Greenwood’s Fry Road Rain Trail
![Page 2: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/2.jpg)
Fry Road Rain TrailGreenwood, Indiana
The Problem
![Page 3: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/3.jpg)
Fry Road Rain TrailGreenwood, Indiana
The Problem
![Page 4: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/4.jpg)
Fry Road Rain TrailGreenwood, Indiana
The Problem• Standing Water• Erosion/Water Quality• Maintenance• Aesthetics
![Page 5: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/5.jpg)
Fry Road Rain TrailGreenwood, Indiana
The Solution
A Pipe!
![Page 6: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/6.jpg)
Fry Road Rain TrailGreenwood, Indiana
“Can we get a sidewalk too? How about a bike path? Something ‘green’ would be nice.”
![Page 7: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/7.jpg)
Fry Road Rain TrailGreenwood, Indiana
A New Approach• What if the path was part of the drainage
conveyance?• If we utilize porous pavement, an aggregate
recharge bed, and perforated pipe; we can reduce the size of the pipe while providing a water quality benefit.
![Page 8: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/8.jpg)
Fry Road Rain TrailGreenwood, Indiana
Introducing: The Rain Trail
![Page 9: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/9.jpg)
Fry Road Rain TrailGreenwood, Indiana
Introducing: The Rain Trail
Porous Asphalt
Aggregate Recharge Bed
Filter Fabric
![Page 10: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/10.jpg)
Fry Road Rain TrailGreenwood, Indiana
How Does it Work?
![Page 11: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/11.jpg)
Fry Road Rain TrailGreenwood, Indiana
How Does it Work?
• Runoff percolates through pavement• Stored in Aggregate Recharge Bed• Runoff in excess of soil infiltration capacity enters
perforated pipe
![Page 12: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/12.jpg)
Fry Road Rain TrailGreenwood, Indiana
Construction
![Page 13: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/13.jpg)
Fry Road Rain TrailGreenwood, Indiana
The Finished Product
![Page 14: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/14.jpg)
Fry Road Rain TrailGreenwood, Indiana
Challenges & Obstacles• Constructability & Durability– Asphalt mix is difficult to work with– Sections adjacent to approaches required
replacement– Some degradation occurred after 1st winter– Require 3-year maintenance bond
![Page 15: Rain Trail Project – Fry Road in Greenwood, Indiana](https://reader031.fdocuments.net/reader031/viewer/2022021813/58d13f201a28ab455d8b5653/html5/thumbnails/15.jpg)
Fry Road Rain TrailGreenwood, Indiana
Challenges & Obstacles• Maintenance– Porous Asphalt must be vacuum cleaned– Fry Road trail was too narrow (8’) for street
sweeper. Recommend 10’ wide trail.– Vac Truck attachment will be used for routine
maintenance