Public-Private Partnership (PPP) Project Status (as of June 2012)

12
a. Project Name b. Description 1. TarlacPangasinanLa Union P 11.59 B ROW P 3,290 M Bidding was conducted November 20, 2007 Toll Expressway (TPLEX) $ 269.53 M. Subsidy P 2,907 M Notice of Award (NOA), was issued February 15, 2008 NOA was accepted by PIDC February 19, 2008 88.58 kilometer, 2lane expressway Notice to Proceed (NTP) to construct Section I July 26, 2010, from Tarlac City, Tarlac to Rosario, were issued to contractors corresponding to November 30, 2010, La Union (Phase I) sections with available RightofWay on January 13 & 24, 2011 Project Components: the following dates: • main expressway Six (6) contractors were awarded construction 2010 • 2 viaducts contract and mobilized at project site. • 8 interchanges Five (5) contractors have ongoing • 2 central toll plaza embankment works from selected borrow • 1 toll operations center building while one (1) contractor is undertaking • 12 bridges clearing and grubbing, verification survey • 63 underpasses of the horizontal & vertical control points & Phase II will be widening to 4 lanes when sampling/testing of embankment materials. Phase I capacity reaches 25,000 vehicles Overall Actual Accomplishment of Section I is June 2012 per day 83.04% Phase I schedule of completion (Tarlac May 2013 Rosales, Pangasinan) (Concessionaire) 2. Daang Hari – SLEx Link Project P 1.96 B ROW P 177.30 M Issuance of Notice of Award December 22, 2011 $ 45.58 M IC P 10.64 M Signing of the Toll Concession Agreement April 03, 2012 New Bridge P 70.50 M Design and Construction April 2012October 2013 Across SLEX Operation November 2013 Expansion of P 30.00 M Toll Plaza Project Status: Contingent P 50.00 M Liability for the Advance Works TOTAL P 338.44 M New 4 kilometer, 4lane paved toll road that will pass through the New Bilibid Prison reservation that will connect Bacoor, Cavite to the South Luzon Expressway (SLEX) thru Susana Heights. Support STATUS OF PPP PROJECTS AS OF 29 JUNE 2012 Processes/Activities Project Cost Total Concession Agreement was signed last 03 April 2012 by DPWH and Ayala Corporation, the Concessionaire of the project. Detailed Design for Segment 2 and Construction already commenced Timelines Government

Transcript of Public-Private Partnership (PPP) Project Status (as of June 2012)

Page 1: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description

1. Tarlac-­‐Pangasinan-­‐La  Union P 11.59 B • ROW P  3,290  M • Bidding  was  conducted     • November  20,  2007        Toll  Expressway  (TPLEX) $ 269.53 M. • Subsidy P  2,907  M • Notice  of  Award  (NOA),  was  issued   • February  15,  2008

• NOA  was  accepted  by  PIDC • February  19,  2008• 88.58  kilometer,  2-­‐lane  expressway • Notice  to  Proceed  (NTP)  to  construct  Section  I • July  26,  2010,    

 from  Tarlac  City,  Tarlac  to  Rosario,        were  issued  to  contractors  corresponding  to   November  30,  2010,  La  Union  (Phase  I)        sections  with  available  Right-­‐of-­‐Way  on   January  13  &  24,  2011  Project  Components:      the  following  dates:•  main  expressway • Six  (6)  contractors  were  awarded  construction   • 2010•  2  viaducts      contract  and  mobilized  at  project  site.  •  8  interchanges      Five  (5)  contractors  have  on-­‐going  •  2  central  toll  plaza      embankment  works  from  selected  borrow•  1  toll  operations  center  building        while  one  (1)  contractor  is  undertaking•  12  bridges        clearing  and  grubbing,  verification  survey•  63  underpasses          of  the  horizontal  &  vertical  control  points  &

• Phase  II  will  be  widening  to  4  lanes  when        sampling/testing  of  embankment  materials.Phase  I  capacity  reaches  25,000  vehicles • Overall  Actual  Accomplishment  of  Section  I  is • June  2012per  day 83.04%

• Phase  I  schedule  of  completion  (Tarlac-­‐ • May  2013Rosales,  Pangasinan)

  (Concessionaire)2. Daang  Hari  –  SLEx  Link  Project P 1.96 B • ROW P  177.30  M • Issuance  of  Notice  of  Award • December  22,  2011

$ 45.58 M • IC P      10.64  M • Signing  of  the  Toll  Concession  Agreement • April  03,  2012• • New  Bridge P      70.50  M • Design  and  Construction • April  2012-­‐October  2013

 Across  SLEX • Operation • November  2013• Expansion  of   P    30.00  M  Toll  Plaza Project  Status:

• Contingent P    50.00  MLiability  for  theAdvance  WorksTOTAL P  338.44  M

New  4  kilometer,  4-­‐lane  paved  toll  road  that  will  

pass  through  the  New  Bilibid  Prison  reservation  

that  will  connect  Bacoor,  Cavite  to  the  South  

Luzon  Expressway  (SLEX)  thru  Susana  Heights.

Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal

Concession  Agreement  was  signed  last  03  April  2012  by  DPWH  and  Ayala  Corporation,  the  Concessionaire  of  the  project.  Detailed  Design  for  Segment  2  and  Construction  already  commenced

TimelinesGovernment  

Page 2: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal TimelinesGovernment  

3. NLEX-­‐SLEX  Link  Connector P 24.51 B • ROW P  4,530  M • Resume  DPWH-­‐MPTDC  negotiations • 04  June  2012$ 570.00 M • Conclude  Negotiations  btween  DPWH  and   • 31  July  2012

• MPTDC  (8  weeks)• DPWH  endorsement  to  NEDA/ICC • 01  August  2012• Approval  by  NEDA/ICC  (15  days) • 02-­‐16  August  2012• Advertisement  for  Letter  of  Interest  (LOI)  for • 17  August  to  prequalification  and  bid  (21  days) 06  September  2012

• Preparation  and  Submision  of  Comparative • 07  September  2012  to• Mostly  elevated  structure Proposals  (120  days) 04  January  2013

• Evaluation  of  Comparative  Proposals  (21  days) • 07-­‐28  January  2013• Original  Proponent  to  match  the  best  proposal • 29  January-­‐Resolution  of  Award  (7  days) 04  February  2013

• Notice  of  Award  (including  compliance  of • 05  Feb  -­‐  06  March  2013conditions  and  requirements  by  winning  bidder  (30  days)

• Approval  of  Contract • 07  -­‐  11  March  2013• Issuance  of  Notice  to  Proceed • 12  March  2013• Detailed  Engineering  Design  (12  months) • 13Mar  2013-­‐13Mar  2014• Construction  (30  months) • 14  March  2014  -­‐

14  September  2016

Construction  of  a  13.4  km.  4-­‐lane  elevated  expressway  to  link  the  existing  NLEX  and  SLEX  passing  through  Metro  Manila  and  utilizing  the  existing  PNR  alignment  as  its  route.    

Page 3: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal TimelinesGovernment  

4. NAIA  Expressway P 15.52 B • ROW P  1,021.76  M • Approval  of  NEDA  Board   • May  30,  2012$ 360.93 M • IC P        113.89  M • Advertisement/Publication • June  30,  July  07,14,  2012

• Starts  from  Sales  Road  going  to  Andrews • Submission  of  Bids • November  2012Avenue,  Domestic  Road,  MIA  Road  and • Notice  of  Award • December  2012ends  at  Macapagal  Boulevard/PAGCOR • Approval  of  Contract • January  2013Entertainment  City • Start  of  Construction • January  2014

• Construction  Completion • January  2016• Total  Length:  7.15  kms.  including  ramps• No.  of  Lanes:  4-­‐lanes Project  Status:• Viaduct  Width:  20  meters      • Right-­‐of-­‐Way:  30  meters• On  Ramps:  6• Off  Ramps:  6

• Entertainment  City  Works• Total  Length:  2.22  kms.  at-­‐grade  road• No.  of  Lanes:  6-­‐8  lanes

PAGCOR  Locators/license  holders  are  willing  to  provide  Php  6.5  B  contribution  for  the  construction  of  the  project.  MOA  between  DPWH  and  PAGCOR  is  under  process.

Page 4: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal TimelinesGovernment  

5. CALA  (Cavite  Side) P 26.88 B • ROW P  5.67  B • Submission  to  NEDA • June  15,  2012$ 625.12 M • NEDA  Board  Approval • July  16,  2012

• • Issued  Bid  Documents • September  2012• Bid/Negotiate/Award • October  2012-­‐

March  2013• Final  Design/ROW  Acquisition • March  2013-­‐Aug.2014• Construction/Opening • April  2014-­‐Nov.2016

Project  Status:

6. CALA  (Laguna  Side) P 17.65 B • ROW   P  3.77  B • Selection  of  Detailed  Design  Consultant • January-­‐July  2013$ 410.46 M • Detailed  Design • August  2013-­‐July  2014

• • ROW  Acquisition • Jan.  2014-­‐Sept.  2015• Selection  of  Contractor • July  2014  -­‐  Sept.  2015• Construction   • Oct.  2015  -­‐  Sept.  2017• Selection  of  Concessionaire • May  2016  -­‐  July  2017• Operation  and  Maintenance • October  2017

Project  Status:Draft  Final  Report  already  completed.  For  submission  to  NEDA  ICC

Construction  of  a  28.9  km,  4-­‐lane  at  grade  highway  from  the  terminus  of  the  R-­‐1  Expressway  in  Kawit,  Cavite  to  Aguinaldo  Highway  at  Silang,  Cavite  and  Laguna

Construction  of  a    18.10  km,  4-­‐lane  at  grade  highway,  a  continuation  of  CALA  Expressway-­‐Cavite  side  Section  to  connect  with  South  Luzon  Expressway  (SLEX)  at  Sta.  Rosa,  Laguna  Province.  

Business  Case  Study  already  completed  while  Feasibility  Study  is  on-­‐going.  For  submission  to  NEDA  ICC.

 

Page 5: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal TimelinesGovernment  

7 C-­‐6  Extension P 26.95 B • ROW   P  4.17  B • Business  Case  Study • Jan.2012  -­‐  June  2012(Flood  Control  Dike  Expressway) $ 626.74 M • Feasibility  Study • Jan.-­‐December  2013   • Detailed  Design  and  Construction • 2014-­‐2016

•Project  Status:

8. Calamba-­‐Los  Baños  Toll  Expressway P 5.15 B • ROW   P  1.41  B • Business  Case  Study • Jan.2012  -­‐  June  2012$ 119.77 M • Feasibility  Study • Jan.-­‐December  2013

• • Detailed  Design  and  Construction • 2014-­‐2016

Project  Status:

Construction  of  a  43.6  km,  4-­‐lane  road  dike  from  the  coastal  area  of  Laguna  de  Bay  from  Taguig,  Rizal  to  Los  Baños,  Calamba.

Construction  of  a  4-­‐lane,  15.5  km  expressway  that  starts  at  SLEX  Extension  (Calamba  Exit  to  Sto.  Tomas)  traverses  along  Laguna  de  Bay  and  ends  up  connecting  a  national  road  at  Bay,  Laguna.

Consultancy  Services  for  the  Business  Case  Study  already  commenced  last  January  2012.  Consultation  with  various  stakeholders  is  on-­‐going.

Consultancy  Services  for  the  Business  Case  Study  already  commenced  last  January  2012.  Consultation  with  various  stakeholders  is  on-­‐going.

Page 6: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal TimelinesGovernment  

9. C-­‐6  Expressway  and  Global  Link   P 44.59 B • ROW P  3.99  B • Feasibility  Study  (FS)  completed     • January  2012(South  Section) $ 1,036.98 M • Supplemental  Study  to  re-­‐evaluate  Phase  I • June  -­‐  September  2012

(Sucat  to  Marcos  Highway)    • • Submission  to  NEDA • October  2012

• NEDA  review  and  approval • November  2012• Detailed  Design  and  Construction • 2013  -­‐  2016

Project  Status:• Supplemental  Study  to  re-­‐evaluate  Phase  I(Sucat  to  Marcos  Highway)  is  on-­‐going

L  =  59.5  kms.  (including  Global  City  AccessLink  Road  with  a  total  of  3  kms.)No.  of  lanes  =  4-­‐6

C-­‐6  Expressway  will  function  as  a  distributor  of  traffic  coming  from  the  North  Luzon  Expressway  (NLEX)    up  to  the  Metro  Rail  Transit  Line  7  (MRT7)  Terminal.  It  will  also  contribute  to  sound  urban  development  of  Rizal  and  Bulacan  Provinces.  It  starts  from  NLEx  intersection  at  Bocaue/Marilao  boundary  and  traverses  to  Sta.  Maria  and  terminates  at  the  municipality  of  San  Jose  del  Monte  in  the  province  of  Bulacan.    The  north  section  is  to  be  built  by  MRT-­‐7  Consortium.

 

Page 7: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal TimelinesGovernment  

10. Central  Luzon    Link  Expressway  (CLLEX), P 15.91 B • ROW P  580.76    M • Selection  of  Detailed  Design  Consultant • Feb.  -­‐  Sept.  2012  Phase  1 $ 370.05 M • Civil  Works P  14,454.33M • Detailed  Design • Oct.  2012  -­‐  Sept.    2013

and  Others • ROW  Acquisition • Mar.2013  -­‐  Aug.2014• • Consultancy P  712.01    M • Selection  of  C/S  Consultant • Jan.  -­‐  Aug.  2014

• Admin.  Cost P  165.33    M • Selection  of  Contractor • Sept.  2013  -­‐  Aug.  2014• Construction • Sept.  2014  -­‐  Dec.  2016

Total P  15,912.43M • Operation  and  Maintenance  proposed   • 2017    -­‐  onwards• This  will  support  development  of  regional      under  PPP  scheme

urban  centers  in  Central  Luzon  and  thePacific  Ocean  Coastal  Areas  in  order  to Project  Status:decrease  overconcentration  of  socio-­‐economic  activities  in  Metro  Manila

Construction  of  a  4-­‐lane  expressway  with  a  total  length  of  30.7  kilometers  to  decongest  traffic  at  Daang  Maharlika

Loan  Agreement  already  signed  last  March  2012  between  the  Philippine  Government  and  the  Government  of  Japan.  The  construction  of  this  project  will  be  financed  through  ODA  while  the  Operation  and  Maintenance  (O  &  M)  will  be  under  PPP.

CLEX  forms  an  important  lateral  (east-­‐west)  link  of  overall  High  Standard  Highway  (or  Expressway)  Network  within  the  200  km  radius  from  Metro  Manila.  It  diverges  from  SCTEx  at  2.5  km  north  of  Luisita  Interchange  and  traverses  flat  plain  of  Central  Luzon  in  the  east-­‐west  direction,  then  passes  Cabanatuan  City  and  ends  at  San  Jose  City  in  Region  III.  Phase  I  ends  at  Cabanatuan  City  and  Phase  II  at  San  Jose  City.

Page 8: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal TimelinesGovernment  

11. Kennon  O&M • Project  Status:• Procurement  for  the  consultancy  services • March  2012

• of  the  business  case  study  is  on-­‐going.• Shortlisting  of  Consultants  is  under  process. • August  2012

12 R7  Expressway P 23.98 B • • Procurement  for  the  consultancy  services • March  2012$ 557.67 M of  the  business  case  study  is  on-­‐going.

• • Shortlisting  of  Consultants  is  under  process. • August  2012

• Will  connect  Quezon  City  and  Manila  City  with  high  speed  transport  facility,  thus  decongest  traffic  of  at-­‐grade  road.  It  will  be  partially  elevated  and  partially  underground  expressway  with4  lanes  and  16.1  km  length.  

The  project  will  be  constructed  over  one  of  the  most  heavily  congested  corridors  in  Metro  Manila,  namely  Quezon  Avenue  and  Don  Mariano  Marcos  Avenue.

This  project  involves  upgrading  and  improvement  of  the  landslide  prone  sections  of  Kennon  Road  and  Marcos  Highway  and  operates  as  toll  roads.  Kennon  Road  has  a  length  of  33.69  kms.  while  Marcos  Highway  has  a  length  of  47.17  kms.  having  a  total  combined  length  of  80.86  kms.  These  roads  start  at  Rosario  and  Agoo,  La  Union,  respectively  and  both  ends  at  Baguio  City.

To  be  determined

the  conduct  of  the  study

the  conduct  of  the  studyTo  be  determined  during

To  be  determined  during

Page 9: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal TimelinesGovernment  

13. NLEX  East  Expressway P 15.77 B • • Procurement  for  the  consultancy  services • March  2012$ 366.74 M of  the  business  case  study  is  on-­‐going.

• • Shortlisting  of  Consultants  is  under  process. • August  2012

• Length:  6.8  km  (including  ramps)• No.  of  Lanes:  2  to  4

The  project  consists  of  Phase  I  and  Phase  II  and  will  form  an  important  transport  access  in  the  eastern  area  of  Region  III.  NLEX  East  Expressway  is  up  to  Cabanatuan  City  starting  from  the  end  point  of  La  Mesa  Parkway  and/or  junction  of  C-­‐6  in  San  Jose  del  Monte  via  Norzagaray,  Angat,  San  Ildefonso,  San  Miguel,  Gapan,  and  Sta.  Rosa  in  parallel  with  the  Pan  Philippine  Highway.  Bridges  will  be  required  for  the  project  to  cross  Angat  River,  Peñaranda  River  and  Pampanga  River.

the  conduct  of  the  studyTo  be  determined  during

Page 10: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal TimelinesGovernment  

14. Quirino  Highway • Project  Status:       •

to  be  determined

The  project  consists  of  the  improvement/rehabilitation  and  Operation  and  Maintenance  of  Quirino  Highway,  a  93.45  km.,  2  lanes  national  road  that  traverses  three  (3)  provinces,  namely  Quezon,  Camarines  Norte,  and  Camarines  Sur.  It  starts  at  the  junction  of  Pan  Philippine  Highway  in  Sipocot,  Camarines  Sur.

To  be  determined The  National  Economic  and  Development  Authority  

(NEDA)  has  already  confirmed  the  inclusion  of  the  project  in  the  Philippine  Public  Investment  Program  (PIP)  2011-­‐2016

Page 11: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal TimelinesGovernment  

15. PPP  Bridges • • Preparation  of  List  of  Candidate  Bridges • January-­‐February  2012• Preparation  of  Bidding  Documents • January-­‐February  2012

• • Preparation  of  Funding  for  Consultancy  Services • February  2012• Informal  consultation  with  private  sector • February  -­‐  March  2012• Site  inspection  for  validation  of  candidate  bridges • February  -­‐  March  2012• Procurement  of  Consultants  &  Contract  Admin. • February  -­‐  April  2012• Submission  of  Final  Draft  Report  (for  Batch  1) • August  2012• Completion  of  Final  Report  (for  Batch  1) • September  2012• Review  and  Approval  of  the  Project  by  NEDA • October  2012• Finalization  of  Transaction  Documents • November  2012• Invitation  to  Bid • December  2012• Pre-­‐qualification  Conference • January  2013• Submission  of  Pre-­‐qualification  documents • March  2013• Evaluation  of  Pre-­‐qualification  documents • March  2013• Preparation  of  bids(including  Pre-­‐bid  Conference) • April  -­‐  July  2013• Submission  and  Evaluation  of  Bids • August  2013• Award  and  Contract  Perfection • September  2013• Preparation  of  DED  and  Approval  by  DPWH • October  2013-­‐May  2014• Construction  Period • June  2014  -­‐  Dec.  2016• Payments • June  2015  -­‐  Dec.  2026

Project  Status:Contract  for  the  Consultancy  Services  forBusiness  Case  Study  is  being  processed  at  BOD

To  be  determined

to  be  determined

Given  that  this  is  the  first  bridge  project  under  the  PPP  framework,  the  DPWH  proposes  to  implement  a  pilot  test  in  Luzon.  In  connection  therewith,  the  Planning  Service  initially  recommended  139  selected  bridges  in  Luzon  for  replacement  and  new  construction.  By  tapping  private  sector  resources  and  skills  in  the  financing,  design,  and  construction  of  the  selected  various  types  of  bridges,  the  project  is  expected  to  improve,  and  provide  direct,  uninterrupted  access  to  and  between  outlying  barangays,  municipalities  and  cities,  thereby  facilitating  the  transport  of  goods  and  services  among  them.  The  project  will  also  lower  the  transport  costs  of  the  products.

Page 12: Public-Private Partnership (PPP) Project Status (as of June 2012)

a. Project  Nameb. Description Support

STATUS  OF  PPP  PROJECTSAS  OF  29  JUNE  2012

Processes/ActivitiesProject  CostTotal TimelinesGovernment  

16. School  Buildings P 10.04 B • Land • Submission  of  Pre-­‐qualification  documents • April  11,  2012$ 233.49 M • Pre-­‐bid  Conference • May  14,  2012

• • Submission  of  Technical  and  Financial  Proposals • July  18,  2012• Signing  of  Contract  Agreement • August  08,  2012• Issuance  of  Notice  to  Proceed • w/in  2  mos.after  signing  of  CA

• Construction  complete  deadline • August  14,  2013

• The project is to partially construct 9,630classrooms to fill-­‐up the 60,000 classroomsbacklog.

A  Finance-­‐Design-­‐Build  Scheme  is  being  studied  whereby  the  contractor  undertakes  the  financing,  design,  and  construction  of  a  package  of  classrooms  and  after  completion,  turns  it  over  to  DEPED  which  shall  pay  the  contractor,  and/or  financier,  its  total  investment  plus  a  reasonable  rate  of  return  on  an  agreed  schedule.