PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES

Transcript of PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS...

Page 1: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

PROPOSAL FOR DUBAI BUS STOP

ENERGY INDIPENDENCE

BY RENEWABLE SOURCES

Page 2: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

SCOPE OF WORK

SHELTERS

ENERGY

INDIPENDENCE

RENEWABLE

ENERGIESSTAND ALONE PHOTOVOLTAIC

GEOTHERMAL HEAT PUMP

SERVICE

UPGRADEINFORMATION

TECHNOLOGIESCMS FOR EMPLOYEER

SERVICE

INTEGRATION

SET UP OF DUBAI BIKE SHARING

PROJECT

MOBILE APP FOR USERS

ENERGY

EFFICIENCYOPTIMIZATION OF HVAC SWITCH ON TIME

LED ILLUMINATION SYSTEM

Page 3: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

SHELTER UPGRADE

Page 4: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

SHELTER UPGRADE

SHELTER DESIGN

AND STRUCTURAL

UPGRADE

PHOTOVOLTAIC

PLANT

BUILDING INTEGRATED

POSSIBLE

INTEGRATION

WITH

BIKE SHARING

SYSTEM

Page 5: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

SHELTER UPGRADE

BUILDING INTEGRATED

STAND ALONE

PHOTOVOLTAIC

GEOTHERMAL

GROUND HEAT

EXCHANGER

Page 6: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

SHELTER UPGRADE

BOX FOR

ELECTRICAL AND

HVAC EQUIPMENTS

BIKE SHARING

SMART CARD

READER

Page 7: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

MOBILE APP - DESIGN

The app is designed for the users of Dubai public transport in order to improve the

service offered by the public transport authority with the latest technologies.

Page 8: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

MOBILE APP - FUNCTIONS

Customized user friendly graphics and interface

Integrated maps of the public transport system

Route planner

Display of nearest bus stop

Display of time of arrival of the means of transport with

push notice

Alerts with useful information for users

(delays, strikes, detours…)

Page 9: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

ADMINISTRATION SOFTWARE

A CMS software will be provided to the management team in order to set up the App

contents.

Page 10: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

PROPOSALSPROPOSALSPROPOSALSPROPOSALS

DESCRIPTIONDESCRIPTIONDESCRIPTIONDESCRIPTION

Page 11: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

PROPOSED ACTIVITIES

RETROFIT ACTIVITIES ON EXISTING BUS SHELTERS

Grid connected photovoltaic plant

Geothermal heat pump

Grid connected photovoltaic plant

and geothermal heat pump

Stand alone photovoltaic plant

and geothermal heat pump

NEW INSTALLATIONS

Geothermal heat pump

Grid connected photovoltaic plant

and geothermal heat pump

Stand alone photovoltaic plant

and geothermal heat pump

Page 12: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

HOW IT WORKS

During central day hours, PV system provides more energy

than used by bus shelters.

- The energy storage system will be charged

- The surplus of energy could be fed into the electric grid

During the beginning and the end of the

day, PV system is not able to provide

energy to bus shelters. In these periods:

- The energy storage system will supply

the necessary energy for the bus

shelters or

- The necessary energy will be taken by

the electric grid

PV system daily production

Energy Consumption of the bus shelters with GHP system

Time

Power

Trends are purely indicatives

Page 13: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

TECHNICAL TECHNICAL TECHNICAL TECHNICAL

DATADATADATADATA

Page 14: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

ENGINEERING SERVICES

The following services are not included in the above mentioned proposal: grounding tests, any specialized reports

(geological report, geotechnical report), management of potential administrative practices (if any), preparation

of the documentation for authorization requests (if any), any duty necessary for authorization requests, anything

not expressly included in the above mentioned services.

M&P DESIGN SERVICES

• On-site visit to verify the status of the locations and carry out a site survey on

a minimum number of 10 bus shelters

• Electric system design (PV plant)

• HVAC system design (Geothermal heat pump)

• Detailed Structural design (Bus shelters upgrade)

The following services are not included in the above mentioned proposal: grounding tests, any specialized reports

(geological report, geotechnical report), management of potential administrative practices (if any), preparation

of the documentation for authorization requests (if any), any duty necessary for authorization requests, anything

not expressly included in the above mentioned services.

Page 15: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

GEOTHERMAL HEAT PUMP

Supply and installation of geothermal heat pump, composed essentially by:

• geothermal heat pump model AERMEC WRL 051HA* or equivalent,

nominal cooling capacity 13,6 kW (46.000 BTU/h) @ B30/W7, including

accessories for the secondary circuit (boiler buffer tank, valves, sensors,

recirculation pumps, plate heat exchangers, and supports flexible

connections, filters, remote control system and management);

• geothermal field, including drilling, supply and installation of heat

exchangers into the ground, cementing of boreholes with specific material

for geothermal applications, installation of primary fluid distribution

(recirculation pumps, manifolds, pipe fittings, valves, control sensors ),

filling fluids, pressure and circulation tests for each geothermal probe.

*Technical data to be confirmed after a detailed feasibility study.

Page 16: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

GEOTHERMAL HEAT PUMP

Supply and installation of air handling unit with structure in galvanized steel

model AERMEC TUN 15* or equivalent. Units equipped with double inlet

centrifugal fans. Multi-speed electric motor. Battery 6 ranks. Nominal air flow

1500 m³/h (880 CFM). Synthetic filters (thickness 50 mm) with G4 efficiency

class (according to EN 779) for lower intake.

*Technical data to be confirmed after a detailed feasibility study.

Supply and installation of ducts for air distribution in rectangular or circular

section made of galvanized steel with flange joints, including special parts,

seals, fasteners and thermal insulation.

Page 17: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

GEOTHERMAL HEAT PUMP

Removal of existing equipment. To be calculated separately transport to landfill

with their charges.

Transportation and equipment rental included. Excluded coordination with

local authorities.

Supply and installation of linear air diffusers in aluminum, slit pattern type,

model Sagicofim LD 613-1000* or equivalent, comprehensive of deflector,

damper and distribution plenum.

*Technical data to be confirmed after a detailed feasibility study.

Page 18: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

GEOTHERMAL HEAT PUMP

*Technical data to be confirmed after a detailed feasibility study.

Page 19: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

CIVIL WORKS

Structural adjustment of the stops bus shelters through the supply and installation: ofStructural adjustment of the stops bus shelters through the supply and installation: of

• New supports in galvanized steel on the back for bikesharing,

• Structural elements in galvanized steel for the expansion of the upper shelter

panels for information and publicity,

• Structural elements in galvanized steel for the installation of the PV system,

• Metal closing panels with curved shape,

• Extension of the foundation for housing the technical room (if any);

• Structural elements in galvanized steel for the expansion side of the shelter for the

construction of the technical room,

• Sandwich panels for roofing and curtain technical room,

• Metal grid for ventilation technical room,

• Transportation and equipment rental included. Excluded coordination with local

authorities.

*Technical data to be confirmed after a detailed feasibility study.

Page 20: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

PHOTOVOLTAIC

• Supply of N°12 310Wp photovoltaic modules. Dimensions: 1956x992x40 mm, 72 cells, front

glass thickness: 4mm, weight 27,6kg, connector type: MC4

• Supply of N°1 SMA Sunny Island 6.0H (or similar) inverter, including all the accessories required

for the proper functioning and the correct installation of the system.

• Supply of N°1 SMA Sunny Boy 2100TL inverter(or similar), including all the accessories required

for the proper functioning and the correct installation of the system. All the certifications required

by regulations in force are included.

• Supply of N°2 storage batteries RES Fiamm 7,2 KWh – 48V

• Supply of mounting structures for photovoltaic modules including all the accessories required for

the correct installation of the modules.

• Supply of wiring elements and switchboards with the related components required for the

proper functioning of the photovoltaic plant. Cables, pipes, clamping tools and brackets,

connectors, switchboards, switching and maneuvering components, safety devices and anything

else necessary in order to deliver a workmanlike completed work are included.

• Installation service related to photovoltaic system

*Technical data to be confirmed after a detailed feasibility study.

Page 21: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

PHOTOVOLTAIC

*Technical data to be confirmed after a detailed feasibility study.

PV Plant Rated Capacity: 3,7 kWp

Annual estimated production

6.030 kWh/year

Annual specific estimated production

1.629 kWh/kWp

The value may vary according to the

shelter roof orientation and slope

Page 22: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

PHOTOVOLTAIC

PHOTOVOLTAIC MODULES lifetime ad warranties

About 25 years according to the manufactures warranties (5 years for defects, 25 years for

performances)

INVERTER lifetime ad warranties

More than 10 years according to the manufactures indication, possible to the extend the warranties

up to 20 years

BATTERIES lifetime

2000 cycles (according to the manufactures indication and IEC 61427)

SPARE PARTS AVAILABILITY

All components are made from most important worldwide manufacures in order to keep spare

parts availability. Is possible to arrange a spare parts storage to minimize intervention time.

Page 23: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

PHOTOVOLTAIC

*Technical data to be confirmed after a detailed feasibility study.

PV Plant Rated Capacity: 3,7 kWp

Annual estimated production

6.030 kWh/year

Annual specific estimated production

1.629 kWh/kWp

The value may vary according to the

shelter roof orientation and slope

Page 24: PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY … · 2015. 6. 22. · PROPOSAL FOR DUBAI BUS STOP ENERGY INDIPENDENCE BY RENEWABLE SOURCES . SCOPE OF WORK SHELTERS ENERGY INDIPENDENCE

Abu Dhabi – U.A.E.Sheikh Zayed Road, 10

P.O. Box: 48238

[email protected]

Camerano (AN) - ItalyVia Del Commercio 14/A

[email protected]

Dubai – U.A.E.P.O. Box - 48987

[email protected]