PRR of SCT off-detector cooling system

29
CCLRC 1 April 05 Jason Tarrant PRR of SCT off-detector cooling system Cooling System » Design - Off-cylinder & On-cylinder » Installation – Off-cylinder & On-Cylinder » Manufacture – On-cylinder only » Assembly – On-cylinder only » Post assembly operations – On-cylinder only » Schedule – On-cylinder only

description

PRR of SCT off-detector cooling system. Cooling System Design - Off-cylinder & On-cylinder Installation – Off-cylinder & On-Cylinder Manufacture – On-cylinder only Assembly – On-cylinder only Post assembly operations – On-cylinder only Schedule – On-cylinder only. - PowerPoint PPT Presentation

Transcript of PRR of SCT off-detector cooling system

Page 1: PRR of SCT off-detector cooling system

CCLRC 1April 05Jason Tarrant

PRR of SCT off-detector cooling system

Cooling System» Design - Off-cylinder & On-cylinder

» Installation – Off-cylinder & On-Cylinder

» Manufacture – On-cylinder only

» Assembly – On-cylinder only

» Post assembly operations – On-cylinder only

» Schedule – On-cylinder only

Page 2: PRR of SCT off-detector cooling system

CCLRC 2April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design» Off-Cylinder» On-Cylinder

Page 3: PRR of SCT off-detector cooling system

CCLRC 3April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design» Off-Cylinder

– HEX / filter– Heater

» On-Cylinder– Inlet– Exhaust– Combined

Page 4: PRR of SCT off-detector cooling system

CCLRC 4April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design» Inlet – with fluid flow

SERTO @ PPF1 5mm OD / 3.4mm ID with filter 3mm OD / 2mm ID through HEX ECcap3 custom connection @ STFT Capillaries LMT cooling circuit (combined) – or –

PPF0 @ Disc

Page 5: PRR of SCT off-detector cooling system

CCLRC 5April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – Inlet…» SERTO @ PPF1

– 6mm OD – 5mm OD

– SERTO issues 316 Magnetic? (Danielsson / Olcese)

– Swagelock issues Not survive many connection / disconnection May need retightening after time

» 5mm OD / 3.4mm ID with filter– Standard Cu tube 5mm OD 0.8mm wall

Joined over 3mm OD tube exiting the HEX (QMUL design)

– Filter design Screen 0.5mm holes (264) > 5x 3.4mm ID of inlet tube Capillary ID 0.68 or 0.76mm

Page 6: PRR of SCT off-detector cooling system

CCLRC 6April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – Inlet…» 5mm OD / 3.4mm ID with filter…

Page 7: PRR of SCT off-detector cooling system

CCLRC 7April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – Inlet…» 3mm OD / 2mm ID through HEX

– CERN stores– Coiled through HEX

8mm ID, 13.5mm OD (touching) 4mm pitch, 84 coils Effective length 2923mm (incl. 10mm each end to start coil)

» ECcap3 custom connection @ STFT– Space, electrical isolation, soldering compatibility

To PPF1

Page 8: PRR of SCT off-detector cooling system

CCLRC 8April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – Inlet…» Capillaries

– ID 0.68mm or 0.76mm– Length around 2.5m (tuned)– Coiled / convoluted routing on cylinder (TBD)– Joined to LMT Cooling circuit or PPF1

» LMT cooling circuit (combined)– 3.74mm OD 70um wall– Swaged-solder connection

Al spreader foil

Power tapes

Cooling tubes

Schematic 2: cross section of cooling concept for 3 stacks of power tapes

Page 9: PRR of SCT off-detector cooling system

CCLRC 9April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – Inlet…» PPF0

– Based on Helicoflex– Already tested (I.Wilmut)– Only hole changes from original design

2 Types 1.3 & 1.25 nominal (0.76 & 0.68mm ID)

Page 10: PRR of SCT off-detector cooling system

CCLRC 10April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design» Exhaust – with fluid flow

PPF0 @ Disc or LMT cooling 6.0mm ID / 8.1mm ID tubing ECex1 HEX ECheat1 custom connection Heater PPF1

Page 11: PRR of SCT off-detector cooling system

CCLRC 11April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – Exhaust…» PPF0 @ Disc or LMT cooling

– PPF0

– LMT Cooling

Page 12: PRR of SCT off-detector cooling system

CCLRC 12April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – Exhaust…» 6.0mm ID / 8.1mm ID tubing

– 6.0mm ID 0.2mm wall = 30mm bend R

– 8.1mm ID 0.15mm wall = straight lengths only 4x8.4mm (+1.2mm gaps) = 37.2mm

Page 13: PRR of SCT off-detector cooling system

CCLRC 13April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – Exhaust…» ECex1

– Custom connection

» HEX– 14mm ID 0.2mm wall CuNi– 370mm long body with end caps

STFT

Page 14: PRR of SCT off-detector cooling system

CCLRC 14April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – Exhaust…» ECheat1 custom connection

– Staggered connections– Insulation issues– Fastening issues– Cu – Stain.s

Page 15: PRR of SCT off-detector cooling system

CCLRC 15April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – Exhaust…» Heater

» PPF1– SERTO 6mm OD - 6mm OD

13

16.2

Page 16: PRR of SCT off-detector cooling system

CCLRC 16April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – Off-cylinder» HEX assemblies (no inlet / filter) complete

– Iteration through QMUL practical experience (end-caps – soldering of ECcap3 & ECex1)

» Higher level, 1 ‘sample’ for in-house tests, rest to do» Assembly of all HEX (new) for overall view» Parameter dwg to do?

Page 17: PRR of SCT off-detector cooling system

CCLRC 17April 05Jason Tarrant

PRR of SCT off-detector cooling system

Design – On-cylinder» Exhaust & LMT circuit design, PPF1 – STFT complete

Page 18: PRR of SCT off-detector cooling system

CCLRC 18April 05Jason Tarrant

PRR of SCT off-detector cooling system

Installation – On-cylinder – Assembly Sites (Liv. NIK.)» Combined (Exhaust / Inlet assembly)

– D9-D7 before D9 or before D6 services laid (avoid layering)– Laid using support frame– STFT clip (await connection), PPF0 connected, LMT Kapton taped– Exhaust uses insert mounted clamp, Inlet clipped to exhaust, LMT wrapped

with LMTs

» Exhaust– D6 –D1 with relevant Disc– Laid by hand STFT clip (await connection), PPF0 connected– Exhaust uses Support Cylinder insert mounted clamp

Page 19: PRR of SCT off-detector cooling system

CCLRC 19April 05Jason Tarrant

PRR of SCT off-detector cooling system

Installation – On-cylinder – Assembly Sites (Liv. NIK.)» Inlet

– D6-D1 with relevant Disc– Pre-formed coils– Laid by hand, supported above STFT, Kapton taped– Inlet clipped to exhaust

Page 20: PRR of SCT off-detector cooling system

CCLRC 20April 05Jason Tarrant

PRR of SCT off-detector cooling system

Installation – On-cylinder – Assembly Sites (Liv. NIK.)» Connection for Testing

Page 21: PRR of SCT off-detector cooling system

CCLRC 21April 05Jason Tarrant

PRR of SCT off-detector cooling system

Installation – Off-cylinder» Space required to ‘insert’ connection

– Use R1116 envelope (post EC insertion)

Page 22: PRR of SCT off-detector cooling system

CCLRC 22April 05Jason Tarrant

PRR of SCT off-detector cooling system

Installation – Off-cylinder» Order of connection

– Low Z to high Z– Special spanner

Z+Z-

Page 23: PRR of SCT off-detector cooling system

CCLRC 23April 05Jason Tarrant

PRR of SCT off-detector cooling system

Installation – Off-cylinder» Strain relief at STFT (ECex1)

– Permanent– Adjustable

positions not guaranteed

Page 24: PRR of SCT off-detector cooling system

CCLRC 24April 05Jason Tarrant

PRR of SCT off-detector cooling system

Installation – Off-cylinder» Connection for Testing

– STFT break & make + drying if cold testing Compromise for maximum HEX length

– Extension pieces connected in, STFT sealed once, testing, remove & integrate SCT EC into ATLAS, add interconnect to PPF1, seal & test seal

Page 25: PRR of SCT off-detector cooling system

CCLRC 25April 05Jason Tarrant

PRR of SCT off-detector cooling system

Manufacture – On-cylinder only» Piece Parts all detailed & out for manufacture with NTE (6

weeks from 24/03/05)» Attempting to get them to deliver those for D9 – D7

(including LMT cooling) ASAP

Page 26: PRR of SCT off-detector cooling system

CCLRC 26April 05Jason Tarrant

PRR of SCT off-detector cooling system

Assembly – On-cylinder only» Jig details out for quote» Jig to be used @ RAL for assembly of Interconnects,

including LMT cooling

Page 27: PRR of SCT off-detector cooling system

CCLRC 27April 05Jason Tarrant

PRR of SCT off-detector cooling system

Post assembly operations – On-cylinder only» Clean circuits

– Flushing with Swansolve

» Pressure test– To 25 Bar

» Leak test– 5x10-8 bar l/s (time / pressure test)

» Check blockage– Simple flow test for circuits with capillaries (based on flow through Disc

capillary for D9 – D7)

» Bar code according to the ATLAS parts ID– With traveller document

Page 28: PRR of SCT off-detector cooling system

CCLRC 28April 05Jason Tarrant

PRR of SCT off-detector cooling system

Schedule – On-cylinder only» Interconnects

– SB - Models / drawings for D9 - D7 including LMT cooling - 09/03/05– JT - Check drawings - 10/03/05– SB - Quote pack to go to NTE - 11/03/05– NTE - Quote back - 16/03/05– SB / OM raise order & release through OM - 17/03/05 (actual 24/03/05)– NTE Manufacture - 6 Weeks(incl. Easter) - 28/04/05– RAL Tech manufacture D9 (all 8 /2 types) incl.LMT cooling - 1 Week -

5/05/05– RAL Tech manufacture D8 (all 8 /2 types) incl.LMT cooling - 1 Week -

12/05/05– RAL Tech manufacture D7 (all 8 /2 types) incl.LMT cooling - 1 Week -

19/05/05

Page 29: PRR of SCT off-detector cooling system

CCLRC 29April 05Jason Tarrant

PRR of SCT off-detector cooling system

Schedule» Jig

– JT-Model Jig - 08/03/05– Contractor detail jig - 2 Weeks - 22/03/05– JT - Check drawings (incl. any changes) - 24/03/05– JT -Quote pack to OM - 29/03/05 – Expected 01/04/05 (companies

turning down!)– JT / OM raise order & release through OM - 29/03/05– Manufacture 4 weeks - 26/04/05