PV Revamping/Repowering and New Build Technical Rules and ... · PV energy production at GSE meter...
Transcript of PV Revamping/Repowering and New Build Technical Rules and ... · PV energy production at GSE meter...
Napoli - April 5th 2018
PV Revamping/Repowering and New Build
Technical Rules and Best Practice
Moroni & Partners is a consultant engineering company specialized in the renewable energy market, headquarters in Ancona, established in 2007 by Mauro Moroni, PhD in Energetics at Politecnico delle Marche. We provide engineering services consultancy to Investors, Banks, Lenders, Industrial customers and EPC Contractors in the field of Renewable Energies. A few numbers about us: - More than 50 professionals - 90% of staff graduated in Engineering - More than 4 GW of experience in Renewable Energies
M&P at a glance
ABOUT US
Membership:
Awards:
Engineering
•Environmental impact assessment and authorisations
•Design, engineering, urban and structural planning
•Detailed Engineering
•Works Management
•Health & Safety
•Energy Efficiency for Industrial & Real Estate applications
•Re-Engineering
Technical Advisory
• Preliminary evaluation and business plan • Technical and Administrative Due Diligence • Testing during and after construction • Instrumental verifications • Insurance appraisal • Final & Provisional Acceptance Tests (FAC/PAC)
Asset Management
•Service supply management
•Validation of Maintenance activities
•Remote monitoring of key performance parameters
•Assistance for administrative and accounting requirements
•Assistance in the relationship with Tax Authority (UTF) and GSE
•O&M supervision
M&P at a glance
OUR DIVISIONS
M&P at a glance
COMPANIES THAT HAVE CHOSEN US
REVAMPING AND REPOWERING
GSE rules
INTERVENTIONS ALLOWED BY GSE
PV Plant Relocation
Components Relocation
Components Replacement
PV Modules Removal
Intervention on building
Electrical configuration variation
Storage systems installation
Not subsidized Repowering
Modules Replacement
ISSUES RELATED TO PV MODULES
PV modules are often affected by different failures according to their life period
EVA yellowing on cracked cells
Backsheet deep cracking
Shunt damage on backsheet
Backsheet delamination
Backsheet air side yellowing
Glass antireflective coating delamination
Modules Replacement
ISSUES RELATED TO PV MODULES
• Material Sciences - for PV panel / cells fabrication Tedlar® / Backsheet Solamet® / PV cell metallization
• Panel & Materials reliability testing • Global presence in the PV value chain
• General Technical Consulting expertise • Instrumental tests expertise • Revamping expertise • Broad contact base / Primary and
Secondary Markets
WORLDWIDE PARTNERSHIP FOR PV SYSTEMS (ON GOING)
TARGETS: • Define an on-site procedure (site visit and instrumental tests) to be performed in order to
detect and analyze the issues on the plants, with particular focus on panels and back-sheet;
• Risk assessment for the most common degradation impacting photovoltaic modules, e.g. back-sheet;
• Mitigance proposal; • Development of technical best practices reducing risk of premature system degradation,
e.g. appropriate BoM selection and O&M protocols; • Assistance to the Operators in developing reliable and durable PV systems for the most
competitive LCOE.
Modules Replacement
THE PARTNERSHIP WITH DUPONT
Modules Replacement
THE BENEFITS OF THE NEW MODULES
IMPROVED ENERGY PRODUCTION
IMPROVED RELIABILITY
IMPROVED TEST PROCEDURE AND CERTIFICATIONS
LOWER PRICE FOR WATTs
IMPROVED Pmax TOLERANCE
Modules Replacement
THE REQUIREMENTS OF THE NEW MODULES
NEW COMPONENTS
AT LEAST 10 YEARS PRODUCT
WARRANTY
The manufacturer must be member of a EU consortium for end-of-life collection
and recycling
ISO 9001:2008
OHSAS 18001
ISO 14001
Factory Inspection Certificate
(Made in EU Where necessary)
PRODUCT REQUIREMENTS
IEC 61215 (61646) IEC 61730
MANUFACTURER REQUIREMENTS
GSE rules for PV Revamping
INVERTER REPLACEMENT BENEFITS
MAIN DETECTED CRITICALITIES
LOW DC/AC CONVERSION EFFICIENCY
WRONG INSTALLATION
(DERATING)
FAULT MANUFACTURER
LACK OF TECHNICAL SERVICE
LOW INVERTER AVAILABILITY
GSE rules for PV Revamping CONFIGURATION VARIATIONS – POWER OPTIMIZERS
STRING OPERATION
WITHOUT SHADOW
OPERATION WITH SHADOWS
OPERATION WITH SHADOW
AND POWER OPTIMIZER
SHADY AREA UNSHADED
UNSHADED SHADY AREA
GSE rules for PV Revamping
CONFIGURATION VARIATIONS – PID RECOVERY
PROBLEM DETECTION PID BOXES INSTALLATION
PID RECOVERY TREND
REVAMPING INTERVENTION BUSINESS CASES
Business Cases
SERVICES PERFORMED BY M&P
• Instrumental Tests • Historical Data Analysis • Reverse Engineering
• Intervention evaluation
• Authorization update • Grid connection
update • Final Design drafting
• Electrical works • Mechanical works • Structural topics
• Civil works • Monitoring • Security
Work Supervision Health & Safety Commissioning
OPTIMIZATION STUDY
PERMITTING DETAIL
ENGINEERING WORKS
EXECUTION
SOLAR TRACKERS – IRRADIATION SENSORS
Business Cases
INSTRUMENTAL TESTS
TERMOGRAPHY
FUNCTIONAL TESTS - I-V CURVE
INVERTER EFFICIENCY - POWER QUALITY
OUTDOOR ELECTRO-LUMINESCENCE GALVANIZATION TESTS
51I-V@STC 51I-V Nominale 51Pot@STC 51Pot Nominale
Tensione [V]
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40
Co
rre
nte
[A
]
0
1
2
3
4
5
6
7
8
9
Po
ten
za
[W]
0
20
40
60
80
100
120
140
160
180
200
220
240
ON PV MODULES ON BALANCE OF SYSTEM
Business Cases
HISTORICAL DATA ANALYSIS
PV energy production at GSE meter [kWh] and
energy exported to the grid at
ENEL meter [kWh]
Performance Assessment considering specif events
O&M Reports including
extraordinary manteinance interventions
Monthly solar irradiation GTI
[kWh/m2], measured on site
(POA)
Monthly total availability values
of PV plants, AV [%] and internal availability INT.AV [%].
SOLARGIS Historical
data
Solar Resource Assessment
FEASIBILITY STUDY - BUSINESS PLAN
Business Cases
REVERSE ENGINEERING
Technical Analisys including:
• DESIGN REVIEW • INSTRUMENTAL
TESTS • HISTORICAL DATA
EVALUATION
Identification of critical design
solutions/technology
Dynamic simulation of upgraded plant performances
Identification and engineering of the upgrades
Upgrades CAPEX estimation
BENEFITS COSTS
Dynamic simulation of current plant performances
Business Cases
FOCUS ON PERMITTING
Irregular historical framework for ground mounted PV
(AU, DIA, PdC, PAS…)
Preliminary Q&A with local authorities to detect the proper
procedure for the substantial/not substantial modification of:
In many cases the As-Built Status is not compliant with
the authorized
A permitting compliance check is suggested before the beginning of the procedure.
(“Accertamento di conformità” procedure if necessary)
Modification of the current AU
Screening VIA in case P>1 MWp (Repowering)
PAS - Procedura Abilitativa Semplificata
Rated Power
Plant Layout
Revamping/Repowering permitting suitable
procedures
PV Modules number (GSE) 4.278
PV Modules Power [Wp] 230
GSE Plant Rated Power [kWp] 983,94
Power up to 1% DTR Limit [kWp] 993,78
Module Rated Efficiency 14%
Modules per string 23
Strings number 186
Inverter 3
GSE FIT (2°Conto Energia) [€/kWh] 0,314
Grid Connection 2011
FIT Period End 2031
AS BUILT – TECHNICAL FEATURES
MODULES STRONGLY AFFECTED BY SAFETY AND PERFORMANCE
DEFECTS
ABOUT 68% TO BE URGENTLY
REPLACED
Business Cases
MODULES REPLACEMENT
Business Cases
MODULES REPLACEMENT
OLD PV MODULES
NEW PV MODULES
MOUNTING RACKS
INVERTER - BOS
RATED POWER
AUTHORIZATION
230Wp - 60 poly-c cells - 14% efficiency – 1.64 m2
Manufacturer not active
270Wp - 60 poly-c cells – 16.5% efficiency – 1.64 m2
Tier 1 Manufacturer
100% Preservation, including layout
- 100% Inverter preservation - Strings configuration and string boxes preservation
-Installation works optimization - Additional inverter in case of repowering
- Up to 1% more than GSE capacity: SUBSIDIZED - Any repowering capacity: GRID PARITY
- AU update necessary (PAS) -Grid Connection procedure in case of repowering
- Screening VIA in case of repowering (P>1MW)
DEFECTIVE DETECTED MODULES AND STRINGS OVER PV PLANT LAYOUT
PERFORMED: DETAILED VISUAL INSPECTIONS
AND INSTRUMENTAL TESTS
- PRODUCT ISSUES - SAFETY ISSUES (INSULATION) - PERFORMANCE ISSUES
2.898 (68%) DEFECTIVE
PV MODULES
Business Cases
MODULES REPLACEMENT
SCENARIO 1 SCENARIO 2 SCENARIO 3
DEFECTIVE MODULES REPLACEMENT
UP TO GSE RATED POWER
100% MODULES REPLACEMENT
UP TO GSE RATED POWER
100% MODULES REPLACEMENT
WITH REPOWERING
N°3 REVAMPING/REPOWERING SCENARIOS TO BE EVALUATED
Modules Number: 3.887 Rated Power: 989,7 kWp
Energy Yield: 1.315,3 kWh/kWp
Modules Number: 3.680 Rated Power: 993,6 kWp
Energy Yield: 1.360 kWh/kWp
Modules Number: 4.278 Rated Power: 1.155,1 kWp
Energy Yield: 1.360 kWh/kWp
Business Cases
MODULES REPLACEMENT
SCENARIO 1
DEFECTIVE MODULES REPLACEMENT
UP TO GSE RATED POWER
Minimum CAPEX to restore
Plant Performance And Eectrical Safety
Residual degradation risk
for the remaining old modules in the
future
Limited recabling works
Electrical design for minimization of
mismatching impact (MPPT)
Simplified Authorization Path (PAS)
Modules Number: 3.887 Rated Power: 989,7 kWp
Energy Yield: 1.315,3 kWh/kWp
Business Cases
MODULES REPLACEMENT
SCENARIO 2
100% MODULES REPLACEMENT
UP TO GSE RATED POWER
Modules Number: 3.680 Rated Power: 993,6 kWp
Energy Yield: 1.360 kWh/kWp
Optimal CAPEX to restore
Plant Performance And Eectrical Safety
NO Residual degradation risk
for the remaining old modules in the
future
Limited recabling works
Minimization of mismatching impact
(MPPT) Simplified Authorization
Path (PAS)
Business Cases
MODULES REPLACEMENT
SCENARIO 3
100% MODULES REPLACEMENT
WITH REPOWERING
Modules Number: 4.278 Rated Power: 1.155,1 kWp
Energy Yield: 1.360 kWh/kWp
Higher CAPEX Due to repowering
NO Residual degradation risk
for the remaining old modules in the
future
Electrical design
considering a new plant section not
subsidized
Authorization Path According to the authority
(Screening VIA P>1MW + PAS) Grid Connection update
Business Cases
MODULES REPLACEMENT - REPOWERING
The additional portion of the system must be equipped with its own dedicated meter (and inverter…) The intervention must be duly authorized in accordance with the urban planning regulations in force. Request for upgrade of the connection for additional power, according to TICA. Registration in Gaudì of the plant upgrade as a new section or creation of new production unit related to the new section inserted (different commercial contracts).
ELECTRICAL GRID
NOT SUBSIDIZED PV 161.4 kWp
SUBSIDIZED PV 993.6 kWp
ADDITIONAL METER
LOADS
Business Cases
MODULES REPLACEMENT - REPOWERING
SCENARIO 1 2 3
CAPEX € 307.086 € 447.184 € 553.226
IRR 8,23% 9,30% 8,76%
NPV € 133.302 € 240.938 € 291.808
Payback Time 9 years 9 years 9 years
Works related to the SCENARIO 2
are currently under execution
Business Cases
MODULES REPLACEMENT
Business Cases
PROCEDURE RECAP
DETAILED DESIGN:
-PV Layout - Electrical Diagram
- Cable routes - Reports
- BOQ
Preliminary discussion with
local authority in order to check
the correct permitting procedure
Permitting procedure for manteinance works
(PAS according to Dlgs
28/2011 or AU according to Dlgs 387/2003)
Grid connection procedure review and
upgrade
(Adjustment of existing connection according to
TICA - Del. ARG/elt 99/08 )
Upgrade of Custom Agency
procedure, GAUDI and
cadastral data
GSE Documents collection:
-Intervention report
-PV modules list - Disposal documents
- Updated layout - Updated electrical
diagrams
WORKS EXECUTION AND
FINAL TEST
PV Modules disposal
INVERTER REPLACEMENT EVALUATION ACCORDING TO AVAILABILITY AND CONVERSION EFFICIENCY INCREASE.
Plant Rated Power: 852 kWp Inverter type: Central
Inverter AC Power: 100 kW Inverter Number: 9
CURRENT EURO EFFICIENCY: 96,2% VS DECLARED 96,4%
HISTORICAL INVERTER AVAILABILITY: 96,8%
CURRENT ENERGY YIELD: 1.729 kWh/kWp
Business Cases
INVERTER REPLACEMENT
INVERTER REVAMPING
TARGETS
EURO EFFICIENCY: FROM 96,2% TO 97,5%
AVAILABILITY: FROM 96,8% TO 98,5%
ENERGY YIELD: FROM 1.729 to 1.769 kWh/kWp +2,3%
Brand Model Max
Efficiency Euro
Efficiency Efficiency Increase
BRAND 1 MODEL 1 (ACTUAL) 97.0% 96,4% -
BRAND 2 MODEL 2 98,0% 97,7% 1,35%
BRAND 2 MODEL 3 98,7% 98,2% 1,87%
BRAND 3 MODEL 4 98,6% 98,5% 2,18%
BRAND 4 MODEL 5 98,7% 98,5% 2,18%
INTERVENTION CAPEX 90-100.000 €/MW
Including transportation, reconfiguration and installation
CAPEX 100.000 €/MW 95.000 €/MW 90.000 €/MW
IRR 13,9% 14,8% 15,8%
NPV € 94.382 € 98.642 € 102.902
PBT 6 6 5
INVESTMENT PROFITABILITY
Business Cases
INVERTER REPLACEMENT
UTILITY SCALE PV IN NEW BUILD MARKET
RES Italian Market
SEN 2017 – SOLAR TARGETS
SOLAR GENERATION x3 by 2030
Additional 40 GW to be installed
(more than 3GW/year)
2018-2020
Competitive auctions organised by the
Government
2020 ---> ?
Regulated PPA to support market transition
Final Stage
MARKET PARITY
Source: 2017 Italy’s National Energy Strategy (SEN=“Strategia Energetica Nazionale”), document published on November 10th, 2017
New Utility Scale PV
SERVICES PERFORMED BY M&P
• Site assessment • Technology selection • Preliminary design
• Performance estimation
• Feasibility recap
• Authorization procedure
(AU and EIA/Screening)
• Grid connection • Design for permitting
drafting
• Electrical works • Mechanical works • Structural topics
• Civil works • Monitoring • Security
• Work Supervision • Tests for components
acceptance • Health & Safety • Commissioning
FEASIBILITY EVALUATION
PERMITTING DETAIL
ENGINEERING WORKS
EXECUTION
New Utility Scale PV
DEVELOPMENT KEY FACTORS
PLANNED PLANT LIFETIME AT LEAST 30 YEARS ACCORDING TECHNOLOGY MATURITY
LAND RIGHTS RoS OR PURCHASE ACCORDING LIFETIME AND COSTS
PERMITTING REDUCING TIME AND COST WITHOUT SITE CONSTRAINT
ENERGY SELL AREA SELECTION ACCORDING THE BEST ZONE PRICE
GRID CONNECTION AREA SELECTION ACCORDING GRID STABILITY AND
EXISTING INFRASTRUCTURE (MV-HV)
PERFORMANCE ESTIMATION
DYNAMIC SIMULATION ACCORDING UPDATED IRRADIATION DATA AND DETAILED SITE MODELING
PERFORMANCE RATIO INCREASE
85% TARGET
Utility Scale PV
ACHIEVABLE YIELD OPTIMIZATION
• FAR AND NEAR SHADING • SOILING
• MODULES QUALITY AND DEGRADATION • MODULES MISMATCH
• OHMIC LOSSES • INVERTER PERFORMANCE
KEY LOSSES TO BE MINIMIZED
DURING DESIGN, PROCUREMENT, COMMISSIONING AND
OPERATION PHASES
SOLAR IRRADIATION
INCREASE SOLAR TRACKERS INSTALLATION
AVAILABILITY INCREASE
99% TARGET
• MONITORING •INVERTER MAINTENANCE • INTERVENTION TIME
• SPARE PARTS MANAGEMENT
AVAILABLE AREA OPTIMIZATION
MODULES EFFICIENCY AND RATED POWER INCREASE