Q'Vive PMP All Docs v4

4
Configuration management plan / Change management plan Integration Stakeholder analysis / Stakeholder register / Stakeholder management strategy Communications Statement of work / Contract / Business case / Charter Integration Initiating Procurement documentation / Change requests Project management plan updates Procurement Quality audit reports / Change requests Project management plan updates Quality Risk register / Risk register updates Risk Project Staff assignments / Resource calendars / Team performance assessments / Training plans / Issue log / Change requests Project management plan updates Human Resources Activity resource requirements / Resource breakdown structure Time Quality control measurements / Validated changes / Change requests Project management plan updates Quality Risk register updates / Change requests Project management plan updates Risk Performance reports / Change requests Communications Work performance measurements / Budget forecasts / Earned value reports / Change requests Project management plan updates Cost Work performance measurements / Change requests Project management plan updates Scope Work performance measurements / Change requests Project management plan updates Time Sellers list / Proposals / Contracts / Change requests Project management plan updates Procurement Change log / Issue log / Change requests Project management plan updates Communications Risk-related contract decisions / Risk register updates Project management plan updates Risk Schedule management plan* Time (Integration) Cost management plan* Cost (Integration) Program schedule network diagrams Time Activity duration estimates Time Project schedule / Schedule data Schedule baseline Time Integration Integration Integration Procurement Risk Communications Human Resources Quality Cost Cost Time Scope Scope Scope (Integration) Knowledge Area Work performance information / Change requests Project management plan updates Executing Change request status updates Project management plan updates Monitoring & Controlling Closing Planning Process Group Project funding requirements Cost performance baseline Quality metrics / Quality checklists / Quality standards Quality management plan / Process improvement plan Project organizational structure / Resource requirements / Responsibility assignment matrix / Roles and responsibilities Human resource plan / Staffing management plan Communications management plan Roles and responsibilities Risk management plan Teaming agreements / Procurement SOW / Make-or-buy decisions / Procurement documents / Source selection criteria / Change requests Procurement management plan Archived project documents Activity cost estimates / Basis of estimates Activity list / Activity attributes / Milestone list Requirements traceability matrix / Assumption log / Technical documentation Scope baseline (Scope statement, WBS, WBS dictionary) Requirements documentation / Stakeholder requirements Requirements management plan Scope management plan* Project Documents Project Management Plan Docs Docs TM TM Docs Docs TM TM TM TM The ultimate PMP ® project plan and documents list. © 2009, 2011 Q'vive, LLC Eric van der Meulen, PMP All rights reserved qvive.biz [email protected] "PMBOK" and "PMP" are registered marks of Project Management Institute, Inc. P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P updates PDL12116 R R R R R R S R * Scope, Schedule, and Cost planning processes are preceded by a planning effort in 4.2 Develop Project Management Plan, which produces management plans for these Knowledge Areas.

description

Q'Vive PMP All Docs v4

Transcript of Q'Vive PMP All Docs v4

  • Configuration management plan / Change management plan

    Integration

    Stakeholder analysis / Stakeholder register / Stakeholder management strategy

    Communications

    Statement of work / Contract / Business case / CharterIntegration

    Initiating

    Procurement documentation / Change requestsProject management plan updatesProcurement

    Quality audit reports / Change requestsProject management plan updatesQuality

    Risk register / Risk register updatesRisk

    Project Staff assignments / Resource calendars / Team performance assessments / Training plans / Issue log / Change requests

    Project management plan updatesHuman Resources

    Activity resource requirements / Resource breakdown structureTime

    Quality control measurements / Validated changes / Change requestsProject management plan updatesQuality

    Risk register updates / Change requestsProject management plan updatesRisk

    Performance reports / Change requestsCommunications

    Work performance measurements / Budget forecasts / Earned value reports / Change requests

    Project management plan updatesCost

    Work performance measurements / Change requestsProject management plan updatesScope

    Work performance measurements / Change requestsProject management plan updatesTime

    Sellers list / Proposals / Contracts / Change requestsProject management plan updatesProcurement

    Change log / Issue log / Change requestsProject management plan updatesCommunications

    Risk-related contract decisions / Risk register updatesProject management plan updatesRisk

    Schedule management plan*Time (Integration)

    Cost management plan*Cost (Integration)

    Program schedule network diagramsTime

    Activity duration estimatesTime

    Project schedule / Schedule dataSchedule baselineTime

    Integration

    Integration

    Integration

    Procurement

    Risk

    Communications

    Human Resources

    Quality

    Cost

    Cost

    Time

    Scope

    Scope

    Scope (Integration)

    Knowledge Area

    Work performance information / Change requestsProject management plan updates

    Executing

    Change request status updatesProject management plan updates

    Monitoring &

    Controlling

    Closing

    Planning

    Process Group

    Project funding requirementsCost performance baseline

    Quality metrics / Quality checklists / Quality standardsQuality management plan / Process improvement plan

    Project organizational structure / Resource requirements / Responsibility assignment matrix / Roles and responsibilities

    Human resource plan / Staffing management plan

    Communications management plan

    Roles and responsibilitiesRisk management plan

    Teaming agreements / Procurement SOW / Make-or-buy decisions / Procurement documents / Source selection criteria / Change requests

    Procurement management plan

    Archived project documents

    Activity cost estimates / Basis of estimates

    Activity list / Activity attributes / Milestone list

    Requirements traceability matrix / Assumption log / Technical documentation

    Scope baseline (Scope statement, WBS, WBS dictionary)

    Requirements documentation / Stakeholder requirementsRequirements management plan

    Scope management plan*

    Project DocumentsProject Management Plan

    DocsDocs TMTMDocsDocs TMTMTMTMThe ultimate PMP project plan

    and documents list.

    2009, 2011 Q'vive, LLC Eric van der Meulen, PMP All rights reserved qvive.biz [email protected] "PMBOK" and "PMP" are registered marks of Project Management Institute, Inc.

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PP

    PPupdates

    PDL12116

    R

    R

    R

    R

    R

    R

    S

    R

    * Scope, Schedule, and Cost planning processes are preceded by a planning effort in 4.2 Develop Project Management Plan, which produces management plans for these Knowledge Areas.

  • ETC = BAC EVAssumes future work to be performed as budgeted

    ETC (for atypical variance)Estimate To Complete

    FormulaDescriptionAbbreviationVariable

    ETC = (BAC EV) / CPIAssumes past performance to continue throughout

    ETC (for typical variance)

    TCPI = (BAC EV) / (BAC AC)

    BASED ON BAC

    or TCPI = (BAC EV) / (EAC AC) BASED ON NEW EAC

    Cost performance necessary to achieve BAC or new EAC goal

    Work remaining divided by funds remaining

    TCPITo-Complete Performance Index

    VAC = BAC EACForecast of varianceVACVariance At Completion

    EAC = AC + ETC = AC + (BAC EV) / CPI

    or EAC = BAC / CPI

    Assumes past performance to continue throughout

    EAC (for typical variance)

    EAC = AC + BAC EVAssumes future work to be performed as budgeted

    EAC (for atypical variance)

    EAC = AC + Bottom-up ETCUse when original est. is flawedEACEstimate At Completion

    Budget assigned for workBACBudget At Completion

    SPI = EV / PVMeasure of schedule efficiencySPISchedule Performance Index

    SV = EV PVMeasure of schedule performanceSVSchedule Variance

    CPI = EV / ACMeasure of cost efficiencyCPICost Performance Index

    CV = EV ACMeasure of cost performanceCVCost Variance

    Budget assigned for work performed

    PVPlanned Value

    Value of work performedEVEarned Value

    Actual cost incurred for work performed

    ACActual Cost

    CO

    ST Earned Value

    CO

    ST Forecasting

    FormulasFormulas TMTMFormulasFormulas TMTMTMTMThe ultimate PMP

    reference sheet.

    2009, 2011 Q'vive, LLC Eric van der Meulen, PMP All rights reserved qvive.biz [email protected] "PMBOK" and "PMP" are registered marks of Project Management Institute, Inc.

    Probability Impact [$]EMVExpected Monetary Value

    90 %Project Manager Communication

    n(n-1) / 2 n = # of stakeholdersCommunication channels

    EMV costNet BenefitNet Benefit

    FormulaAbbreviationVariable

    1 = 68.26 % 3 = 99.73 %

    2 = 95.46 % 6 = 99.99985 %

    1 standard deviation =

    1 STD = 1 sigma = 1

    Normal Distribution

    +/- 50% from actualRough Order of MagnitudeEstimating in Initiating

    -10% to +25% from actualBudgetary / Top Down / Analogous

    Estimating early in Planning

    -5% to +10% or +/-10% from actualDefinitive / Bottom-upEstimating late in Planning

    P + 4M + O P = pessimistic, M = most likely, O = optimistic

    6

    PERT (Program Evaluation and Review Technique)

    Three point estimate for activity duration, weighted average

    (PERT1 + PERT2 + PERT3 + ) + (# of sigmas STDproject)critical path activities only:Project Duration

    Var1 + Var2 + Var3 + STDproject (or project)Standard Deviation of Project

    ((P O) / 6)2

    Varactivity (or 2 activity)Variance of Activity

    (P O) / 6STDactivity (or activity)Standard Deviation of Activity

    TIM

    E/C

    OST Estimating

    PFS12117

  • DefinedDefinedTMTMDefinedDefinedTMTMTMTMThe ultimate PMP

    charter glossary.

    Purpose, Objectives, Requirements

    Purpose: Reason(s) for doing this project in terms of business objective and related strategic goal. Description of issue or opportunity addressed.

    Objective: Targeted result of the project.

    Success Criteria: SMART objectives are quantifiable criteria used to measure project success (Specific, Measurable, Achievable, Realistic, Time-bound).

    Requirement: Quantified and prioritized attribute, capability, characteristic, or quality of the (product of) the project that is wanted, needed, or expected by Sponsor and Stakeholders (Customers).

    Milestones/Deliverables, Constraints

    Milestone: Major Deliverable or significant event in the project used to measure progress.

    Deliverable : Any unique and verifiable product, result, or capability that must be produced to complete the stage, phase, or project; tangible, measurable, and easily proved.

    Constraint : A restriction or limitation, either internal or external to a project, which will affect the performance of the project. A boundary condition within which the project must remain, e.g., scope, cost, schedule, resources, quality, etc.

    In Scope*

    What is included in the project and its Deliverables . The who, what, where, when, and why of the project.

    Product Scope : Features and functions that characterize the product or result of the project.

    Project Scope : Work required to deliver the product.

    Assumptions & Risks

    Assumption : Factor (event, action, condition) that, for planning purposes, is considered to be true, real or certain without proof or demonstration.

    Risk: An uncertain event or condition that, if it occurs, has a positive or negative effect on the projects Objectives.NEGATIVE RISK: The possibility that an undesired outcome or the absence of a desired outcome disrupts the project; always reflects uncertainty, a potential loss, and a time component.

    Out Of Scope*

    What is not included in the project and its deliverables.

    * NOTE: In Scope and Out Of Scope define the Project Boundaries

    Team: Project Manager (or Project Management Team) and Team Members.

    Stakeholders: Persons or organizations (Customer, performing organization, public) that are actively involved in the project, or whose interests may be positively or negatively impacted by execution or completion of the project; may also exert influence over the project and its Deliverables .

    2010, 2011 Q'vive, LLC Eric van der Meulen, PMP All rights reserved qvive.biz [email protected] "PMBOK" and "PMP" are registered marks of Project Management Institute, Inc.PTG12114

    The Project Charter can take on many forms.

    Commonly used in a New Product Development or Stage-Gate environment is the project 4-block. See the example below with typical terminology. The 4-block is a communication tool that is used between Project Team and Senior Management. Financial justification is usually obtained through separate spreadsheet calculations, which depend on the practices of the performing organization.

    The use of common format and terminology promotes efficient and focused project reviews.

    Although the terms have distinct definitions, there can be some apparent overlap, which is inevitable. In these cases, go with the spirit, not the letter. For instance, there are fine lines between Purpose, Objective, Scope, Deliverable, and Requirement.

    The process of obtaining clarity is a very important activity. During project initiation the 4-block is a powerful tool to build consensus among Stakeholders as well the Project Team, especially when defining what is Out Of Scope.

    S

    S

    S

    S

    S

    S

    S

    S

  • DefinedDefinedTMTMDefinedDefinedTMTMTMTMThe ultimate PMP

    Whos Who.

    Project Manager typically in matrix or projectized organization

    The person ultimately responsible for the outcome of the project

    Authorized to spend Budget and assign Project Resources to realize project goals

    Authorized to make decisions for the project

    Ultimate owner of project related problems

    Balances Stakeholder interests

    Balances Constraints

    Project Coordinator in weak matrix or functional organization

    Weaker than Project Manager

    Some authority to assign Project Resources

    Not authorized to spend funds or make overall project decisions

    Project Expeditor staff assistant, typically in functional organization

    Weakest of Project Management roles with little or no formal authority

    Reports on project progress

    No authority over Project Resources or funds

    Project Team Member

    Assists in creating WBS and Schedule

    Executes project activities

    Creates Deliverables

    Tracks and reports status

    Project (Management) Office or PMO

    Department that controls all projects in an organization

    Defines standards, best practices

    Audits projects for conformance

    Supports Project Managers with:

    Methodologies

    Tools

    Training

    Project Sponsor

    Responsible for funding the project

    Sometimes called Project Champion

    Typically a Senior Manager (see Senior Management)

    Typically internal to the company, while Customer is external, however:

    Can be internal or external to the performing organization

    May or may not be the Customer

    Can help resolve dispute between performing organization and Customer

    Stakeholder

    Anyone that has an effect on, or is affected by the project

    Individual who is involved in the project (PM, PM Team Member, Project Team Member)

    Person being impactedpositively or negativelyas a result of the project, incl. Customer

    Person exerting influence over the project, its Constraints , and results

    Senior Management

    Higher in the organization than the Project Manager

    Prioritizes projects in line with company strategy and goals

    Authorizes Project Manager, ensures access to Project Resources

    Can help resolve organizational conflicts and issues

    Functional Manager

    Department Manager who owns Project Resources

    Human resource management responsibilities for employees

    Program Manager

    Responsible for programs

    Coordinates multiple related projects to achieve a common goal

    Manages at a higher level than the Project Manager

    2011 Q'vive, LLC Eric van der Meulen, PMP All rights reserved qvive.biz [email protected] "PMBOK" and "PMP" are registered marks of Project Management Institute, Inc.PRD12111

    The Communications Management Knowledge Area is focused on the people outside the project, i.e., Sponsor, Stakeholders, Customer, Senior Management, Functional Managers, Program Manager.

    In the Human Resource Management Knowledge Area, the Project Manager or Project Coordinator is focused on the Project Resources, the people inside the project, i.e., Project Management Team (PM Team), and Project Team.

    S

    S