PUBLIC WORKS TABLE OF CONTENTS FOR THE MANDATORY ...
Transcript of PUBLIC WORKS TABLE OF CONTENTS FOR THE MANDATORY ...
PUBLIC WORKS
TABLE OF CONTENTS
FOR THE
MANDATORY SPECIFICATIONS
SECTION 1000
1. Contractor Performance Evaluation
2. Public Works Record Drawings
3. Sanitary Sewer Manhole Inserts
4. Traffic Signal Employee’s Qualifications
Last Revised February 12, 2010
1
MANDATORY SPECIFICATIONS
FOR
CONTRACTOR PERFORMANCE EVALUATION
Section I – General Project Information – Must be completed in its entirety.
Name of Firm: Name of Prime: Name of Project Manager: Name of Superintendent(s):
Prime Phone: Project Manager Phone: Superintendent(s) Phone:
Project Manager Department/Title:
Date:
Contract Cost Including Change Order: $ Initial Award: Change Order(s) Amt: Final Contract Amt:
Project Title & Number:
Contract Start/End Dates:
Description of Project: [Design] [Construction] [ Other (specify _____________)]
Last Revised February 12, 2010
2
Section II – Project Performance Please rate this contractor’s performance in each of the following areas. If you need additional space,
attach additional sheets. If you rate the contractor below “satisfactory” in any area, please provide
detailed information to explain the rating assigned. You are not restricted to using the numerical
values (points) shown and may scale in between the points shown.
1. Quality of Workmanship/Project Management (0-25 points)
Rate the quality of this contractor’s workmanship. Were there quality-related or
workmanship problems? Was the contractor responsive to remedial work required? If so
or if not, provide specific examples.
Satisfactory ● ● ● 0 20 25
Score: ______ 2. Scheduling (0-15 points)
Rate this contractor’s performance with regard to adhering to contract schedules. Did this
contractor meet the contract schedule or the schedule as revised by approved change
orders? If not, was the delay attributable to this contractor? If so, provide specific
details/examples.
Satisfactory ● ● ● 0 12 15
Score: ______
Last Revised February 12, 2010
3
3. Woman and Minority Subcontractor Utilization (0-15 points)
Rate this contractor’s effort and success in utilizing woman and minority subcontractors.
Did the contractor submit a credible plan? Did the contractor meet or exceed the plan?
Satisfactory ● ● ● 0 10 15
Score: ______
4. Environmental Compliance (0-15 points)
Did the contractor comply with local, state and federal environmental standards,
requirements, laws, statutes, regulations or the law of nuisance in the performance of this
contract?
Satisfactory ● ● ● 0 12 15
Score: ______
Last Revised February 12, 2010
4
5. General Performance of On-Site Supervisory Personnel (0-15 points)
Rate the general performance of this contractor’s on-site supervisory personnel. Did they
have the knowledge, management skills and experience to run a project of this size and
scope? If not, provide specific examples.
Satisfactory ● ● ● 0 12 15
Score: ______
6. Subcontractor Management (0-10 points)
Rate this contractor’s ability, effort and success in managing and coordinating
subcontractors. Was this contractor able to effectively resolve problems? If not, provide
specific examples. NOTE: If no subcontractor(s) were utilized, then score this as N/A.
Satisfactory
● ● ● 0 7 10
Score: ______
7. Safety and Housekeeping Procedures (0-10 points)
Rate this contractor’s safety and housekeeping procedures on this project. Were there any
OSHA violations or serious safety accidents or notification of violations? If so, provide
specific examples.
Satisfactory ● ● ● 0 7 10
Last Revised February 12, 2010
5
Score: ______
8. Change Order(s) (0-10 points)
Were the contractor’s change orders reasonable and equitable? Did the contractor attempt
to unreasonably claim change orders or extras? If so, provide specific examples. NOTE: If
no change orders were made, then score this as N/A.
Satisfactory ● ● ● 0 7 10
Score: ______
9. Working Relationships (0-10 points)
Rate this contractor’s working relationships with other parties (i.e., awarding authority,
designer, subcontractors, government inspectors, the public, etc.). Did this contractor
interact with other parties in a professional manner? If not, give specific examples.
Satisfactory
● ● ● 0 7 10
Score: ______
Last Revised February 12, 2010
6
10. Documentation and Submittals (0-10 points)
Rate this contractor’s performance in completing and submitting required documentation
(i.e., change orders, electronic submittals, drawings, invoices, payrolls, workforce reports,
warranty, final as-builts, etc.). Did the contractor submit the required paperwork promptly
and in proper form? If not, give specific examples.
Satisfactory ● ● ● 0 7 10
Score: ______
Please add up all points of the 10 evaluated performance areas from the preceding pages
and enter the total score below.
Total Score: _____ Possible Max Score: __135_(If all areas rated) __
Satisfactory Score: ___75%
Contractors Score ____________ / ____________ % Overview/Explanation of Score:
Last Revised February 12, 2010
7
Section III: Legal and Administrative Proceedings Are you aware of any legal or administrative proceedings, invoked bonds, assessed damages,
liquidated damages, demands for direct payment, payment bond claims, contract failures, contract
terminations or penalties involving this contractor on this contract? What is the status of any
pending litigation? What was the final outcome of any completed litigation? What are the dollar
amounts of assessed damages or penalties?
Comments: ______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ Section IV: Evaluation Certification I certify that the information contained in this evaluation form represents, to the best of my
knowledge, a true analysis of this contractor’s performance record on this contract.
I also certify that I have no ties with this contractor either through a business or family relationship.
I have mailed a copy of this completed evaluation form to the contractor on ______________.
Enter Date
(Public Awarding Authorities must mail a copy of this completed evaluation form to the contractor.) Signatures: ________________________ ________________________________ ____________ Signature Name and Title of Inspector Date ________________________ ________________________________ ____________ Signature Name of Project Manager Date ________________________ ________________________________ ____________ Signature Division Manager Date ________________________ ________________________________ ____________ Signature Department Director Date ________________________ ________________________________ ____________ Signature Purchasing Agent or Designee Date
Last Revised April 11, 2019
1
MANDATORY SPECIFICATION
FOR
PUBLIC WORKS RECORD DRAWINGS
1.0 Scope:
The Contractor shall keep one (1) set of record drawings on site updated with all changes,
revisions, and change orders made during the construction of this project and/or
requested by the Owner. These record drawings are a specific contract requirement of
the Contractor and final payment will not be made until these drawings have been
submitted and accepted by the Owner.
2.0 Procedure:
All notations shall be neat and complete on the record drawings. The record drawings
will include, but not limited to, the record location(s) for changes, revisions, and change
orders made for the following items:
A. drainage basins, inlets, manholes, junction boxes, and their station, rim elevations,
and invert(s);
B. drainage pipes, culverts, paved flumes, and their size, type of material and invert(s);
C. endwalls, headwalls, flared end sections, and their station, type of material and
invert(s);
D. riprap, sheet pile, bulkheads, and their station and type of material;
E. traffic signal poles, pedestrian poles, school crossing caution lights, electrical
services, controller, traffic control equipment, junction boxes, splice boxes, signal and
controller foundations, and their station;
F. traffic and streetlight conduits, conductor cables, interconnect cables, and their size
and type of cables and conduits;
G. streetlight poles, junction boxes, signs, and the type of item and station;
H. pavement markers, pavement message markings, pavement line markings, and their
width and color for the markings;
I. watermains, water service lines, bends, tees, crosses, branches, reducers, plugs, casing
pipes, and their size and type of material;
J. water valves, boxes, detector check, vaults, manhole, and their station, valve box rim,
operating nut length and elevation;
K. fire hydrants, meters, and their station;
L. sanitary sewer gravity lines, laterals, sanitary sewer forcemain, bends, tees, crosses,
branches, reducers, plugs, casing pipe, and their size and type of material;
Last Revised April 11, 2019
2
M. forcemain valves, air vents, boxes, blow-off, forcemain manholes, cleanouts and
their station, valve box rim, operating nut length and elevation;
N. gravity sewer manholes, conflict manholes, cleanouts, and their station, rim
elevations, and invert(s);
O. commercial and residential entrances, brick and concrete pavers, curb ramps,
truncated domes, and their type of material and type of entrances;
P. top of curb, curb & gutter, sign island, and median elevations as (+) shown on the
plans and the type of curb and curb & gutter;
Q. guardrail, guardrail terminals, delineators, and their type of material and type of
guardrail and guardrail terminal;
R. bridge piles, bridge parapets, railings, and their size and type of material;
S. bridge approaches, bridge decking, bridge joints, abutments, and their type of
material;
T. retaining walls, foundations, soundwalls, fences, fence gates, and their type of
material, and height;
U. trees, bushes, landscape beds, and their type of plants;
In addition, the Contractor will show any field changes or change orders made by the
Owner.
At the conclusion of the project, the record drawings shall be presented to the Owner and
remain the property of the Owner. Prior to final payment, the Contractor must submit to
the Owner and have accepted these record drawings.
3.0 Measurement and Payment:
The cost of preparing the Record Drawings will not be measured separately and shall be
considered incidental to other items.
Last Revised November 3, 2008
1
MANDATORY SPECIFICATION
FOR
SANITARY SEWER MANHOLE INSERTS
520.02 – Materials - is amended as follows
(hh) Manholes – replace the following paragraph
1. Manhole frames and covers shall be roadway type with deep socket covers
and shall be fitted with dust covers and manhole inserts. Machine the frames
and covers to prevent rattling. Each cover shall be cast or embossed on it in
letters not less than 1-inch high “SEWER”. The frame and cover assembly
shall weigh at least 380 pounds. Manhole frames and covers shall be Capital
Foundry Model MH-C-21-Y and water tight manhole frames and covers shall
be MH-C-Y/WT or MH-C-21-JC-WT. All frames and covers shall receive a
coat of black asphalt paint prior to delivery. The dust cover shall be ⅝-inch
thick by 23 ½-inch diameter and furnished with two 1 ¼-inch round handles
at 180 degrees. All castings shall conform to the latest edition of ASTM A-
48 Class 30 and shall be uniform in quality.
Manholes inserts shall be manufactured from corrosion-proof stainless steel
suitable for atmospheres containing hydrogen sulfide and diluted sulfuric acid
and other gasses and liquids associated with sanitary sewer collection
systems. The insert shall be manufactured to fit the dust cover ring, upon
which it rests. A vent hole and/or a valve, or a self-sealing gas detection
pressure port, shall be provided. The hole or valve shall allow a maximum
release of 0.5 to 1.5 psi and 5 gallons of water per 24 hours and must be
unaffected by debris that may collect in the bottom of the insert.
a. The insert body shall be manufactured of 304 stainless steel with a
thickness of not less than 18 gauge. The insert body shall have a
straight-side design and be properly sized to fit into the manhole
frame ring, or dust cover ring, as applicable, for easy removal.
b. The outside rim of the insert shall be manufactured with a gasket to
provide a seal between the insert rim and the dust cover ring upon
which it rests. The gasket material shall be made of close-cell
neoprene and have a pressure sensitive adhesive on one side. The
gasket shall be installed by the manufacturer and must be compatible
with the insert material to form a long-lasting bond in wet or dry
conditions
c. The insert shall have a stainless steel “D” type spring-loaded handle,
with rubber coated grip, attached to the body of the insert with high-
Last Revised November 3, 2008
2
grade stainless steel continuous fillet type weld.
d. For new construction, the insert shall be “22-inch Model C-WH
Rainstopper” manufactured by Southwestern Packing & Seals, Inc.
or “22-inch Lockdry” manufactured by Barton Southern Company,
or approved equal.
520.06 – Method of Measurement – replace with the following paragraph
(x) Manhole Frames and Covers shall be measured for each frame and cover complete
with dust cover and manhole insert installed.
520.07 - Basis of Payment – replace with the following paragraph
(x) Standard Sanitary Sewer Manhole Frame and Cover (Size and type) shall be
paid for at the contract unit price for each frame and cover complete with dust cover
and manhole insert installed including adjustment to final grade.
Last Revised July 1, 2014
1
MANDATORY SPECIFICATION
FOR
TRAFFIC SIGNAL EMPLOYEE’S QUALIFICATIONS
703.01 – Description – add the following:
The Contractor and his subcontractors shall employ competent, qualified personnel skilled in the
electrical and non-electrical related traffic signal construction and modification work executed
under this contract. The employee qualification requirements shall include:
A. An International Municipal Signal Association (IMSA) certified Level II or higher
Traffic Signal Electrician to perform or be present on the job site to supervise the
following work:
1. All electrical wiring terminations, splices and required tests including but not
limited to: grounding, service entrances, loops, vehicle and pedestrian signal
heads and pedestrian pushbuttons, interconnect cables, video detection
equipment, illuminated signs and emergency preemption detectors.
2. All electrical field wiring terminations in the controller cabinet, and installation
and connection of the controller and auxiliary equipment in the controller
cabinet.
3. An operational test and review of all electrical wiring and signal operation prior
to the scheduled activation of the signal, and correction of any defects found
during the test. Unless otherwise approved by the Owner, such test shall be
conducted a minimum of 24 hours in advance of the scheduled activation of the
signal, and shall be conducted in the presence of the Owner’s designated
representative.
4. Present for the new or modified traffic signal scheduled activation.
B. An employee holding a VDOT Intermediate Work Zone Traffic Control Training and
Flagger Certification or an equivalent certification approved by the Owner shall be
present on the job site for all non-electrical and electric traffic signal related work in or
over travel lanes, including but not limited to loop detector installation, conduit
installation, foundation installation, and setting poles and mast arms. This employee
shall be responsible for establishing and maintaining the work site traffic controls related
to the signal work. The Contractor shall have the employee to be assigned to this work
trained and certified within 60 days of the execution of the Contract. The cost for
certification training and testing shall be at the expense of the Contractor.
Last Revised July 1, 2014
2
C. The Contractor will present the following information and proof of certification at the
Preconstruction Conference:
1. The identity of the each IMSA Level II or higher Traffic Signal Electrician and a
copy of his/her certification.
2. The identity of the employees either holding a VDOT Intermediate Work Zone
Traffic Control Training and Flagger Certification or an equivalent certification
with a copy of each employee’s certificate, or those employees who will receive
and complete certification training within 60 days of the execution of the
Contract.
703.04 – Measurement and Payment – add the following:
The cost for qualified traffic signal employee will not be measured separately and shall be
considered incidental to the traffic signal pay items.