Rajasthan Electricity Regulatory Commission, Jaipur Rajasthan Electricity Regulatory Commission...
Transcript of Rajasthan Electricity Regulatory Commission, Jaipur Rajasthan Electricity Regulatory Commission...
1
Rajasthan Electricity Regulatory Commission
Petition No. RERC/255/11
RERC/256/11
In the matter of adoption of transmission charges, discovered through the
process of competitive bidding as per the guidelines for determination of
tariff by competitive bidding process, with respect to transmission system
being established by Aravali Transmission Service Company and Maru
Transmission Service Company.
Coram: Sh. D.C. Samant, Chairman
Sh. S.K. Mittal, Member
Petitioners : 1. Aravali Transmission Service Company Ltd.
(ATSCL)
2. Maru Transmission Service Company Ltd.
(MTSCL)
Respondents : 1. Rajasthan Rajya Vidyut Prasaran Nigam Ltd.,
2. Jaipur Vidyut Vitran Nigam Ltd.,
3. Ajmer Vidyut Vitran Nigam Ltd.,
4. Jodhpur Vidyut Vitran Nigam Ltd.
Date of hearing : 06.07.11
Presents:
1. Sh. S.N.Sunkari, General manager, Aravali TSCL & Maru TSCL
2. Sh. Gautam Sen, General manager, Aravali TSCL & Maru TSCL
3. Sh. M.K. Kasliwal, Advisor, GMR Energy
4. Sh. D.S. Sharma, S.E. (NPP&R), RVPN
5. Sh. R.P. Gupta, XEn (PMU), RVPN
6. Sh. J.K. Sharma, S.E.,AVVNL
7. Sh. Madan Rana, XEn, Jd. VVNL
8. Sh. G.L. Sharma, Individual
Date of Order: 30.09.2011
ORDER
1. M/s. Aravali Transmission Service Company Ltd. (ATSCL) and M/s Maru
Transmission Service Company Ltd.(MTSCL) filed petitions for adoption
of transmission charges, for the projects to be developed by them,
2
identified through competitive bidding process. Petitioners submitted
that M/s ATSCL and M/s MTSCL were incorporated by RVPN as its
wholly owned subsidiary to initiate the work on identified transmission
projects and subsequently to act as Transmission Service Provider (TSP)
after being acquired by successful bidder.
2. Petitioners submitted that M/s Rajasthan Rajya Vidyut Prasaran Nigam
Ltd.,(RVPN), authorized by the State Level Empowered Committee
(SLEC) functioned as Bid Process Coordinator (BPC) and prepared RFQ
& RFP documents in accordance with Standard Bid Documents (SBD)
issued by Ministry of Power, Government of India and invited Request
for Proposals (RFP) for selection of Transmission service Provider(TSP)
through competitive bidding process to establish transmission system,
as per guidelines issued by Ministry of Power, Government of India
(hereinafter referred as „GoI guidelines‟). Petitioners further submitted
that on evaluation of bids M/s GMR Energy Limited was declared
lowest bidder for Raj/PPP-2 : 400kV S/c Hindaun-Alwar line with
400/200kV GSS at Alwar and Raj/PPP-1 : 400kV S/c Bikaner-Deedwana-
Ajmer with 400/200kV GSS at Deedwana & associated works.
Subsequently GMR Energy Limited acquired M/s ATSCL & MTSCL after
execution of share purchase agreement. Both the petitioners signed
Transmission Service Agreement (TSA) with JVVNL, AVVNL & Jd. VVNL
and also filed petition for grant of licence. Petitioners prayed for
adoption of transmission charges identified through competitive
bidding process.
3. The Commission noted that the petitioner has been selected through
the process of bidding conducted by M/s RVPN working as Bid Process
Coordinator and the petitioner has not made RVPN respondent in the
matter. The Commission, therefore, impleaded RVPN as respondent in
the matter and directed it to file an affidavit detailing the complete
procedure adopted during bidding process so that bidding process
may be examined.
4. In response to this direction, S.E. (NPP&R), RVPN on behalf of CMD,
RVPN filed an affidavit detailing the bid process for selection of
petitioners. The salient points of affidavit submitted by RVPN are as
under:
3
(1) The Govt. of Rajasthan vide letter No. F.12(21)Energy/04/pt. dated 15.10.2008
constituted a State Level Empowered Committee (SLEC) with a view to
encourage competition in private sector participation for development of
transmission projects in State.
The Empowered Committee consists of the following:-
1. Member RERC Chairman
2. Secretary Energy Member
3. Secretary Plan Member
4. Chairman Discoms Member
5. Director (Tech.), RVPN Member Secretary
The function of the Committee would be as follows:
(i) To identify the projects to be developed by competitive bidding.
(ii) To facilitate preparation of bid documents and invitation of bids
through a suitable agency.
(iii) To facilitate evaluation of bids.
(iv) To facilitate finalisation and signing of TSA between developer and
concerned utilities.
(v) To facilitate development of projects by competitive bidding for
transmission.
Further, the Empowered Committee will also take care of the functions of
the BPC till a Bid Process Coordinator (BPC) is set up.
(2) The State Level Empowered Committee (SLEC) in its first meeting held on
16.1.2009 decided the following schemes to be implemented through
competitive bidding process and authorized Rajasthan Rajya Vidyut Prasaran
Nigam Limited to act as Bid Process Coordinator (BPC) for the purpose of
selection of Bidder as Transmission Service Provider (TSP).
Project No. Project Details
RAJ/PPP-1 400 kV S/C Bikaner- Deedwana- Ajmer Line with 400
kV/220 kV GSS at Deedwana and associated works.
RAJ/PPP-2 400 kV S/C Hindaun-Alwar Line with 400/220 kV GSS at
Alwar and associated works.
RAJ/PPP-3 220 kV S/C Sikar (400 kV) - Nawalgarh-Jhunjhunu Line
with 220/132 kV GSS at Nawalgarh and associated
works.
(3) Second meeting of SLEC was held on 26.2.2009 where it was decided that :-
4
(i) Bidding documents approved by MoP, GoI be adopted and RVPN may
go ahead with publication of RFP in newspapers taking 01.03.2009 as
zero date.
(ii) For speedy completion of the bidding process, single stage two
envelope bid process be adopted.
(iii) Cost of the document be fixed as Rs. 10,000 / US$200 and
(iv) Bids be invited on Built, Own and Operate basis.
(4) In pursuance to decisions of SLEC‟s first and second meetings, Notice inviting
Bids were published in two State level newspaper (all editions), two National
level newspapers (all editions), Indian Trade Journal and The Financial Times,
London, worldwide for aforesaid projects.
(5) The Single stage two envelope bidding process was adopted for all the three
projects. Accordingly, the bidding documents {i.e. Request for Qualification
(RFQ), Request for proposal (RFP) and Transmission Service Agreement (TSA)}
based on Standard Bidding Documents (SBDs) of MoP, GoI, were issued on
1.3.2009 for selection of Transmission Service Provider through competitive
bidding process on Build, Own, Operate and Maintenance basis. The Pre-bid
conference was held on 31.3.2009. The revised RFP project documents were
issued on 15.4.09. The Pre-signed bidding documents were issued on 10.6.2009.
Draft of Share Purchase Agreement was issued on 1.7.2009.
(6) As per Bidding Documents/guidelines, the SPVs which would eventually be
taken over by the successful bidder after payment of all the costs incurred by
RVPN for the selection of the service provider and other associated
clearances etc. were registered with the Registrar of Companies as under:
Project Name of SPV
Raj/PPP-1 Maru Transmission Service Company Limited
Raj/PPP-2 Aravali Transmission Service Company Limited
Raj/PPP-3 Shekhawati Transmission Service Company Limited
(7) The last date of receipt of RFP including RFQ bids was 04.11.2009 and the RFQ
of bids for the Transmission Projects were opened on same date i.e. 4.11.09.
The following ten bids were received for Raj/PPP-1 and Raj/PPP-2 :
SNo Bidder/Consortium
1. M/s. EMCO Ltd
2. M/s. GMR Energy Ltd.
3. M/s. Jyoti Energy Ltd.
5
4. M/s. ABL-AMR-SREI-ITL Consortium
5. M/s. L&T Transco Pvt. Ltd
6. M/s. Hecate Power Transmission Ltd.-
7. M/s. GPEC Gammon Consortium
8. M/s. Lanco Infratech Ltd.
9. M/s. Kalpataru Power Transmission Ltd.- Techno Electric &
Engineering Co. Ltd. Consortium
10. M/s. Sterlite Technologies Ltd.
(8) RVPN having being designated as BPC by the State Level Empowered
Committee (SLEC) constituted by GoR, had to carry out the function of BPC
as per Clause 3.1 of Guidelines. Accordingly, Bid Evaluation Committee,
which was required to be formed by RVPN as BPC as per Clause 9.8 of of
Guidelines, was constituted vide order No. RVPN/ AAO/ Admn-Store/F.
/D.328 dated 29.12.2009 issued by Secretary (Admn.), RVPN for
evaluation/short listing of Bidders/ TSP through Tariff Based Competitive
Bidding process. It was later re-constituted vide order dated 08.1.2010 and
the re-constituted committee consists of the following :
(i) Shri B.N. Saini, Chief Engineer (PPM), RVPN
(ii) Shri Deepak Srivastava, CCOA, RVPN
(iii) Shri N.M. Agarwal, Dy. Chief Engineer (MM), RVPN
(iv) Shri R.K. Kasliwal, Dy. Chief Engineer (NPP-R), RVPN
(v) Shri B.K. Makhija, Retd. C.E. (RPPC), Project Consultant, RVPN
(vi) Shri Bharat Bhushan Gupta, C.A, Financial Expert
(9) The committee was framed taking into consideration the provision Clause
9.8 and implicit provisions of Clause 3.1 & 3.3 of Guidelines being intra-state
transmission projects and decision of Empowered Committee to authorise
RVPN to act as BPC, Shri Bharat Bhushan Gupta, C.A. was taken as
independent Member having expertise in financial matter. Sh. B.K. Makhija,
an Ex. Chief Engineer, who has headed the RPPC and was associated as
Chief Engineer with all the PPP projects including these transmission projects,
was also included in the committee.
(10) The recommendations of the Bid Evaluation Committee regarding
evaluation of RFQ and declaring all the bidders who had submitted the bids
as qualified was approved by the Board of Directors of RVPN in its 176th
meeting held on 23.2.2010. BoD further authorised the bid evaluation
committee for opening of envelope of RFP bids containing non-financial
and financial bids and further opening of non-financial bids.
(11) The bids for non-financial part of RFP were opened on 3.3.2010 in presence
of bidders and the recommendations of the Bid Evaluation Committee
regarding these were approved by BoD in its 181th meeting held on
26.4.2010 and accorded its approval for opening of financial bids.
6
(12) The financial bids of all above bidders/consortiums were opened on
13.5.2010 in presence of bidders who wished to be present. The levelised
transmission charges for the above projects were compared .
(13) The Bid Evaluation Committee in its meeting on 18.6.2010 recommended M/s
GMR Energy Ltd. for Letter of Intent (LoI) for both the transmission projects
being the lowest among quoted and also found to be reasonable.
Accordingly, BoD in 187th meeting held on 28.9.2010 decided to issue LoI in
favour of M/s. GMR Energy Ltd. for transmission projects Raj/PPP-1: 400 kV S/C
Bikaner- Deedwana- Ajmer Line with 400 kV/220 kV GSS at Deedwana and
associated works and Raj/PPP-2 : 400 kV S/C Hindaun-Alwar Line with
400/220 kV GSS at Alwar and associated works. These were issued on
30.9.2010.
(14) BoD in its 189th meeting held on 15.12.2010 approved transfer of 100%
shareholding of RVPN and its nominee in Aravali Transmission Service
Company Limited and Maru Transmission Service Company Limited to M/s.
GMR Energy Ltd., the successful bidder.
(15) The Share Purchase Agreement (SPA) for transfer SPV - Aravali Transmission
Service Company Limited was signed on 19.1.2011 among Rajasthan Rajya
Vidyut Prasaran Nigam Limited, Aravali Transmission Service Company
Limited and GMR Energy Ltd. The Transmission Service Agreement (TSA) was
also signed on same day i.e. 19.1.2011 among M/s Aravali Transmission
Service Company Limited and Long Term Transmission Customers (LTTCs)
namely Jaipur Vidyut Vitran Nigam Ltd., Jodhpur Vidyut Vitran Nigam Ltd.
and Ajmer Vidyut Vitran Nigam Ltd.
(16) The Share Purchase Agreement (SPA) for transfer of SPV - Maru Transmission
Service Company Limited was signed on 15.2.2011 among Rajasthan Rajya
Vidyut Prasaran Nigam Limited, Maru Transmission Service Company Limited
and GMR Energy Ltd. The Transmission Service Agreement (TSA) was also
signed on same day i.e. 15.2.2011 among M/s Maru Transmission Service
Company Limited and Long Term Transmission Customers (LTTCs) namely
Jaipur Vidyut Vitran Nigam Ltd., Jodhpur Vidyut Vitran Nigam Ltd. and Ajmer
Vidyut Vitran Nigam Ltd.
5. The matter was heard on 06.07.11. Sh. S.N. Sunkari, on behalf of
petitioners submitted that they have been selected through the
transparent process of bidding and prayed for adoption of tariff
discovered through the bidding. He also submitted that as a bidder
they do not have any control on the methodology and process
adopted by the RVPN or State Govt.
6. During hearing the Commission raised doubts that the process followed
was not strictly as per guidelines issued by central government. Sh. D.S.
7
Sharma, on behalf of RVPN submitted that the process followed was
transparent and as per guidelines. He further submitted that the
guidelines issued by GoI are not very clear and being first case of its
kind they tried to infer the guidelines as per State government orders.
He submitted that State government order dated 15.10.08 read with
Empowered committee minutes dated 16.1.09 empowers RVPN to
evaluate the bids. He submitted that the minor lapses should be
allowed by Commission considering as deviation in guidelines.
Competitive-bidding Guidelines issued by Central Government
7. We find that the petitions has been filed for adoption of tariff, which is
covered under section 63 of the Act which provides:
“63. Notwithstanding anything contained in section 62, the
Appropriate Commission shall adopt the tariff if such tariff has been
determined through transparent process of bidding in accordance
with the guidelines issued by the Central Government.”
8. Section 63 of the Act casts a mandate on this Commission to adopt
the tariff if such tariff is determined through transparent process of
bidding in accordance with the Guidelines. Thus the Commission is
required to scrutinize the entire process of selection through
competitive bidding as per guidelines issued by GoI.
9. The Ministry of Power, Government of India under section 63 of the Act
has issued “Tariff based Competitive-bidding Guidelines for
Transmission service” vide Resolution No.11/5/2005-PG(i) dated
17.4.2006 and amendments thereof. The salient features of the bidding
process as laid down in the guidelines, as amended, are discussed
hereunder for convenience of reference:
a) The Guidelines are applicable for procurement of transmission
services for transmission of electricity through tariff based
competitive bidding and for selection of transmission service
provider for new transmission lines and to build, own, maintain and
operate the specified transmission system elements.
b) A Bid Process Coordinator, herein after referred to as BPC, would be
responsible for coordinating the bid process for procurement of
required transmission services for each inter-state Transmission Project
to be implemented under tariff-based competitive bidding in
accordance with these guidelines.
8
c) For procurement of transmission services, for intra-state transmission,
the appropriate State Government may notify any Organization/
State Public Sector Undertaking especially engaged for this purpose
by the appropriate state government or BPC notified by the Central
Government to be the BPC for the state.
d) The BPC shall prepare the bid documentation in accordance with
the Guidelines and obtain approval of the Appropriate Commission
or alternatively, the BPC can use the standard bid documents
notified by the Ministry of Power. Approval of the Appropriate
Commission would be necessary if any material deviation is
proposed to be made in the Standard Bid Documents. Intimation
about the initiation of the bid process shall be sent by the BPC to the
Appropriate Commission.
e) For procurement of transmission services under the Guidelines, the
BPC may adopt at its option either a two-stage process featuring
separate Request for Qualifications (RFQ) and Request for
Proposal(RFP) or adopt a single stage two envelope tender process
combining both RFQ and RFP processes.
f) RFQ or combined RFQ and RFP notice shall be issued in at least two
national newspapers, website of the BPC and the appropriate
Government and preferably in the trade magazines also to provide
wide publicity. For the purpose of issue of RFQ minimum conditions to
be met by the bidder shall be specified in the RFQ notice. The
bidding shall be by way of International Competitive Bidding.
g) Standard documentation to be provided in the RFQ stage shall
include definitions of requirements including the details of location
and technical qualifications for each component of the transmission
lines, construction milestones, and financial requirements to be met
by the bidders; proposed Transmission Service Agreement; period of
validity of offer of bidder; conditions as specified by the Appropriate
Commission for being eligible to obtain a transmission licence; and
other technical and safety criteria to be met by the bidder/TSP
including the provisions of IEGC.
h) Standard documentations to be provided by the BPC in the RFP shall
include specified target dates/months for commissioning and
commercial operations and start of providing transmission services;
TSA proposed to be entered with the selected bidder; bid evaluation
methodology to be adopted by the BPC; Discount Factor to be used
for evaluation of the bids; specification regarding the bid bond and
9
project completion guarantee to be furnished by the bidders;
proposed indemnification agreement between the TSP and the
utilities; amount of contract performance guarantee as percentage
of the project cost; and the liquidated damages that would apply in
the case of delay in start of providing the transmission services.
i) To ensure competitiveness, the minimum number of qualified bidders
will be two. The Empowered Committee shall constitute a
committee for evaluation of the bids with at least one member from
Central Electricity Authority (CEA) and not less than two
representatives from the concerned Regional Power Committees
with at least one representative from every concerned RPC and one
independent member. The independent member shall have
expertise in financial matter/bid evaluation. The bids shall be
opened in public and the representative of the bidders shall be
allowed to remain present. The technical bids shall be scored to
ensure that only the bids that meet the minimum technical criteria
set out in the RFQ shall be considered for further evaluation on the
transmission charge bids. The transmission charge bid shall be
rejected if it contains any deviation from the tender conditions for
submission of the same. The bidder who has quoted the lowest
levelised transmission charge as per the evaluation procedure shall
be considered for the award.
j) The Guidelines provide for suggested time tables for the bid process.
The timeline suggested for a two stage bid process is 240 days and
single stage two envelope bid process is 180 days. The procurer may
give extended time-frame based on the prevailing circumstances
and such alterations shall not be construed as the deviation from the
Guidelines.
k) After selection and issue of LOI from the BPC, the selected bidder
shall acquire the SPV created for the Project to become TSP and sign
the TSA, if not already signed by the SPV, in accordance with the
terms and conditions as finalized in the bid document.
l) The BPC shall make the final result of evaluation of all bids public. The
final TSA alongwith the certification of BEC shall be forwarded to the
Appropriate Commission for adoption of tariff in terms of section 63
of the Act.
10
Adoption of Transmission charges and related issues:
10. In the light of the above provisions of the Guidelines, we have
examined in the succeeding paragraphs the process of international
competitive bidding adopted in the present case for selection of the
successful bidder on the basis of the lowest levelised transmission
charges.
11. The petition was admitted by the Commission on 12.5.2011. The
Commission sought affidavit from RVPN to establish that transmission
charges has been determined through transparent process of bidding
in accordance with the „guidelines‟ issued by the Central
Government. The affidavit was submitted on 17.6.11 and the matter
was heard on 06.07.2011 wherein the RVPN submitted further
clarification on the process as sought by the Commission.
12. Based on the submissions made by the petitioner, RVPN and
subsequent submissions made during hearing by the RVPN it is
observed that RVPN on behalf of SLEC acted as BPC and invited bid
for selection of TSP in accordance with the guidelines issued by the
GoI.
13. We find that it is not only the question of transparency of the selection
of the GMR as the successful bidder but also the selection process of
bidding being as per the Guidelines would have to be scrutinized by
the Commission for adoption of tariff to meet the requirements of
Section 63 of the Act and the Guidelines.
14. The Commission, on scrutiny of affidavit and submissions made by
RVPN, found following main issues which had arisen in the matter :
(i) The appointment of RVPN as BPC;
(ii) Constitution of Bid Evaluation Committee by RVPN;
Analysis of issues and decisions thereon:
15. There being difference in views amongst the member and chairman
on some important issues; the analysis of the issues and conclusion
thereon is being dealt with in two parts, one incorporating the views of
Mr. S.K.Mittal, Member, and the views of Mr. D.C.Samant, Chairman
followed by decision of the Commission.
11
Views of Sh. S.K. Mittal, Member
16. During hearing certain variations were pointed out from the bidding
guidelines, therefore, it would be appropriate to first see what the
variations are and how they are affecting the transparency of Bidding
Process. In the following matrix the procedure adopted vis-a-vis the
guidelines prescribed by the Ministry has been analysed.
17. Compliance of Guidelines
Clause Guideline Compliance
3.2
Government shall notify any
Central Govt. Organisation/
Central Public Sector
undertaking or its wholly
owned subsidiary (SPV) to be
the BPC. It will be open for
MoP to review the nomination
of BPC at any time. For
immediate implementation of
these guidelines the
Empowered Committee
constituted as per provisions
of the Guidelines for
encouraging competition in
development of Transmission
Projects will be the BPC till any
other organisation is
nominated as BPC by the
Ministry/GoR.
In the instant case Energy
Department, Govt. of Rajasthan
constituted an Empowered
Committee by order dated
13/15.10.2008. It was also
mentioned in the order that
Empowered Committee will also
take care of the functions of the
BPC till a Bid Process Co-
0rdinator(BPC) is set up.
As per Bidding Documents/
Guidelines, there is need to
create SPV under the Companies
Act 1956. The SPV would perform
the role that is envisaged for
Transmission Service Provider
under the tariff based bidding
guidelines. The SPV would
eventually be taken over by the
successful bidder after payment
of all the costs incurred by RVPN
for selection of the provider and
other associated clearances etc.
The following SPVs were
registered with the Registrar of
Companies:
Raj/PPP-1: Maru Transmission
Service Company Ltd. for 400 kV
S/C Bikaner-Deedwana-Ajmer line
with 400 kV/220 kV GSS at
Deedwana and associated
works.
Raj/PPP-2: Aravali Transmission
Service Co. Ltd. for 400 kV S/C
Hindaun-Alwar line with 400/220
12
3.3
4.1
9.1
For procurement of
transmission services required
for intra-State Transmission,
the appropriate State Govt.
may notify any organisation/
State Public Sector
undertaking especially
engaged for this purpose by
the appropriate State Govt.
or BPC notified by the Central
Govt. to be the BPC for the
State.
The BPC shall prepare the bid
documentation in
accordance with these
guidelines and obtain
approval of the appropriate
Commission. If standard bid
documents notified by the
Ministry are used then
approval of appropriate
Commission is not required.
For the procurement of
transmission services under
these guidelines, BPC may at
kV GSS at Alwar and associated
works.
Here, the Govt. of Rajasthan
appointed empowered
Committee as detailed above.
The Empowered Committee in its
first meeting held on 16.1.2009
constituted the BPC, the relevant
para reads as under:
The State Transmission Utility (STU)
i.e. RVPN shall be a nodal agency
on behalf of the Committee to
act a Bid Process Co-
ordinator(BPC) for procurement
of required transmission services
as per GOI guidelines till a
separate BPC is constituted by
the GoR.
Here RVPN i.e. the Rajasthan
Vidyut Prasaran Nigam is the
State Public Sector undertaking
engaged in the business of
transmission of electricity. Hence,
there is a deviation that the BPC
has been nominated/constituted
by a Committee (Empowered
Committee) constituted by the
GoR and not directly by the GoR.
(emphasis supplied)
COMMON ANSWER TO PARA 4.1,
9.1, 9.2 AND 9.5
In pursuance to decisions of
SLEC‟s first and second meetings,
Notice Inviting Bids was published
in Two State level newspapers (all
editions), Two National level
Newspaper (all editions), Indian
Trade Journal and the Financial
Times, London, Worldwide; for
following projects:
RAJ/PPP-1: 400 kV S/C Bikaner-
Deedwana-Ajmer line with 400
kV/220 kV GSS at Deedwana and
13
9.2
9.5
its option either adopt a two
stage process featuring
separate Request for
Qualification (RFQ) and
Request for Proposal (RFP) or
adopt a single stage two
envelope tender process
combining the RFP and RFQ
processes. The bid documents
shall be prepared in
accordance with para 4.1 of
these guidelines.
RFQ or combined RFQ and
RFP notice should be
published in at least two
national newspapers, website
of the BPC and the
appropriate Government and
preferably in trade magazines
also, so as to accord it wide
publicity. The bidding shall
necessarily be by way of
International Competitive
Bidding(ICB). For the purpose
of issue of RFQ minimum
conditions to be met by th
bidder shall be specified in he
RFQ notice.
RFP shall be issued to all
bidders who have qualified at
the RFQ stage. BPC may call
a pre bid conference with all
the developers who have
sought documents for RFP
stage. In case the bidders
seek any deviations and BPC
finds those deviations are
reasonable, the BPC may
agree to such deviations. The
clarification/revised-bidding
document shall be given to all
who had sought the RFP
document informing about
associated works.
RAJ/PPP-2: 400 kV S/C Hindaun-
Alwar line with 400/220 kV GSS at
Alwar and associated works.
The Single stage two envelope
bidding process was adopted for
both the projects.
Accordingly, the bidding
documents (i.e. Request for
Qualification (RFQ), Request for
proposal (REP) and Transmission
Service Agreement(TSA) based
on Standard Bidding Documents
(SBDs) of Ministry of Power (MoP),
Government of India (GoI), were
issued on 1.3.2009 for selection of
Transmission Service Provider
through competitive bidding
process on Build, Own, Operate
and Maintenance basis.
The Pre-bid conference was held
on 31.3.2009. The revised RFP
project documents were issued
on 15.4.2009. The pre-signed
bidding documents (i.e. Request
for Qualification (RFQ), Request
for Proposal (RFP) and
Transmission Service Agreement
(TSA) were issued on 10.6.2009.
Draft of Share Purchase
Agreement was issued on
1.7.2009.
14
4.2
9.8
the deviations and
clarifications. Wherever
revised bidding documents
are issued, the BPC shall
provide bidders at least two
months after issue of such
documents for submission of
bids.
Intimation shall be sent by the
BPC to the appropriate
Commission about initiations
of the bidding process.
Bid evaluation committee:
The Empowered Committee
shall constitute a committee
for evaluation of the bids with
at least one representative
from CEA and not less than
two representatives from the
concerned Regional Power
Committees with at least one
representative from every
concerned RPC and one
independent member. The
independent member shall
have expertise in financial
matter/bid evaluation.
RVPN vide letter No.
RVPN/SE(NPP)PMU/D/2006 dated
27.2.2009 forwarded to Secretary,
RERC a copy of the Notice
Inviting Bid in respect of projects
mentioned at para 4(2) above.
Similarly RVPN vide reference No.
2110 dated 13.3.2009 sent to
Secretary, RERC a copy of Project
Estimate Report of these projects.
This implies that Commission was
informed about the initiation of
the biding process
In this context, respondent RVPN
has categorically replied as
follows:
“In view of clause 9.8, the RVPN
having being designated as BPC
by the State Level Empowered
Committee(SLEC) constituted by
GoR, had to carry out the
function of BPC as per Clause 3.1
Tariff based Competitive Bidding
Guidelines for Transmission
Service. Accordingly, Bid
Evaluation Committee was
required to be formed by RVPN
as BPC as per Clause 9.8 of Tariff
based Competitive Bidding
Guidelines for Transmission
Service. Accordingly, a
Committee was constituted vide
Secretary (ADmn.)RVPN Order
No. RVPN/AAO/Admn-Store/F. /D.
328 dated 29.12.2009 (Exhitit-6)
15
which was re-constituted vide No.
RVPN/AAO/Admn-Store/F./D. 346
dated 8.1.2010 for evaluation/
short listing of Bidders
/Transmission Service Provider(TSP)
through Tariff Based Competitive
Bidding process by way of
including Shri B.K. Makhija, Retd.
CE(RPPC), Project Consultant,
RVPN. The re-constituted
committee consists of the
following:
1.Sh. B.N. Saini, CE(Project
Planning and Management),
RVPN
2. Sh. Deepak Srivastava, Chief
Controller of Accounts, RVPN
3. Shri N.M. Agarwal, Dy.
CE(Material Management), RVPN
4. Shri R.K. Kasliwal, Dy. CE(New
Power Projects – Regulations),
RVPN
5. Shri B.K. Makhija, Retd.
CE(Rajasthan Power Procurement
Cell), Project Consultant, RVPN
6. Shri Bharat Bhushan Gupta,
C.A. Financial Expert
This being intra-state transmission
projects, the committee was
framed taking into consideration
the provisions of Clause 9.8 and
implicit provisions of Clause 1 and
3.3 of Tariff based Competitive
Bidding Guidelines for
Transmission Service and decision
of Empowered Committee to
authorise RVPN to act as BPC, the
CE(Project Planning and
Monitoring), RVPN, the CE(MM),
RVPN were taken as Members of
the Committee and Shri Bharat
Bhushan Gupta, C.A. was taken
as independent Member having
expertise in financial matter. Shri
B.K. Makhija, is an Ex. Chief
16
Engineer who has headed the
RPPC and was associated as
Chief Engineer with all the PPP
projects including these
transmission projects, under
reference undertaken by RVPN as
BPC. He was associated with the
projects since inception but
retired before completion of the
bidding process. He was retained
as Project Consultant.”
18. Selection of bidder:
(i) The Board of Directors (BoD) of RVPN in 187th meeting held on
28.9.2010 decided to issue LoI in favour of M/s GMR Energy Ltd.
and LoI were issued on 30.9.2010 for transmission projects Raj/PPP-
1: 400 kV S/C Bikaner-Deedwana-Ajmer Line with 400 kV/220 kV
GSS at Deedwana and associated works and Raj/PPP-2: 400 kV
S/C Hindaun-Alwar Line with 400/220 kV GSS at Alwar and
associated works.
(ii) The BoD in its 189th meeting held on 15.12.2010 decided for
transfer of 100% shareholding of RVPN and its nominee in Aravali
Transmission Service Company Limited and Maru Transmission
Service Company Limited. (The SPVs)
(iii) The statutory Audit of Aravali Transmission Service Company
Limited was done by 16.12.2010. As per the requirement of the
guidelines, the Share Purchase Agreement (SPA) for transfer of
TSP i.e. SPV – Aravali Transmission Service Company Limited was
signed on 19.1.2011 among Rajasthan Rajya Vidyut Prasaran
Nigam Limited, Aravali Transmission Service Company Limited
and GMR Energy Ltd. The Transmission Service Agreement (TSA)
was also signed on same day i.e. 19.1.2011 among M/s Aravali
Transmission Service Company Limited and Long Term
Transmission Customers (LTTCs) namely Jaipur Vidyut Vitran Nigam
Limited, Jodhpur Vidyut Vitran Nigam Ltd. and Ajmer Vidyut
Vitran Nigam Limited.
(iv) The statutory Audit of Maru Transmission Service Company Limited
was done by 1.2.2011. As per the requirement of the guidelines
the Share Purchase Agreement (SPA) for transfer of TSP i.e. SPV –
Maru Transmission Service Company Limited was signed on
17
15.2.2011 among Rajasthan Rajya Vidyut Prasaran Nigam Limited,
Maru Transmission Service Company Limited and GMR Energy Ltd.
The Transmission Service Agreement (TSA) was also signed on
same day i.e. 15.2.2011 among M/s Maru Transmission Service
Company Limited and Long Term Transmission Customers (LTTCs)
namely Jaipu Vidyut Vitran Nigam Ltd., Jodhpur Vidyut Vitran
Nigam Ltd. and Ajmer Vidyut Vitran Nigam Ltd.
(v) The Bid Evaluation Committee issued certificates on 17.5.2011
certifying that work has been carried out in conformity to the
provisions of the Ministry of Power, Government of India guidelines
for Tariff Based Competitive Bidding and M/s GMR Energy Ltd.
with the lowest levelised transmission charges over a period of
23.5 years, of Rs. 203.97 million for project RAJ/PPP-2: 400 KV S/C
Hindaun-Alwar Line and of Rs. 327.84 million for project RAJ/PPP-1:
400 KV S/C Bikaner-Deedwana-Ajmer Line is successful bidder.
19. From the analysis given in above matrix one can infer that there may
be two deviations from the guidelines:
i. The Bidding Process Co-ordinator (BPC) was constituted by a
Committee (Empowered Committee) instead being appointed
by the Government of Rajasthan. However, the Empowered
Committee was constituted by the Government of Rajasthan.
Therefore, it cannot be treated as a major deviation.
ii. The Bid Evaluation Committee was constituted by the Rajasthan
Vidyut Prasaran Nigam Limited i.e. the Organisation which was
acting as BPC and not by the Empowered Committee. However,
RVPN being the State Organisation, which is engaged in the
business of transmission of electricity and therefore, was
competent enough to deal with the subject matter. The details of
members of Bidding Evaluation Committee have been given in
the above matrix with reference to the guideline 9.8. The detail of
the members of the Bidding Evaluation Committee has similarity
with the details given in the guidelines.
20. In sum total, it can be safely inferred that there is a variance in the
precise adoption of the guidelines to the extent as discussed in para
19 above. The adoption of guidelines may vary to some extent
according to the organizational structure available in the State. It
would be observed that the spirit of the guidelines has been followed.
18
21. From the above discussion a view may be taken that instead of
summarily rejecting the adoption on the basis of mechanical
application of guidelines, it would perhaps be prudent to assess
whether the price was discovered in a transparent manner and is
reasonable. In this context, it can be observed that the guidelines are
not absolutely binding and deviations can be accepted if in a
specific case the object of transparency and competitiveness has
been followed.
22. In search of this objective reference to judgment pronounced by the
Appellate Tribunal of Electricity on 4th Sept., 2009 in Appeal No.
109/2009 would be appropriate. In para 20 of the said judgment
Hon‟ble Tribunal has observed as under:
“While the bidding Guidelines allow the role of the State Commission to be
only the ministerial for the adoption of Tariff when there is more than one
bidder, there is a specific reference to the consent in the case of a single
bid. This variation denotes that „adoption‟ is routine and the „consent‟ is the
outcome of the proactive consideration.” In the instant case there were
10 bidders.
23. Similarly the Central Electricity Regulatory Commission while
discharging the petition No. 18/2007 filed by Coastal Gujarat Power
Limited has observed at para 15 of its Order dated 19th Sept., 2007 as
under:
“15. It is evident from the guidelines that in contrast to the elaborate role
of the Commission in the tariff determination under Section 62 of the Act, its
role in case of tariff discovery through the competitive bidding process
undertaken under Section 63 is essentially confined to adoption of tariff, on
being satisfied that transparent process of bidding in accordance with the
guidelines have been followed in determination of such tariff. While
adopting the tariff discovered through the competitive bidding process, the
Commission is not required to go into the merits or analysis of the tariff so
discovered. Neither is it possible for the Commission to do so as no
supporting details are required to be submitted by the bidders.”
24. Besides above, the rejection on the basis of mechanical application
of guidelines would result in zeroing the efforts made in past 2-3 years
and the expenditure incurred. Further delay in implementation of the
project for another 2-3 years will result in cascading effect of cost
19
overruns. This should also be avoided when the objectivity of
transparency and competitiveness is not lost sight of.
25. In the light of foregoing discussions, it can be concluded that
selection of the successful bidder and the process of arriving at the
levelised tariff of the project mentioned in para 1 has been carried out
by the Bid Process Coordinator through a transparent process
competitive bidding following the spirit of the Guidelines and
Standard Bid Documents.
Views of Sh. D.C. Samant, Chairman
26. Before dealing with the petition and issues, it may be mentioned that
the role of the Commission in „adoption‟ of tariff under Sec. 63 is
distinct from determination of tariff under Sec. 62 of the Act. The role
of the Commission under Sec. 63 is essentially of being satisfied that
transparent process of bidding in accordance with guidelines has
been followed in tariff discovery.
27. The APTEL in its judgment in Appeal No. 109 of 2009 dated 4th
September, 2009 has clearly spelt out the functions of Commission in
adoption of tariff the relevant part is quoted as under :
“15. As referred to above, Section 63 has got two ingredients:
(1) There shall be a transparent process of bidding.
(2) The price is fixed in accordance with the Guidelines of the
Central Government.
Unless these two ingredients are satisfied, the Commission cannot
blindly adopt and accept the tariff determined. It is not correct on the
part of the Appellant to contend that when there is a transparent
bidding process, it is sufficient to adopt the price determined by the
authorities. It is to be stated that for invoking Section 63 of the Act not
only the transparent bidding process has to be followed but also has
to be verified as to whether the bidding Guidelines issued by the
Central Government have been followed. In other words, Section 63
of the Act provides that there shall be not only a transparent bidding
process but also the same shall be in accordance with the bidding
Guidelines. In the light of these things, the Commission is bound to
apply its mind whether both the ingredients are satisfied.”(Emphasis
supplied)
20
28. In the light of above discussed position, due consideration needs to
be given to the issues relevant to transparency of the process as well
as adherence by the procurer to the guidelines of the Central
Government. The Commission has to satisfy itself on both transparency
of process as well as adherence to guidelines of Central Government.
29. It would be appropriate now to deal with the main issues, which have
arisen in the matter i.e. appointment of RVPN as BPC, constitution of
Bid Evaluation Committee (BEC) by RVPN and Certificate issued by
BEC on compliance of the guidelines of the Central Government.
The appointment of RVPN as BPC
30. The guidelines regarding BPC says “3.3. For procurement of
transmission services required for intra-state transmission, the
appropriate State Government may notify any Organization/State
Public Sector Undertaking especially engaged for this purpose by the
appropriate state government or BPC notified by the Central
Government to be the BPC for the state.”
31. The State Government vide its order dated 15.10.08 constituted
empowered committee wherein it was specifically mentioned that
the Empowered Committee will also take care of the functions of the
BPC till a Bid Process Coordinator (BPC) is set up. This is in line with the
clause 3.2 of guidelines which specifies that “…For immediate
implementation of these guidelines the Empowered Committee
constituted as per the provisions of the guidelines for encouraging
competition in development of Transmission Projects will be the BPC
till any other organization is nominated as BPC by the Ministry of
Power.”
32. As per said order dated 15.10.08 the secretarial services was to be
provided by RVPN. However, the Empowered Committee in its
meeting dated 16.1.09 recorded “The STU (RVPN) shall be a nodal
agency on behalf of the Committee to act as Bid Process Coordinator
(BPC) for procurement of required transmission services as per
guidelines till a separate BPC is constituted by the GoR.”.
21
33. It is not very clear from the decision of the Empower Committee
whether RVPN was designated as BPC or whether it was to act as a
nodal agency on behalf of the Empowered Committee. In any case,
the BPC could be appointed only by the Government as per
guidelines of the Central Government and Empowered Committee
having been so appointed by the State Government cannot on its
own delegate the functions of BPC to RVPN.
Constitution of Bid Evaluation Committee by RVPN
34. The guidelines regarding Evaluation committee specifies; “9.8. Bid
evaluation committee: The Empowered Committee shall constitute a
committee for evaluation of the bids with at least one representative
from CEA and not less than two representatives from the concerned
Regional Power Committees with at least one representative from
every concerned RPC and one independent member. The
independent member shall have expertise in financial matter/bid
evaluation.”
35. In the present case, RVPN acting as BPC, constituted Bid Evaluation
Committee vide order dated 29.12.2009 for evaluation of bids, which
was later re-constituted vide order dated 08.1.2010. It has obviously
been incorrectly constituted, as it is the function assigned to the
Empowered Committee.
36. BEC has been assigned important role in the bid process as per the
guidelines issued by the Central Government. The adoption of tariff
hinges on the certification by the Bid Evaluation Committee. As per
guidelines, the Bid Evaluation Committee was to certify as to the
whole process being as per guidelines of the Central Government as
well as reasonability of charges was also to be evaluated by this
committee.
37. As has come out, both Bid Process Coordinator as well as Bid
Evaluation Committee have been incorrectly constituted. BPC as well
as BEC have key role in the entire bid process. These two
omissions/mistakes, when seen together, lead to deviations in the
process which cannot be reckoned as minor. The inference,
22
therefore, emerges that the bidding process has not been in
accordance with the guidelines of the Central Govt. The contention
of RVPN that the guidelines are not clear and they interpreted
guidelines in light of GoR order & Empowered Committee‟s decisions
and acted accordingly are well taken. However, Since Commission
under Sec. 63 of the Electricity Act, 2003 has to only satisfy itself as
regards the process being in accordance in the guidelines of the
Central Government, the said contention is not sufficient to infer that
the process is in accordance with the guidelines of the Central
Government.
38. In the light of what has been discussed above, the conclusions that
clearly emerges is that bidding has not been in accordance with the
guidelines of the Central Government. It may be mentioned that
nothing adverse has been noticed or raised as far as transparency of
the bidding is concerned. However, as discussed in para 28 of this
order, the Commission is to get satisfied on both transparency of
process as well as process being in accordance with guidelines. As
has been mentioned earlier, the satisfaction as regards the process
being accordance with the guidelines of the Central Government
cannot be arrived at due to the reasons discussed earlier in the order.
Conclusion & Decision of the Commission
39. There being difference in views of the members of the bench in the
matter the views as of Chairman would prevail as per Sec. 92 (3) of
the Electricity Act, 2003. Accordingly, it is held that the process
followed has not been in accordance with the guidelines of the
Central Government and therefore the proposed tariff cannot be
adopted under Section 63 of the Electricity Act, 2003. The petition is,
therefore, dismissed with no order as to cost.
(S.K.Mittal) (D.C. Samant) Member Chairman