Facility Location Operations Management Dr. Ron Tibben-Lembke.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
-
Upload
marvin-long -
Category
Documents
-
view
230 -
download
0
Transcript of Projects: Critical Paths Dr. Ron Lembke Operations Management.
PERT & CPMPERT & CPM• Network techniques• Developed in 1950’s
• CPM by DuPont for chemical plants• PERT by U.S. Navy for Polaris
missile• Consider precedence relationships
& interdependencies• Each uses a different estimate of
activity times
• Completion date?• On schedule? Within budget?• Probability of completing by ...?• Critical activities?• Enough resources available?• How can the project be finished early at
the least cost?
Questions Answered by PERT & CPMQuestions Answered by PERT & CPM
PERT & CPM StepsPERT & CPM Steps
• Identify activities• Determine sequence• Create network• Determine activity times• Find critical path
• Earliest & latest start times • Earliest & latest finish times • Slack
Activity on Node (AoN)Activity on Node (AoN)
2
4? Years
EnrollReceive diploma
Project: Obtain a college degree (B.S.)
1 month
Attend class, study etc.
1
1 day
3
Activity on Arc (AoA)Activity on Arc (AoA)
4,5 ? Years
Enroll
Receive diploma
Project: Obtain a college degree (B.S.)
1 month
Attend class, study,
etc.1
1 day
2 3 4
AoA Nodes have meaningAoA Nodes have meaning
GraduatingSenior
Applicant
Project: Obtain a college degree (B.S.)
1
Alum
2 3 4
Student
Network ExampleNetwork Example
You’re a project manager for Bechtel. Construct the network.
Activity PredecessorsA --B AC AD BE BF CG DH E, F
AOA Diagrams
2 31A
C
BD
A precedes B and C, B and C precede D
2 41A C
B
D
3
5
4
Add a phantom arc for clarity.
Critical Path AnalysisCritical Path Analysis• Provides activity information
• Earliest (ES) & latest (LS) start• Earliest (EF) & latest (LF) finish• Slack (S): Allowable delay
• Identifies critical path• Longest path in network• Shortest time project can be
completed• Any delay on activities delays project• Activities have 0 slack
Critical Path Analysis ExampleCritical Path Analysis Example
Event ID
Pred. Description Time (Wks)
A None Prepare Site 1 B A Pour fdn. & frame 6 C B Buy shrubs etc. 3 D B Roof 2 E D Do interior work 3 F C Landscape 4 G E,F Move In 1
Earliest Start & Finish StepsEarliest Start & Finish Steps
• Begin at starting event & work forward• ES = 0 for starting activities
• ES is earliest start• EF = ES + Activity time
• EF is earliest finish• ES = Maximum EF of all predecessors for
non-starting activities
Activity ES EF LS LF SlackA 0 1BCDEF
Activity AEarliest Start Solution
Activity AEarliest Start Solution
For starting activities, ES = 0.For starting activities, ES = 0.
AAEEDDBB
CC FF
GG
1
6 2 3
1
43
Activity ES EF LS LF Slack A 0 1 B 1 7 C 1 4 D 7 9 E 9 12 F 4 8 G 12 13
Earliest Start SolutionEarliest Start Solution
AAEEDDBB
CC FF
GG
1
6 2 3
1
43
Latest Start & Finish StepsLatest Start & Finish Steps
• Begin at ending event & work backward• LF = Maximum EF for ending activities
• LF is latest finish; EF is earliest finish• LS = LF - Activity time
• LS is latest start• LF = Minimum LS of all successors for
non-ending activities
Activity ES EF LS LF SlackA 0 1B 1 7C 1 4D 7 9E 9 12F 4 8G 12 13 13
Earliest Start SolutionEarliest Start Solution
AAEEDDBB
CC FFGG
1
6 2 31
43
Activity ES EF LS LF Slack A 0 1 0 1 B 1 7 1 7 C 1 4 5 8 D 7 9 7 9 E 9 12 9 12 F 4 8 8 12 G 12 13 12 13
Latest Finish SolutionLatest Finish Solution
AAEEDDBB
CC FF
GG
1
6 2 3
1
43
Activity ES EF LS LF Slack A 0 1 0 1 0 B 1 7 1 7 0 C 1 4 5 8 4 D 7 9 7 9 0 E 9 12 9 12 0 F 4 8 8 12 4 G 12 13 12 13 0
Compute SlackCompute Slack
New notation
• Compute ES, EF for each activity, Left to Right
• Compute, LF, LS, Right to Left
C 7C 7LS LF
ES EF
Exhibit 6
A 21A 21
E 5E 5D 2D 2B 5B 5
C 7C 7 F 8F 8
G 2G 2
21 28 28 36
36 38
28 3326 2821 26
0 21
F cannot start until C and D are done.G cannot start until both E and F are done.
Exhibit 6
A 21A 21
E 5E 5D 2D 2B 5B 5
C 7C 7 F 8F 8
G 2G 2
21 26
0 21
26 28 31 36
36 38
21 28 28 36
21 28 28 36
36 38
28 3326 2821 26
0 21
E just has to be done in time for G to start at 36, so it has slack.D has to be done in time for F to go at 28, so it has no slack.
Solved Problem 2
A 1A 10 1
0 1
B 4B 41 5
1 5
C 3C 36 9
1 4
D 7D 72 9
1 8
E 6E 65 11
5 11
F 2F 29 11
8 10
H 9H 99 18
8 17
I 4I 418 22
18 22
G 7G 711 18
11 18