Pulkit Ppt Steam Turbine3 (2)
-
Upload
abhishek-kumar -
Category
Documents
-
view
235 -
download
3
description
Transcript of Pulkit Ppt Steam Turbine3 (2)
IMPROVING EFFICIENCY & RELIABILITY
of
STEAM TURBINEPROJECT REPORT
BY:NAME: PULKIT KHANDURI
SUBMITTED TO:DGM (TMD NTPC BADARPUR) S K GARG
ROLL NO:12109059FINAL YEAR (MECHANICAL ENGINEERING)
NIT JALANDHAR
IN THE PRESENT POWER SECTOR SCENARIO
FOCUS IS ON
• ENHANCING EFFICIENCY• RELIABILITY• STRICTER POLLUTION NORMS• COST REDUCTION
RESULT IN IMPROVEMENT IN EFFICIENCY OF TURBINE
1. REDUCTION IN GENERATION COST HIGH EFFICIENCY OF THE CYCLE
LOWER EQUIPMENT COST SHORTER GESTATION PERIOD
REDUCED MAINTENANCE TIME2. INCREASED RELIABILITY
3. MINIMIZING ENVIRONMENTAL HAZARDS
IMPROVEMENT IN STEAM TURBINE IMPROVEMENT IN STEAM TURBINE PERFORMANCEPERFORMANCE
POSSIBLE BY1. IMPROVED BLADE PROFILE• REDUCTION IN THE AERODYNAMIC
FLOW LOSSES e.g.PROFILE LOSSSECONDARY FLOW LOSSTIP LEAKAGE LOSS
•MORE UNIFORM FLOW DISTRIBUTIONCONTD……..
IMPROVEMENT IN STEAM TURBINE PERFORMANCEIMPROVEMENT IN STEAM TURBINE PERFORMANCE
POSSIBLE BY ….contd...
2. OPTIMISED FLOWPATH
3. IMPROVEMENT IN SHAFT SEALING SYSTEM
4. REDUCTION IN PRESSURE DROPS
5. REDUCED FRICTION LOSSES
6. OPTIMISATION OF INLET & EXHAUST SECTION
7. OPTIMISED EXHAUST LOSS
METHODS EMPLOYED TO IMPROVE STEAM TURBINE EFFICIENCY
1. DEVLOPEMENT OF BETTER BLADE PROFILE FOR STEAM TURBINE.
2.2. RETROFITTING & UPGRADATION OF RETROFITTING & UPGRADATION OF OLDER SETS INOLDER SETS IN
(A)(A) HP TURBINEHP TURBINE(B)(B) LP TURBINELP TURBINE3. TECHNICAL PROPOSALS FOR IMPROVEMENT 3. TECHNICAL PROPOSALS FOR IMPROVEMENT
IN DESIGNIN DESIGN
1. IMPROVEMENT IN OF PROFILES FOR 1. IMPROVEMENT IN OF PROFILES FOR
CYLINDRICAL TURBINE BLADESCYLINDRICAL TURBINE BLADES
T4 PROFILE HAS 1% LOWER PROFILE LOSSES COMPARED TO T2 PROFILE.
NEWLY DEVELOPED TX HAS 0.2% LOWER PROFILE LOSSES COMPARED TO T4 PROFILE.
2 . CONSIDERATIONS IN RETROFITTING & UPGRADATION 2 . CONSIDERATIONS IN RETROFITTING & UPGRADATION OF OLDER SETSOF OLDER SETS
• COST EFFECTIVENESS• MODIFICATIONS IN TURBINE INTERNALS ONLY• INCREASE IN POWER OUTPUT WITH MINIMUM CHANGES• OUTER CASING, PIPINGS, VALVES, PEDESTAL FIXING ARRANGEMENT , STEAM PARAMETERS & FOUNDATION DETAILS REMAIN UNALTERED• SHORTEST POSSIBLE OUTAGE TIME
RETROFITTING & UPGRADATION OF OLDER SETSRETROFITTING & UPGRADATION OF OLDER SETS
PRE-REQUISITE
•IDENTIFY THE UNIT
•PRESENT LEVEL OF PERFORMANCE
•RESIDUAL LIFE ASSESSMENT STUDY OF CRITICAL COMPONENTS
•ANALYSIS OF HISTORY & OPERATING DETAILS
RETROFITTING & UPGRADATION OF OLDER SETSRETROFITTING & UPGRADATION OF OLDER SETS
• MAJOR MODIFICATIONS INMAJOR MODIFICATIONS IN GUIDE & MOVING BLADE GUIDE & MOVING BLADE
(LATEST STATE OF ART PROFILE)(LATEST STATE OF ART PROFILE) STEAM FLOWPATHSTEAM FLOWPATH ROTORS & INNER CASINGS OF ROTORS & INNER CASINGS OF
TURBINETURBINE SHAFT SEALINGSSHAFT SEALINGS [ADVANTAGE IN HEATRATE / [ADVANTAGE IN HEATRATE /
OUTPUT CAN BE WORKED OUT OUTPUT CAN BE WORKED OUT ON CASE TO CASE BASISON CASE TO CASE BASIS]]
3 DS BLADE
(HPT/IPT)
TWISTED PROFILE
BLADE (HP/IPT)
BANANA TYPE
BLADE (LPT)
210 MW STEAM TURBINE
(IMPULSE DESIGN SET-LMW) HP TURBINE
2(A) RETROFITTING OF HP TURBINE
EXISTING 210 MW HP TURBINE EXISTING 210 MW HP TURBINE WITH IMPULSE BLADINGWITH IMPULSE BLADING
PROPOSED NEW DESIGN WITH PROPOSED NEW DESIGN WITH LATEST STATE OF ART BLADINGLATEST STATE OF ART BLADING
210 MW STEAM TURBINE (IMPULSE DESIGN SET) HP TURBINE
HP TURBINE
EXISTINGEXISTING IMPULSE BLADING ( PRESSURE DROP ONLY IN
STATIONARY BLADES) EFFICIENCY : 83.6 % (FOR NEW MACHINE) EFFICIENCY FOR EXISTING
CONDITION : ~ 80%
NEWNEW• REACTION BLADING
( PRESSURE DROP IN STATIONARY AS WELL AS MOVING BLADES
EFFICIENCY : 86.5 %
ACTIVITIES INVOLVED
REMOVAL OF EXISTING HP ROTOR, LINERS AND DIAPHRAGMS
INSTALLATION OF NEW LINERS FITTED WITH STATIONARY BLADES AND NEW HP ROTOR
FITTING DIMENSIONS ARE TO BE MEASURED DURING PREVIOUS OVERHAUL AND LINERS ARE MACHINED ACCORDINGLY.
REMOVED HP ROTOR AND DIAPHRAGMS CAN BE USED AS SPARE FOR OTHER SETS
A. Reference data for ORIGINAL brand new turbineReference Heat Balance Diagram TCD - 210 - 33 - 2, Regime No. 1
Rated parameters
Main steam Flow 662 T/h
Main Steam Pressure 130 ata
Main Steam Temperature 535 Deg C
Hot reheat Temperature 535 Deg C
Condenser Vacuum 0.1042 ata
TG Heatrate 2062 kCal/kWh
A. Reference data for ORIGINAL brand new turbineReference Heat Balance Diagram TCD - 210 - 33 - 2, Regime No. 1
Rated parameters
Main steam Flow 662 T/h
Main Steam Pressure 130 ata
Main Steam Temperature 535 Deg C
Hot reheat Temperature 535 Deg C
Condenser Vacuum 0.1042 ata
TG Heatrate 2062 kCal/kWh
B. Expected present performance level (210 MW Original rating)
Considering deterioration due to ageingdeterioration due to ageing as per ASME-PTC-6Report 1985•Expected Power output
with 662 T/h main steam flow
and rated parameters 202.4 MW
•Expected TG Heatrate with 662 T/h main steam flow
and rated parameters 2164 kCal/kWh
B. Expected present performance level (210 MW Original rating)
Considering deterioration due to ageingdeterioration due to ageing as per ASME-PTC-6Report 1985•Expected Power output
with 662 T/h main steam flow
and rated parameters 202.4 MW
•Expected TG Heatrate with 662 T/h main steam flow
and rated parameters 2164 kCal/kWh
EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING IMPULSE DESIGN SET DUE TO HP TURBINE REFURBISHMENTIMPULSE DESIGN SET DUE TO HP TURBINE REFURBISHMENT
• INCREASE IN POWER OUTPUT : 8.6 MW
• IMPROVEMENT IN HEATRATE : 4% (FROM EXISTING PERFORMANCE LEVEL OF
THE SET WITH RATED STEAM PARAMETERS & THROTTLE STEAM FLOW)
BRAND NEW SET
EXPECTED PRESENT
DETERIORATED CONDITION
UPGRADED HPT
OUTPUT (MW)
210 202.4 (3.6% DECREASE)
211 (4.2% INCREASE)
HEAT RATE (KCAL/ KWh)
2062 2164 (4.9% INCREASE)
2077 (4.02% IMPROVEMENT)
EXPECTED PERFORMANCE IMPROVEMENT IN THE EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING IMPULSE DESIGN SET DUE TO HP TURBINE EXISTING IMPULSE DESIGN SET DUE TO HP TURBINE
REFURBISHMENTREFURBISHMENT
EXISTING AFTER RETROFIT
WORK INVOLVED IN RETROFIT OF LP WORK INVOLVED IN RETROFIT OF LP TURBINETURBINE
WORK TO BE DONE AT SITE:
•CUTTING OF DEFLECTORS / RIBS & BLANKING THE SPACE IN LP CASING TO FACILITATE REMOVAL OF BAUMEN STAGE.•MODIFICATION OF STRUCTURE AT THE EXHAUST END OF LPC TO FACILITATE INSTALLATION OF DIFFUSOR.•MODIFICATION OF STRUCTURE AT THE STEAM INLET END OF LPC TO FACILITATE INSTALLATION OF 1ST STAGE OF GUIDE BLADES.
.
A. Reference data for ORIGINAL brand new turbineReference Heat Balance Diagram TCD - 210 - 33 - 2, Regime No. 1
Rated parameters
Main steam Flow 662 T/h
Main Steam Pressure 130 ata
Main Steam Temperature 535 Deg C
Hot reheat Temperature 535 Deg C
Condenser Vacuum 0.1042 ata
TG Heatrate 2062 kCal/kWh
A. Reference data for ORIGINAL brand new turbineReference Heat Balance Diagram TCD - 210 - 33 - 2, Regime No. 1
Rated parameters
Main steam Flow 662 T/h
Main Steam Pressure 130 ata
Main Steam Temperature 535 Deg C
Hot reheat Temperature 535 Deg C
Condenser Vacuum 0.1042 ata
TG Heatrate 2062 kCal/kWh
B. Expected present performance level (210 MW Original rating)
Considering deterioration due to ageingdeterioration due to ageing as per ASME-PTC-6Report 1985•Expected Power output
with 662 T/h main steam flow
and rated parameters 202.4 MW
•Expected TG Heatrate with 662 T/h main steam flow
and rated parameters 2164 kCal/kWh
B. Expected present performance level (210 MW Original rating)
Considering deterioration due to ageingdeterioration due to ageing as per ASME-PTC-6Report 1985•Expected Power output
with 662 T/h main steam flow
and rated parameters 202.4 MW
•Expected TG Heatrate with 662 T/h main steam flow
and rated parameters 2164 kCal/kWh
BRAND NEW ST
EXPECTED PRESENT DETERIORATED CONDITION
UPGRADED HPT
UPGRADED LPT
UPGRADED HPT & LPT
OUTPUT (MW)
210 202.4 211 212.5 214HEAT RATE (KCAL / KWH)
2062 2164 2077 2066 2047
ADDITIOAL GEN (MU)
NA NA 55.04 64.64 74.24
COMPARISONCOMPARISON
• INCREASE IN POWER OUTPUT : 10.1 MW• IMPROVEMENT IN HEATRATE : 102 KCAL / KWH (FROM EXISTING PERFORMANCE LEVEL OF THE SET
WITH RATED STEAM PARAMETERS & THROTTLE STEAM FLOW)
3.TECHNICAL PROPOSAL
FOR R & D OF 210 MW STEAM TURBINES (KW/U
DESIGN)
EXISTING DESIGN:
HP Turbine:•HP ROTOR : WITH MOVING BLADES OF T2 PROFILE
•INNER CASING: WITH STATIONARY BLADES OF T2 PROFILE
•INLET INSERTS: WITH 580X9 MM BUTTRESS THREADS
•EXHAUST ELBOWS: WITH SERRATED GASKET.
CROSS SECTIONAL VIEW OF 210 MW STEAM TURBINE
210 MW STEAM TURBINE (REACTION DESIGN SET-KWU)
HP TURBINE
RETROFITTING 210 MW REACTION TURBINE WITH IMPROVED BLADING
IMPROVEMENTS IN PROPOSED IN DESIGN:
HP MODULE:
1 INNER CASING & HP ROTOR WITH OPTIMISED HIGHLY EFFICIENT T4 PROFILE BLADING.
ADVANTAGE:INCREASED EFFICIENCY
2 MODIFIED HPT INLET INSERTS WITH BUTTRESS THREADS OF SIZE 580X20 MM IN HP OUTER CASING & BREECH NUTS.ADVANTAGE:EASE IN ASSEMBLY & DISMANTLING
3 MODIFIED HP EXHAUST ELBOWS WHICH HAVE U-RING IN PLACE OF SERRATED GASKET.ADVANTAGE:ENHANCED RELIABILITY
HP EXHAUST ELBOWS
Exhaust ElbowHP OUTER CASING
HP EXHAUST ELBOWS
HP EXHAUST ELBOWS
U-RING
SCOPE OF SUPPLY
FOR HP TURBINE:
•COMPLETELY ASSEMBLED HP MODULE WITH T4 PROFILE BLADING ALONGWITH MODIFIED HP INLET ASSEMBLY & HP EXHAUST ELBOWS.
210 MW STEAM TURBINE (REACTION DESIGN SET-KWU)
IP TURBINE
RETROFITTING 210 MW REACTION TURBINE WITH IMPROVED T4 PROFILE BLADING
ADVANTAGE:IMPROVED PERFORMANCE.
SCOPE OF SUPPLY (CONTD.)
FOR IP TURBINE:• IP INNER CASING & IP ROTOR•WITH T4 PROFILE BLADING.•A SET OF HPR-IPR & IPR-LPR COUPLING BOLTS.•NECESSARY KEYS ETC.
WORK REQUIRED TO BE DONE AT SITE:
[NOT INCLUDED IN THE SCOPE OF THIS TECHNICAL OFFER]• PERFORMANCE TESTING PRIOR & AFTER R & M.•OVERHAULING.•RLA STUDY.•COMPONENTS IDENTIFIED DURING OVERHAULING/ RLA STUDY WHICH NEED REPLACEMENT
WORK REQUIRED TO BE DONE AT SITE: (FOR HP Turbine)
•REMOVAL OF OLD HP MODULE FROM ITS POSITION AFTER
DISMANTLING OF HP INLET INSERTS AND HP EXHAUST ELBOWS.
•OLD HP INLET ASSEMBLY (INLET INSERTS WITH BREECH NUTS) & HP EXHAUST ELBOWS ARE TO BE CUT FROM MS PIPES & CRH PIPES RESPECTIVELY.• HP EXHAUST ELBOWS ARE TO BE WELDED WITH CRH STEAM PIPES.
•ASSEMBLY OF HP INLET INSERTS & HP EXHAUST ELBOWS TO BE COMPLETED
•INSTALLATION OF NEW IMPROVISED HPT MODULE IN POSITION,
CENTERING & ALIGNMENT.
•WELDING OF HP INLET ASSEMBLY OF NEW MODULE WITH MAIN
STEAM PIPES
WORK REQUIRED TO BE DONE AT SITE:FOR IP Turbine
•REMOVAL OF OLD IP ROTOR & IP INNER CASING.
•INSTALLATION OF NEW IP INNER CASING & IP ROTOR WITH T4 PROFILE BLADING, ITS CENTERING & ALIGNMENT.•COMPLETION OF BOX UP OF IP Turbine.
CONDITION AFTER R & M OF HPT & IPT (UNDER RATED CONDITION):
RATED PARAMETERS:At 100% MCR condition
•MAIN STEAM FLOW : 641.3 T/HR•MS/ HRH STEAM TEMP:535/535 DEG C•MAIN STEAM PR: 150 ATA•BACK PR: 0.121 ATA
EXPECTED PRESENT PERFORMANCE:
CONSIDERING DETERIORATION DUE TO AGING AS PER ASME-PTC-6 REPORT 1985 FOR AVERAGE LIFE OF 20 YEARS, FOLLOWING WILL BE EXPECTED PERFORMANCE AT 641.3 T/HR MAIN STEAM FLOW AND RATED PARAMETERS OUTPUT: 202.3 MW HEAT RATE: 2067 KCAL/KWH
COMPARISON OF PERFORMANCE:
PAY BACK PERIOD1) REDUCTION IN OF PERIOD: 25 DAYSRESULTING TO ADDITIONAL POWER GENERATION FOR 25 DAYSYIELDING TO
GUAREENTED MINIMUM ADDITIONAL REVENUE:= 209MW x 1000 x 25DAYS x 24HRS x 0.80PLF x 2.00RS
=RS 20.06 CRORES
2)ADDITIONAL ANNUAL REVENUE GENERATION DUE TO INCREASE IN OUTPUT & IMPROVED HEAT RATE:
= 6.7 MW x 1000 x 8000 HRS x 0.80 PLF x RS 2.00 = RS 8.576 CRORES PER YEAR
HENCE, PAY BACK PERIOD < 3 YEARS
THANK YOU