Site Technical Practice
MAJOR Pre-Startup Safety Review (PSSR) Checklist
FACILITY:
IVANHOE - ORION ENGINEERED CARBONS
MOC NUMBER:
MOC TITLE:
ItemQuestionGroup / NAInitials
PIPING
1Piping is routed and valved according to the P&ID.Construction
2Inspect valves, flanges and spec breaks to confirm proper pressure rating and compatibility.Construction
3Piping and equipment has been inspected for damage, debris, integrity, and anodesOperations
4All critical piping systems have hydro, pneumatic or non-destructive testing completed and QA documentation has been reviewed.Construction
5Relief systems, PSV's, PCV's, vent piping, flare stacks, and vent booms are installed per construction dwgs.Construction
6All permanent blinds are in place; all temporary blinds have been removed. The blind list has been reviewed and approved.Operations
7Flange installations have been inspected for proper bolting, gaskets, isolation kits, and restriction orifices.Construction
8All purging, flushing, draining, and pickling complete.Operations
9All drains and sewers have been inspected for plugs and covers.Operations
10Proper installation, operation and orientation of valves (process, instrumentation, utility...) have been ensured.Construction
11All filters, screens, and strainers (temporary or permanent) are properly located and installed.Construction
12Piping systems have been reviewed allowing for equipment/facility blowdown and isolationConstruction
13Vents have spark / detonation arrestors, where appropriate.Engineering
14The integrity of all thermowells and bull plugs have been inspected.Construction
15Exhaust lines / vents are properly located away from air intakes, air conditioners, fans, sources of ignition, etc.Construction
16All block valves on the relief systems have been locked or car sealed open and are in a functional stateConstruction
17Lock open and lock closed valves have been inspected and are properly secured in their intended position.Construction
18All block valves have been reviewed for normal position (norm. open or closed) and handle has full travel.Construction
19All fail safe valves have been reviewed for proper action (fail open, fail close, fail unchanged); and location.Construction
CIVIL
20Structural steel installed to engineering design specifications.Engineering
21Supports required meet design structural engineering standards.Engineering
MECHANICAL
22All equipment meets design specifications.Engineering
23Mechanical equipment has been checked for proper alignment, lubrication, and rotation; functional checkouts have been performed on equipment and controls.Construction
24All equipment has been filled with proper fluids to the appropriate level and charged as necessary.Construction
25Adequate spare parts are available.Operations
ELECTRICAL
26Electrical Motors (check for proper rotation and heaters are connected).Construction
27All equipment and structures grounded and tested.Operations
28Electrical relays, circuit breakers, transformers, lighting and emergency power systems inspected and tested.Construction
29Controllers and disconnects are labeled if the device being controlled is not obvious.Construction
30All electrical equipment installed to design specifications.Construction
31All electrical seals have been packed and poured; all explosion-proof boxes, conduit covers are properly secured and all electrical connections tightened and checked.Construction
32Any equipment and associated breaker panels not to be used or not available for use are out of service. All lockouts are flagged, tagged and listed.Construction
33Rotating equipment trip points, especially over speed, have been checked and tested.Construction
34The UPS and/or emergency power systems have been tested.Construction
INSTRUMENTATION
35All instrumentation installed to engineering design specifications (API RP 14C)Engineering
36All electrical and pneumatic loop checks completed.Operations
37Interlocks (Electrical and Mechanical) have been reviewed and tested for proper operation.Operations
38All tubing and tubing fittings have been inspected for proper fit-up and leakage.Operations
39All instruments weatherproofed.Operations
40Emergency equip. alarms, communication equip, and shutdown devices calibrated, tested, documented and activated.Operations
41The fire and gas detection systems have been inspected and tested and are in auto mode.Operations
42All bypasses and jumpers on control or safety circuits have been removed.Operations
43PLC logic tested and documentation completed.Engineering
44Backup batteries at full charge.Operations
HEALTH AND SAFETY
45Safety equipment, including fire fighting devices, escape devices, safety showers and eye wash stations, have been inspected and reviewed for proper operation and location.Operations
46Ladders, handrails, and guards (rotating equipment and heat) constructed correctly.Operations
47Fire detection system has been reviewed for proper detector location and correct response / action.Operations
48All safeguards including signs (DANGER, HIGH VOLTAGE, KEEP OUT, HEARING PROTECTION REQUIRED), chains, safety equipment boxes, PPE boxes, etc. are installed and adequately stocked.Operations
49Area has been cleared of construction equipment, surplus equipment, combustible materials, extraneous tools, unused parts, scaffolding and empty drums.Construction
DOCUMENTATION
50All applicable permits and approvals have been received from regulatory agencies (MMS / USCG)Engineering
51Emergency response and evacuation procedures/plans updated, communicated, and in place.Operations
52Hazard analysis recommendations have been addressed and implemented.Engineering
53Flare System /PSV/ Ventilation System design basis updated.Engineering
54Safety information is complete and in place.Operations
55A start-up plan has been prepared and applied.Operations
56Written startup, operating and shutdown procedures are in place (SOPs).Engineering
57Training of affected personnel has been completed (operations, maintenance, emergency response, etc.).Operations
58All construction punch list items have been reviewed and completedConstruction
59Piping and Instrumentation Diagrams (P&ID's) redlined.Engineering
60Process Flow Diagrams (PFD's) redlined.Engineering
61Process and Safety Flow Diagrams (PSFDS) redlined.Engineering
62SAFE chart redlined.Engineering
63Fire and Safety Equipment Locations Plans redlinedEngineering
64Electrical Area Classification Plan drawings redlined.Engineering
65Electrical One-line drawings redlined.Engineering
66Structural and Isometric drawings redlined.Engineering
67MSDS files updated.Operations
68Weight Management Program impacts addressed.Engineering
69PS/IM program updated.Engineering
70Inspections and Maintenance requirements addressed in MAXIMO.Engineering
71All applicable vendor data updated. (i.e., mechanical, electrical, instrument, etc.)Engineering
72Pressure Equipment Pre Commissioning Form completed and sent to Operating Centre IM Specialist FormConstruction
APPROVALS
All Responses reviewed by and agreed to by:
Title/PositionNameDate
Title/PositionNameDate
Authorization to Startup
Title/PositionNameDate