Network Analysis
Project Management - CPM/PERT
OR
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
2/39
2
What exactly is a project?PM 1 Im in charge of the construction of a retail development in thecentre of a large town. There are 26 retail units and a super market inthe complex. My main responsibilities are to co-ordinate the work of the various contractors to ensure that the project is completed tospecification, within budget and on time.
PM 2 I am directing a team of research scientists. We are runningtrials on a new analgesic drug on behalf of a pharmaceutical company.It is my responsibility to design the experiments and make sure that
proper scientific and legal procedures are followed, so that our resultscan be subjected to independent statistical analysis.
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
3/39
3
PM 2 I am directing a team of research scientists. We are runningtrials on a new analgesic drug on behalf of a pharmaceutical company.
It is my responsibility to design the experiments and make sure thatproper scientific and legal procedures are followed, so that our resultscan be subjected to independent statistical analysis.
PM 1 Im in charge of the construction of a retail development in thecentre of a large town. There are 26 retail units and a super market in
the complex. My main responsibilities are to co-ordinate the work of the various contractors to ensure that the project is completed tospecification, within budget and on time.
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
4/39
4
Characteristic of a project
A project is a temporary endeavour involving a connected sequence of activities and a range of resources, which is designed to achieve a
specific and unique outcome and which operates within time, costand quality constraints and which is often used to introduce change.
A unique, one-time operational activity or effortRequires the completion of a large number of interrelated activitiesEstablished to achieve specific objectiveResources, such as time and/or money, are limited
Project
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
5/39
5
Examples constructing houses, factories, shopping malls,
athletic stadiums or arenas developing military weapons systems, aircrafts,
new ships launching satellite systems constructing oil pipelines developing and implementing new computer
systems
planning concert, football games, or basketballtournaments introducing new products into market
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
6/39
6
Project Scheduling and Control Techniques
Gantt Chart
Critical Path Method (CPM)
Program Evaluation and Review Technique (PERT)
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
7/39
7
History of CPM/PERT
Critical Path Method (CPM) E I Du Pont de Nemours & Co. (1957) for construction of new
chemical plant and maintenance shut-down Deterministic task times Activity-on-node network construction Repetitive nature of jobs
Project Evaluation and Review Technique (PERT) U S Navy (1958) for the POLARIS missile program
Multiple task time estimates (probabilistic nature) Activity-on-arrow network construction Non-repetitive jobs (R & D work)
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
8/39
8
Project Network Network analysis is the general name given to certain specifictechniques which can be used for the planning, management andcontrol of projects Use of nodes and arrows
Arrows : An arrow leads from tail to head directionally Indicate ACTIVITY, a time consuming effort that is required to perform a
part of the work.where j > i
Nodes : A node is represented by a circle- Indicate EVENT, a point in time where one or more activities start and/or
finish.
Activity - A task or a certain amount of work required in the project Requires time to complete Represented by an arrow
Dummy Activity It indicates only precedence relationships
Does not require any time of effort
i j
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
9/39
9
Event Signals the beginning or ending of an activity Designates a point in time Represented by a circle (node)
Network Shows the sequential relationships among activities using nodes
and arrows
Activity-on-node (AON)
nodes represent activities, and arrows show precedencerelationships
Activity-on-arrow (AOA)
arrows represent activities and nodes are events for points intime
Project Network
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
10/39
10
AOA Project Network for House
32 0
13
1 11
1 2 4 6 7
3
5
Layfoundation
Design houseand obtainfinancing
Order andreceivematerials
Dummy
Finishwork
Selectcarpet
Selectpaint
Buildhouse
AON Project Network for House
13
2
2
43
31 5
1
61
71Start
Design house andobtain financing
Order and receivematerials
Select paintSelect carpet
Lay foundations Build house
Finish work
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
11/39
11
Situations in network diagram
AB
C
A must finish before either B or C can start
A
B
C both A and B must finish before C can start
D
C
B
Aboth A and C must finish before either of Bor D can start
A
C
B
D
DummyA must finish before B can start
both A and C must finish before D can start
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
12/39
12
Concurrent Activities
2 3
Lay foundation
Order material
(a) Incorrect precedencerelationship
(b) Correct precedencerelationship
3
42
DummyLayfoundation
Order material
1
2 0
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
13/39
13
Network exampleImmediate
Activity Predecessor Time (Hr.)A -- 6B -- 8C -- 5D B 13E C 9F A 15G A 17H F 9I G 6J D, E 12
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
14/39
14
CPM Example: CPM Network
1 8
3
7
4
2
5
A (6)
F(15)
B (8)
C (5)E(9)
D(13)
G(17) H(9)
I(6)
J(12)
6
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
15/39
15
CPM calculation
Path A connected sequence of activities leading from
the starting event to the ending event
Critical Path The longest path (time); determines the project
duration
Critical Activities
All of the activities that make up the critical path
d
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
16/39
16
Forward Pass Earliest Start Time (ES) - Earliest time an activity can start
ES = maximum EF of immediate predecessors Earliest finish time (EF) - Earliest time an activity can finish
It is computed by earliest start time plus activity timeEF= ES + t
Earliest Occurrence time of event i is denoted by E i.Therefore, E j = E i + t
Latest Start Time (LS) - Latest time an activity can start withoutdelaying critical path time
LS = LF t
Latest finish time (LF) - Latest time an activity can be completedwithout delaying critical path time
LF = minimum LS of immediate predecessorsLatest Occurrence time of event i is denoted by L j.Therefore, L i = L j t.
Backward Pass
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
17/39
17
CPM analysis
Draw the CPM network
Analyze the paths through the network Determine the float for each activity
Compute the activitys float float = LS - ES = LF - EF
Float is the maximum amount of time that this activity can bedelay in its completion before it delays completion of theproject.
Find the critical path is that the sequence of activities and events
where there is no slack i.e.. Zero slack Longest path through a network
Find the project duration is minimum project completion time
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
18/39
18
CPM Example: CPM Network
1 8
3
7
4
2
5
A (6)
F(15)
B (8)
C (5)E(9)
D(13)
G(17) H(9)
I(6)
J(12)
6
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
19/39
19
CPM Example: Forward Pass
1 8
3
7
4
2
5
A (6)
F(15)
B (8)
C (5)E(9)
D(13)
G(17) H(9)
I(6)
J(12)
6
E8=33
E6=21
E7=23
E5=21
E3=6
E2=8
E4=5
E1=0
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
20/39
20
CPM Example: Backward Pass
1 8
3
7
4
2
5
A (6)
F(15)
B (8)
C (5)E(9)
D(13)
G(17) H(9)
I(6)
J(12)
6
E8=33
E6=21
E7=23
E5=21
E3=6
E2=8
E4=5
E1=0L8=33
L7=27
L6=24
L5=21
L4=12
L3=9
L2=8
L1=0
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
21/39
21
After Forward and Backward Pass
1 8
3
7
4
2
5
A (6)
F(15)
B (8)
C (5)E(9)
D(13)
G(17) H(9)
I(6)
J(12)
6
E8=33
E6=21
E7=23
E5=21
E3=6
E2=8
E4=5
E1=0L8=33
L7=27
L6=24
L5=21
L4=12
L3=9
L2=8
L1=0
Critical Path1-2-5-8 or B-D-J
Total ProjectCompletiontime = 33 Hrs
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
22/39
22
CPM Example
ES and EF Times
1 8
3
7
4
2
5
A(6)
F(15)
B(8)
C(5)E(9)
D(13)
G(17) H(9)
I(6)
J(12)
6
0 6
0 8
0 5
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
23/39
23
CPM Example
ES and EF Times
1 8
3
7
4
2
5
A(6)
F(15)
B(8)
C(5)E(9)
D(13)
G(17) H(9)
I(6)
J(12)
6
0 6
0 8
0 55 14
8 21
6 23
6 21
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
24/39
24
CPM Example
ES and EF Times
1 8
3
7
4
2
5
A(6)
F(15)
B(8)
C(5)E(9)
D(13)
G(17) H(9)
I(6)
J(12)
6
0 6
0 8
0 55 14
8 21
6 23
6 21
21 33
21 30
23 29
Projects EF = 33
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
25/39
25
CPM Example
1 8
3
7
4
2
5
A(6)
F(15)
B(8)
C(5)E(9)
D(13)
G(17)
H(9)
I(6)
J(12)
6
0 6
0 8
0 55 14
8 2121 33
6 23
21 30
23 29
6 21
21 33
27 33
24 33
LS and LF Times
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
26/39
26
CPM Example
1 8
3
7
4
2
5
A(6)
F(15)
B(8)
C(5)E(9)
D(13)
G(17)
H(9)
I(6)
J(12)
6
21 33
21 30
23 29
21 33
27 33
24 33
LS and LF Times
0 6
0 8
0 55 14
8 21
6 23
6 21
4 10
0 8
7 12
12 21
8 21
10 27
18 24
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
27/39
27
CPM Example Float = LS - ES = LF - EF
1 8
3
7
4
2
5
A(6)
F(15)
B(8)
C(5)E(9)
D(13)
G(17)
H(9)
I(6)
J(12)
6
0 6
0 8
0 55 14
8 21 21 33
6 23
21 30
23 29
6 21
3 9
0 8
7 1212 21
21 33
27 33
8 21
10 27
24 33
9 24
3 4
3
3
4
0
0
77
0
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
28/39
28
CPM Example Critical Path
1 8
3
7
4
2
5
A (6)
F(15)
B (8)
C (5)E(9)
D(13)
G(17) H(9)
I(6)
J(12)
6
Critical Path1-2-5-8 or B-D-J
Total ProjectCompletiontime = 33 Hrs
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
29/39
29
Draw Network Compute Project Completion time and Find Critical path
Immediate
Activity Predecessor Time (days)A -- 8B A 12C A 4D B 2E B 8F D 2G E, F 3H C, G 2I E, F 2J I, H 2
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
30/39
30
PERT PERT is based on the assumption that an activitys duration
follows a probability distribution instead of being a single value
Three time estimates are required to compute the parameters of an activitys duration distribution: pessimistic time (t p ) - the time the activity would take if
things did not go well
most likely time (t m ) - the consensus best estimate of theactivitys duration optimistic time (t o ) - the time the activity would take if things
did go well
Mean (expected time): t e = tp + 4 tm + to 6
Variance: Vt= 2 =
tp - to
6
2
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
31/39
31
PERT analysis Draw the network.
Analyze the paths through the network and find the critical path. The length of the critical path is the mean of the project duration
probability distribution which is assumed to be normal The standard deviation of the project duration probability
distribution is computed by adding the variances of the criticalactivities (all of the activities that make up the critical path) andtaking the square root of that sum
Probability computations can now be made using the normal
distribution table.
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
32/39
32
Probability computation
Determine probability that project is completed within specified time
Z =x -
where = t p = project mean time or mean of the project duration
= project standard mean time
x = (proposed ) specified time
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
33/39
33
Normal Distribution of Project Time
Time x
Z
Probability
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
34/39
34
PERT Example
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.)A -- 4 6 8B -- 1 4.5 5C A 3 3 3D A 4 5 6E A 0.5 1 1.5F B,C 3 4 5
G B,C 1 1.5 5H E,F 5 6 7I E,F 2 5 8J D,H 2.5 2.75 4.5
K G,I 3 5 7
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
35/39
35
PERT ExampleActivity Expected Time Variance
A 6 4/9B 4 4/9C 3 0D 5 1/9
E 1 1/36F 4 1/9G 2 4/9H 6 1/9
I 5 1J 3 1/9K 5 4/9
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
36/39
36
PERT Example
7
2 5
3
A (6)
D (5)
C (3)
B (4)F (4)
E (1)
G (2)
I (5)
H (6)
K (5)
J (3)
1
6
4
PERT Network
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
37/39
37
PERT Example
Activity ES EF LS LF Slack A 0 6 0 6 0 *criticalB 0 4 5 9 5C 6 9 6 9 0 *D 6 11 15 20 9E 6 7 12 13 6F 9 13 9 13 0 *G 9 11 16 18 7H 13 19 14 20 1I 13 18 13 18 0 *J 19 22 20 23 1K 18 23 18 23 0 *
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
38/39
38
PERT Example
Vcritical path = V A + V C + V F + V I + V K = 4/9 + 0 + 1/9 + 1 + 4/9
= 2critical path = 1.414
z = (24 - 23)/ (24-23)/1.414 = .71
From the Standard Normal Distribution table:P(z < .71) = .5 + .2612 = .7612
What is the probability that the project will complete in 24 days ?
-
7/30/2019 Project_Network Analysis(PERT and CPM) L1
39/39
Probability the project will be completed within 24 hrs
23x
f (x)
24
P (z < .71) = .5 + .2612 = .7612
P (T< 24) = .7612
. 5 0 0 0
. 2 6 1 2