PNM’s TTC/ATC Determination Document 1
PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)
Determination and Posting Of Total Transfer Capability (TTC) &
Available Transfer Capability (ATC)
Prepared By:
Transmission/Distribution Planning and Contracts Department
March 1, 2017
PNM’s TTC/ATC Determination Document 2
Table of Contents
1. Basic TTC, ATC, TRM, and CBM Determination Methodology ______________________ 4
1.1 Transmission Path Diagram _____________________________________________________ 5
_________________________________________________________________________________ 5
1.2 Northern New Mexico Total Transfer Capability (TTC) Summary Table __________________ 6
1.3 Southern New Mexico Total Transfer Capability (TTC) Summary Table __________________ 7
2. Northern New Mexico _____________________________________________________ 8
2.1 FOURCORNE/SJ345 - WNM/ABQ/NEA Path ________________________________________ 8
2.2 WNM/ABQ - FOURCORNE/SJ345 Path ____________________________________________ 9
2.3 STORLK115 - NEA/ABQ Path ___________________________________________________ 10
2.4 NEA - SJ345 Path ____________________________________________________________ 11
2.5 SJ345 – FOURCORNE345 Path __________________________________________________ 12
2.6 SJ345 to SHIPROCK345 Path ___________________________________________________ 14
2.7 SHIPROCK345 – FOURCORNE345 Path ___________________________________________ 16
2.8 FOURCORNE230 – GALLEGOS115 Path ___________________________________________ 18
2.9 SJ345 –MCKINLEY345 Path ____________________________________________________ 20
2.10 MCKINLEY345– SPRINGER345 Path ____________________________________________ 22
2.11 SPRINGER345-CORONADO500 Path ___________________________________________ 24
2.12 SJ345 – GREENLEE345 Path __________________________________________________ 26
2.13 PALOVERDE500 - East (WESTWING500, KYRENE500 & JOJOBA500) Path ______________ 28
2.14 WESTWING500 to PALOVERDE500 Direction ____________________________________ 29
2.15 WESTWING500 – WESTWING230 Path _________________________________________ 30
2.16 KYRENE500 – KYRENE230 Path _______________________________________________ 32
2.17 FOURCORN345 - FOURCORN230 Path __________________________________________ 34
2.18 SJ345 to HOGBACK -Path ____________________________________________________ 36
2.19 REEVES - WNM/ABQ Path ___________________________________________________ 38
2.20 DELTA - WNM/ABQ Path ____________________________________________________ 39
2.21 VEF - ABQ Path ____________________________________________________________ 40
2.22 BW345 – BW230 Path ______________________________________________________ 41
2.23 TAIBAN – BW345 Path ______________________________________________________ 43
2.24 TAIBAN – GUADALUPE Path _________________________________________________ 45
2.25 GUADALUPE-ABQ Path _____________________________________________________ 47
2.26 WILLARD115-ABQ Path _____________________________________________________ 49
PNM’s TTC/ATC Determination Document 3
2.27 RED MESA115- FOURCORNE Path _____________________________________________ 50
2.28 LALUZ-ABQ Path ___________________________________________________________ 50
3. Southern New Mexico ____________________________________________________ 51
3.1 HIDALGO345 – HIDALGO115 Path _______________________________________________ 51
3.2 LORDSBURG115 – HIDALGO115 Path ____________________________________________ 53
3.3 EDDY230 – AMRAD345 Path ___________________________________________________ 55
3.4 AMRAD115 – ALAMOGORDO 115 Path __________________________________________ 57
3.5 GREENLEE345 – HIDALGO345 Path ______________________________________________ 59
3.6 HIDALGO345 – LUNA345 Path __________________________________________________ 61
3.7 LUNA345 – LUNA115 Path _____________________________________________________ 63
3.8 LUNA115 – MIMBRES115 Path _________________________________________________ 65
3.9 MIMBRES115 – LASCRCS115 Path _______________________________________________ 67
PNM’s TTC/ATC Determination Document 4
1. Basic TTC, ATC, TRM, and CBM Determination Methodology
PNM’s methodology for determining TTC and ATC values is in the Public Service Company of New Mexico Available Transfer Capability Implementation Document (ATCID). This document is posted on the PNM OASIS site. PNM’s methodology for determining TRM values is in the Public Service Company of New Mexico Transmission Reliability Margin Implementation Document (TRMID). This document is posted on the PNM OASIS site. PNM does not maintain CBM.
PNM’s TTC/ATC Determination Document 5
1.1 Transmission Path Diagram
WESTWING500
CORONAD500
PALOVERDE500
JOJOBA500
SRP
APS
GREENLEE345
SPRINGER345
TEP
HIDALGO115
MD#1
EDDYCOUNTY
345
ALAMOGORDO115
HOLLYWOOD115
EPE
AMRAD345 EPE
SPS
PNM
Southern New Mexico
GALLEGOS11
5
VAL115
NEA
WNM BW230
WAPA
PNM
Northern New
Mexico NNMI
NEA
ABQ POR/POD
BA 115 WM115 WM345
NEA POR/POD
ETA115
NORTON115 OJO345
FOURCORNE POR/POD
FOURCORNE345 FOURCORNE230
EPE POR/POD
115 KV COMMON BUS
PICHACHO/DONA ANA/LAS CRUCES
WESTWING230
KYRENE230
AMRAD115
T
A
I
B
A
N
G
U
A
D
A
L
U
P
E
B
W
3
4
5
WNM POR/POD
AMB230
YAH-TA-HEY115
REEVES115
LORDSBURG115
MCKINLEY345
SJ345
DELTA
FOURCORNE
KYRENE500
TURQUOISE115
MIMBRES115
HIDALGO345 LUNA345
ABQ
LUNA115
SHIPROCK345
LALUZ VEF
REDMESAA115
R
E
D
M
E
S
A
1
1
5
PNM’s TTC/ATC Determination Document 6
1.2 Northern New Mexico Total Transfer Capability (TTC) Summary Table
Path
Reference Direction
Reverse Direction
MW MW
FOURCORNE/SJ345 – WNM/ABQ/NEA Variable* NA
WNM/ABQ – FOURCORNE/SJ345 Variable* NA
STORLK115 – NEA/ABQ 33 NA
NEA – SJ345 203 NA
SJ345 – FOURCORNE345 229 299
SJ345 – SHIPROCK345 269 269
SHIPROCK345 – FOURCORNE345 300 300
FOURCORNE230 – GALLEGOS115 100 100
SJ345 – MCKINLEY345 200 150
MCKINLEY345 – SPRINGER345 100 100
SPRINGER345 – CORONADO500 100 100
SJ345 – GREENLEE345 50 50
PALOVERDE500 –EAST (WESTWING500, KYRENE500 & JOJOBA500) 669 NA
WESTWING500 – PALOVERDE500 106 NA
WESTWING500 – WESTWING230 182 182
KYRENE500 – KYRENE230 298 298
FOURCORN345 – FOURCORN230 157 157
SJ345 – HOGBACK 200 200
REEVES – WNM/ABQ 157 NA
DELTA – WNM/ABQ 149 NA
VEF – ABQ 158 NA
BW345 – BW230 Variable* Variable*
TAIBAN – BW345 200 372
TAIBAN – GUADALUPE 572 200
GUADALUPE345 – ABQ 662 201
WILLARD115 – ABQ 137 NA
REDMESA115 – FOURCORNE 102 NA
LALUZ–ABQ 42 NA
*Variable refers to the dynamic nature of this path’s TTC due to seasonal or system configuration parameters including flows held by the Arroyo and Gladstone Phase-Shifting Transformers, the Blackwater AC/DC/AC 200 MW converter flow and generation resources.
PNM’s TTC/ATC Determination Document 7
1.3 Southern New Mexico Total Transfer Capability (TTC) Summary Table
Path
Reference Direction
Reverse Direction
MW MW
HIDALGO345 – HIDALGO115 448 448
LORDSBURG115 – HIDALGO115 80 80
EDDY230 – AMRAD345 67 67
AMRAD115 – ALAMOGORDO115 91 91
GREENLEE345 – HIDALGO345 160 300
HIDALGO345 - LUNA345 214 214
LUNA345 – LUNA115 162 162
LUNA115 – MIMBRES115 200 200
MIMBRES115 – LASCRCS115 133 133
PNM’s TTC/ATC Determination Document 8
2. Northern New Mexico
2.1 FOURCORNE/SJ345 - WNM/ABQ/NEA Path
Points of Receipt: Four Corners 230 kV Bus
Four Corners 345 kV Bus McKinley 345 kV Bus San Juan 345 kV Bus
Points of Delivery: Ambrosia 230 kV Bus
West Mesa 345 kV Bus Yah-Ta-Hey 115 kV Bus Ojo 345 kV Bus ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus) Jicarilla 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = Variable (1)
Existing Transmission Commitments Native Load Commitment / NLF
Network Customer Commitment to City of Gallup / NITSF
Network Customer Commitment to Kirtland Air Force Base (KAFB ) / NITSF
Network Customer Commitment to Los Alamos County / NITSF
Network Customer Commitment to Tri-State / NITSF
Network Customer Commitment to NTUA / NTISF
Network Customer Commitment to Jicarilla / NTISF
Network Customer Commitment to Kit Carson Electric Cooperative/ NTISF
247 MW Grandfathered Commitment to WAPA / GFF
20 MW Grandfathered Commitment to EPE / GFF
104 MW Point to Point Commitment to EPE / PTPPF
TRM
(1) Variable refers to the dynamic nature of this path’s TTC due to seasonal or system configuration parameters including capacitor, reactors, and generation resources.
PNM’s TTC/ATC Determination Document 9
2.2 WNM/ABQ - FOURCORNE/SJ345 Path
Points of Receipt: Ambrosia 230 kV Bus West Mesa 345 kV Bus Yah-Ta-Hey 115 kV Bus ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)
Points of Delivery: Four Corners 230 kV Bus Four Corners 345 kV Bus McKinley 345 kV Bus San Juan 345 kV Bus
TTC Determination
The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID).
TTC = Variable (1)
Existing Transmission Commitments
15 MW Point to Point Commitment to Aragonne Wind, LLC /PTPF
25 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF
50 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF
100 MW Point to Point Commitment to High Lonesome Mesa, LLC/ PTPF
75 MW Point to Point Commitment to Grady Wind Energy Center, LLC (2)/ PTPF
130 MW Point to Point Commitment to Broadview Energy KW, LLC (3)/PTPF
42 MW Point to Point Commitment to Broadview Energy JN, LLC (4)/PTPF
125 MW Point to Point Commitment to Broadview Energy JN, LLC (5)/PTPF
(2) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to January 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC. (3)This commitment becomes effective on May 1, 2017. (4) This commitment becomes effective on May 1, 2017. (5) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to May 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC.
PNM’s TTC/ATC Determination Document 10
2.3 STORLK115 - NEA/ABQ Path
STORLK115 to NEA/ABQ Direction Points of Receipt: Storrie Lake 115 kV Bus Points of Delivery: Ojo 345 kV Bus Norton 115 kV Bus
West Mesa 345 kV Bus ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 33 MW
Existing Transmission Commitments None
NEA/ABQ to STORLK115 Direction The path is not rated in this direction.
PNM’s TTC/ATC Determination Document 11
2.4 NEA - SJ345 Path
NEA - SJ345 Direction Points of Receipt: Ojo 345 kV Bus Norton 115 kV Bus Points of Delivery: San Juan 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 203 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 12
2.5 SJ345 – FOURCORNE345 Path
SJ345 to FOURCORNE345 Direction Points of Receipt: San Juan 345 kV Bus Points of Delivery: Four Corners 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 299 MW
Existing Transmission Commitments
50 MW Grandfathered Commitment to Anaheim / GFF
36 MW Grandfathered Commitment to UAMPS / GFF
PNM’s TTC/ATC Determination Document 13
FOURCORNE345 to SJ345 Direction Points of Receipt: Four Corners 345 kV Bus Points of Delivery: San Juan 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 299 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 14
2.6 SJ345 to SHIPROCK345 Path
SJ345 to SHIPROCK345 Direction Point of Receipt: San Juan 345 kV Bus Point of Delivery: Shiprock 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 269 MW
Existing Transmission Commitments
43 MW Grandfathered Commitment to City of Farmington / GFF
PNM’s TTC/ATC Determination Document 15
SHIPROCK345 TO SJ345 Direction Point of Receipt: Shiprock 345 kV Bus Point of Delivery: San Juan 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 269 MW
Existing Transmission Commitments
68 MW Network Customer Commitment to NUA for New Mexico Load / NITSF
PNM’s TTC/ATC Determination Document 16
2.7 SHIPROCK345 – FOURCORNE345 Path
SHIPROCK345 to FOURCORNE345 Direction Points of Receipt: Shiprock 345 kV Bus Points of Delivery: Four Corners 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 300 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 17
FOURCORNE345 to SHIPROCK345 Direction Points of Receipt: Four Corners 345 kV Bus Points of Delivery: Shiprock 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 300 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 18
2.8 FOURCORNE230 – GALLEGOS115 Path
FOUCORNE230 to GALLEGOS115 Direction Points of Receipt: Four Corners 230 kV Bus Points of Delivery: Gallegos 115 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW
Existing Transmission Commitments
75 MW Grandfathered Commitment to NAPI / GFF
PNM’s TTC/ATC Determination Document 19
GALLEGOS115 to FOURCORNE230 Direction Points of Receipt: Gallegos 115 kV Bus Points of Delivery: Four Corners 230 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW
Existing Transmission Commitments
75 MW Grandfathered Commitment to NAPI / GFF
PNM’s TTC/ATC Determination Document 20
2.9 SJ345 –MCKINLEY345 Path
SJ345 to MCKINLEY345 Direction Points of Receipt: San Juan 345 kV Bus Points of Delivery: McKinley 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW
Existing Transmission Commitments
162 MW Native Load Commitment at McKinley / NLF
38 MW Network Customer Commitment / NITSF
PNM’s TTC/ATC Determination Document 21
MCKINLEY345 to SJ345 Direction Points of Receipt: McKinley 345 kV Bus Points of Delivery: San Juan 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 150 MW
Existing Transmission Commitments
94 MW Native Load Commitment for southern New Mexico generation / NLF
PNM’s TTC/ATC Determination Document 22
2.10 MCKINLEY345– SPRINGER345 Path
MCKINLEY345 to SPRINGER 345 Direction Points of Receipt: McKinley 345 kV Bus Points of Delivery: Springerville 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW
Existing Transmission Commitments
38 MW Network Customer Commitment / NITSF
PNM’s TTC/ATC Determination Document 23
SPRINGER345 to MCKINLEY345 Direction Points of Receipt: Springerville 345 kV Bus Points of Delivery: San Juan 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW
Existing Transmission Commitments
94 MW Native Load Commitment for southern New Mexico generation / NLF
PNM’s TTC/ATC Determination Document 24
2.11 SPRINGER345-CORONADO500 Path
SPRINGER345-CORONADO500 Direction Points of Receipt: Springerville 345 kV Bus Points of Delivery: Coronado 500 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 25
CORONADO500- SPRINGER345 Direction Points of Receipt: Coronado 500 kV Bus Points of Delivery: Springerville 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 100 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 26
2.12 SJ345 – GREENLEE345 Path
SJ345 to GREENLEE345 Direction Points of Receipt: San Juan 345 kV Bus Points of Delivery: Greenlee 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 50 MW
Existing Transmission Commitments
50 MW Native Load Commitment / NLF
PNM’s TTC/ATC Determination Document 27
GREENLEE345 to SJ345 Direction Points of Receipt: Greenlee 345 kV Bus Points of Delivery: San Juan 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 50 MW
Existing Transmission Commitments
50 MW Native Load Commitment for southern New Mexico generation resources / NLF
PNM’s TTC/ATC Determination Document 28
2.13 PALOVERDE500 - East (WESTWING500, KYRENE500 & JOJOBA500) Path
PALOVERDE500 to WESTWING500, KYRENE500 & JOJOBA500 Direction Points of Receipt: Palo Verde 500 kV Bus Points of Delivery: Westwing 500 kV Bus
Kyrene 500 kV Bus Jojoba 500 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 669 MW
Existing Transmission Commitments
274 MW Native Load Commitment for Palo Verde Generation / NLF 48 MW Native Load Commitment for Palo Verde Generation (6) / NLF
87 MW Native Load Commitment for Palo Verde Generation (7) / NLF
(6) Start date January 1, 2018 (7) Start date January 1, 2018
PNM’s TTC/ATC Determination Document 29
2.14 WESTWING500 to PALOVERDE500 Direction
WESTWING500 to PALOVERDE500 Direction Points of Receipt: West Wing 500 kV Bus Points of Delivery: Palo Verde 500 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 106 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 30
2.15 WESTWING500 – WESTWING230 Path
WESTWING500 to WESTWING230 Direction Points of Receipt: West Wing 500 kV Bus Points of Delivery: West Wing 230 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 182 MW
Existing Transmission Commitments
134 MW Native Load Commitment for WAPA Deliveries of Palo Verde Generation / NLF 48 MW Native Load Commitment for Palo Verde Generation (8) / NLF
(8 ) Starting 01/01/2016
PNM’s TTC/ATC Determination Document 31
WESTWING 230 to WESTWING 500 Direction Points of Receipt: West Wing 230 kV Bus Points of Delivery: West Wing 500 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 182 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 32
2.16 KYRENE500 – KYRENE230 Path
KYRENE 500 to KYRENE230 Direction Points of Receipt: Kyrene 500 kV Bus Points of Delivery: Kyrene 230 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 298 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 33
KYRENE230 to KYRENE500 Direction Points of Receipt: Kyrene 230 kV Bus Points of Delivery: Kyrene 500 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 215 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 34
2.17 FOURCORN345 - FOURCORN230 Path
FOURCORN345 to FOURCORN230 Direction Points of Receipt: Four Corners 345 kV Bus Points of Delivery: Four Corners 230 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 157 MW
Existing Transmission Commitments
157 MW Native Load Commitment / NLF
PNM’s TTC/ATC Determination Document 35
FOURCORN230 to FOURCORN345 Direction Points of Receipt: Four Corners 230 kV Bus Points of Delivery: Four Corners 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 157 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 36
2.18 SJ345 to HOGBACK -Path
SJ345 to HOGBACK Direction Point of Receipt: San Juan 345 kV Bus Point of Delivery: Hogback 230 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW
Existing Transmission Commitments
43 MW Grandfathered Commitment to City of Farmington / GFF
157 MW Point to Point Commitment to the City of Farmington / PTPF
PNM’s TTC/ATC Determination Document 37
HOGBACK to SJ345 Direction Point of Receipt: Hogback 230 kV Bus Point of Delivery: San Juan 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW
Existing Transmission Commitments
200 MW Point to Point Commitment to the City of Farmington / PTPF
PNM’s TTC/ATC Determination Document 38
2.19 REEVES - WNM/ABQ Path
REEVES to WNM/ABQ Direction Points of Receipt: Reeves 115 kV Bus Points of Delivery: West Mesa 345 kV Bus ABQ (Albuquerque Area: BA 345 kV, BA 115 kV, West Mesa 115 kV)
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 157 MW
Existing Transmission Commitments
157 Native Load Commitment for Reeves Generation / NLF
WNM/ABQ to REEVES Direction The path is not rated in this direction.
PNM’s TTC/ATC Determination Document 39
2.20 DELTA - WNM/ABQ Path
DELTA to WNM/ABQ Direction Points of Receipt: Person 115 kV Bus Points of Delivery: West Mesa 345 kV Bus
ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 149 MW
Existing Transmission Commitments
149 MW Native Load Commitment for Delta Generation / NLF
WNM/ABQ to DELTA Direction The path is not rated in this direction.
PNM’s TTC/ATC Determination Document 40
2.21 VEF - ABQ Path
VEF to ABQ Direction Points of Receipt: VEF (Tome 115 kV Bus) Points of Delivery: ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 158 MW
Existing Transmission Commitments
158 MW Native Load Commitment for VEF Generation / NLF
ABQ-VEF Direction The path is not rated in this direction.
PNM’s TTC/ATC Determination Document 41
2.22 BW345 – BW230 Path
TAIBAN to BW230 Direction Points of Receipt: Blackwater 345 kV Bus Points of Delivery: Blackwater 230 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = Variable(9): Minimum of 15 MW, Maximum of 200 MW
Existing Transmission Commitments
11 MW Grandfathered Commitment to Eastern Coop projected load / GFF
9 The Blackwater converter capacity on this path is determined by available short circuit capacity at the Blackwater 345 kV bus. Starting May 1, 2017, this short circuit capacity is shared with the Broadview wind farm and available short circuit capacity is dependent on the Broadview wind generation level.
PNM’s TTC/ATC Determination Document 42
BW230 to BW345 Direction Points of Receipt: Blackwater 230 kV Bus Points of Delivery: Blackwater 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = Variable(10): Minimum of 15 MW, Maximum of 200 MW
Existing Transmission Commitments - 125 MW Point to Point Commitment to Broadview Energy JN, LLC (11) / PTPF
- 25 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF
- 50 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF
10 The Blackwater converter capacity on this path is determined by available short circuit capacity at the Blackwater 345 kV bus. Starting May 1, 2017, this short circuit capacity is shared with the Broadview wind farm and available short circuit capacity is dependent on the Broadview wind generation level. (11)The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to May 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC.
PNM’s TTC/ATC Determination Document 43
2.23 TAIBAN – BW345 Path
TAIBAN to BW345 Direction Points of Receipt: Taiban Mesa 345 kV Bus Points of Delivery: Blackwater 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW
Existing Transmission Commitments
11 MW Grandfathered Commitment to Eastern Coop projected load / GFF
PNM’s TTC/ATC Determination Document 44
BW345 to TAIBAN Direction Points of Receipt: Blackwater 345 kV Bus Points of Delivery: Taiban Mesa 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 372 MW
Existing Transmission Commitments - 125 MW Point to Point Commitment to Broadview Energy JN, LLC (12) / PTPF
- 130 MW Point to Point Commitment to Broadview Energy KW, LLC (13) / PTPF
- 42 MW Point to Point Commitment to Broadview Energy JN, LLC (14)/ PTPF
- 25 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF
- 50 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF
(12) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to May 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC. (13) This commitment becomes effective on May 1, 2017. (14) This commitment becomes effective on May 1, 2017.
PNM’s TTC/ATC Determination Document 45
2.24 TAIBAN – GUADALUPE Path
TAIBAN to GUADALUPE Direction Points of Receipt: Taiban Mesa 345 kV Bus Points of Delivery: Guadalupe 345 kV
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 572 MW
Existing Transmission Commitments
- 200 MW Native Load Commitment for Contracted Purchase from FPLE (Taiban Mesa) / NLF - 125 MW Point to Point Commitment to Broadview Energy JN, LLC (15) / PTPF - 42 MW Point to Point Commitment to Broadview Energy JN, LLC (16)/ PTPF - 130 MW Point to Point Commitment to Broadview Energy KW, LLC (17) / PTPF - 25 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF - 50 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF
(15) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to May 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC. (16) This commitment becomes effective on May 1, 2017. (17) This commitment becomes effective on May 1, 2017.
PNM’s TTC/ATC Determination Document 46
GUADALUPE to TAIBAN Direction Points of Receipt: Guadalupe 345 kV Bus Points of Delivery: Taiban 345 kV
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW
Existing Transmission Commitments
11 MW Grandfathered Commitment to Eastern Coop projected load / GFF
PNM’s TTC/ATC Determination Document 47
2.25 GUADALUPE-ABQ Path
GUADALUPE to ABQ Direction Points of Receipt: Guadalupe 345 kV Bus Points of Delivery: West Mesa 345 kV Bus
ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 662 MW
Existing Transmission Commitments
200 MW Native Load Commitment for Contracted Purchase from FPLE (Taiban Mesa) / NLF
75 MW Point to Point Commitment to Grady Wind Energy Center, LLC(18)/PTPF
15 MW Point to Point Commitment to Aragonne Wind, LLC /PTPF
25 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF
50 MW Point to Point Commitment to Aragonne Wind, LLC / PTPF
130 MW Point to Point commitment to Broadview Energy KW, LLC (19) / PTPF
42 MW Point to Point Commitment to Broadview Energy JN, LLC (20)/ PTPF
125 MW Point to Point Commitment to Broadview Energy JN, LLC (21) / PTPF
(18) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to January 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC. (19) This commitment becomes effective on May 1, 2017. (20) This commitment becomes effective on May 1, 2017. (21) The customer has elected to invoke Section 17.7 (“Extension for Commencement of Service”) of the Tariff, wherein they have extended the service commencement date to May 1, 2017. PNM has reposted the ATC and can grant requests by other eligible customers for daily, weekly, and monthly firm transmission service using this ATC.
PNM’s TTC/ATC Determination Document 48
ABQ to GUADALUPE Direction Points of Receipt: West Mesa 345 kV Bus
ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)
Points of Delivery: Guadalupe 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 212 MW
Existing Transmission Commitments
11 MW Commitment to Eastern Coop projected load / GFF
PNM’s TTC/ATC Determination Document 49
2.26 WILLARD115-ABQ Path
WILLARD115- ABQ Direction Points of Receipt: Willard 115 kV Bus Points of Delivery: West Mesa 345 kV Bus
ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 137 MW
Existing Transmission Commitments
90 MW Point to Point Commitment to High Lonesome Mesa, LLC/ PTPF
10 MW Point to Point Commitment to High Lonesome Mesa, LLC/ PTPF
ABQ-WILLARD115 Direction The path is not rated in this direction.
PNM’s TTC/ATC Determination Document 50
2.27 RED MESA115- FOURCORNE Path
REDMESA to FOURCORNE Direction Points of Receipt: Red Mesa 115 kV Bus Points of Delivery: Four Corners 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 102 MW
Existing Transmission Commitments None
FOURCORNE to REDMESA Direction The path is not rated in this direction.
2.28 LALUZ-ABQ Path
LALUZ to ABQ Direction Points of Receipt: La Luz 115 kV Bus Points of Delivery: West Mesa 345 kV Bus ABQ (Albuquerque Area: BA 345 kV Bus, BA 115 kV Bus, West Mesa 115 kV Bus)
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 42 MW
Existing Transmission Commitments None
ABQ to LALUZ Direction The path is not rated in this direction.
PNM’s TTC/ATC Determination Document 51
3. Southern New Mexico
3.1 HIDALGO345 – HIDALGO115 Path
HIDALGO 345 to HIDALGO 115 Direction Points of Receipt: Hidalgo 345 kV Bus Points of Delivery: Hidalgo 115 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 448 MW
Existing Transmission Commitments
34 MW Native Load Commitment / NLF
96 MW Existing Commitment for Freeport McMoRanLoad / NLF
PNM’s TTC/ATC Determination Document 52
HIDALGO115 to HIDALGO345 Direction Points of Receipt: Hidalgo 115 kV Bus Points of Delivery: Hidalgo 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 448 MW
Existing Transmission Commitments
50 MW Native Load Commitment for Supplying Native Load From Southern New Mexico Generation Resources / NLF
54 MW Network Customer Commitment to Tri-State for Pyramid Generation / NITSF
60 MW Point to Point Commitment to Tri-State for Pyramid Generation / PTPF
PNM’s TTC/ATC Determination Document 53
3.2 LORDSBURG115 – HIDALGO115 Path
LORDSBURG115 to HIDALGO115 Direction Points of Receipt: Lordsburg 115 kV Bus Points of Delivery: Hidalgo 115 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 80 MW
Existing Transmission Commitments
80 MW Native Load Commitment/ NLF
PNM’s TTC/ATC Determination Document 54
HIDALGO115 to LORDSBURG115 Direction Points of Receipt: Hidalgo 115 kV Bus Points of Delivery: Lordsburg 115 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 80 MW
Existing Transmission Commitments
11 MW Native Load Commitment / NLF
PNM’s TTC/ATC Determination Document 55
3.3 EDDY230 – AMRAD345 Path
EDDY230 to AMRAD345 Direction Points of Receipt: Eddy County 230 kV Bus Points of Delivery: Amrad 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 67 MW
Existing Transmission Commitments None A technical investigation assessment was completed in 2006 on the Eddy County HVDC converter station to identify all components that could impact the reliability of the converter station due to age, condition, availability of spare parts, cost, or obsolesce. Based on this assessment major equipment components have reached the end of their respective useful life. In addition, more recently the converter station has not had a high availability track record which has raised concerns about the ongoing reliability of the station. Based on these facts, PNM will only be posting non-firm transmission service for this path.
PNM’s TTC/ATC Determination Document 56
AMRAD345 to EDDY230 Direction Points of Receipt: Amrad 345 kV Bus Points of Delivery: Eddy County 230 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 67 MW
Existing Transmission Commitments None A technical investigation assessment was completed in 2006 on the Eddy County HVDC converter station to identify all components that could impact the reliability of the converter station due to age, condition, availability of spare parts, cost, or obsolesce. Based on this assessment major equipment components have reached the end of their respective useful life. In addition, more recently the converter station has not had a high availability track record which has raised concerns about the ongoing reliability of the station. Based on these facts, PNM will only be posting non-firm transmission service for this path.
PNM’s TTC/ATC Determination Document 57
3.4 AMRAD115 – ALAMOGORDO 115 Path
AMRAD115 to ALAMOGORDO115 Direction Points of Receipt: Amrad 115 kV Points of Delivery: Alamogordo 115 kV
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 91 MW
Existing Transmission Commitments
91 MW Projected Native Load / NLF
PNM’s TTC/ATC Determination Document 58
ALAMOGORDO115 to AMRAD115 Direction Points of Receipt: Alamogordo 115 kV Points of Delivery: Amrad 115 kV
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 91 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 59
3.5 GREENLEE345 – HIDALGO345 Path
GREENLEE345 to HIDALGO345 Direction Points of Receipt: Greenlee 345 kV Bus Points of Delivery: Hidalgo 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 160 MW
Existing Transmission Commitments
64 MW Native Load Commitment / NLF
96 MW Existing Commitment for Freeport McMoRan Load / NLF
PNM’s TTC/ATC Determination Document 60
HIDALGO345 to GREENLEE345 Direction Points of Receipt: Hidalgo 345 kV Bus Points of Delivery: Greenlee 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 300 MW
Existing Transmission Commitments
50 MW PNM’s resource commitments supplying native load from southern New Mexico generation resources / NLF
60 MW Point to Point Commitment to Tri-State for Pyramid Generation / PTPF
PNM’s TTC/ATC Determination Document 61
3.6 HIDALGO345 – LUNA345 Path
HIDALGO345 to LUNA345 Direction Points of Receipt: Hidalgo 345 kV Bus Points of Delivery: Luna 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 214 MW
Existing Transmission Commitments
50 MW Native Load Commitment / NLF
54 MW Network Customer Commitment to Tri-State for Pyramid Generation / NITSF
PNM’s TTC/ATC Determination Document 62
LUNA345 to HIDALGO345 Direction Points of Receipt: Luna 345 kV Bus Points of Delivery: Hidalgo 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 214 MW
Existing Transmission Commitments
20 MW Native Load Commitment / NLF
PNM’s TTC/ATC Determination Document 63
3.7 LUNA345 – LUNA115 Path
LUNA345 to LUNA115 Direction Points of Receipt: Luna 345 kV Bus Points of Delivery: Luna 115 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 162 MW
Existing Transmission Commitments
54 MW Network Customer Commitment to Tri-State for Pyramid Generation / NTISF
108 MW Native Load Commitment / NLF
PNM’s TTC/ATC Determination Document 64
LUNA115 to LUNA345 Direction Points of Receipt: Luna 115 kV Bus Points of Delivery: Luna 345 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 162 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 65
3.8 LUNA115 – MIMBRES115 Path
LUNA115 to MIMBRES115 Direction Points of Receipt: Luna 115 kV Bus Points of Delivery: Mimbres 115 kV Bus Picacho 115 kV Bus Airport 115 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW
Existing Transmission Commitments
70 MW Native Load Commitment / NLF
54 MW Network Customer Commitment to Tri-State for Pyramid Generation / NITSF
PNM’s TTC/ATC Determination Document 66
MIMBRES115 to LUNA115 Direction Points of Receipt: Mimbres 115 kV Bus Picacho 115 kV Bus Airport 115 kV Bus Points of Delivery: Luna 115 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 200 MW
Existing Transmission Commitments None
PNM’s TTC/ATC Determination Document 67
3.9 MIMBRES115 – LASCRCS115 Path
MIMBRES115 to LASCRUCS115 Direction Points of Receipt: Mimbres 115 kV Bus Points of Delivery: Las Cruces 115 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 133 MW
Existing Transmission Commitments
43 MW Native Load Commitment / NLF
16 MW Network Customer Commitment to Tri-State for Pyramid Generation / NITSF
PNM’s TTC/ATC Determination Document 68
LASCRCS115 to MIMBRES115 Direction Points of Receipt: Las Cruces 115 kV Bus Points of Delivery: Mimbres 115 kV Bus
TTC Determination The TTC value was determined using the NERC Reliability Standard MOD-029 methodology and Public Service Company of New Mexico Available Transfer Capability Implementation Documents (ATCID). TTC = 133 MW
Existing Transmission Commitments None