by 15 - no of repetitions) Props Nos. 42 50 140.00 (divided by 15 - no of repetitions) Nails kg 1.6 40 64 Binding wire kg 1.5 35 52.5 Deshuttering oil Lit 2 15 30
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for First Floor slab.
Total material rate 619.73
[B] Labours Skilled 2.94 150 441 Unskilled 2.56 90 230.4 10% extra for rise 67.14
Total labour rate 738.54
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 27.17
[E] Profit & overhead @ 15% of A+B+C+D 207.82
Total cost 1593.25
Unit Rate 124
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Item Item Description Unit Quantity Rate AmountNo.4.12
Sq.m
For 1.98 Sqm beam formwork
[A] Materials 12mm ply wood BWR grade Sqm 1.677 485 54.22 (divided by 15 - no of repetitions) Wooden battens Cum 0.07 12350 53.52 (divided by 15 - no of repetitions) Props Nos 5 50 12.5 Nails kg 0.25 40 10 Binding wire kg 0.2 35 7 Deshuttering oil Lit 0.2 15 3 Shankaja Nos 5 40 4
Total material rate 140.24
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for Lintel beams First Floor lintel level.
[B] Labours Skilled 0.5 150 75 Unskilled 0.3 90 27 10% extra for rise 10.2
Total labour rate 112.20
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 5.05
[E] Profit & overhead 38.62
Total cost 296.11
Unit Rate 150
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Item Item Description Unit Quantity Rate AmountNo.4.13
Sq.m
For 12.8 Sqm
[A] Materials Shuttering plate Nos. 23.7 300 203.14 (divided by 35 - no of repetitions) Wooden battens Cum 0.16 12350 130.09 (divided by 15 - no of repetitions) Props Nos. 42 50 140.00 (divided by 15 - no of repetitions) Nails kg 1.6 40 64 Binding wire kg 1.5 35 52.5 Deshuttering oil Lit 2 15 30
Total material rate 619.73
Name of the Project: Vrajnandan Bunglows
Providing and erecting formwork including deshuttering etc. complete for First Floor Lintel slab.
[B] Labours Skilled 2.5 150 375 Unskilled 2 90 180 10% extra for rise 55.5
Total labour rate 610.50
[C] Water + electric @ 2% of A+B 0.00
[D] Tools, Equipments & plants @ 2% A+B 24.60
[E] Profit & overhead @ 15% of A+B+C+D 188.23
Total cost 1443.06
Unit Rate 113
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Length=2 x (1.2+1.2+0.03) =4.86 (here 0.3 is for thickness of ply for both sides)
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Q=2 x (0.45 + 0.03) x 2.4=2.30 (here 0.3 is for thickness of ply for both sides)
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
For Winder Side a (0.915 x 0.23)
For Winder Side b (0.915 x 0.16)
WINDER (BRICK
900
1250
MASONRY)WAIST SLAB
250
180
STEPS
LANDING
665
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Length=2 x (0.28+0.025) x 2.5=1.525 (here 0.025 is for thickness of ply for both sides)
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs/Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.5.01
Kg.
For 100 Kg
[A] Materials Reinforcement Bars kgs. 102.00 33.00 3366.00 Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3821.00
[B] Labours Skilled 1 150 150 Unskilled 1 90 90
Total labour rate 240.00
[C] Water + electric @ 2% of A+B --- --- 0.00
[D] Tools, Equipments & plants @ 2% A+B --- --- 81.22
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 621.33
Total cost 4763.55 Rs
Unit Rate 48 Rs / Kg
Checked by:
Name of the Project: Vrajnandan Bunglows
Providing, fabricating & erecting tor steel ( yield strength 4250 kg/cm2 ) bars for RCC work Including binding, bending and placing in position etc. complete. for below plinth level. (coping, footing, plinth beam, column)
Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.5.02
Kg.
For 100 Kg
[A] Materials Reinforcement Bars kgs. 102.00 31.00 3162.00 Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3617.00
[B] Labours Skilled 1 150 150 Unskilled 1 90 90
Total labour rate 240.00
[C] Water + electric @ 2% of A+B --- --- 0.00
[D] Tools, Equipments & plants @ 2% A+B --- --- 77.14
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 590.12
Total cost 4524.26 Rs
Unit Rate 45 Rs / Kg
Name of the Project: Vrajnandan Bunglows
Providing, fabricating & erecting mild steel ( yield strength 2600 kg/cm2 )bars for RCC work Including binding, bending and placing in position etc. complete for below plinth level. (coping, footing, plinth beam, column)
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.5.03
Kg.
For 100 Kg
[A] Materials Reinforcement Bars kgs. 102.00 33.00 3366.00 Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3821.00
[B] Labours Skilled 1 150 150 Unskilled 1 90 90
Total labour rate 240.00
[C] Water + electric @ 2% of A+B --- --- 0.00
[D] Tools, Equipments & plants @ 2% A+B --- --- 81.22
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 621.33
Total cost 4763.55 Rs
Unit Rate 48 Rs / Kg
Name of the Project: Vrajnandan Bunglows
Providing, fabricating & erecting tor steel ( yield strength 4250 kg/cm2 ) bars for RCC work Including binding, bending and placing in position etc. complete. for Ground Floor slab level. (beam, slab, stub column)
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.5.04
Kg.
For 100 Kg
[A] Materials Reinforcement Bars kgs. 102.00 31.00 3162.00 Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3617.00
[B] Labours Skilled 1 150 150 Unskilled 1 90 90
Total labour rate 240.00
[C] Water + electric @ 2% of A+B --- --- 0.00
[D] Tools, Equipments & plants @ 2% A+B --- --- 77.14
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 590.12
Total cost 4524.26 Rs
Unit Rate 45 Rs / Kg
Name of the Project: Vrajnandan Bunglows
Providing, fabricating & erecting mild steel ( yield strength 2600 kg/cm2 )bars for RCC work Including binding, bending and placing in position etc. complete for Ground Floor slab level. (beam, slab, stub column)
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.5.05
Kg.
For 100 Kg
[A] Materials Reinforcement Bars kgs. 102.00 33.00 3366.00 Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3821.00
[B] Labours Skilled 1 150 150 Unskilled 1 90 90 10% extra for rise 24
Total labour rate 264.00
[C] Water + electric @ 2% of A+B --- --- 0.00
[D] Tools, Equipments & plants @ 2% A+B --- --- 81.70
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 625.01
Total cost 4791.71 Rs
Unit Rate 48 Rs / Kg
Name of the Project: Vrajnandan Bunglows
Providing, fabricating & erecting tor steel ( yield strength 4250 kg/cm2 ) bars for RCC work Including binding, bending and placing in position etc. complete. for First Floor slab level. (beam, slab, stub column)
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount Remarks
No.5.06
Kg.
For 100 Kg
[A] Materials Reinforcement Bars kgs. 102.00 31.00 3162.00 Binding wire (@ 1.3kg/ 100kgs.) kgs. 13.00 35.00 455.00
Total material rate 3617.00
[B] Labours Skilled 1 150 150 Unskilled 1 90 90 10% extra for rise 24
Total labour rate 264.00
[C] Water + electric @ 2% of A+B --- --- 0.00
[D] Tools, Equipments & plants @ 2% A+B --- --- 72.82
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 557.07
Total cost 4270.89 Rs
Unit Rate 43 Rs / Kg
Checked by:Date: Page No.
Name of the Project: Vrajnandan Bunglows
Providing, fabricating & erecting mild steel ( yield strength 2600 kg/cm2 )bars for RCC work Including binding, bending and placing in position etc. complete for First Floor slab level. (beam, slab, stub column)
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.01
Sq.m
For 100 Sqm
[A] Materials Cement Bags 16.94 160.00 2710.40 Sand Cum 2.29 110.00 251.90
Total material rate 2962.30
[B] Labours Skilled 8.50 150 1275 Unskilled 28.00 90 2520
Total labour rate 3795.00
[C] Water + electric @ 2% of A+B --- --- 135.15
[D] Tools, Equipments & plants @ 2% A+B --- --- 135.15
[E] Scaffolding @ 2% A+B --- --- 135.15
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1074.41
Total cost 8237.15
Unit Rate 82
Checked by:
Name of the Project: Vrajnandan Bunglows
Proving and laying 20 mm thick double coat Mala finished cement plaster consisty of 10mm thick cement plaster each in two coats on fair sides of Brick walls for interior plastering in C.M. 1:3 (1 cement : 3 sand) including Mala finishing etc. complete for
Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis of 100 Sqm
[A] Materials1st Coat (1:4)Wet Mortar = 100 x 0.012 = 1.20 + 10% Wastage = 1.32 cu.m.Dry Mortar = 1.32 x 1.25 (25% Shrinkage) = 1.65 cu.m.
Cement = 1.65 / 5 = 0.33 + 2% Wastage = 0.34 / 0.345 = 9.60 Bags
Sand = (1.65 x 4) / 5 = 1.32 + 10% Wastage = 1.45 cu.m.
2nd Coat (1:3)Wet Mortar = 100 x 0.008 = 0.80 + 10% Wastage = 0.82 cu.m.Dry Mortar = 0.82 x 1.25 (25% Shrinkage) = 1.02 cu.m.
Cement = 1.02 / 4 = 0.255 + 2% Wastage = 0.26 / 0.345 = 7.34 Bags
Sand = (1.02 x 3) / 4 = 0.765 + 10% Wastage = 0.84 cu.m. For Third coat = 10 Kg Total weight=30.7 Kg + 10% wastage Total qty = 33.77 Kg
Name of the Project: Vrajnandan Bunglows
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.02
Sq.m
For 100 Sqm
[A] Materials Cement Bags 7.07 160.00 1131.20 Sand Cum 1.08 110.00 118.80
Total material rate 1250.00
[B] Labours Skilled 4.00 150 600 Unskilled 20.00 90 1800
Total labour rate 2400.00
[C] Water + electric @ 2% of A+B --- --- 73.00
[D] Tools, Equipments & plants @ 2% A+B --- --- 73.00
[E] Scaffolding @ 2% A+B --- --- 73.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 580.35
Total cost 4449.35
Unit Rate 44
Name of the Project: Vrajnandan Bunglows
Proving and laying 20 mm thick double coat Mala finished cement plaster consisty of 10mm thick cement plaster each in two coats on ceiling, soffit of beam of concrete for interior plastering in C.M. 1:3 (1 cement : 3 sand) including Mala finishing etc. co
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis of 100 Sqm
[A] MaterialsProportion 1:4Wet Mortar = 100 x 0.010 = 1.00 + 10% Wastage = 1.1 cu.m.Dry Mortar = 1.1 x 1.25 (25% Shrinkage) = 1.23 Cum
Cement = 1.45 / 5 = 0.24 + 2% Wastage = 0.244 / 0.345 = 7.07 Bags
Sand = (1.65 x 4) / 5 = 0.98 + 10% Wastage = 1.08 Cum
Name of the Project: Vrajnandan Bunglows
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.03
Sq.m
For 100 Sqm
[A] Materials Cement Bags 15.68 160.00 2508.80 Sand Cum 2.35 110.00 258.50
Total material rate 2767.30
[B] Labours Skilled 9.50 150 1425 Unskilled 30.00 90 2700
Total labour rate 4125.00
[C] Water + electric @ 2% of A+B --- --- 137.85
[D] Tools, Equipments & plants @ 2% A+B --- --- 137.85
[E] Scaffolding @ 2% A+B --- --- 137.85
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1095.88
Total cost 8401.71
Unit Rate 84
Name of the Project: Vrajnandan Bunglows
Providing & applying 20mm thick double coat sand face external plaster consisry of 10mm thick plaster each in two coats, first coat in CM 1:4 (1cement : 4sand), second coat in CM 1:2 (1cemnt : 2sand) on fair sides of Brick wall including scaffolding, curi
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis of 100 Sqm
[A] Materials1st Coat (1:4)Wet Mortar = 100 x 0.012 = 1.20 + 10% Wastage = 1.32 cu.m.Dry Mortar = 1.32 x 1.25 (25% Shrinkage) = 1.65 cu.m.
Cement = 1.65 / 5 = 0.33 + 2% Wastage = 0.34 / 0.345 = 9.60 Bags
Sand = (1.65 x 4) / 5 = 1.32 + 10% Wastage = 1.45 cu.m.
2nd Coat (1:4)Wet Mortar = 100 x 0.008 = 0.80 + 10% Wastage = 0.82 cu.m.Dry Mortar = 0.82 x 1.25 (25% Shrinkage) = 1.02 cu.m.
Cement = 1.02 / 5 = 0.204 + 2% Wastage = 0.21 / 0.345 = 6.08 Bags
Sand = (1.02 x 4) / 5 = 0.816 + 10% Wastage = 0.90 cu.m.
Name of the Project: Vrajnandan Bunglows
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.10
Sq.m
For 100 Sqm
[A] Materials Cement Bags 16.94 160.00 2710.40 Sand Cum 2.29 110.00 251.90
Total material rate 2962.30
[B] Labours Skilled 8.50 150 1275 Unskilled 28.00 90 2520 10% extra for rise 379.5
Total labour rate 4174.50
[C] Water + electric @ 2% of A+B --- --- 142.74
[D] Tools, Equipments & plants @ 2% A+B --- --- 142.74
[E] Scaffolding @ 2% A+B --- --- 142.74
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1134.75
Total cost 8699.76
Unit Rate 87
Name of the Project: Vrajnandan Bunglows
Proving and laying 20 mm thick double coat Mala finished cement plaster consisty of 10mm thick cement plaster each in two coats on over head water tank plastering in C.M. 1:3 (1 cement : 3 sand) including Mala finishing etc. complete for Tarrace.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.06
Sq.m
For 100 Sqm
[A] Materials Cement Bags 16.94 160.00 2710.40 Sand Cum 2.29 110.00 251.90
Water proofing agent @ 100ml/bag Lit 1.69 100.00 169.00Total material rate 3131.30
[B] Labours Skilled 8.00 150 1200 Unskilled 28.00 90 2520 10 % extra for rise 37.2
Total labour rate 3757.20
[C] Water + electric @ 2% of A+B --- --- 137.77
[D] Tools, Equipments & plants @ 2% A+B --- --- 137.77
[E] Scaffolding @ 2% A+B --- --- 137.77
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1095.27
Total cost 8397.08
Unit Rate 84
Name of the Project: Vrajnandan Bunglows
Proving and laying 20 mm thick double coat Mala finished cement plaster consisty of 10mm thick cement plaster each in two coats on ceiling, soffit of beam of concrete for interior plastering in C.M. 1:3 (1 cement : 3 sand) including Mala finishing etc. complete for First Floor.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.04
Sq.m
For 100 Sqm
[A] Materials Cement Bags 15.68 160.00 2508.80 Sand Cum 2.35 110.00 258.50
Total material rate 2767.30
[B] Labours Skilled 9.50 150 1425 Unskilled 30.00 90 2700 10% extra for lift 412.5
Total labour rate 4537.50
[C] Water + electric @ 2% of A+B --- --- 146.10
[D] Tools, Equipments & plants @ 2% A+B --- --- 146.10
[E] Scaffolding @ 2% A+B --- --- 146.10
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1161.46
Total cost 8904.55
Unit Rate 89
Name of the Project: Vrajnandan Bunglows
Providing & applying 20mm thick double coat sand face external plaster consisry of 10mm thick plaster each in two coats, first coat in CM 1:4 (1cement : 4sand), second coat in CM 1:2 (1cemnt : 2sand) on fair sides of Concrete slab including scaffolding, c
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.05
Sq.m
For 100 Sqm
[A] Materials Cement Bags 16.94 160.00 2710.40 Sand Cum 2.29 110.00 251.90
Total material rate 2962.30
[B] Labours Skilled 8.50 150 1275 Unskilled 28.00 90 2520 20% extra for rise 759
Total labour rate 4554.00
[C] Water + electric @ 2% of A+B --- --- 150.33
[D] Tools, Equipments & plants @ 2% A+B --- --- 150.33
[E] Scaffolding @ 2% A+B --- --- 150.33
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1195.09
Total cost 9162.37
Unit Rate 92
Name of the Project: Vrajnandan Bunglows
Proving and laying 20 mm thick double coat Mala finished cement plaster consisty of 10mm thick cement plaster each in two coats on fair sides of Brick walls for interior plastering in C.M. 1:3 (1 cement : 3 sand) including Mala finishing etc. complete for First Floor.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.09
Sq.m
For 100 Sqm
[A] Materials Cement Bags 7.07 160.00 1131.20 Sand Cum 1.08 110.00 118.80
Total material rate 1250.00
[B] Labours Skilled 4.00 150 600 Unskilled 20.00 90 1800 20% extra for rise 480
Total labour rate 2880.00
[C] Water + electric @ 2% of A+B --- --- 82.60
[D] Tools, Equipments & plants @ 2% A+B --- --- 82.60
[E] Scaffolding @ 2% A+B --- --- 82.60
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 656.67
Total cost 5034.47
Name of the Project: Vrajnandan Bunglows
Providing & applying 20mm thick double coat sand face external plaster consisry of 10mm thick plaster each in two coats, first coat in CM 1:4 (1cement : 4sand), second coat in CM 1:2 (1cemnt : 2sand) on both sides of Brick wall including scaffolding, curing etc. complete for at Tarrace level.
Unit Rate 50
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.07
Sq.m
For 100 Sqm
[A] Materials Cement Bags 15.68 160.00 2508.80 Sand Cum 2.35 110.00 258.50
Total material rate 2767.30
[B] Labours Skilled 9.50 150 1425 Unskilled 30.00 90 2700 20% extra for lift 825
Total labour rate 4950.00
[C] Water + electric @ 2% of A+B --- --- 154.35
[D] Tools, Equipments & plants @ 2% A+B --- --- 154.35
[E] Scaffolding @ 2% A+B --- --- 154.35
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1227.05
Name of the Project: Vrajnandan Bunglows
Providing & applying 20mm thick double coat sand face external plaster consisry of 10mm thick plaster each in two coats, first coat in CM 1:4 (1cement : 4sand), second coat in CM 1:2 (1cemnt : 2sand) on fair sides of Brick wall including scaffolding, curing etc. complete for at First Floor level.
Total cost 9407.39
Unit Rate 94
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.08
Sq.m
For 100 Sqm
[A] Materials Cement Bags 15.68 160.00 2508.80 Sand Cum 2.35 110.00 258.50
Total material rate 2767.30
[B] Labours Skilled 9.50 150 1425 Unskilled 30.00 90 2700 30% extra for lift 1237.5
Total labour rate 5362.50
[C] Water + electric @ 2% of A+B --- --- 162.60
[D] Tools, Equipments & plants @ 2% A+B --- --- 162.60
[E] Scaffolding @ 2% A+B --- --- 162.60
Name of the Project: Vrajnandan Bunglows
Providing & applying 20mm thick double coat sand face external plaster consisry of 10mm thick plaster each in two coats, first coat in CM 1:4 (1cement : 4sand), second coat in CM 1:2 (1cemnt : 2sand) on fair sides of Concrete slab including scaffolding, curing etc. complete for at First Floor level.
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1292.64
Total cost 9910.23
Unit Rate 99
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
= 1.20 + 10% Wastage
= 0.80 + 10% Wastage
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
= 1.00 + 10% Wastage
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
= 1.20 + 10% Wastage
= 0.80 + 10% Wastage
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.10.01
Sq.m
For 1.78 Sqm
[A] Materials
Teak Wood Cum 0.07 20000.00 1340.00
Glass Sqm 1.23 300.00 369.00
Beading Rmt 3.47 21.00 72.79
Bars Kg 10.85 32.00 347.20
Hardware
Handles Nos. 2.00 15.00 30.00
Hook & Eye Nos. 4.00 7.00 28.00
Butt Hinges Nos. 4.00 9.00 36.00
Stopper Nos. 4.00 10.00 40.00
Holdfast Nos. 4.00 3.00 12.00
Nails + Fevicol (2% of Hardware) 2.92Total material rate 2277.91
[B] Labours Skilled 2.31 150 346.5 Unskilled 0.71 90 63.9 Fixing 40
Total labour rate 450.40
[C] Water + electric @ 2% of A+B --- --- 54.57
[D] Tools, Equipments & plants @ 2% A+B --- --- 54.57
[E] Scaffolding @ 2% A+B --- --- 54.57
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 433.80
Total cost 3325.81
Unit Rate 1868
Checked by:
Name of the Project: Vrajnandan Bunglows
Providing and fixing frame of C P sag and glassed window including hardware, finishing etc. complete at Ground Floor level.
Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis of 1.92 Sqm
[A] Materials
For Shutter: 1. Wood(30 mm): Style (Nos. - 4) Q= 4 x 0.03 x 0.075 x 1.3 = 0.0117 Cum Rails (Nos. - 4) Q= 4 x 0.03 x 0.075 x 0.685 = 0.00616 CumFor Frame: (125 x 65) Length = 1.37+1.37+1.3+1.3 = 5.34 Q= 0.125 x 0.065 x 5.34 = 0.0433 Cum Total = 0.06116Cum Total = 0.06116 + 10% Wastage = 0.0672
2. Glass (6 mm): Q= 2 x 0.535 x 1.15 = 1.23 Sqm
3. Beading: (0.685 + 1.15) Q= 2 x 2 x 0.685 x 1.15 = 3.466 CumTotal = 0.0024 + 5% Wastage = 0.00364. For steel bar (Nos. - 9) Q= 9 x 0.88 x 1.37 = 10.85 KgTotal = 10.85 + 5% Wastage = 16.275
Name of the Project: Vrajnandan Bunglows
6851520
1300
535
1150
GLAZING
HORNS
HOLDFAST
BEADING
FRAME
RAILS
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.10.02
Sq.m
For 1.92 Sqm
[A] Materials
BlockBoard Sqm 1.92 550.00 1056.00
6mm Plywood Sqm 3.84 260.00 998.40
Wood Cum 0.04 20000.00 878.00
Hardware
Handles Nos. 2.00 20.00 40.00
Tower Bolts Nos. 1.00 15.00 15.00
Butt Hinges Nos. 3.00 11.00 33.00
Aldrop Nos. 1.00 15.00 15.00
Holdfast Nos. 6.00 3.00 18.00
Nails + Fevicol (2% of Hardware) 2.42Total material rate 3055.82
[B] Labours Skilled 2.49 150 373.5 Unskilled 0.77 90 69.12 Fixing 40
Total labour rate 482.62
[C] Water + electric @ 2% of A+B --- --- 70.77
[D] Tools, Equipments & plants @ 2% A+B --- --- 70.77
[E] Scaffolding @ 2% A+B --- --- 70.77
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 562.61
Total cost 4313.36
Unit Rate 2247
Name of the Project: Vrajnandan Bunglows
Providing and fixing frame of C P sag and flushed door including hardware, finishing etc. complete at Ground Floor level.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis of 1.92 Sqm
[A] Materials
For Shutter: 1. Block Board (25 mm): Q= 0.915 x 2.1 = 1.92 Sqm Total = 1.92 + 5% Wastage = 0.096
2. Plywood (6 mm): Q= 2 x 0.915 x 2.1 = 3.84 SqmTotal = 3.84 + 5% Wastage = 4.03
3. Wood (5 mm): L= 6.03 Q= 2 x 0.040 x 6.03 x 0.005 = 0.0024 CumTotal = 0.0024 + 5% Wastage = 0.0036
For Frame: (125 x 65)3. Wood Length = 2.1+2.1+0.915 =5.115 Q= 0.125 x 0.065 x 5.115 = 0.0415 CumTotal = 0.0415 + 5% Wastage = 0.0436
Name of the Project: Vrajnandan Bunglows
HOLDFAST
HORNS
WOODEN FRAME
915
2100
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.10.05
Sq.m
For 1.78 Sqm
[A] Materials
Teak Wood Cum 0.07 20000.00 1340.00
Glass Sqm 1.23 300.00 369.00
Beading Rmt 3.47 21.00 72.79
Bars Kg 10.85 32.00 347.20
Hardware
Handles Nos. 2.00 15.00 30.00
Hook & Eye Nos. 4.00 7.00 28.00
Butt Hinges Nos. 4.00 9.00 36.00
Stopper Nos. 4.00 10.00 40.00
Holdfast Nos. 4.00 3.00 12.00
Nails + Fevicol (2% of Hardware) 2.92Total material rate 2277.91
[B] Labours Skilled 2.31 150 346.5 Unskilled 0.71 90 63.9 Fixing 60
Total labour rate 470.40
[C] Water + electric @ 2% of A+B --- --- 54.97
[D] Tools, Equipments & plants @ 2% A+B --- --- 54.97
[E] Scaffolding @ 2% A+B --- --- 54.97
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 436.98
Total cost 3350.19
Name of the Project: Vrajnandan Bunglows
Providing and fixing frame of C P sag and glassed window including hardware, finishing etc. complete at First Floor level.
Unit Rate 1882
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.10.06
Sq.m
For 1.92 Sqm
[A] Materials
BlockBoard Sqm 1.92 550.00 1056.00
6mm Plywood Sqm 3.84 260.00 998.40
Wood Cum 0.04 20000.00 878.00
Hardware
Handles Nos. 2.00 20.00 40.00
Tower Bolts Nos. 1.00 15.00 15.00
Butt Hinges Nos. 3.00 11.00 33.00
Aldrop Nos. 1.00 15.00 15.00
Holdfast Nos. 6.00 3.00 18.00
Nails + Fevicol (2% of Hardware) 2.42Total material rate 3055.82
[B] Labours Skilled 2.49 150 373.5 Unskilled 0.77 90 69.12 Fixing 60
Total labour rate 502.62
[C] Water + electric @ 2% of A+B --- --- 71.17
[D] Tools, Equipments & plants @ 2% A+B --- --- 71.17
[E] Scaffolding @ 2% A+B --- --- 71.17
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 565.79
Total cost 4337.74
Unit Rate 2259
Name of the Project: Vrajnandan Bunglows
Providing and fixing frame of C P sag and flushed door including hardware, finishing etc. complete at First Floor level.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
6851520
1300
535
1150
GLAZING
HORNS
HOLDFAST
BEADING
FRAME
RAILS
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
HOLDFAST
HORNS
WOODEN FRAME
915
2100
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
6.01
Sqm
For 100 Sqm
[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
White Cement Bags 6.00 550.00 3300.00
Marble (With Polishing) Sqm 105.00 970.00 101850.00Total material rate 109956.80
[B] Labours Skilled 5.20 150 780 Unskilled 9.80 90 882
Total labour rate 1662.00
[C] Water + electric @ 2% of A+B --- --- 2232.38
[D] Tools, Equipments & plants @ 2% A+B --- --- 2232.38
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 17412.53
Total cost 133496.08
Unit Rate 1335
Name of the Project: Vrajnandan Bunglows
Providing and laying marble flooring with bed mortar 1:8 (1 cement, 8sand) including cutting finishing, filling up of joints, polishing etc. complete for above plinth lvl. below GF slab.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis of 100 Sqm
[A] MaterialsMarble = 100 sq.m. + 5% Wastage = 105 sq.m.
Wet Mortar = 100 x 0.05 = 5 cu.m.Dry Mortar = 5 cu.m. x 1.25 (Shrinkage Factor 25%) = 6.25 cu.m.
Cement = 6.25 / 7 = 0.89 + 2% Wastage = 0.90 / 0.0345 = 26 Bags
Sand = 6.25 x 6 / 7 = 5.35 + 10% Wastage = 5.88 cu.m.
White Cement = 3 kg. per sq.m. = 3 x 100 = 300 kgs. = 3 Bags.
Name of the Project: Vrajnandan Bunglows
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.02
Rmt
For 100 Rmt
[A] Materials
Cement (OPC) Bags 2.21 160.00 353.60
Sand Cum 0.08 110.00 8.80
White Cement Bags 0.47 550.00 258.50
Marble (With Polishing) Sqm 7.88 970.00 7643.60Total material rate 8264.50
[B] Labours Skilled 4.00 150 600 Unskilled 4.00 90 360
Total labour rate 960.00
[C] Water + electric @ 2% of A+B --- --- 184.49
[D] Tools, Equipments & plants @ 2% A+B --- --- 184.49
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1439.02
Total cost 11032.50
Unit Rate 110
Name of the Project: Vrajnandan Bunglows
Providing and laying marble skirting of 75mm including cutting finishing, filling up of joints, polishing etc. complete. For above plinth lvl. below GF slab.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis of 100 Sqm
[A] MaterialsMarble = 100 x 0.075 = 7.5 sq.m. + 5% Wastage = 7.88 sq.m.Wet Mortar = 100 x 0.075 x 0.015 = 0.1125 cu.m. + 5% Wastage = 0.12 cu.m.
Dry Mortar = 0.12 x 1.25 (Shrinkage Factor 25%) = 0.15 cu.m.
Cement = 0.15 / 2 = 0.075 + 2% Wastage = 2.21 Bags
Sand = 0.15 / 2 = 0.075 + 10% Wastage = 0.08 cu.m.
White Cement = 3 kgs. per sq.m. = 3 x 7.88 = 23.64kgs. = 0.47 bags
Name of the Project: Vrajnandan Bunglows
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.03
Sqm
For 100 Sqm
[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
Glazed Tiles Sqm 105.00 375.00 39375.00
White cement Bags 0.50 550.00 275.00
Colouring pigment Kg 1.00 75.00 75.00Total material rate 44531.80
[B] Labours Skilled 4.70 150 705 Unskilled 9.10 90 819
Total labour rate 1524.00
[C] Water + electric @ 2% of A+B --- --- 921.12
[D] Tools, Equipments & plants @ 2% A+B --- --- 921.12
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 7184.70
Total cost 55082.74
Unit Rate 551
Name of the Project: Vrajnandan Bunglows
Providing and laying of glazed tiles for floor in bathroom terrace etc. including cutting finishing, filling up of joints etc. complete. for above plinth lvl. below GF slab.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.04
Sqm
For 100 Sqm
[A] Materials
Cement (OPC) Bags 18.49 160.00 2958.40
Sand Cum 0.69 110.00 75.90
Glazed Tiles Sqm 105.00 375.00 39375.00
White cement Bags 0.50 550.00 275.00
Colouring pigment Kg 1.00 75.00 75.00Total material rate 42759.30
[B] Labours Skilled 5.00 150 750 Unskilled 10.00 90 900
Total labour rate 1650.00
[C] Water + electric @ 2% of A+B --- --- 888.19
[D] Tools, Equipments & plants @ 2% A+B --- --- 888.19
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 6927.85
Total cost 53113.52
Unit Rate 531
Name of the Project: Vrajnandan Bunglows
Providing and laying of glazed tiles for vertical surface in bathroom, kitchen etc. including cutting finishing, filling up of joints etc. complete. for above plinth lvl. below GF slab.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.05
Sqm
For 100 Sqm
[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
White Cement Bags 5.00 550.00 2750.00
Marble (With Polishing) Sqm 105.00 970.00 101850.00Total material rate 109406.80
[B] Labours Skilled 6.20 150 930 Unskilled 11.00 90 990
Total labour rate 1920.00
[C] Water + electric @ 2% of A+B --- --- 2226.54
[D] Tools, Equipments & plants @ 2% A+B --- --- 2226.54
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 17366.98
Total cost 133146.85
Name of the Project: Vrajnandan Bunglows
Providing and laying marble flooring for steps with bed mortar 1:8 (1 cement, 8sand) including cutting finishing, filling up of joints, polishing etc. complete for above plinth lvl. below GF slab.
Unit Rate 1331
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
6.06
Nos.
For 100 Nos
[A] Materials
Cement (OPC) Bags 1.00 160.00 160.00
Sand Cum 0.10 110.00 11.00
White Cement Bags 0.25 550.00 137.50
Marble (With Polishing) Sqm 2.50 970.00 2425.00Total material rate 2733.50
[B] Labours Skilled 2.00 150 300 Unskilled 2.00 90 180
Total labour rate 480.00
[C] Water + electric @ 2% of A+B --- --- 64.27
[D] Tools, Equipments & plants @ 2% A+B --- --- 64.27
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 501.31
Total cost 3843.35
Name of the Project: Vrajnandan Bunglows
Providing and laying marble skirting 75mm for steps with including cutting finishing, filling up of joints, polishing etc. complete for above plinth lvl. below GF slab.
Unit Rate 38
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
6.08
Sqm
For 100 Sqm
[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
White Cement Bags 5.00 550.00 2750.00
Marble (With Polishing) Sqm 105.00 970.00 101850.00Total material rate 109406.80
[B] Labours Skilled 5.20 150 780 Unskilled 9.80 90 882 10% extra for rise 166.2
Total labour rate 1828.20
[C] Water + electric @ 2% of A+B --- --- 2224.70
[D] Tools, Equipments & plants @ 2% A+B --- --- 2224.70
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 17352.66
Name of the Project: Vrajnandan Bunglows
Providing and laying marble flooring with bed mortar 1:8 (1 cement, 8sand) including cutting finishing, filling up of joints, polishing etc. complete for above GF slab below FF slab.
Total cost 133037.06
Unit Rate 1330
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
6.09
Rmt
For 100 Rmt
[A] Materials
Cement (OPC) Bags 2.21 160.00 353.60
Sand Cum 0.08 110.00 8.80
White Cement Bags 0.47 550.00 258.50
Marble (With Polishing) Sqm 7.88 970.00 7643.60Total material rate 8264.50
[B] Labours Skilled 4.00 150 600 Unskilled 4.00 90 360 10% extra for rise 96
Total labour rate 1056.00
[C] Water + electric @ 2% of A+B --- --- 186.41
[D] Tools, Equipments & plants @ 2% A+B --- --- 186.41
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1454.00
Name of the Project: Vrajnandan Bunglows
Providing and laying marble skirting of 75mm including cutting finishing, filling up of joints, polishing etc. complete for above GF slab below FF slab.
Total cost 11147.32
Unit Rate 111
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
6.10
Sqm
For 100 Sqm
[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
Glazed Tiles Sqm 105.00 375.00 39375.00
Colouring pigment Kg 1.00 75.00 75.00Total material rate 44256.80
[B] Labours Skilled 4.70 150 705 Unskilled 9.10 90 819 10% extra for rise 152.4
Total labour rate 1676.40
[C] Water + electric @ 2% of A+B --- --- 918.66
[D] Tools, Equipments & plants @ 2% A+B --- --- 918.66
[E] Scaffolding @ 2% A+B --- --- 0.00
Name of the Project: Vrajnandan Bunglows
Providing and laying of glazed tiles for floor in bathroom terrace etc. including cutting finishing, filling up of joints etc. complete. for above GF slab below FF slab.
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 7165.58
Total cost 54936.11
Unit Rate 549
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
6.11
Rmt
For 100 Rmt
[A] Materials
Cement (OPC) Bags 2.21 160.00 353.60
Sand Cum 0.08 110.00 8.80
White Cement Bags 0.47 550.00 258.50
Glazed tiles Sqm 7.88 375.00 2955.00Total material rate 3575.90
[B] Labours Skilled 4.00 150 600 Unskilled 4.00 90 360 10% extra for rise 96
Total labour rate 1056.00
[C] Water + electric @ 2% of A+B --- --- 92.64
[D] Tools, Equipments & plants @ 2% A+B --- --- 92.64
Name of the Project: Vrajnandan Bunglows
Providing and laying of glazed tiles for skirting 75mm in bathroom terrace etc. including cutting finishing, filling up of joints etc. complete. for above GF slab below FF slab.
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 722.58
Total cost 5539.75
Unit Rate 55
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
6.12
Sqm
For 100 Sqm
[A] Materials
Cement (OPC) Bags 18.49 160.00 2958.40
Sand Cum 0.69 110.00 75.90
Glazed Tiles Sqm 105.00 375.00 39375.00
White cement Bags 0.50 550.00 275.00
Colouring pigment Kg 1.00 75.00 75.00Total material rate 42759.30
[B] Labours Skilled 5.00 150 750 Unskilled 10.00 90 900 10% extra for rise 165
Total labour rate 1815.00
[C] Water + electric @ 2% of A+B --- --- 891.49
Name of the Project: Vrajnandan Bunglows
Providing and laying of glazed tiles for vertical surface in bathroom, kitchen etc. including cutting finishing, filling up of joints etc. complete for above GF slab below FF slab.
[D] Tools, Equipments & plants @ 2% A+B --- --- 891.49
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 6953.59
Total cost 53310.86
Unit Rate 533
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.13
Sqm
For 100 Sqm
[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
White Cement Bags 5.00 550.00 2750.00
Marble (With Polishing) Sqm 105.00 970.00 101850.00Total material rate 109406.80
[B] Labours Skilled 6.20 150 930 Unskilled 11.00 90 990 10% extra for rise 192
Total labour rate 2112.00
Name of the Project: Vrajnandan Bunglows
Providing and laying marble flooring for steps with bed mortar 1:8 (1 cement, 8sand) including cutting finishing, filling up of joints, polishing etc. complete for above GF slab below FF slab.
[C] Water + electric @ 2% of A+B --- --- 2230.38
[D] Tools, Equipments & plants @ 2% A+B --- --- 2230.38
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 17396.93
Total cost 133376.48
Unit Rate 1334
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.3.14
Nos.
For 100 Nos
[A] Materials
Cement (OPC) Bags 1.00 160.00 160.00
Sand Cum 0.10 110.00 11.00
White Cement Bags 0.25 550.00 137.50
Marble (With Polishing) Sqm 2.50 970.00 2425.00Total material rate 2733.50
[B] Labours Skilled 2.00 150 300 Unskilled 2.00 90 180 10% extra for rise 48
Total labour rate 528.00
Name of the Project: Vrajnandan Bunglows
Providing and laying marble skirting 75mm for steps with including cutting finishing, filling up of joints, polishing etc. complete for above GF slab below FF slab.
[C] Water + electric @ 2% of A+B --- --- 65.23
[D] Tools, Equipments & plants @ 2% A+B --- --- 65.23
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 508.79
Total cost 3900.75
Unit Rate 39
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.15
Sqm
For 100 Sqm
[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
White Cement Bags 5.00 550.00 2750.00
Marble (With Polishing) Sqm 105.00 970.00 101850.00Total material rate 109406.80
[B] Labours Skilled 5.20 150 780 Unskilled 9.80 90 882 20% extra for rise 332.4
Name of the Project: Vrajnandan Bunglows
Providing and laying marble flooring with bed mortar 1:8 (1 cement, 8sand) including cutting finishing, filling up of joints, polishing etc. complete for above FF slab below SF slab.
Total labour rate 1994.40
[C] Water + electric @ 2% of A+B --- --- 2228.02
[D] Tools, Equipments & plants @ 2% A+B --- --- 2228.02
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 17378.59
Total cost 133235.84
Unit Rate 1332
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.6.16
Rmt
For 100 Rmt
[A] Materials
Cement (OPC) Bags 2.21 160.00 353.60
Sand Cum 0.08 110.00 8.80
White Cement Bags 0.47 550.00 258.50
Marble (With Polishing) Sqm 7.88 970.00 7643.60Total material rate 8264.50
[B] Labours Skilled 4.00 150 600 Unskilled 4.00 90 360
Name of the Project: Vrajnandan Bunglows
Providing and laying marble skirting of 75mm including cutting finishing, filling up of joints, polishing etc. complete for above FF slab below SF slab.
20% extra for rise 192Total labour rate 1152.00
[C] Water + electric @ 2% of A+B --- --- 188.33
[D] Tools, Equipments & plants @ 2% A+B --- --- 188.33
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 1468.97
Total cost 11262.13
Unit Rate 113
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
6.17
Sqm
For 100 Sqm
[A] Materials
Cement (OPC) Bags 26.00 160.00 4160.00
Sand Cum 5.88 110.00 646.80
Glazed Tiles Sqm 105.00 375.00 39375.00
Colouring pigment Kg 1.00 75.00 75.00Total material rate 44256.80
[B] Labours Skilled 4.70 150 705
Name of the Project: Vrajnandan Bunglows
Providing and laying of glazed tiles for floor in bathroom terrace etc. including cutting finishing, filling up of joints etc. complete. for above FF slab below SF slab.
Unskilled 9.10 90 819 20% extra for rise 304.8
Total labour rate 1828.80
[C] Water + electric @ 2% of A+B --- --- 921.71
[D] Tools, Equipments & plants @ 2% A+B --- --- 921.71
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 7189.35
Total cost 55118.38
Unit Rate 551
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
6.18
Sqm
For 100 Sqm
[A] Materials
Cement (OPC) Bags 18.49 160.00 2958.40
Sand Cum 0.69 110.00 75.90
Glazed Tiles Sqm 105.00 375.00 39375.00
White cement Bags 0.50 550.00 275.00
Colouring pigment Kg 1.00 75.00 75.00
Name of the Project: Vrajnandan Bunglows
Providing and laying of glazed tiles for vertical surface in bathroom, kitchen etc. including cutting finishing, filling up of joints etc. complete for above FF slab below SF slab.
Total material rate 42759.30
[B] Labours Skilled 5.00 150 750 Unskilled 10.00 90 900 20% extra for rise 330
Total labour rate 1980.00
[C] Water + electric @ 2% of A+B --- --- 894.79
[D] Tools, Equipments & plants @ 2% A+B --- --- 894.79
[E] Scaffolding @ 2% A+B --- --- 0.00
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 6979.33
Total cost 53508.20
Unit Rate 535
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
3.19
Sqm
For 100 Sqm
[A] Materials China Mosaic Sqm 100.00 64.56 6456.00 Cement Bags 18.45 160.00 2952.00 Sand Cum 2.75 100.00 275.00 White Cement Bags 5.00 550.00 2750.00
Total material rate 12433.00
Name of the Project: Vrajnandan Bunglows
Providing and laying china mosaic including cutting finishing, filling up of joints etc. complete for above FF slab below SF slab.
[B] Labours Skilled 10.00 150 1500 Unskilled 30.00 90 2700 20% extra for rise 84
Total labour rate 4284.00
[C] Water + electric @ 2% of A+B --- --- 334.34
[D] Tools, Equipments & plants @ 2% A+B --- --- 334.34
[E] Scaffolding @ 2% A+B --- --- 334.34
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2658.00
Total cost 20378.02
Unit Rate 204
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis of 100 Sqm
[A] Materials1. China mosaic Qty 100 Sqm
2.Cement Quantity of mortar required: 100 Sqm x 0.025m
Wet volume: 2.5 Cum Dry volume: 2.5x1.25 (25%-shrinkage factor) : 3.12cu.m.
Name of the Project: Vrajnandan Bunglows
CEMENT = 1x3.12
(4+1) x0.0345 =18.09 bags + 2% wastage =18.45 bags
3. Sand Sand: 1x3.12x4/5=2.75
4. White Cement 2.5 Kg / Sqm =100 x 2.5=2500 Kg = 5 Bags
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.
6.21
Sqm
For 100 Sqm
[A] Materials China Mosaic Sqm 100.00 64.56 6456.00 Cement Bags 18.45 160.00 2952.00 Sand Cum 2.75 100.00 275.00
Name of the Project: Vrajnandan Bunglows
Providing and laying china mosaic including cutting, finishing, filling up of joints etc. complete for above SF slab below TF slab.
White Cement Bags 5.00 550.00 2750.00Total material rate 12433.00
[B] Labours Skilled 10.00 150 1500 Unskilled 30.00 90 2700 20% extra for rise 84
Total labour rate 4284.00
[C] Water + electric @ 2% of A+B --- --- 334.34
[D] Tools, Equipments & plants @ 2% A+B --- --- 334.34
[E] Scaffolding @ 2% A+B --- --- 334.34
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 2658.00
Total cost 20378.02
Unit Rate 204
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Rmt
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
= 7.88 sq.m.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Nos
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Rmt
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Rmt
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Nos
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Rmt
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.11.01
Sq.m
For 100 Sqm
[A] Materials Slaked lime Kg 30.8 5 154.00 Glue Kg 0.08 150 12.00 Ultramarine blue Kg 0.09 70 6.30 Sodium chloride Kg 4.01 5 20.05 Cement kg 33.77 11 371.47 Brush etc @ 10% 56.38
Total material rate 620.20
[B] Labours Skilled 2.7 150 405 Unskilled 1.14 90 102.6
Total labour rate 507.60
[C] Water + electric @ 2% of A+B --- --- 0.00
[D] Tools, Equipments & plants @ 2% A+B --- --- 22.56
[E] Scaffolding @ 2% A+B --- --- 22.56
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 175.94
Total cost 1348.85
Unit Rate 13
Name of the Project: Vrajnandan Bunglows
Providing and applying 3 coats of white wash on newly plastered internal surface including finishing etc. complete at Ground Floor level.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Calculations for rate analysis of 100 Sqm
[A] Materials1. Slaked lime For first coat =12 Kg For second coat = 8 Kg For Third coat = 8 Kg Total weight=28 Kg + wastage Total qty = 30.8 Kg
2. Glue For first coat =0.03 Kg For second coat = 0.02 Kg For Third coat = 0.02 Kg Total weight=0.07 Kg + 10% wastage Total qty = 0.077 Kg
3. Ultramarin blue For first coat =0.04 Kg For second coat = 0.02 Kg For Third coat = 0.02 Kg Total weight=0.08 Kg + 10% wastage Total qty = 0.088 Kg
4. Sodium Chloride For first coat =1.55 Kg For second coat = 1.05 Kg For Third coat = 1.05 Kg Total weight=3.65 Kg + 10% wastage Total qty = 4.01 Kg
5. Cement For first coat =10.7 Kg For second coat = 10 Kg For Third coat = 10 Kg Total weight=30.7 Kg + 10% wastage Total qty = 33.77 Kg
Name of the Project: Vrajnandan Bunglows
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
ItemItem Description Unit Quantity Rate Amount
No.11.02
Sq.m
For 100 Sqm
[A] Materials Cement Paint Kg 42 25 1050.00 Brush sand etc. @ 10% 105.00
Total material rate 1155.00
[B] Labours Skilled 5.5 150 825 Unskilled 4 90 360
Total labour rate 1185.00
[C] Water + electric @ 2% of A+B --- --- 0.00
[D] Tools, Equipments & plants @ 2% A+B --- --- 46.80
[E] Scaffolding @ 2% A+B --- --- 46.80
[F] Profit & overhead @ 15% of A+B+C+D+E --- --- 365.04
Total cost 2798.64
Unit Rate 28
Name of the Project: Vrajnandan Bunglows
Providing and applying 2 coats of semi-acrylic paint on newly plastered external surface including finishing etc. complete at Ground Floor level.
Checked by:Date: Page No.
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm
School of Building Science & TechnologyQuantity Surveying & Specifications
CALCULATIONS FOR RATE ANALYSISStudent Name: Japan ShahCode No: 2404
School of Building Science & TechnologyQuantity Surveying & Specifications
RATE ANALYSISStudent Name: Japan ShahCode No: 2404
Remarks
Rs
Rs / Sqm