Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of...

16
Omaha Combined Sewer Overflow Control Program Implementation Phase Quarterly Report | 2016 Q2 April–June 2016

Transcript of Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of...

Page 1: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

Omaha Combined Sewer Overflow Control ProgramImplementation Phase

Quarterly Report | 2016 Q2April–June 2016

Page 2: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

CONTENTS

HIGHLIGHTS . . . . . . . . ii

PROGRAM

OVERVIEW . . . . . . . . . . 1

GOAL

REVIEW . . . . . . . . . . . . . 2

PROJECT

SPOTLIGHT. . . . . . . . . . 6

BUDGET

DETAILS. . . . . . . . . . . . . 9

PROJECTS UNDER

CONSTRUCTION. . . . 10

KEY ACTIVITIES. . . . . 12

APPENDIX. . . . . . . . . . A1

For additional information regarding the Omaha CSO Program, please visit www.OmahaCSO.com or call the CSO Program Hotline at (402) 341-0235.

A City of Omaha Public Works Initiative

2nd Quarter Highlights

ON THE COVER: (Clockwise) Vinton Street Green Infrastructure, Adams Park Wetlands Improvement Project, Nicholas Street Phase 2 to 23rd and Grace, Spring Lake Park Landscaping and Leavenworth Lift Station.

• Saddle Creek Retention Treatment Basin (RTB) Early Soils Removal Project

neared completion. The purpose of this project is to prepare the site for

the Combined Sewer Overflow (CSO) control facility to be constructed in

the future for CSO 205 for the Saddle Creek Basin.

• Coordination efforts commenced for start-up activities for Leavenworth

Lift Station, Missouri River Wastewater Treatment Plant (MRWWTP)

Projects and South Interceptor Force Main (SIFM) North and South/Central

Segment Projects.

• Extensive efforts were completed to communicate with the contracting

community on the MRWWTP B2 Project, which resulted in a favorable

construction bid.

• Spring-fed water and rainfall runoff began to fill the lagoon at Spring Lake

Park, as originally designed.

• Construction issues were addressed and contractor continued work on

the MRWWTP Bank Stabilization.

• Gilmore Avenue Landscape Improvement Project construction was put

out for bid and the design work continued on the Fontenelle Lagoon

Improvement Project so that bidding could take place this summer.

Missouri River Wastewater Treatment Plant grit removal system (left), Spring Lake Park pond (top-right), and South Interceptor Force Main North drop shaft (bottom-right).

ii Omaha Combined Sewer Overflow Control Program | Implementation Phase

Page 3: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

CSO

Solutions

Goal 1:

Regulatory

Compliance.Meet specific regulatory requirements as identified by the EPA and NDEQ.

• Complete

implementation of

CSO solutions within

schedule identified.

• Reduce pollutant

discharge to the Missouri River

and Papillion Creek.

Goal 2:

Economic Affordability.Minimize cost impact to ratepayers by completing CSO control options within or under budget.

Goal 3:

Community Acceptance. Maintain continuous public dialogue, provide information and pursue opportunities for multiple benefits in CSO solutions.

The Program schedule, which began in 2006, is shown below. The final implementation is targeted for 2027. The Program is divided into two groups: major projects and sewer separation projects. Project implementation was selected based on its positive effect on water quality, supporting development, its priority in the construction sequence, and cost. The schedules were further coordinated to allow for concurrent construction. A list of projects by LTCP phase is located in the Appendix.

PROGRAMOVERVIEWIn order to comply with the

requirements of the Clean Water

Act, the United States Environmental

Protection Agency (EPA) Combined

Sewer Overflow (CSO) Control Policy

of 1994 and Administrative Consent

Order with the Nebraska Department

of Environmental Quality (NDEQ),

the City of Omaha developed a

Long Term Control Plan (LTCP)

that outlines the actions to control

overflows from its combined sewer

system. The purpose of the Omaha

CSO Control Program (Program)

Implementation Phase is to ensure

that CSO projects outlined in the City

of Omaha’s LTCP are cost effectively

designed, constructed, and placed

into operation by 2027.

CURRENT CSO PERMIT IS VALID THROUGH

OCTOBER 2020The CSO permit was approved by NDEQ in September 2015 with refined requirements that lower the City’s costs and in support of Omaha’s Program. The next required CSO permit renewal is October 2020.

2020Program Schedule

www.OmahaCSO.com Clean Solutions for Omaha Quarterly Report | 2nd Quarter 2016 1

Page 4: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

Project Phase

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

Phase 1

Phase 2

Phase 3

Phase 4

Phase 5

Phase 6

Phase 7

Phase Project Name

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

1Missouri River Wastewater Treatment Plant

Improvements/Collection System Improvements

Saddle Creek Retention Treatment Basin/

Collection System Improvements

Minne Lusa Stormwater Conveyance

System and Detention Basin

Paxton Blvd Stormwater Conveyance

Sewer, 41st to 49th (ML-105-13A Phase 2)

Deep Tunnel/Missouri River Retention

Treatment Basin

2

3A

3B

4

Notice to Proceed to Consultant for Final Design

Notice to Proceed to Constructor

Notice to Proceed to Consultant for Final Design

All ConstructionProjects Complete

OperationallyComplete

MAJOR PROJECTS

SEWER SEPARATION PROJECTS

Current Status

Goal 1: Regulatory ComplianceRegulatory Compliance includes two items: 1) implement projects within the identified

schedule, and 2) reduce pollutant discharge to the Missouri River and Papillion Creek.

SCHEDULEThe following charts show the implementation milestones and project status, with a list of

projects by phases located in the Appendix. All regulatory milestones have been met to date.

PROJECT STATUS:

Bid/Construction/Complete Projects

22Study & Design

Projects

15Future

Projects

37

Engineer Selected

Engineer was selected for Nicholas Street

Phase 3 Design and the agreement is

underway (Lamp, Rynearson and Associates).

Out to Bid

Construction plans were put out

to bid this quarter for Gilmore

Avenue Landscaping Contract.

Projects on Hold

Both the Saddle Creek

Retention Treatment Basin

(RTB) and the Minne Lusa

Stormwater Conveyance

System Projects were put

on hold this quarter due

to significantly increased

costs. These are under

evaluation to find more

cost-effective approaches

and additional information on potential

alternatives will be provided at a later date.

2 Omaha Combined Sewer Overflow Control Program | Implementation Phase

Page 5: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

Delivered thro

ug

h

2002 City Existing Conditions; previously captured by the City

prior to the CSO Program

volume capture by completed CSO Program projects to date

15% residual, left uncaptured

85% overall, reductionmandatedCSO Program Wet Weather

Capture Requirement

Original Long

Term Control Plan

(LTCP) projects

92

Construction

packages

Multiple packages

provide more opportunities for

local contractors and provide for

efficient delivery.

119

STATISTICS

Construction value

of projects in

bid or current

construction

$269M

Projects completed

(dollars paid out)

$104MConstruction value

of projects in design

$328M

COMPANIES ENGAGED:

** Unique businesses may have multiple contracts.

As of May 2016,

$280M has been

paid out for

construction activities

City Small BusinessesReceived Contracts, of which

As of 2015,

Small Business Contracts Awarded to Omaha Area Companies

Over 80%

28

General ContractorsReceived Contracts

16Design Firms

(Including Subcontracted Companies)

77**

PROGRESS TOWARDCSO WET WEATHERVOLUME CAPTURENearly 33% of CSO Program wet weather capture goal amount has been achieved using only 23% of the CSO Program budget.

www.OmahaCSO.com Clean Solutions for Omaha Quarterly Report | 2nd Quarter 2016 3

PROGRAM OVERVIEW: GOAL 1

Page 6: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

$353.5M 2013 Rate Model Budget

$307M Contracts

2013 Rate

CONSTRUCTION COSTS

Model Budget

Bid

Awards

LEGISLATIVE ACTION IN SUPPORT OF THE PROGRAMThe City of Omaha is working with the Nebraska Department

of Natural Resources (NDNR) Grant Award Contract to finance

the construction of CSO projects and the water quality

improvements. Under this action NDNR will provide $2.9 million

in 2016 and approximately $1 million per year from 2017 through

2027. This agreement with NDNR for grant funds appeared

on the City Council agenda in June and July 2016 for the

Council’s approval.

Value Engineering (VE) efforts continue on the Saddle Creek RTB project to assess potential cost savings to the Combined Sewer Overflow (CSO) Program as well as providing benefit to the surrounding community. The outcome and recommendations from this VE effort is expected early fall 2016.

VALUE ENGINEERING TO

IMPLEMENT COST-EFFECTIVE

SOLUTIONS

Economic Affordability is the minimization of the cost impact to the ratepayers.

Construction costs have been contained as shown in the following metrics.

Goal 2: Economic Affordability

CURRENT & COMPLETED PROJECTCONSTRUCTION COSTS

RATEPAYER ASSISTANCEWhen the long term control plan (LTCP) was approved it marked the start of a ratepayer assistance plan to help low income and fixed income households with the rate increases necessary to fund the Program.

From April 2016 through June 2016, over $94,443 has been provided in assistance; to date $4.5 million has

been provided. Ratepayers are eligible if they receive Low Income Heat and Energy Assistance (LIHEAP) from their utility. This has kept administrative costs to a minimum and provided the maximum benefit to those who need it.

For assistance or to apply for Nebraska LIHEAP, call 800-383-4278.

PROGRAM OVERVIEW: GOAL 2

4 Omaha Combined Sewer Overflow Control Program | Implementation Phase

Page 7: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

Community Acceptance provides continuous open dialogue with the public along

with timely and accurate project information. The Program is also providing additional

neighborhood benefits, beyond the improved sewer system and water quality enhancements.

PUBLIC INFORMATION

The Combined Sewer Overflow (CSO) Program hosts a

public website and provides updates via Twitter including

up-to-date information to the ratepayers. A Contractor’s

Corner, which identifies upcoming bidding opportunities,

is also on the website.

ADDITIONAL PUBLIC BENEFITSIn addition to the over 56,000 feet of sewer pipe removed,

constructed and/or rehabilitated, the Program construction

projects have provided a total Community Enhancement

value of over $36 million, as identified below.

OUTREACH & STAKEHOLDER ENGAGEMENTInformation is regularly made available to the public

about upcoming construction projects and the Program.

347equivalent

blocks of

replaced

street

728impacteddriveway

approachesreplaced

4,125linear feet of

new trails

419equivalent

blocks

of replaced

sidewalk

1,085new trees

960curb ramps

59acres of enhanced park/

open space 136,000linear feet of upgraded

gas & water

utility infrastructure

Goal 3: Community Acceptance

Presentations for Civic or

other Professional Groups

3

Project Hotline

Calls

37Public Meetings

3Website and Twitter Statistics

Users 23,337

Web pages viewed 7,209

Visits (all users) 2,949

Twitter followers 51

www.OmahaCSO.com Clean Solutions for Omaha Quarterly Report | 2nd Quarter 2016 5

PROGRAM OVERVIEW: GOAL 3

Page 8: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

6 Omaha Combined Sewer Overflow Control Program | Implementation Phase

Page 9: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

Adams Park outfall structure and wetlands near 36th and Bedford.

Adams Park Wetlands Improvement ProjectThis project consists of wetlands

designed to reduce Combined Sewer

Overflow (CSO) volumes, sewer

backups, improve water quality, and

provide a neighborhood amenity.

The existing combined sewer will be

converted into a sanitary sewer that

will provide sewer separation for the

sub-basin. The new storm sewers

will drain into a new wetland area in

Adams Park.

The Adams Park wetlands and

detention area is designed to provide

the maximum practical stormwater

storage to reduce the size of

future downstream facilities. The

wetlands consist of an area covering

approximately 14 acres, separated

by the park road. A low dam with

an emergency spillway is complete

on the north side of the park,

near Bedford Avenue, to provide

detention volume of up to 77 acre-

feet, which will detain the 100-year

storm event. The wetland facility is

designed to provide water quality

benefits and beautification elements.

www.OmahaCSO.com Clean Solutions for Omaha Quarterly Report | 2nd Quarter 2016 7

PROJECT SPOTLIGHT

Page 10: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

A separate construction contract

for the installation of trees and

landscape features included a

two year maintenance agreement

to ensure the plantings are well-

established before the project is

considered complete.

Additional information on this project can be found in the Appendix.

Adams Park wetlands looking east from the northwest corner of the park.

Bridge crossing looking to the east.

South channel looking north from the southwest corner of the park.

PROJECT SPOTLIGHT

8 Omaha Combined Sewer Overflow Control Program | Implementation Phase

Page 11: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

PROGRAM BUDGET STATUS

PROGRAM CAPITAL ALLOCATION

$0

$200 M

$300 M

$100 M

$400 M

$500 M

$600 M

$700 M

$800 M

$900 M

$1 B

$1.1 B

Program Mgmt.

$41 M

$163.6 M

$82.7 M

$174.2 M

$4.9 M

SewerSeparation

Conveyance

Facilities

Misc.Projects

Actual Cost Total Capital Cost (2015 Dollars)

2009

$466.5 Mactual cost

2027

Spent to Date:

EstimatedComplete:

In 2015 dollars

$2.171 B

The Combined Sewer Overflow (CSO) Program is

maintaining schedule and budget to meet current

regulatory and financial expectations.

While there is still much work to be done, a significant amount of progress has been made towards Program implementation and the Program continues to meet all regulatory milestones.

CSO Program Elements:Program Management: Management and administration of Program related activities

Sewer Separation: Sewer projects that will reduce flows to the combined sewer system

Conveyance1: South Interceptor Force Main (SIFM)

Facilities1: Deep tunnel, Missouri River Wastewater Treatment Plant (MRWWTP), high rate treatment, lift station, and storage structure projects

Miscellaneous: Miscellaneous study related projects

1 The combination of conveyance and facilities constitutes most of the major projects.

BUDGET DETAILS

Regulatory Progress

www.OmahaCSO.com Clean Solutions for Omaha Quarterly Report | 2nd Quarter 2016 9

Page 12: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

Missouri River

Missouri River

COLE CREEK

BRIDGESTREET

MINNELUSA

BURT-IZARD

PAPILLIONCREEKNORTH

SADDLECREEK

PAPILLION CREEKSOUTH

OHERN/MONROE

SOUTH INTERCEPTOR

LEAVENWORTH

30

th S

t

Dodge St

Center St

10

th S

t

24

th S

t2

4th

St

42

nd

St

42

nd

St

72

nd

St

72

nd

St

L Street

Q Street

Maple St

Sa

dd

le C

ree

k

Ab

bo

tt D

r

Eppley Airfield

Carter Lake

City Council District 1

City Council District 2

City Council District 3

City Council District 4

City Council District 5

City Council District 6

City Council District 7

CSO Study Basins

North Segment

Completed Projects

Current Projects

LEGEND

Y

UW

Q

AABB

J

Z

T

Figure 1 and corresponding table to the right identify project details and completed projects.

FIGURE 1

10 Omaha Combined Sewer Overflow Control Program | Implementation Phase

PROJECTS UNDER CONSTRUCTION

Page 13: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

CURRENT CONSTRUCTION KEY PROJECT NAME CONSTRUCTION MANAGER’S

CURRENT ESTIMATE AT COMPLETION

JImprovements to

the Missouri River

Wastewater Treatment

Plant–Schedule B198% Project Complete

$61,900,00

Q South Interceptor Force

Main-North Segment 75% Project Complete

$21,550,000

T

Missouri Avenue/

Spring Lake Park

Sewer Separation 97% Project Complete

$10,200,000

Spring Lake Park,

Landscaping 18% Project Complete

$596,650

U

John Creighton

Boulevard & Miami Street

Phases 1 & 2 Sewer

Separation & Adams Park75% Project Complete

$20,098,981

Adams Park

Landscaping

Improvements

Project99% Project Complete

$652,050

WNicholas Street Phase 2

to 23rd and Grace 90% Project Complete

$19,765,428

YCole Creek CSO 204

Sewer Separation

Phase 1 90% Project Complete

$3,990,526

ZGilmore Avenue Sewer

Separation Phase 1

and 2 37% Project Complete

$10,390,000

AASaddle Creek Retention

Treatment Basin Early

Soil Removal 100% Project Complete

$2,231,691

BB Vinton Street

Green Infrastructure 93% Project Complete

$1,065,868

* Shaded bars indicate the progress toward completion of each project.

Change Order

Approximately

14% over

construction bid

due to additional

soil removal which

lowers cost of the

future project on

the site.

Change Order

Approximately

17% over

construction bid

due to unexpected

debris found on

the site.

www.OmahaCSO.com Clean Solutions for Omaha Quarterly Report | 2nd Quarter 2016 11

Page 14: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

KEY ACTIVITIESBelow is a list of key activities for the current quarter and upcoming

quarter. A full list is included in the Appendix.

CURRENT 2016 2ND QUARTER KEY ACTIVITIESRegulatory

• Held quarterly meeting with Nebraska Department

of Environmental Quality (NDEQ) and Environmental

Protection Agency (EPA) to discuss Program progress

on May 12.

• Continued discussions with NDEQ regarding

concerns related to higher project costs for Minne

Lusa Stormwater Conveyance Sewer and Saddle

Creek Retention Treatment Basis (RTB).

• Collaborated with the other local entities on ratepayer

increase issues.

Program

• Held internal workshops to identify Program

cost savings.

Projects

• Opened Bids for Missouri River Wastewater Treatment

Plant (MRWWTP) Schedule B2.

• Held public meetings for:

• Fontenelle Park Lagoon Improvement

• Hanscom Park

• Missouri Avenue Phase 2

• Interviewed and selected MRWWTP Schedule B2

special inspections firm.

• Advertised Gilmore Avenue Landscaping

Construction Project.

• City contracted a consultant to perform a Financial

Capability Assessment and Rate Model Update.

• Prepared Professional Services Contracts for:

• MRWWTP B2 Special Inspections

UPCOMING 2016 3RD QUARTER KEY ACTIVITIESRegulatory

• Hold quarterly meetings with NDEQ

and EPA to discuss Program progress.

• Continue discussion with NDEQ on Saddle Creek RTB

path forward.

Program

• Look for ways to save money for the ratepayers while

still meeting the objectives and requirements of the

Clean Water Act.

Projects

• Public meetings for:

• Burt-Izard

• Missouri Avenue Sewer Separation

• Prepare professional services contracts for:

• Burt-Izard Lift Station Improvements

• MRWWTP B2 – Special Inspection

• Issue construction Notice to Proceed (NTP) for

MRWWTP Schedule B2.

• Complete construction for Saddle Creek RTB Early

Soils Project.

• Complete construction of the Nicholas Street

Phase 2 Project.

• Open bids for Gilmore Avenue Landscaping.

• Advertise for bids for:

• 42nd & Q/Hitchcock Park landscaping

• Lake James to Fontenelle Park,

Pond Improvements

• Kickoff Rate Model Update review.

12 Omaha Combined Sewer Overflow Control Program | Implementation Phase

Page 15: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

This page intentionally left blank.

Page 16: Quarterly Report | 2016 Q2 Omaha Combined Sewer Overflow Control Program · 2016. 9. 21. · As of 2015, Small Business Contracts Awarded to Omaha Area Companies Over 80% 28 General

Printed August 2016