Chapter 1_ Introduction to PSoC _ Architecture and Programming of PSoC, Free
psoc
-
Upload
adarsh-surendran -
Category
Documents
-
view
49 -
download
1
Transcript of psoc
1.Control Centre Operation of Power Systems
Introduction
o The power system of today has evolved from its early stage of point
to point transmission system into a complex interconnected system.
This has made the control and operation of the system quite a
sophisticated task. Hence, in order to monitor and control such a vast
network, human expertise coupled with computer assistance became
inevitable.
o A power control center is thus formed where information from the
entire system is collected and analyzed. The analyzed results are then
used for taking proper decisions regarding the operation of the entire
system, such as allocating generation level at each generation stations,
managing load dispatch and protecting vital installations.
o The main function of the control center is:
(a)To collect the information, such as voltage, current, frequency,
transformer tap settings, etc, through various communication
channels.
(b)To coordinate the power transferred/shared among various
loads.
(c)To coordinate the response of network elements in both normal
and emergency conditions .
o Power system control involves:
(1) Ensuring power quality: The system’s parameters such as voltage
and frequency are to be maintained within the specified limits.
(2)Economic operation: The energy should be supplied with minimum
loss and cost.
(3)Ensuring adequate supply of active and reactive power: In order to
meet the continually changing load demand for active and reactive
power, adequate “spinning” reserve of active and reactive power should
be maintained and appropriately controlled at all times.
Note : The power control center is so designed that system operation is
possible without the power control center.
Subsystems of a power system
Note: simplify the above diagram as done in sir notes.
The subsystem of a power system consists of the following:
(1) Generating unit controls: It consists of prime mover, speed governing
system, generator, and excitation system.The function of the speed
governing system is to sense changes in speed of the prime mover and
accordingly increase/decrease decrease the speed of the prime mover in
order to regulate the frequency. The function of the excitation system is
to control the reactive power generation. It senses the generator’s
voltage and accordingly adjusts the excitation to regulate the voltage.
(2) System generation and control: In a system there should be adequate
generation to meet all kinds of load demand. The primary function of the
system generation and control is to balance the mismatch between the
load demand and the generation so that the desired frequency and power
interchange with neighbouring systems(i.e, tie line flows) is maintained.
(3) Transmission controls: Transmission controls include power and
voltage control devices, such as static var compensators, synchronous
condensers, switched capacitors, tap changing transformers, phase-
shifting transformers, and HVDC transmission controls.
Operating states of a system
The various operating states of a system are as follows:
(1)Normal state: All the system variables are within the specified levels
and the system is in a secure state. Moreover, the system will remain in
stable condition even after a contingency.
(2) Alert state: In this state, the system is said to be conditionally stable
as long as there is no contingency. The stable system may become
unstable after a contingency.
(3) Emergency state: The system enters the emergency state if a
sufficiently severe disturbance occurs when the system is in the alert
state. The voltages at several buses may be low and the generators may
be overloaded. The system in the emergency state can be restored to the
alert state by initiating actions such as fault clearing, excitation control,
generation tripping, etc.
(4)In extremis state: The system enters the in extremis state when the
system cannot be restored to the alert state. This state can result in
cascading outages and possibly a shutdown of a major portion of the
system.
(5)Restorative state: In the restorative state, some control actions will be
initiated to reconnect all the facilities and restore system load. Attempts
will be made to restore the system back either to either the alert state or
the normal state.
Hierarchial representation of a power system
At the lower level controllers such as plant controllers such as power
plant controllers and transmission plant controllers directly control the
the operation of devices such as boilers,steam valve,transformer tap
changers,etc.there is usually some form of overall plant controller that
coordinates the controls of closely linked elements.The plant controllers
are supervised by system control centre ,which in turn is supervised by
the pool control centre.
SCADA systems provide information to indicate the system status. State
estimation programs filter the monitored data and provide an accurate
picture of the system’s condition. The human operator plays an
important role at various levels in this hierarchy. The primary function
of the operator is to monitor system performance and manage resources
so as to ensure economical operation while maintaining the required
quality and reliability of power supply.
SCADA
Follow sir notes, for more information refer your kusic T.book chapter1.
Automatic generation control
In an interconnected power system, automatic generation control and
economic load dispatch are two significant areas of concern for
generation control.
Automatic generation control (AGC): Automatic generation control is an
on-line computer control that maintains the system frequency at or very
close to the specified nominal value (50 Hz) as well as the net
interchange of power(tie-line interchange) between the control areas.
The common practice is to carry out generation control on a
decentralized basis. That is, each individual area tries to maintain its
scheduled interchange of power.
Economic load dispatch (ELD): It is also an on-line computer control,
whose function is to assign the generation level to each of the generators
in order to share the system load in the most economical manner.
Several constraints (e.g., pollution control, etc) are to be satisfied while
carrying out economic load dispatch.
Area control error
To maintain the net interchange of power of an area with its
neighbouring areas, an AGC uses real power flow measurements of all
tie lines emanating from the area and subtracts the scheduled
interchange value from it. This error value, along with a gain B(called
frequency bias) as a multiplier on the frequency deviation, f, is called the
area control error(ACE) and is given by
ACE= ∑PK−¿PS¿ + 10B (f act−f 0) MW
where
K= particular tie line
GA= MW tie line flow out of the area (defined as positive)
PS= Scheduled MW interchange
f 0= Scheduled base frequency
B =Frequency bias in MW/0.1 Hz
A positive ACE represents a flow out of the area. Fig(a) shows the use
of ACE signal as an input to AGC to control generation.
Wheeling power
Area D
Area BArea A
Ps=0
Ps=0
Ps=+P ACE=0
Ps=-PACE=0Area C
Fig(a) Transfer of power from area A to area C
Consider the four area power pool shown in fig(a).If the power is
transferred from area A to area C, area A would introduce a scheduled
interchange, Ps= +p, into its own ACE so that power flows out of area A
until its AGC forces ACE to become zero. Simultaneously, area C would
also introduce a scheduled interchange, Ps=-p, into its own ACE so that
power flows into area C until its AGC forces ACE to zero. Notice that
the areas B and D participate in this transfer of power, but power is not
consumed in them. This is because input and output tie line powers for
areas B and D are equal and opposite, hence ACE=0 in both the cases.
Thus, we see that some power is transmitted via the areas B and D,
but not consumed by them. This power which is transmitted via an area
but not consumed by it, is known as wheeling power.
Objectives and functions of AGC:
Objectives:
(1)To maintain overall system frequency at or very close to the specified
nominal value(50 Hz).The maximum permissible change in power
frequency is ± 0.5 Hz.
(2) To maintain the correct value of net interchange of power between
control areas.
(3)To maintain each unit’s generation at the most economic value.
Functions:
(1)The AGC brings about net interchange of power between areas on a
scheduled basis.
(2)The AGC senses the area control error(ACE), which is the measure of
the error in net interchange of power of an area with its neighbouring
areas from the desired/scheduled net interchange value,and accordingly
sends control signals to generating units to increase/decrease generation
so as to obtain the desired or scheduled flow value. This is done until
ACE becomes zero.
(3)The ACE also contains the change in frequency term, i.e. the
deviation of the system frequency from the scheduled frequency. Thus,
AGC also regulates the system frequency by sending control signals to
the generating units.
Tie-line
In interconnected power systems, the neighbouring power systems are
interconnected by one or more transmission lines called the tie lines, as
shown in fig(a).
Area KArea K
Area 1 Area 2
Tie-line
Fig.(a) Typical interconnected power systems
Tie lines are employed due to the following reasons:
Tie lines allow exchange of power between the areas on a
scheduled basis as forced by the AGC.
Tie lines allow areas experiencing disturbances to draw on other
areas for help.
Tie lines provide a long- distance transmission link for the sale and
transfer of power.
Operation without central computers(or AGC)
The speed governing system built for the turbine-generator set and
the excitation system for the generator allows the operation of power
systems without a central computer.
Any change in load will force generators within neighbouring areas
to share load.
Fig.(a) A simple interconnected system
Consider a simple interconnected system as shown in fig(a).Assume
that the breaker is open and there is no tie line flow between areas A
and D. Let the area A overall generation-frequency characteristic br
represented by curve GG in fig.(b).
Frequency(Hz)
GGeneration(MW)
49.5
50.0
50.5
0G
A
fig(b)generation- freq. characteristic curve
The generation frequency characteristic curve is described by the
equation
GA=G0+ 10β1(f act-f 0)
Similarly, the overall load- frequency curve for area A can be
represented by curve LL in fig(c).
L
Frequency(Hz)
49.5
50.0
50.5
LA
0(f )
Load(MW)
The load-frequency characteristic curve is described by the equation
LA=L0+10β2(f act-f 0)
Effect of load increase in area A
The operating frequency is determined by the point of intersection (Io) of
the GG and LL curves,shown at 50 Hz in fig(d).
fig(d)
GG=gen freq. plot
LL=Load freq. plot
CC=combined area characteristic
Now, assume that there is load increase in area A,which shifts LL to the
new position L’L’. The intersection of L’L’ and GG gives the new
operating point(I1) at 49.9 Hz.
In order to restore the operating frequency to 50 Hz,GG is shifted to the
new position G’G’. The intersection of L’L’ and G’ G’ gives the new
operating point (I2) at 50 Hz. The resulting combined characteristic is
now shown by line C’C’.
The combined characteristic is given by
GA−LA=G0+ 10β1(f act-f 0¿−L0−¿10β2(f act-f 0)
This can be rewritten in terms of increments
ΔA= (GA−G0) + (L0−LA)= 10β1(f act-f 0) −¿10β2(f act-f 0)
=10BA X A ¿¿-f 0)
=10BA X AΔf
Where BA=¿Natural egultion characteristic of area A
X A=¿ Generating capacity of area A
or Δf = ΔA /(10BA X A ¿
Effect of tie line flow
Consider the interconnected system shown above, with breaker T closed.
Suppose the area D experiences a disturbance due to which the systems
freq. drops from 50 Hz to 49.9 Hz. Now, the power generation no longer
matches with the load demand in area A and the difference between
them is defined by the difference between intercepts I2 and
I1,respectively, of the GG and LL curve with the 49.9 HZ line, as shown
in fig(a).
If ΔLArepresents the decrease in load in area A and ΔGA represents the
increase in generation in area A, then the tie-line flow between A and D
is
ΔT L=ΔGA- ΔLA MW
If area A has an AGC that applies frequency bias B, GG will be shifted
to the new position G’G’, resulting in a large tie line flow ΔT L' .
Derivation of ΔT L and Δf
Consider the interconnected system shown above, with breaker T closed.
Let area D experiences a disturbance ΔD.Now,the freq. change due to
disturbance ΔD and tie line flow from A to D, is given by
Δf = ( ΔD−¿ ΔT L¿/(10BD XD) ………..(1)
(ΔT L is taken as negative since it flows into the area D)
Also, with respect to area A, we have
Δf = ΔT L /¿10BA X A) ………..(2)
(sinceΔA = 0. Here, ΔT L is taken as positive
it flows out of the area A)
Since the frequency is same for both the areas,
Δf=( ΔD−¿ ΔT L¿/(10BD XD) = ΔT L /¿10BA X A) …….(3)
Tie line flow, ΔT L =¿10BA X A) ΔD /(10BA X A + 10BD XD ) ……(4)
Substituting eqn(4) in eqn.(2), we get
Δf = ΔD /¿(10BA X A + 10BD XD ) ……….(5)
Parallel operation of generators
Parallel operation of two dissimilar units
Fig(b)Parallel operation of two dissimilar units
Consider the case of two units of different capacity and regulation
characteristics operating in parallel,as shown in fig(b).The regulations R1
and R2 are
R1= Δf(p.u)/ΔP1(p.u) = (Δf/50)/( ΔP1/P1rated) pu
Δf=50R1( ΔP2/P2rated) ……(1)
R2 =(Δf/50)/( ΔP1/P1rated) ……(2)
The sharing ratio of the two units is obtained by dividing eqn (1) by (2)
(ΔP1/ ΔP2) = (R2/R1) x (P1rated/P2rated) ……(3)
If the initial load is P1.0 + P2.0, then a change in load will be,
ΔL= ΔP1+ ΔP2 = (Δf x P1 rated/R1)+ (Δf x P2 rated/R2) ……(4)
Thus, the equilvalent regulation of the paralleled system is,
Ŕsystem = Δf/ ΔL= 1/ [(P1rated/R1)+(P2rated/R2)] 1/MW
In terms of p.u.,
Rsystem= Ŕsystem(P1 rated + P2 rated) p.u