Customer Service and Operations Committee Board Information Item III-B November 4, 2010 Rail Mileage-Based Asset Management Page 23 of 52

Transcript of Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project...

Page 1: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

Customer Service and Operations Committee

Board Information Item III-B

November 4, 2010

Rail Mileage-Based Asset Management

Page 23 of 52

Page 2: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

TITLE:

Rail Mileage-Based Asset Management Project

PURPOSE:

Provide the Customer Service and Operations (CSO) Committee with an overview of the Rail Mileage-Based Asset Management Project.

DESCRIPTION:

The Rail Mileage-Based Asset Management Project demonstrates Metro`s commitment to delivering quality service and using every resource wisely by reducing unnecessary and unscheduled maintenance and improving the overall reliability of the fleet.

A mileage-based system:

Aligns maintenance on individual vehicles with acutal wear;

Triggers maintenance schedules based on mileage;

Improves the accuracy of mileage calculation;

Improves forecasting for parts inventory and maintenance staffing requirements;

Permits efficient management of component requirements across the large variety of railcar configurations;

Reduces unnecessary maintenance; and

Improves the overall reliability of the fleet.

FUNDING IMPACT:

On the Board approved Plan of Contracts; CIP140.

RECOMMENDATION:

None.

Washington Metropolitan Area Transit Authority

Board Action/Information Summary

Action Information MEAD Number: Resolution:Yes No

Page 1 of 2

10/28/2010http://mead/prod/reports/bais.cfm?RequestTimeout=300

Page 24 of 52

Page 3: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

Washington Metropolitan Area Transit Authority

R il Mil B d A tRail Mileage-Based Asset Management Project

Customer Service and Operations CommitteeCustomer Service and Operations Committee

November 4, 2010

Page 25 of 52

Page 4: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

Purpose

• Update the CSO Committee on the status of the Rail Mileage-Based Asset Management Project

• Rail Mileage-Based Asset Management Project is a part of the Board approved FY2011 Plan ofpart of the Board approved FY2011 Plan of Contracts

Page 26 of 52

Page 5: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

Railcar Mileage Today

• Presently, mileage is computed via software algorithms that l l d b d l destimate miles traveled based on manual data input

• This artificially computed mileage is subject to human input error and has an error rate of approximately 10% or 7.2M miles annually

• Current scheduled maintenance activities are based solely upon time intervals that may result in railcars receiving maintenance regardless of accumulated mileage and whether g gthey are in or out of service

Page 27 of 52

Page 6: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

Benefits – Actual Mileage Based

• The new maintenance approach focuses on actual mileage that will improve cost controls overall reliability and minimizes unnecessary railcar movescost controls, overall reliability and minimizes unnecessary railcar moves and maintenance activities

• Wireless technology will allow actual railcar mileage data to be collected gy greal time using secure Wide Area Network (WLAN) network

• Common WLAN technology platform will enable full capability of the 7000 se ies i eless design to t ansmit and tili e maintenance data s stem ideseries wireless design to transmit and utilize maintenance data system wide

• Provides expandable capability for wireless diagnostics on existing fleets and identifies faults and issues before they impact serviceand identifies faults and issues before they impact service

• Standard approach of maintenance based upon actual miles is being done at Metropolitan Atlanta Rapid Transit Authority, Massachusetts Bay Transportation Authority, Denver Regional Transportation, Los Angeles County Metropolitan Authority and Portland (Oregon) Light Rail

Page 28 of 52

Page 7: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

Benefits – Asset Management

• Asset configuration software expands the capability of Maximo to utilize railcar mileage data to develop maintenance on a mileage based scheduleschedule

• Mobile inventory software expands the capability of Maximo for improved management of parts and materialimproved management of parts and material

• Barcode requirements specified on new car contracts and new long term part procurement approachterm part procurement approach

Page 29 of 52

Page 8: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

Project Cost & Major Deliverables

• Project Cost: $8 07MProject Cost: $8.07M

• Major Deliverables:

o Mileage-capture device installation on rail fleet

o Asset configuration manager software

o Mobile Maximo for inventory software

o WLAN – IT infrastructure upgrade at rail yardso WLAN – IT infrastructure upgrade at rail yards

Page 30 of 52

Page 9: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

Project Schedule

• Pilot (8-months): Testing on limited number of railcars at one rail yard

Page 31 of 52

Page 10: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

Wireless Electronic Odometer & Wireless LAN OverviewWireless LAN Overview

Page 32 of 52

Page 11: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

APPENDIX

Page 33 of 52

Page 12: Rail Mileage-Based Asset Management - WMATA€¦ · Project Cost & Major Deliverables • Project Cost: $8 07MProject Cost: $8.07M • Major Deliverables: o Mileage-capture device

Project Elements

• Mileage-capture device installation on rail fleet $2.0MMileage capture device installation on rail fleet $2.0M

• WLAN – IT infrastructure upgrade at rail yards $.77M

• Asset Configuration Manager Software Maximo 7 $2 0M• Asset Configuration Manager Software, Maximo 7 $2.0M

• Mobile Maximo for Inventory Software, Maximo 7 $.50M

/ S $2 8• Project Management/Engineering Services $2.8M