QS/QC questions
Transcript of QS/QC questions
-
7/28/2019 QS/QC questions
1/16
&CONSTRUCTION
QUALITY ASSURANCE (QA)
and QUALITY CONTROL (QC):Instituting strict compliance to undertake
Trial Section in all road constructionand rehabilitation schemes
under MRDP2
Q
A
Questionsand
Answerson
Department of Agriculture
MINDANAO RURAL DEVELOPMENT PROGRAM 2
-
7/28/2019 QS/QC questions
2/16
Information Bulletin No. 12/October 2012
About MRDP
The Mindanao Rural Development Program -
Adaptable Program Loan Phase 2 (MRDP2) continues to implement poverty-
reducing interventions in more poor communities across Mindanao as it
expands in scope of coverage (225 towns in 26 provinces).
Implemented under the Department of Agriculture, MRDP1 accomplished
various projects and provided signicant learning experiences on which
MRDP2 takes off.
MRDP2 seeks to further improve rural incomes and achieve security
through agri-sheries infrstructure, livelihood enterprise, and biodiversity
conservation projects.
Partnership with LGUs and other national agencies are also forged for
laudible impact in Mindanao rural communities.
Alongside poverty-reducing initiatives, the Program likewise reinforces the
implementation of the Local Government Code and the Agricultural andFisheries Mondernization Act.
Working interdependently to bring development in the country-side are four
MRDP components: Rural Infrastructure, Community Fund Agricultural
Development, Natural Resources Management and Investment for
Governance Reforms and Program Administration.
-
7/28/2019 QS/QC questions
3/16
1
?1. What is Quality AssuranceQuality Assurance (QA) is a funcon of the owner and/or implemenng
unit to verify that the work is done in accordance with the specicaons.
It includes all those planned and systemac acons necessary to providecondence that the product or service will sasfy given requirements for
quality.
QA usually requires connuing evaluaon of factors that aect the
design or specicaon for intended applicaon as well as vericaon of
installaon and inspecon operaons.
2. What is Quality Control
Quality Control (QC) is checking for conformance materials
specicaons and methods of construcon or workmanship.
Control on the correct plan interpretaon, proper engineering
construcon methodology, and strict compliance of the standard
specicaons.
Includes all procedures, which are necessary to insure that thematerials used, and workmanship employed conform to the standard
of quality specied.
Instuted during the course of construcon as a prevenve tool,
not as a correcve measure. Prevenve measures are always more
economical.
A technique that ensures to fulll the requirements for quality in any
operaonal procedures.
A process that is done to eliminate causes of unsasfactory
performance of the works.
To summarize:
Quality - Degree of excellence
Control - To check and regulate
Assurance - Degree of certainty
?
-
7/28/2019 QS/QC questions
4/16
2
3. How can QAand QCbe carried out
To ensure QA and QC in the project, provisions spulated in the Contract
must be carried out. The project must conform to the requirements
specied in the following documents, which form part of the Contract:
1. Condions of Contract;
2. Special Condions of Contract;
3. Specicaons;
4. Performance Security;
5. Plans and Drawings;
6. Construcon Monitoring and Reporng Templates;
7. Comprehensive All-Risk Insurance;
8. Construcon Safety, Health and Environmental Management
Program;
9. Materials Quality Control Program; and
10. Constructors Performance Evaluaon System (CPES).
4. What are the common issuesencountered byLGU contractors
Aer contract award and upon resource mobilizaon, the pledged
key technical personnel (SCC Clause 6.5) are nowhere to be found.
In most cases these are replaced with unauthorized, somemes
unqualied personnel. Equipment mobilized are not the equipment pledged and most of the
mes Contractor fails to meet minimum requirement.
Does not undertake as-stake survey resulng in quanty and
eventually funding issues due to unforeseen variaons.
Materials tested for quality are not representave samples extracted
from actual quarry sites.
?
?
-
7/28/2019 QS/QC questions
5/16
3
5. What are some commonissues encountered byLGU
Construction Supervision team
Lacks necessary qualicaon and experience in construcon
supervision
Poor supervisory and documentaon skills therefore cannot enforce
authority to undertake QA\QC procedures
Mul-tasked with o-project responsibilies due to LGUs lack of
technical personnel therefore daily presence at the site is not assured
Lack of surveying skills
Poor communicaon skills
Lack of materials tesng and inspecon skills
6. What are the consequencesifQAand QC is overlooked
QA/QC issues are likely to happen if there is no concisedocumentaon of project acvies
Compromise human and environmental safety
Causes unnecessary reworks
Creates conict on contract me management- owner and contractor
having dierent accounts on delays
Project design life is likely to shorten due to poor quality
Breeding ground for fraud
Creates reputaonal risks
And a host of other issues
?
?
-
7/28/2019 QS/QC questions
6/16
4
7. What are the auxillary (tool) kits forStandard Construction Supervision
and Contract Management
Contract Domain Toolkit Control measures
1. Quality Materials QCP, Technical
Specicaons, Plans (lines
and grades), Shop Drawings,
Site Instrucons, Request for
Informaon, Work Requests,
Materials Test Report, CPES,
DLP, Performance Security
1. Concise and
up-to-date
documentaon of
daily acvies.
2. Contract
Management and
QA/QC skills
3. Variaons - Workfor aected work
items can only
commence aer
approval of VO
2. Quanty Approved as-stake survey,
Approved as-staked quanty,
Inspecon Report, Back-up
Calculaons, SWA, Weekly
Accomplishment Report,
Straight Line Diagram, PERT-
CPM
3. Cost Approved Unit Cost Analysis,
SWA, Cash Flow Schedule,
Payment Cercates, CARI
4. Time Weather Chart, Suspension
and Extension of Time,
Producvity Losses, Statement
of Time Elapsed, S-curve and
Bar Chart, Request for Time
Extension
8.What are the constructionpreparatory procedures
For materials quality tests:
Joint Owner-Contractor reconnaissance survey on materials source
sites
Extracon, marking of samples, preparaon of sample cards and
delivery to accredited tesng center under an approved Work Request
Preparaon and submission by Contractor its Quality Control Plan
(QCP) for approval by Owners representave.
?
?
-
7/28/2019 QS/QC questions
7/16
5
Sampling, marking and tesng of
roadway materials
Blending aer obtaining sasfactory
test results from laboratory
For as-stake survey:
Joint Owner-Contractor As-staked (pre-construcon) survey (Specs,
Item 104.3.20). Idenfy and adjust/incorporate into the As-Staked
Survey the secons, sites and other details from original approved
plans not consistent with actual site condions as jointly surveyed.
Submission of As-staked plans and quanes for approval by Owner. Introduce Variaon Order No. 1 if possible changes in me, quanty
and cost are found necessary based on the results of the as-staked
survey.
As-stake survey is one of the rst stages ofaaining QA and QC.
-
7/28/2019 QS/QC questions
8/16
6
9.What are the requirements that needs to besubmitted by the contractor to the LGU once the
Notice to Commence Work (NTC) takes effect
Materials QCP
As-Staked Plans
Revised Construcon Schedule (in PERT-CPM, S-Curve with Bar Chart,
Manpower, Equipment)
Contractors Health, Safety and Environment (HSE) Program
Credenals of Key Personnel (CVs)
Project Signboard MRDP Standard Reporng Templates
Photo Documentaon Procedures
Relevant Implementaon Guidelines (on Variaons, Time Suspension/
Extension, etc.)
Contractors Organizaonal Structure
Discussing these concerns in pre-construcon conferences does notassure Contractors compliance.
TRIAL SECTIONS
10.What are the DPWH Standard Specifcations
for Roads and Highways (2004, Blue Book)
>>Clause200.3.4and201.3.4TrialSecons
Purpose - to check the suitability of the materials and the
eciency of the equipment and construcon method which is
proposed to be used by the Contractor.
Contractor must use the same material, equipment and
procedures that he proposes to use for the main work.
One trial secon of about 500 square meters shall be made
for every type of material and/or construcon equipment/
procedure proposed for use.
Aer nal compacon of each trial secon, the Contractor shall
carry out such eld density tests and other tests required as
directed by the Engineer.
?
?
-
7/28/2019 QS/QC questions
9/16
7
A new trial secon shall be constructed if:
a. the proposed materials, equipment or procedures in the
Engineers opinion are not suitable for sub-base,
b. the basic condions regarding the type of material or
procedure change during the execuon of the work
>> Tolerances
Quality indicator Item 200 Item 201
Permied variaon from design
Thickness of Layer
20 mm 10 mm
Permied variaon from design Level
of Surface
+10 mm
-20 mm
+ 5 mm
-10 mmPermied Surface Irregularity
Measured by 3-m straight-edge
20 mm 5 mm
Permied variaon from design
Crossfall or Camber
0.3% 0.2%
Permied variaon from design
Longitudinal Grade over 25 m in length
0.1% 0.1%
11.What are the procedures in preparing trial sections
Step 1. In coordinaon with the Contractors Project Engineer (PE),
LGU Resident Engineer (RE) idenes road secon where Trial Secon
will be undertaken in accordance with minimum requirements of the
Specicaons (Block 8).
RE issues Site Instrucon to Contractor to undertake Trial Secon
starng with subrade preparaon.
PE submits Work Request indicang type of acvity, staon limits and
esmated item quanes for approval by RE. Materials Quality Tests
and As-staked Plans should be approved prior to approval of Work
Request.
Note: Preparaon of the trial secon should not be a prior
requirement for inial/preparatory acvies such as Clearing and
Grubbing and Earthworks. These acvies can proceed independently
in accordance with approved construcon schedule.
?
-
7/28/2019 QS/QC questions
10/16
8
Step 2. Inspecon and Cercaon
Lines and Grades: Refer to: a) Approved As-staked Plan, and b)
Allowable Tolerances (Block 8)
Quality of Compacon: Field Density Test (FDT) - refer to approved
Quality Control Plan (QCP) requirements
- Determine number of passes for type of roller used
Repeat process if results are unsasfactory via issuance of Site
Instrucon. Proceed to the next layer (Item 200) otherwise.
RE signs o on Inspecon Report to manifest Contractors compliance
to requirements.
Step 3. Item 200
PE submits Work Request for approval by RE
Lines and Grades Must comply with the allowable tolerances for
Item 200 (Block 8)
Quality - Compacon via Field Density Test (FDT) - refer to QCP and
Specs requirements
-Determine number of passes for type of roller used
Repeat process if results are unsasfactory via issuance of SiteInstrucon. Proceed to the next layer (Item 201) otherwise.
RE signs o on Inspecon Report to manifest Contractors compliance
to requirements.
Step 4. Item 201
Repeat the same procedures in Item 3.
Note: Make sure that all materials incorporated into the various
roadway layers are in accordance with approved grading, blending
and moisture content requirements, immediately preceding its
incorporaon. Materials passing individual quality tests done at
laboratory may not necessarily qualify for incorporaon due to
inappropriate processing and handling.
Approved QCP Approved As-Staked
Survey
Site Instrucon
Trial Secon
Work RequestExecuonInspecon and
Cercaon
-
7/28/2019 QS/QC questions
11/16
9
Item 105 - Sub-grade preparaon. Check
compliance to lines and grades aer applicaonthen for compliance to compacon requirements
via FDT.
2
Spreading. Compacon. Check for compliance to lines and
grades prior to FDT.
1
3 4
5 6
-
7/28/2019 QS/QC questions
12/16
10
Repeat the sameprocedure for Item 201
(and 300 if required)
SamplephotosofTrialSeconacvies
Making available
standard set of eld
Materials Tesng
Apparatus saves the
Contractor substanal
amount of me and
money. This requirementcould form part of the
SCC.
7
-
7/28/2019 QS/QC questions
13/16
11
QUICK NOTES:
1. (Strictly) enforcing Trial Secon is not an assurance of full
compliance to the Projects QA/QC objecves.
2. It is only an inial step in achieving quality assurance related to
workmanship and procedures specially for LGUs who play the major
role as Construcon Supervisors and Contract Managers.
3. This exercise is meant to raise the awareness of sub-project
implementaon stakeholders of the standard procedures of
check and balance right at project start up by achieving: a.Proper
construcon methodology b.Concise and up-to-date documentaon
and monitoring of sub-project acvies using basic tools such as
Work Requests, Site Instrucons, Requests for Informaon and Daily
Acvity Log/Weather Report.
4. QA/QC conicts can only be resolved if the proper ow of
documentaon is observed to a high degree of specicity by both
Contractor and Owner.
5. PSO/RPCO RIEs presence are required in this exercise.
-
7/28/2019 QS/QC questions
14/16
Produced by:
Informaon, Advocacy, Communicaon and
Educaon (InfoACE) UnitIn coordinaon with the
Rural Infrastructure Component
Mindanao Rural Development Program 2
PROGRAM SUPPORT OFFICE
-
7/28/2019 QS/QC questions
15/16
Department of Agriculture
MINDANAO RURAL DEVELOPMENT PROGRAM
PROGRAM SUPPORT OFFICE
Alvarez Bldg., A. Angliongto Sr. Ave.,
Lanang, Davao City 8000
Telephone No.: (082) 235-8665
Telefax: (082) 235-8664
Email: [email protected]
Website: www.damrdp.net
REGIONAL PROGRAM COORDINATION OFFICES
Region 9
Department of Agriculture
Western Mindanao Integrated
Agricultural Research Center
(WESMIARC)
Ipil, Zamboanga Sibugay 7001
Tel.: (062) 333-2508Email: [email protected]
Region 10
Department of Agriculture
Regional Field Unit 10
A. Luna St.,
Cagayan de Oro City 9000
Te.: (08822) 728-236
Fax: (08822) 726564 | 725725
Region 11
Department of Agriculture
Regional Field Unit 11
F. Bangoy St., Davao City 8000
Te.: (082) 221-9697
Fax: (082) 226-3625
Email: [email protected]
Region 12
Department of Agriculture
Regional Field Unit 12
3rd Flr. CSA Bldg., cor. Zulueta Gensan
Drive., Koronadal City 9506
Te.: (083) 520-0622/0624/0625
Fax: (083) 520-0628
Region 13
Department of Agriculture
Regional Field Unit 13
Capitol Site, Butual City 8600
Te.: (085) 341-2045
Fax: (085) 341-2114
Email: [email protected]
ARMM
Department of Agriculture and
Fisheries (DAF) ARMM
ORG Compound, Cotabato City 9600
Te.: (064) 421-1396
Fax: (064) 421-1396
Email: [email protected]
-
7/28/2019 QS/QC questions
16/16
www.damrdp.net