    Purple Line ExtensionStation Advisory Group June 6, 2013

  • 8/22/2019 Purple Line Extension June meeting PPT

    2/45

    Tonights Agenda

    Project Overview & Schedule

    Role of Advisory Group

    Construction Relations

    Construction Overview

    Questions & Answers

  • 8/22/2019 Purple Line Extension June meeting PPT

    3/45

    Project Overview & ScheduleRole of Advisory Group

    Jody Litvak

  • 8/22/2019 Purple Line Extension June meeting PPT

    4/45

    Meet the Team

    Dennis Mori

    Executive Officer, Project Management

    Jim Cohen

    Deputy Executive Officer, Project Management

    Scott McConnellDirector, Construction Management

    David Mieger

    Deputy Executive Officer, Countywide Planning & Development

    Yvette Rapose

    Director, Construction Relations

    Jody Litvak

    Director, Community Relations

  • 8/22/2019 Purple Line Extension June meeting PPT

    5/45

    Approved Project

  • 8/22/2019 Purple Line Extension June meeting PPT

    6/45

    Approved Project - Schedule

    Planned Schedule Forecasted Schedule

    Section 1 Section 2 Section 3

    Length 3.9 Miles 2.6 Miles 2.9 Miles

    New Stations

    Wilshire/La Brea

    Wilshire/Fairfax

    Wilshire/La Cienega

    Wilshire/Rodeo

    Century City

    Westwood/UCLA

    Westwood/VA

    Hospital

    Pre-Construction

    ActivitiesCurrent - 2014 2017 - 2018 2025 - 2027

    Construction 2014 - 2023 2019 - 2026 2027 - 2035

    Operations 2023 2026 2035

  • 8/22/2019 Purple Line Extension June meeting PPT

    7/45

    Section 1 Next Steps

    Now and ongoing: Pre-construction (selecting

    Design-Build contractor, utility relocations,

    exploratory shaft, real estate acquisitions,discussions with cities, etc.)

    January 2014: Full-Funding Grant Agreement

    (FFGA) anticipated 2014: Construction begins

  • 8/22/2019 Purple Line Extension June meeting PPT

    8/45

    Station Advisory Group Section 1

    Comprised of representatives from communities in the

    project area including residents, businesses, property

    owners, key institutions and associations

    Representatives suggested by elected officials and otherkey organizations

    Provide ongoing dialog with community representatives

    Provide ongoing feedback between Metro and the

    community

    May occasionally meet as sub-groups

    Meet quarterly for duration of project (8 - 10 years)

  • 8/22/2019 Purple Line Extension June meeting PPT

    9/45

    Construction Relations

    Yvette Rapose

  • 8/22/2019 Purple Line Extension June meeting PPT

    10/45

    Construction Relations - Role

    Specialized Unit Matrixed to Construction

    Public Outreach, Stakeholder Communication & Direct

    Construction Impact Mitigation Project Management Plan

    Mitigation Measures Reporting Plan

  • 8/22/2019 Purple Line Extension June meeting PPT

    11/45

    Construction Relations - Structure

    Construction Relations Director

    Construction Relations Manager

    Sr. CRO Sr. CRO New Media Officer ELTP

    Project DirectorConstruction

    Communications

    Construction Relations

    Construction

  • 8/22/2019 Purple Line Extension June meeting PPT

    12/45

    Construction Relations - Support

    Direct Project & Contractor Support:

    Interdepartmental Management Coordination

    Pre-Construction Coordination Business Preparation & Coordination

    Resident Preparation & Coordination

  • 8/22/2019 Purple Line Extension June meeting PPT

    13/45

    Construction Relations Tactics & Outreach

    Did You Know?Public Outreach Tactics:

    Door-to-Door Distribution

    E-blasts

    Project Website Project Hotline

    3rd Party Websites/Blogs/Other Media

    Construction Notices, Fact Sheets & Educational

    Videos

    Social Media Outreach:

    Facebook

    Twitter

    YouTube

  • 8/22/2019 Purple Line Extension June meeting PPT

    14/45

    Construction Relations - Community

    Construction Safety Awareness Training, Local

    Construction Activities, Schedule Stakeholder

    Communications: Station Advisory Group (SAG)

    Elected Officials Staff

    Neighborhood Councils, HOAs & Residents

    Chambers of Commerce/BIDs/Business Associations

    Business Owners Educational & Cultural Institutions

    Faith-Based Organizations

  • 8/22/2019 Purple Line Extension June meeting PPT

    15/45

    Construction Relations Issues Resolution

    Implement measures in support of the

    approved Environmental Impact

    Statement/Report (EIS/R)

    Contractor coordination

    Resolution of direct impacts

    Facilitate complaints between the public &

    the Contractor

  • 8/22/2019 Purple Line Extension June meeting PPT

    16/45

    Business Profiles - Goals

    Metro Construction Relations will conduct

    business profile surveys along the Purple Line

    Extension Section 1

    Visit every business along the alignment

    Conduct thorough interviews

    Coordinate construction activities

    Understand business operations

  • 8/22/2019 Purple Line Extension June meeting PPT

    17/45

    Pre-Construction Business Support -

    Project Area Discount Program

    The Project Area Discountprogram is an opportunity for

    businesses directly along the alignment, and within a mile

    radius, to advertisewithout coston the Purple Line

    Extension project page and the Metro website in exchange

    for providing customers an added value incentive

    Free to businesses

    Metro.net enjoys 1.5 million viewers monthly

    Full marketing program

  • 8/22/2019 Purple Line Extension June meeting PPT

    18/45

  • 8/22/2019 Purple Line Extension June meeting PPT

    19/45

  • 8/22/2019 Purple Line Extension June meeting PPT

    20/45

  • 8/22/2019 Purple Line Extension June meeting PPT

    21/45

  • 8/22/2019 Purple Line Extension June meeting PPT

    22/45

  • 8/22/2019 Purple Line Extension June meeting PPT

    23/45

    Construction Overview

    Dennis Mori

  • 8/22/2019 Purple Line Extension June meeting PPT

    24/45

    Section I Wilshire/Western to

    Wilshire/La Cienega

  • 8/22/2019 Purple Line Extension June meeting PPT

    25/45

    Section I - Wilshire/La Brea Station

    Entrance at NW corner on

    Metro-owned property

    Construction staging on

    NW & SW corners ofWilshire/La Brea

    TBM launched from this

    location

    Crossover tracks extend

    box to the east

  • 8/22/2019 Purple Line Extension June meeting PPT

    26/45

    Section I - Wilshire/Fairfax Station

    Entrance at SE corner

    Wilshire/Orange Grove

    2 construction staging sites: South side of Wilshire between

    Orange Grove & Ogden NW corner of Wilshire/Fairfax

    (Johnies)

    Discussions with LACMA

    about potential second

    entrance on north side ofWilshire

    Johnies will be preserved;

    potential future entrance

  • 8/22/2019 Purple Line Extension June meeting PPT

    27/45

    Section I - Wilshire/La Cienega Station

    Entrance at NE Corner

    2 construction staging

    sites: NE corner Wilshire/La Cienega

    NW corner Wilshire/Gale

    Crossover tracks extend

    box to the east

    TBM removal site at

    conclusion of tunneling

  • 8/22/2019 Purple Line Extension June meeting PPT

    28/45

    Standardized (Modular) Station Design

    Kit of Parts

    Station Entrance Canopy and Plaza

    Canopy as a Metro iconic design element

    Standardized elements for passenger familiarity, circulation and security

  • 8/22/2019 Purple Line Extension June meeting PPT

    29/45

    Major Activities

  • 8/22/2019 Purple Line Extension June meeting PPT

    30/45

    Utility Design/Station Construction

    Third Party Coordination

    Relocation and final design of utilities require close third

    party coordination between Metro, the utility companies,

    the City of Los Angeles, City of Beverly Hills and the

    contractors.

  • 8/22/2019 Purple Line Extension June meeting PPT

    31/45

    Advanced Utility Relocation

    Wilshire/La Brea Station

    Shoring Piles (Typical)

    Relocated Utilities

    (Clear of Shoring Piles)

    To facilitate the construction of major critical path construction activities, three contracts are being

    initiated to relocate water, power and sewer lines in advance of awarding the Design/Build tunnels and

    stations contract.

    The contract for the Wilshire/La Brea advanced utility relocation work was awarded and will begin

    construction in July 2013. Invitation For Bids (IFB) for the remaining two Advance Utility Relocations

    Contracts for Wilshire/Fairfax and Wilshire/La Cienega are being solicited in June and July 2013.

  • 8/22/2019 Purple Line Extension June meeting PPT

    32/45

    Traffic Control Plans

    Work

    Zone

    Final Traffic

    Control Plans are

    done by the

    Design-Builder

    Traffic Control Plans to be approved by Cities of Los Angeles & Beverly Hills

  • 8/22/2019 Purple Line Extension June meeting PPT

    33/45

    Typical Station Box Construction

    Work ZoneProtective

    Concrete

    Traffic Barrier

    Construction

    Fence

    Installation of Soldier Piles

    Soldier pile installation in Hollywood during

    Metro Red Line construction (1995)

  • 8/22/2019 Purple Line Extension June meeting PPT

    34/45

    Typical Station Box Construction

    Deck

    Beam

    Decking

    Installation of Deck Beams

  • 8/22/2019 Purple Line Extension June meeting PPT

    35/45

    Typical Station Box Construction

    Traffic Control Plans during deck installation to be approved

    by Cities of Los Angeles & Beverly Hills

    Typical Sequence Plan forDeck Construction

    Hollywood/

    Highland

    Station

    Completed Deck

    Installation

  • 8/22/2019 Purple Line Extension June meeting PPT

    36/45

    Construction Relations & Third Party

    Coordination

    Community meetings and internet project updates and construction notices

    will be provided by Metro Construction Relations Department.

    Early community outreach involving major stakeholders related to real estate

    activities began after the FTA issued a Record of Decision in August 2012.

    Early utility work involving the relocation of communication cables began inNovember 2012 at the Wilshire/La Brea station site.

    Plan reviews, permitting and other early construction activities to support the

    advance utility relocations in the City of Los Angeles and City of Beverly Hills

    are continuing.

    Continue third party coordination with City of Los Angeles and City of Beverly

    Hills to receive approvals to optimize work hours in an effort to reduce overallconstruction duration and impacts at station sites.

  • 8/22/2019 Purple Line Extension June meeting PPT

    37/45

    What Exemptions is Metro Seeking?

    Exemptions:

    Peak Hour:Allows construction to continue in the public right of way

    during peak hours (rush hours)

    Extended Work Hours: Allows overnight work within specific noise

    limits Holiday Moratorium:Allows construction to continue between

    Thanksgiving and New Years Day

    Objectives:

    Minimize overall duration of construction impacts

    Begin Advance Utility Relocation in July 2013

    Exemptions in Bid Documents

    Complete project in early 2023

  • 8/22/2019 Purple Line Extension June meeting PPT

    38/45

    Weekday Work Hour Restrictions

    Non-Restricted Work Hours

  • 8/22/2019 Purple Line Extension June meeting PPT

    39/45

    Optimal Schedule Without Restrictions

  • 8/22/2019 Purple Line Extension June meeting PPT

    40/45

    Work shiftsPeak Hour

    Exemption

    Night-time

    Noise Variance

    Holiday

    Moritorium

    Weekend

    Closures

    Utilities, shoring and street decking

    Utility Relocations Days / Nights Building Demolition - Laydown Areas Days Pile Installation Days / Nights Street Decking Days / Nights Hauling / Materials Deliveries Days / Nights

    Below Street Decking

    Tunnel Construction Days / Nights Station Construction Days / Nights Hauling / Materials Deliveries Days / Nights

    Remove street decking & street restoration

    Street Decking Removal Days / Nights Street Restoration Days / Nights Hauling / Materials Deliveries Days / Nights

    Activity

    Activities Requiring Exemptions

  • 8/22/2019 Purple Line Extension June meeting PPT

    41/45

    Wilshire/Fairfax Station Site

    Exploratory Shaft

    La Brea Tar Pits

    PageMuseum

    6th St

    Wilshire Blvd

    Exploratory Shaft Site

  • 8/22/2019 Purple Line Extension June meeting PPT

    42/45

    Wilshire/Fairfax Station Site

    Exploratory Shaft

    Purpose

    Gain better understanding of unique

    ground conditions

    Measure behavior of ground support

    structure

    Refine methods for finding & recovering

    fossils

    Provide data and information to

    Design/Builder for tunnels andunderground station design and

    construction

    Fossil Recovery at LACMA Parking Garage

  • 8/22/2019 Purple Line Extension June meeting PPT

    43/45

    Wilshire/Fairfax Station Site

    Exploratory Shaft

    Fencing will include project banners

    Placement of geotechnical instrumentation before shaft construction

    Contractor began site

    construction activities

    in April 2013

    Construction fencing

    installation will include

    Metro signage andgraphics

    18 W x 38 L X 70 D

    exploratory shaft will

    be constructed by 2014

    9 month monitoring

    period to obtain data

    following construction

    of the exploratory shaft

    to begin in January

    2014

  • 8/22/2019 Purple Line Extension June meeting PPT

    44/45

    Stay in Touch

    metro.net/purplelineext

    [email protected]

    Infoline: 213.922.6934

    Twitter.com/purplelineext

    Facebook.com/purplelineext

  • 8/22/2019 Purple Line Extension June meeting PPT

    45/45

    Questions?