RAILROAD COMMISSION OF TEXAS Drilling Permits Statewide Rule 37 & 38 Exceptions Lorenzo Garza.
RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II...
-
Upload
harriet-louise-wilkins -
Category
Documents
-
view
218 -
download
0
Transcript of RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II...
![Page 1: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/1.jpg)
RAILROAD COMMISSION OF TEXAS
UIC Completion Reporting Guidance
Jim Moore, Engineering Specialist IIInjection-Storage Permits & Support
![Page 2: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/2.jpg)
2
PRESENTATION OVERVIEW
A few examples of RRC webpage research including UIC webpages then a step-by-step guidance for W-2/G-1 online completions for injection / disposal / storage / brine mining wells. Steps include log in, starting or updating a completion packet, entering data, additional forms, submitting, messaging, and problem resolution.
Please ask questions during the presentation.
![Page 3: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/3.jpg)
3
RRC HOMEPAGE
Data – Online Research Queries
Oil & Gas link or pull-down menu
RRC Online Log In
![Page 4: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/4.jpg)
4
RRC WEBPAGE
Oil & Gas Completion Query
Online Research Queries
Injection/Disposal Permit Query
Oil & Gas Imaged Records Menu
![Page 5: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/5.jpg)
5
RRC WEBPAGE
Oil & Gas Well RecordsGAU LettersDisposal Permits (W-14)Injection/Disposal Permits (H-1/H-1A)
Oil and Gas Imaged Records Query Menu
These are links to Neubus
![Page 6: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/6.jpg)
6
OVERVIEW INJECTION PERMIT TYPES
• H-1/H-1A – Enhanced Recovery– Oil and Gas Waste Disposal
• W-14– Oil and Gas Waste Disposal
• H-2– Brine Mining
• H-4– Underground Hydrocarbon Storage
![Page 7: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/7.jpg)
7
INJECTION/DISPOSAL PERMIT DETAIL
• Base of Usable Quality Water• Casing Record• Injection Interval• Tubing/Packer Depth• Formation Name(s)• Permit Special Conditions
![Page 8: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/8.jpg)
8
IMPORTANT PERMIT DATA
• Field Name & Field Number– Matches on Completion (Form W-2/G-1), Drilling Permit (Form W-1)
• Well Number– Can be changed/updated with Completion
Injection Disposal
Well
Drilling Permit
UIC Permit
Completion Report
![Page 9: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/9.jpg)
9
COMPLETION OVERVIEW
• Packet Data• Form W-2/G-1 Data• Complete Additional Forms– P-4, W-12, L-1
• Load Attachments– W-15, W-12, GAU Letter (formerly TCEQ ),
Log Header, others e.g. SWR13 Exception Letter• Submit
![Page 10: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/10.jpg)
10
ONLINE SYSTEM
Select Completions
![Page 11: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/11.jpg)
11
FILING OPTIONS & MESSAGES
File a New Completion or Update Existing Completion Packet
Check Messages for your User ID, orfind all Messages for this Operator
![Page 12: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/12.jpg)
12
UPDATE EXISTING PACKET
Packet Status:- Submitted
Packet Status:- Work In Progress- Pending Operator Update- Hard Copy
View By options
![Page 13: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/13.jpg)
13
FILE A NEW COMPLETION PACKET
Click Search
EnterDrilling Permit No. orAPI No.
![Page 14: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/14.jpg)
14
Multiple Field Names Allowed on Drilling Permit New Packet
FILE A NEW COMPLETION PACKET
![Page 15: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/15.jpg)
15
o Multiple Drilling Permits may be populated when searching with APIo Drilling Permit’s can have multiple field nameso Choosing the Correct Drilling Permit is very Important!
CHOOSE THE CORRECT DRILLING PERMIT
![Page 16: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/16.jpg)
16
PACKET DATA
Purpose of FilingType of CompletionWell TypeWellbore ProfilePacket Type
Definitions for Purpose of Filing
Recommended sequence
![Page 17: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/17.jpg)
17
PACKET DATA
![Page 18: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/18.jpg)
18
PACKET DATA
![Page 19: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/19.jpg)
19
PACKET DATA
(For WSW, Water Supply Wells)
![Page 20: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/20.jpg)
20
PACKET DATA
Wellbore Profile is auto-populated from Drilling Permit, Form W-1
![Page 21: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/21.jpg)
21
PACKET DATA
![Page 22: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/22.jpg)
22
PACKET DATA
Click Create Packet tab
Tracking Number gets assigned
Purpose of FilingType of CompletionWell TypeVertical ProfilePacket Type
Done1
2
3
![Page 23: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/23.jpg)
23
PACKET DATA
Fill in Well Data
Recompletion/Reclass Table
Save
Change Packet Description
![Page 24: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/24.jpg)
24
PACKET DATA
New data fields 01/2014
Enter Permit No. & Date
Prior Service TypeSearch for Field & Reservoir
![Page 25: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/25.jpg)
25
PACKET DATA
Search for Field & Reservoir
1 result
Select
![Page 26: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/26.jpg)
26
W-2/G-1 PAGE 1
Page 1: Potential Test Data
Save, Select Page #
Select W-2 to continue
![Page 27: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/27.jpg)
27
W-2/G-1 PAGE 2
Save
Fill In Well Data
System responds with red text warnings if critical data is missing on this page.
![Page 28: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/28.jpg)
28
W-2/G-1 PAGE 3
New data fields 01/2014
![Page 29: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/29.jpg)
29
W-2/G-1 PAGE 4
New data fields 01/2014
Type of Casing (pull-down)ConductorSurfaceIntermediateConventional ProductionTapered ProductionOther
Top of Cement Determined By (pull-down) CalculationTemperature SurveyCement Evaluation LogCirculated
![Page 30: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/30.jpg)
30
W-2/G-1 PAGE 4
Active UIC:Tubing & Packer SetPossible exceptions- Brine mining- Hydrocarbon storage- Permit exception
![Page 31: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/31.jpg)
31
Perforations and Packer Depth
Permitted Interval
Needs to be less than 100’ unless permitted packer depth allows it
Injection Interval
o Insure Packer, Perforations and Plug Back depth all agree
![Page 32: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/32.jpg)
32
Example Permit
o Permitted Interval: 5577-6468’
o Actual Packer depth: 5800’
![Page 33: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/33.jpg)
33
Example of Inaccurate Reporting
5577
6468
5800Actual
Perforations:6000-6150
o If the permitted interval is reported instead of the completed interval, there is an obvious discrepancy
![Page 34: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/34.jpg)
34
W-2/G-1 PAGE 5
This table is required for Well Type: Active UIC
Can be “Yes” for Shut-In UIC
Injection/Disposal Interval is within Permitted Interval
![Page 35: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/35.jpg)
35
W-2/G-1 PAGE 5
Process (pull-down)AcidFractureCement SqueezeCast Iron Bridge Plug*RetainerOther
New data fields 01/2014
List all Work Chronologically, attach Form W-15 for new CIBP, Cement Squeeze, Squeeze Perfs, etc.
![Page 36: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/36.jpg)
36
W-2/G-1 PAGE 5
When to mark “Encountered”, “Isolated”
New data fields 01/2014
![Page 37: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/37.jpg)
37
RRC WEBPAGE
Revised SWR 13 – Casing, Cementing, Drilling, Well Control, and Completion Requirements
Oil & Gas page
Compliance & Enforcement
Quick recommendation!!
![Page 38: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/38.jpg)
38
RRC WEBPAGE
Rule 13 – Geologic Formation Information
Compliance & Enforcement page
![Page 39: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/39.jpg)
39
EXAMPLE FORMATION TOPS
![Page 40: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/40.jpg)
40
W-2/G-1 PAGE 6
Certify (or Re-certify)
Electronic Signature
Red text warnings if critical data is missing on W-2/G-1.
![Page 41: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/41.jpg)
41
COMPLETE ADDITIONAL FORMS
Additional Forms
Attachments
Select P-4 Certificate of Compliance and Transportation Authority
Determine All Required Forms
![Page 42: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/42.jpg)
42
ADDITIONAL FORM: P-4
Service Well, Yes
Certify (or Re-certify)
Gatherers and/or Purchasers info left blank.*
RRC Gas ID or Oil Lease No. is blank/zero
![Page 43: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/43.jpg)
43
ADDITIONAL FORM: P-4
Certify (or Re-certify)
Electronic Signature
![Page 44: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/44.jpg)
44
ADDITIONAL FORM: W-12
Well Information
Shot Point Information
Certify (or Re-certify)Electronic Signature
![Page 45: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/45.jpg)
45
ADDITIONAL FORM: L-1
Certify (or Re-certify)Electronic Signature
Basic Electric Log Run
Option: ConfidentialityAttach Log Header
Option: Log AttachedMail Log to RRC AustinAttention: Proration or UIC
![Page 46: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/46.jpg)
46
LOAD ATTACHMENTS
Additional Forms
Attachments
Select W-15 Cementing Report
Determine All Required Forms
![Page 47: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/47.jpg)
47
LOAD ATTACHMENTS: W-15
Current Attachments
Browse to file location such as your Desktop
Upload
21 3
Formats: .pdf or .tif
![Page 48: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/48.jpg)
48
RRC WEBPAGE
Forms- Proposed Form Changes
Oil & Gas page
Quick recommendation!!
![Page 49: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/49.jpg)
49
RRC WEBPAGE
W-15 Cementing Report
Proposed Form Changes
![Page 50: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/50.jpg)
50
LOAD ATTACHMENTS: W-12
Current Attachments
Pick 1 of 2 ways to initiate the Upload Attachment step
![Page 51: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/51.jpg)
51
LOAD ATTACHMENTS: W-12
Select W-12
Pull-Down/Pull-Up Menu for Attachment Type
![Page 52: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/52.jpg)
52
COMPLETION OVERVIEW
• Packet Data• Form W-2/G-1 Data• Complete Additional Forms– P-4, W-12, L-1
• Load Attachments– W-15, W-12, GAU Letter (formerly TCEQ ),
Log Header, others e.g. SWR13 Exception Letter• Submit
![Page 53: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/53.jpg)
53
SUBMIT PACKET
Form Name
Attachments
Submit
Service Well, Yes
![Page 54: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/54.jpg)
54
SUBMIT PACKET
Submit
NoNo
![Page 55: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/55.jpg)
55
SUBMIT FORMS LACKING
• Submit with required forms missing or uncertified?: • Submit with required attachments missing?:
Answer 1 or both “Yes”
If RRC analysts give Final Approval to the Completion Packet with Forms Lacking, then the Operator will need to provide the missing forms or attachments as soon as possible. Warning letter will follow.
![Page 56: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/56.jpg)
56
SUBMIT PACKET
… submitted successfully message
![Page 57: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/57.jpg)
57
PROBLEM RESOLUTION
• Respond to RRC messages on packet• Provide additional data, forms, attachments• Electronic signature & re-certify all forms released• Re-submit packet if released• Problem resolution
– W-1 Drilling Permit Amendment– H-1/H-1A or W-14 Injection/Disposal Permit Amendment– UIC Certified Letter– UIC Severance Letter– Refer to SWR 16
![Page 58: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/58.jpg)
58
REQUIREMENTS
• W-1 Drilling Permit – refer to SWR 5 (512) 463-6751– New Well– Deepening– Re-enter– Plug Back / Re-Completion in a Different Field
• W-15 Cementing Report – check with RRC Districts– New Well– Cement (CS)/ Block Squeeze (CS), Squeeze Perfs, Bridge Plug (CIBP),
Plug Back– May relate to Injection/Disposal Permit Special Conditions
![Page 59: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/59.jpg)
59
REQUIREMENTS
• W-12 Inclination Report – refer to SWR 11– New Well, Total Depth > 2000 feet– Re-Enter requires new survey if one was not already filed
• exception for Enhanced Recovery– Deepening
• Directional Survey– New Drill if the Wellbore Profile is Directional or Horizontal– New Drill if the Wellbore Profile is Vertical
• and the W-12 violates 11(c)(1)(A)– Applicable to some Re-Entry, or Deepening– Directional Surveys filed/uploaded by the responsible service company– RRC Engineering Unit & Support (512) 463-1126
![Page 60: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/60.jpg)
60
TERMS & DEFINITIONS
• UIC : Underground Injection Control • UIC Number : 9 digit number assigned to Well• H-1 Number : Project number– Fluid Injection Permit No. (label on Packet Data)– F- followed by 5 digits
• W-14 Number : Permit number– O&G Waste Disposal Permit No. (label on Packet Data)– 5 digits
![Page 61: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/61.jpg)
61
TERMS & DEFINITIONS
• API Number : 10-digit number assigned to Well• Well Number : D or L D D D L L , D=digit L=letter• RRC District No.• RRC Oil Lease No. : 5 digit Number • RRC Gas ID : 6 digit Number• Plat : Lease Map, Survey Location
![Page 62: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/62.jpg)
62
TERMS & DEFINITIONS
• H-1 Field Name– correlative to injection/disposal Formation(s)– use deepest if more than one Formation– well is on current schedule in one of the proposed
Formations, then keep current Field Name• W-14 Field Name– correlative to disposal Formation(s) more than
2 miles away– or to Formation that is source of disposal fluids
![Page 63: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/63.jpg)
63
QUESTIONS
![Page 64: RAILROAD COMMISSION OF TEXAS UIC Completion Reporting Guidance Jim Moore, Engineering Specialist II Injection-Storage Permits & Support.](https://reader035.fdocuments.net/reader035/viewer/2022062518/56649d6e5503460f94a4fd63/html5/thumbnails/64.jpg)
64
CONTACT INFORMATION
• Jim Moore– Injection / Disposal Permitting– UIC Completions
• 512-463-6443 (Direct)• 512-463-6792 (Main)• 512-463-6780 (Fax)• [email protected]