Proposed Quintette Mine Re-opening

17
Proposed Quintette Mine Re- opening February 2011

description

Proposed Quintette Mine Re-opening. February 2011. Location. The Quintette Property is located in the Peace River Coal Field of northeast British Columbia Approximately 20km south of the town of Tumbler Ridge. History. - PowerPoint PPT Presentation

Transcript of Proposed Quintette Mine Re-opening

Page 1: Proposed Quintette Mine Re-opening

Proposed Quintette Mine Re-openingFebruary 2011

Page 2: Proposed Quintette Mine Re-opening

Location

• The Quintette Property is located in the Peace River Coal Field of northeast British Columbia

• Approximately 20km south of the town of Tumbler Ridge

2

PACIFIC OCEAN

Calgary

Edmonton CNR

Prince

George

CNR

CPR

U.S.A.

British Columbia Alberta

CNR

Sask

Prince

Rupert`

Vancouver

QQuuiinntteettttee

DDiissttaannccee ttoo ppoorrtt ~~ 11005500 kkmm

Page 3: Proposed Quintette Mine Re-opening

History

• Quintette Mine was approved under the Guidelines for Coal Development in 1982

• 1982 Mine Plan was comprised of three components:

– Sheriff (Wolverine and Mesa pits)

– Frame (Shikano Pit)– Babcock (Windy

and Window pits)• Mining of Windy Pit was

authorized under Mines Act Permit C-156 in 1997 and continued until closure in 2000

3

Page 4: Proposed Quintette Mine Re-opening

Current Plans

• Teck is exploring the feasibility of re-opening the Quintette Mine:

– Windy Pit– Window Pit

• Teck will maximize the use of existing infrastructure:

– Rejuvenate processing plant

4

Page 5: Proposed Quintette Mine Re-opening

Quintette Plant Site

5

Page 6: Proposed Quintette Mine Re-opening

Mining

• All coal will be mined by open pit operations• Utilize existing infrastructure• Anticipated 15-17 year mine life • Average production rate of 3.0-3.5 Mmtcc/year• Feasibility study is in progress and anticipated production

rates and waste spoil volumes are being refined

6

Page 7: Proposed Quintette Mine Re-opening

Mine Plan Comparison(Production Capacity)

• The 2010 Mine Plan will be smaller than that which was approved in 1982

7

Mmtcc: Million metric tonnes clean coalMbcm: Million bench cubic metres

2010 Mine Plan

Waste (Mbcm) 650

Clean Coal (Mmtcc) 45-50

Page 8: Proposed Quintette Mine Re-opening

Regulatory: British Columbia Environmental Assessment Act (BC EAA)

8

Requirement for approval under BC EAA not required because:• Project is not a reviewable modification of an existing mine:

– Windy and Window Pits were approved by Environmental Land Use Committee in 1982 under Guidelines for Coal Development

– Windy and Window pits together will create ~400 ha of new disturbance, which is below BC EAA thresholds of:

• More than 750 ha of new disturbance• More than 50% of land that was previously permitted for disturbance

(3,500 ha)

• Project will utilize existing, permitted infrastructure (processing plant, tailings pond, sedimentation ponds, roads, power lines, mine office buildings, etc.)

Page 9: Proposed Quintette Mine Re-opening

Regulatory: Canadian Environmental Assessment Agency (CEAA)

Requirements for approval under CEAA being investigated:

• No federal funds or federal lands involved

• DFO will be engaged to clarify authorizations regarding fish and fish habitat

9

Page 10: Proposed Quintette Mine Re-opening

Regulatory: Mines Act

• Mines Act Permit C-156, authorizing works and reclamation plan, was amended to include Windy Pit in 1997 and remains in good standing

• Re-opening Windy Pit and developing Window Pit requires an amendment of Mines Act Permit C-156

• Teck is working with the Ministry of Natural Resource Operations to ensure that the Regional Mine Development Review Process is robust and meets the needs and expectations of First Nations, government agencies and communities

10

Page 11: Proposed Quintette Mine Re-opening

Key Issues

11

Environmental

First Nations Interests

and Treaty Rights

Social and Economic

Concerns of Public, First Nations and Communities

Rights and Activities of

Other Tenure Holders

Environmental:• Development of Management Plans

for the protection of Mountain Caribou, Goats and Grizzly Bears

• Protection of Water Quality, Aquatic Resources, Fish and Waterfowl through mine planning and design and the implementation of Selenium, Explosives and Water Management Plans

• Cumulative Effects• Prevention of ML/ARD• Reclamation

Page 12: Proposed Quintette Mine Re-opening

Community Engagement

12

Environmental

First Nations Interests

and Treaty Rights

Social and Economic

Concerns of Public, First Nations and Communities

Rights and Activities of

Other Tenure Holders

First Nations communities:• Building a long-term relationship based

on: – Respect for community needs, treaty

rights and traditional knowledge– Sharing of information and

resources (capacity building)• Working together to:

– Identify potential environmental, social and economic effects

– Develop workable solutions to avoid or mitigate potential effects

– Identify cooperative approaches to articulate the maximum amount of project benefits

Page 13: Proposed Quintette Mine Re-opening

Update on First Nation and Community Engagement

13

• Ray Proulx hired as a Community Liaison for Quintette Project • Summary of engagement activities to date:

– Introductory meetings July – Sept. 2010 with District of Tumbler Ridge, 5 First Nations and one Metis community.

– Additional discussions occurred between Sept. and Nov. 2010– A draft Working Protocol Agreement with McLeod Lake Indian

Band is under development– Teck has entered into a service agreement with the Saulteau

First Nations for the completion of a Culture and Traditions Study

– Permitting review discussions began mid-February 2011

Page 14: Proposed Quintette Mine Re-opening

Quintette Proposed Timeline

14

2010• Engagement• Geotechnical drilling• Mine planning• Environmental baseline studies

Mid 2011• Feasibility study

completed• Initiate

preparation of Application to amend Mines Act Permit C-156

• Engagement

Q4 2011• Permitting

completed• Board gives

Project approval• Construction

begins in the Plant

• Engagement

2013• Mining

potentially begins in Windy Pit

• Engagement

Page 15: Proposed Quintette Mine Re-opening

Summary

15

Project Features:• Reduced footprint of mine pits and waste spoils compared to

1982 Project• Maximize use of existing infrastructure• Conventional truck and shovel operation• Production of 45 - 50 Mmtcc over a 15+ year mine life, starting

in 2013• Capital costs estimated to be <$500 million• Approximately 350 - 400 employees required

Page 16: Proposed Quintette Mine Re-opening

Summary (cont'd)

16

Social Requirements:• Community engagement and dialogue• Developing a better mine that will:

• be valued by the communities• adhere to Teck’s corporate principles and commitments

Regulatory Requirements:• Amend Mines Act Permit C-156• Amend/obtain Environmental Management Act Permits (discharges

from tailings pond, sediment ponds and processing plant)

Page 17: Proposed Quintette Mine Re-opening

Next Steps

17

• Continue engagement with First Nations and communities

• Meet with Department of Fisheries and Oceans

• Meet with Regional Mine Development Review Committee

• Initiate Review of Application to Amend Mines Act Permit C-156