QS/QC questions

download QS/QC questions

of 16

Transcript of QS/QC questions

  • 7/28/2019 QS/QC questions

    1/16

    &CONSTRUCTION

    QUALITY ASSURANCE (QA)

    and QUALITY CONTROL (QC):Instituting strict compliance to undertake

    Trial Section in all road constructionand rehabilitation schemes

    under MRDP2

    Q

    A

    Questionsand

    Answerson

    Department of Agriculture

    MINDANAO RURAL DEVELOPMENT PROGRAM 2

  • 7/28/2019 QS/QC questions

    2/16

    Information Bulletin No. 12/October 2012

    About MRDP

    The Mindanao Rural Development Program -

    Adaptable Program Loan Phase 2 (MRDP2) continues to implement poverty-

    reducing interventions in more poor communities across Mindanao as it

    expands in scope of coverage (225 towns in 26 provinces).

    Implemented under the Department of Agriculture, MRDP1 accomplished

    various projects and provided signicant learning experiences on which

    MRDP2 takes off.

    MRDP2 seeks to further improve rural incomes and achieve security

    through agri-sheries infrstructure, livelihood enterprise, and biodiversity

    conservation projects.

    Partnership with LGUs and other national agencies are also forged for

    laudible impact in Mindanao rural communities.

    Alongside poverty-reducing initiatives, the Program likewise reinforces the

    implementation of the Local Government Code and the Agricultural andFisheries Mondernization Act.

    Working interdependently to bring development in the country-side are four

    MRDP components: Rural Infrastructure, Community Fund Agricultural

    Development, Natural Resources Management and Investment for

    Governance Reforms and Program Administration.

  • 7/28/2019 QS/QC questions

    3/16

    1

    ?1. What is Quality AssuranceQuality Assurance (QA) is a funcon of the owner and/or implemenng

    unit to verify that the work is done in accordance with the specicaons.

    It includes all those planned and systemac acons necessary to providecondence that the product or service will sasfy given requirements for

    quality.

    QA usually requires connuing evaluaon of factors that aect the

    design or specicaon for intended applicaon as well as vericaon of

    installaon and inspecon operaons.

    2. What is Quality Control

    Quality Control (QC) is checking for conformance materials

    specicaons and methods of construcon or workmanship.

    Control on the correct plan interpretaon, proper engineering

    construcon methodology, and strict compliance of the standard

    specicaons.

    Includes all procedures, which are necessary to insure that thematerials used, and workmanship employed conform to the standard

    of quality specied.

    Instuted during the course of construcon as a prevenve tool,

    not as a correcve measure. Prevenve measures are always more

    economical.

    A technique that ensures to fulll the requirements for quality in any

    operaonal procedures.

    A process that is done to eliminate causes of unsasfactory

    performance of the works.

    To summarize:

    Quality - Degree of excellence

    Control - To check and regulate

    Assurance - Degree of certainty

    ?

  • 7/28/2019 QS/QC questions

    4/16

    2

    3. How can QAand QCbe carried out

    To ensure QA and QC in the project, provisions spulated in the Contract

    must be carried out. The project must conform to the requirements

    specied in the following documents, which form part of the Contract:

    1. Condions of Contract;

    2. Special Condions of Contract;

    3. Specicaons;

    4. Performance Security;

    5. Plans and Drawings;

    6. Construcon Monitoring and Reporng Templates;

    7. Comprehensive All-Risk Insurance;

    8. Construcon Safety, Health and Environmental Management

    Program;

    9. Materials Quality Control Program; and

    10. Constructors Performance Evaluaon System (CPES).

    4. What are the common issuesencountered byLGU contractors

    Aer contract award and upon resource mobilizaon, the pledged

    key technical personnel (SCC Clause 6.5) are nowhere to be found.

    In most cases these are replaced with unauthorized, somemes

    unqualied personnel. Equipment mobilized are not the equipment pledged and most of the

    mes Contractor fails to meet minimum requirement.

    Does not undertake as-stake survey resulng in quanty and

    eventually funding issues due to unforeseen variaons.

    Materials tested for quality are not representave samples extracted

    from actual quarry sites.

    ?

    ?

  • 7/28/2019 QS/QC questions

    5/16

    3

    5. What are some commonissues encountered byLGU

    Construction Supervision team

    Lacks necessary qualicaon and experience in construcon

    supervision

    Poor supervisory and documentaon skills therefore cannot enforce

    authority to undertake QA\QC procedures

    Mul-tasked with o-project responsibilies due to LGUs lack of

    technical personnel therefore daily presence at the site is not assured

    Lack of surveying skills

    Poor communicaon skills

    Lack of materials tesng and inspecon skills

    6. What are the consequencesifQAand QC is overlooked

    QA/QC issues are likely to happen if there is no concisedocumentaon of project acvies

    Compromise human and environmental safety

    Causes unnecessary reworks

    Creates conict on contract me management- owner and contractor

    having dierent accounts on delays

    Project design life is likely to shorten due to poor quality

    Breeding ground for fraud

    Creates reputaonal risks

    And a host of other issues

    ?

    ?

  • 7/28/2019 QS/QC questions

    6/16

    4

    7. What are the auxillary (tool) kits forStandard Construction Supervision

    and Contract Management

    Contract Domain Toolkit Control measures

    1. Quality Materials QCP, Technical

    Specicaons, Plans (lines

    and grades), Shop Drawings,

    Site Instrucons, Request for

    Informaon, Work Requests,

    Materials Test Report, CPES,

    DLP, Performance Security

    1. Concise and

    up-to-date

    documentaon of

    daily acvies.

    2. Contract

    Management and

    QA/QC skills

    3. Variaons - Workfor aected work

    items can only

    commence aer

    approval of VO

    2. Quanty Approved as-stake survey,

    Approved as-staked quanty,

    Inspecon Report, Back-up

    Calculaons, SWA, Weekly

    Accomplishment Report,

    Straight Line Diagram, PERT-

    CPM

    3. Cost Approved Unit Cost Analysis,

    SWA, Cash Flow Schedule,

    Payment Cercates, CARI

    4. Time Weather Chart, Suspension

    and Extension of Time,

    Producvity Losses, Statement

    of Time Elapsed, S-curve and

    Bar Chart, Request for Time

    Extension

    8.What are the constructionpreparatory procedures

    For materials quality tests:

    Joint Owner-Contractor reconnaissance survey on materials source

    sites

    Extracon, marking of samples, preparaon of sample cards and

    delivery to accredited tesng center under an approved Work Request

    Preparaon and submission by Contractor its Quality Control Plan

    (QCP) for approval by Owners representave.

    ?

    ?

  • 7/28/2019 QS/QC questions

    7/16

    5

    Sampling, marking and tesng of

    roadway materials

    Blending aer obtaining sasfactory

    test results from laboratory

    For as-stake survey:

    Joint Owner-Contractor As-staked (pre-construcon) survey (Specs,

    Item 104.3.20). Idenfy and adjust/incorporate into the As-Staked

    Survey the secons, sites and other details from original approved

    plans not consistent with actual site condions as jointly surveyed.

    Submission of As-staked plans and quanes for approval by Owner. Introduce Variaon Order No. 1 if possible changes in me, quanty

    and cost are found necessary based on the results of the as-staked

    survey.

    As-stake survey is one of the rst stages ofaaining QA and QC.

  • 7/28/2019 QS/QC questions

    8/16

    6

    9.What are the requirements that needs to besubmitted by the contractor to the LGU once the

    Notice to Commence Work (NTC) takes effect

    Materials QCP

    As-Staked Plans

    Revised Construcon Schedule (in PERT-CPM, S-Curve with Bar Chart,

    Manpower, Equipment)

    Contractors Health, Safety and Environment (HSE) Program

    Credenals of Key Personnel (CVs)

    Project Signboard MRDP Standard Reporng Templates

    Photo Documentaon Procedures

    Relevant Implementaon Guidelines (on Variaons, Time Suspension/

    Extension, etc.)

    Contractors Organizaonal Structure

    Discussing these concerns in pre-construcon conferences does notassure Contractors compliance.

    TRIAL SECTIONS

    10.What are the DPWH Standard Specifcations

    for Roads and Highways (2004, Blue Book)

    >>Clause200.3.4and201.3.4TrialSecons

    Purpose - to check the suitability of the materials and the

    eciency of the equipment and construcon method which is

    proposed to be used by the Contractor.

    Contractor must use the same material, equipment and

    procedures that he proposes to use for the main work.

    One trial secon of about 500 square meters shall be made

    for every type of material and/or construcon equipment/

    procedure proposed for use.

    Aer nal compacon of each trial secon, the Contractor shall

    carry out such eld density tests and other tests required as

    directed by the Engineer.

    ?

    ?

  • 7/28/2019 QS/QC questions

    9/16

    7

    A new trial secon shall be constructed if:

    a. the proposed materials, equipment or procedures in the

    Engineers opinion are not suitable for sub-base,

    b. the basic condions regarding the type of material or

    procedure change during the execuon of the work

    >> Tolerances

    Quality indicator Item 200 Item 201

    Permied variaon from design

    Thickness of Layer

    20 mm 10 mm

    Permied variaon from design Level

    of Surface

    +10 mm

    -20 mm

    + 5 mm

    -10 mmPermied Surface Irregularity

    Measured by 3-m straight-edge

    20 mm 5 mm

    Permied variaon from design

    Crossfall or Camber

    0.3% 0.2%

    Permied variaon from design

    Longitudinal Grade over 25 m in length

    0.1% 0.1%

    11.What are the procedures in preparing trial sections

    Step 1. In coordinaon with the Contractors Project Engineer (PE),

    LGU Resident Engineer (RE) idenes road secon where Trial Secon

    will be undertaken in accordance with minimum requirements of the

    Specicaons (Block 8).

    RE issues Site Instrucon to Contractor to undertake Trial Secon

    starng with subrade preparaon.

    PE submits Work Request indicang type of acvity, staon limits and

    esmated item quanes for approval by RE. Materials Quality Tests

    and As-staked Plans should be approved prior to approval of Work

    Request.

    Note: Preparaon of the trial secon should not be a prior

    requirement for inial/preparatory acvies such as Clearing and

    Grubbing and Earthworks. These acvies can proceed independently

    in accordance with approved construcon schedule.

    ?

  • 7/28/2019 QS/QC questions

    10/16

    8

    Step 2. Inspecon and Cercaon

    Lines and Grades: Refer to: a) Approved As-staked Plan, and b)

    Allowable Tolerances (Block 8)

    Quality of Compacon: Field Density Test (FDT) - refer to approved

    Quality Control Plan (QCP) requirements

    - Determine number of passes for type of roller used

    Repeat process if results are unsasfactory via issuance of Site

    Instrucon. Proceed to the next layer (Item 200) otherwise.

    RE signs o on Inspecon Report to manifest Contractors compliance

    to requirements.

    Step 3. Item 200

    PE submits Work Request for approval by RE

    Lines and Grades Must comply with the allowable tolerances for

    Item 200 (Block 8)

    Quality - Compacon via Field Density Test (FDT) - refer to QCP and

    Specs requirements

    -Determine number of passes for type of roller used

    Repeat process if results are unsasfactory via issuance of SiteInstrucon. Proceed to the next layer (Item 201) otherwise.

    RE signs o on Inspecon Report to manifest Contractors compliance

    to requirements.

    Step 4. Item 201

    Repeat the same procedures in Item 3.

    Note: Make sure that all materials incorporated into the various

    roadway layers are in accordance with approved grading, blending

    and moisture content requirements, immediately preceding its

    incorporaon. Materials passing individual quality tests done at

    laboratory may not necessarily qualify for incorporaon due to

    inappropriate processing and handling.

    Approved QCP Approved As-Staked

    Survey

    Site Instrucon

    Trial Secon

    Work RequestExecuonInspecon and

    Cercaon

  • 7/28/2019 QS/QC questions

    11/16

    9

    Item 105 - Sub-grade preparaon. Check

    compliance to lines and grades aer applicaonthen for compliance to compacon requirements

    via FDT.

    2

    Spreading. Compacon. Check for compliance to lines and

    grades prior to FDT.

    1

    3 4

    5 6

  • 7/28/2019 QS/QC questions

    12/16

    10

    Repeat the sameprocedure for Item 201

    (and 300 if required)

    SamplephotosofTrialSeconacvies

    Making available

    standard set of eld

    Materials Tesng

    Apparatus saves the

    Contractor substanal

    amount of me and

    money. This requirementcould form part of the

    SCC.

    7

  • 7/28/2019 QS/QC questions

    13/16

    11

    QUICK NOTES:

    1. (Strictly) enforcing Trial Secon is not an assurance of full

    compliance to the Projects QA/QC objecves.

    2. It is only an inial step in achieving quality assurance related to

    workmanship and procedures specially for LGUs who play the major

    role as Construcon Supervisors and Contract Managers.

    3. This exercise is meant to raise the awareness of sub-project

    implementaon stakeholders of the standard procedures of

    check and balance right at project start up by achieving: a.Proper

    construcon methodology b.Concise and up-to-date documentaon

    and monitoring of sub-project acvies using basic tools such as

    Work Requests, Site Instrucons, Requests for Informaon and Daily

    Acvity Log/Weather Report.

    4. QA/QC conicts can only be resolved if the proper ow of

    documentaon is observed to a high degree of specicity by both

    Contractor and Owner.

    5. PSO/RPCO RIEs presence are required in this exercise.

  • 7/28/2019 QS/QC questions

    14/16

    Produced by:

    Informaon, Advocacy, Communicaon and

    Educaon (InfoACE) UnitIn coordinaon with the

    Rural Infrastructure Component

    Mindanao Rural Development Program 2

    PROGRAM SUPPORT OFFICE

  • 7/28/2019 QS/QC questions

    15/16

    Department of Agriculture

    MINDANAO RURAL DEVELOPMENT PROGRAM

    PROGRAM SUPPORT OFFICE

    Alvarez Bldg., A. Angliongto Sr. Ave.,

    Lanang, Davao City 8000

    Telephone No.: (082) 235-8665

    Telefax: (082) 235-8664

    Email: [email protected]

    Website: www.damrdp.net

    REGIONAL PROGRAM COORDINATION OFFICES

    Region 9

    Department of Agriculture

    Western Mindanao Integrated

    Agricultural Research Center

    (WESMIARC)

    Ipil, Zamboanga Sibugay 7001

    Tel.: (062) 333-2508Email: [email protected]

    Region 10

    Department of Agriculture

    Regional Field Unit 10

    A. Luna St.,

    Cagayan de Oro City 9000

    Te.: (08822) 728-236

    Fax: (08822) 726564 | 725725

    Region 11

    Department of Agriculture

    Regional Field Unit 11

    F. Bangoy St., Davao City 8000

    Te.: (082) 221-9697

    Fax: (082) 226-3625

    Email: [email protected]

    Region 12

    Department of Agriculture

    Regional Field Unit 12

    3rd Flr. CSA Bldg., cor. Zulueta Gensan

    Drive., Koronadal City 9506

    Te.: (083) 520-0622/0624/0625

    Fax: (083) 520-0628

    Region 13

    Department of Agriculture

    Regional Field Unit 13

    Capitol Site, Butual City 8600

    Te.: (085) 341-2045

    Fax: (085) 341-2114

    Email: [email protected]

    ARMM

    Department of Agriculture and

    Fisheries (DAF) ARMM

    ORG Compound, Cotabato City 9600

    Te.: (064) 421-1396

    Fax: (064) 421-1396