VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR

Transcript of Qantas repair

Page 1: Qantas repair

VH-OJH INCIDENT

23 SEPTEMBER 1999PETER THOMASOJH PROJECT COORDINATOR

Page 2: Qantas repair

THE FIRST DAY

• VH-OJH left the end of RWY 21L at BKK INTERNATIONAL AIRPORT on the night of 23 SEPTEMBER 1999. The A/C travelled a further 200 metres across the RWY run-off area.

• On its way the A/C collided with the RWY 03R Localiser Antenna before coming to rest in a RWL position.

Page 3: Qantas repair

pth13:

Localiser Antenna

Page 4: Qantas repair

pth13:

“The Day After”

Page 5: Qantas repair
Page 6: Qantas repair
Page 7: Qantas repair

pth13:

No.3 Pylon

pth13:

Note failure of Diagonal Brace “end fitting”

Page 8: Qantas repair

pth13:

Golf Course Road

Page 9: Qantas repair

THE RECOVERY

• The importance of keeping the “Station Aircraft Recovery List” updated, including checking Emergency Contacts and Equipment Suppliers phone numbers.

• An assistant is required to keep notes during the initial Recovery planning period.

Page 10: Qantas repair
Page 11: Qantas repair

pth13:

Construction of a road to return to RWY 21L.

Page 12: Qantas repair

pth13:

Road constructed to allow unloading of aft cargo and parking of crane.

Page 13: Qantas repair

pth13:

Stabilising R/H wing to prevent A/C movement.

Page 14: Qantas repair

pth13:

Fuselage damage due to ingress of NLG Assy.

Page 15: Qantas repair

pth13:

“Classic” failure of R/H WLG.

Page 16: Qantas repair

ARRIVAL OF PARTS

• To ensure swift delivery of Parts, Materials and Tooling a Custom’s Agent must be engaged who has contacts at the HIGHEST LEVELS”. Arranging a “Custom’s Carnet” is of utmost importance to overcome “heavy” Customs Duties.

• To ensure these deliveries are completed with the utmost promptness, cooperation with all levels of the Airport Authority is required.

Page 17: Qantas repair
Page 18: Qantas repair
Page 19: Qantas repair

INCIDENT SITE SCRAP

• All scrap had to be collected for documentation.

• To conform to “Customs” regulations all parts and raw materials movements had to be thoroughly documented and presented to the Authorities for approval so as not to incur large Customs duties. This procedure was also required for all scrap material.

Page 20: Qantas repair
Page 21: Qantas repair

JANUARY 23 2000REPAIR BEGINS

• The Boeing Team begins the repair by first stabilising and “jigging” the Aircraft to prevent fuselage movement during the removal of the lower sections of Sections41 and 42.

Page 22: Qantas repair

pth13:

A/C was “tied” to the tail jack and the jack was cabled to the ground. Jack point was “drilled” to allow fitment of a rod between the jack adaptor and the jack point.

Page 23: Qantas repair

pth13:

Installation of “Tower Jacks”

Page 24: Qantas repair

pth13:

Fuselage “stabilisation” complete.

Page 25: Qantas repair

AIRCRAFT REPAIR BEGINS

• Removal of Section 41 and 42 begins.• Replacement of the damaged “window-

belt” has to be done before removal of the lower Section 41. This is to ensure the alignment of the Aircraft is maintained.

Page 26: Qantas repair

pth13:

“Window belt” repair.

Page 27: Qantas repair

pth13:

No.3 Pylon repair.

Page 28: Qantas repair

pth13:

“Wiring pull-back”

Page 29: Qantas repair

pth13:

“Wiring pull-back” completed.

Page 30: Qantas repair

pth13:

Sections 41/42 removed.

Page 31: Qantas repair

pth13:

“Aligning Sect.41.

Page 32: Qantas repair

pth13:

Installation of Sect.42 “plug”.

Page 33: Qantas repair

pth13:

“Final Alignment”

Page 34: Qantas repair
Page 35: Qantas repair

pth13:

Skin “finish” after repair.

Page 36: Qantas repair

STORES PERSONNEL

• A team of Stores Personnel was required to acquit all the Parts demands and to administer a Parts store to ensure a “smooth” production flow is maintained.

• Boeing were ordering “hundreds” of parts daily from Seattle and expecting 2 days delivery at the site.

Page 37: Qantas repair

pth13:

Mick Gledhill

Page 38: Qantas repair

DOCUMENTING AND CERTIFICATION

• To lessen the impact of the “cost” of the repair to QANTAS a lot of rotable parts were supplied by QANTAS. The Insurance Company will only pay “Market Price” for these parts.

• A Team of LAME’s were needed to document and certify these parts as a lot of the Parts were delivered straight from the Vendor. This included all the Landing Gear assembly’s.

Page 39: Qantas repair

pth13:

Mark Coffey

Page 40: Qantas repair

pth13:

First Engine installed by QANTAS LAME’s

Page 41: Qantas repair

pth13:

Zones 1 & 2 rework by QANTAS.

Page 42: Qantas repair

pth13:

A “few” of the 300+ F/G repairs to the L/E.

Page 43: Qantas repair
Page 44: Qantas repair

HI - BLOW TEST

• “Seats” all the rivets and frame joints.• Exposes any fuselage skin joints leakage.• Fuselage blown to 12.5 psid.

Page 45: Qantas repair
Page 46: Qantas repair

pth13:

“Hi-Blow” relief vlv.

Page 47: Qantas repair

ROLL-OUT AFTER REPAIR

• Rollout from Hangar after approx. 6 months.

• Due to publicity sensitivity the A/C had to be similar in appearance to other B744’s prior to “rollout”.

• The repaint of the repaired areas was achieved by “paint rollers”.

Page 48: Qantas repair
Page 49: Qantas repair
Page 50: Qantas repair
Page 51: Qantas repair

pth13:

Thorough wash before “functional checks begin”.

Page 52: Qantas repair
Page 53: Qantas repair
Page 54: Qantas repair

pth13:

Second Test Flt. Return.

Page 55: Qantas repair

pth13:

Taxi-In after 2nd Test Flt.return.

Page 56: Qantas repair
Page 57: Qantas repair

AFTER A/C DEPARTURE

• A/C Departs for Paint Facility in Xiamen.• Final Clean-up underway.

Page 58: Qantas repair

pth13:

Signing of “Certificate of Completion”.

Page 59: Qantas repair

pth13:

Departure for repaint at Xiamen, China.

Page 60: Qantas repair

pth13:

All scrap had to be disposed of so as to not arouse “Media” interest.

Page 61: Qantas repair

pth13:

Last shipment of scrap is loaded before returning the Hangar to Thai Airways.

Page 62: Qantas repair

pth13:

The crash site 6 months later. Note: the addition of landing lights.

Page 63: Qantas repair

THE END

VH-OJH RETURNED TO SERVICE AFTER REPAIR AND REPAINT