ProjectManagementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/lesson_6.pdf ·...

50
CLAMDAIM Giuseppe Gherardi Project Management 3. The Project Planning a. Project Plan Techniques a. Time planning b. Resource planning c. Economic planning

Transcript of ProjectManagementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/lesson_6.pdf ·...

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Project  Management  

3.  The  Project  Planning  

a.  Project  Plan  Techniques  a.  Time  planning  b.  Resource  planning  c.  Economic  planning  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  •  Up  to  now  we  have  been  planning  without  any  doubt  about  

the  resource  availability.  That  means  we  have  planned  with  an  unlimited  capacity.  

•  Yet,  resources  are  never  limitless,  that  is  why  we  have  to  create  a  logical  connecIon  between  acIvity  execuIon  and  resources  allocated  for  it.  This  means  working  with  a  limited  capacity.  

•  We  will  see  how  to  integrate  Ime  planning  with  resource  planning,  how  to  define  resource  availability,  how  to  balance  resource  allocaIon,  how  to  react  when  resources  are  not  enough.  

•  Resources  are  not  only  HR,  but  also  machinery,  ICT,  structures,  etc.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  •  Unit  of  measurement  –  once  we  have  allocated  resources,  the  

first  problem  we  have  is  how  to  measure  their  use.  We  need  to  choose  the  unit  of  measurement.  How  we  will  allocate  costs  depends  on  this  choice.  Typical  units  are:  

 

–  Hours/man,  days/man  –  Hours  machinery  –  Design  hours  –  ICT  or  Data  Processing  hours  –  ….  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  •  CreaIng  an  integraIon  between  .me  and  resources  is  a  

criIcal  operaIon.  In  order  to  understand  which  of  the  two  variables  is  prevailing,  we  need  to  understand  in  what  planning  situaIon  we  are  working  in.  

–  Time  Limited  situa.on  –  the  project  must  be  completed  within  a  defined  Ime  and  cannot  be  delayed.  The  criIcal  variable  is  TIME.  Every  over  allocaIon  must  be  saIsfied  by  adding  resources.  Es:  projects  with  delay  fees.  

–  Resource  Limited  situa.on  –  the  project  must  be  completed  in  the  shortest  Ime  possible,  but  we  have  a  limited  number  of  resources  and  we  cannot  increase  it.  The  criIcal  variable  is  RESOURCES.  Every  over  allocaIon  will  not  be  solved  adding  resources,  but  adding  Ime  (which  means  a  delay).  

 

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  •  Once  we  have  esImated  the  resource  quanIty  we  

need  to  complete  the  task  within  the  requested  Ime,  we  need  to  evaluate  the  total  resource  investment  (resource  charge).  

•  InformaIon  we  need  to  evaluate  resources  charges  are:  –  Resource  descrip,on  –    –  Resource  use  quan,ty–  tell  how  the  resource’s  Ime  is  

employed,  i.e.  what  is  forecasted  from  the  resource  calendar  

–  Resource  use  dura,on  –  how  long  a  resource  is  busy  in  a  specific  task  for.  

 

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  •  Recall  the  example:  

•  The  unit  of  measurement  is  the  standard  working  day,  8  hours.  All  the  resources  are  on  duty  at  100%.  No  lead  Ime.  

Code Description Duration Att. Prec. Resource Quantity (h) Duty (days)1 Start 0 - -2 A 7 1 Riffoni 8 73 B 5 2 Cerami 8 54 C 2 1 Massi 8 25 D 17 4 Massi 8 176 E 12 2,4 Cerami 8 127 End 0 3,5,6 FS

S  A  

C  

B  

E  

D  

F  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  

•  Recall  the  example:   S  A  

C  

B  

E  

D  

F  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  •  Riffoni  Charge  Diagram  will  be:  

•  Riffoni  is  allocated  8  hours  a  day  for  the  first  7  project  days.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  •  Cerami  Load  Diagram  is:  

•  Cerami  is  over  charged  for  a  200%  of  his  availability..  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  •  In  this  case  Mr  Cerami  sums  up  the  work  on  the  acIvity  B  and  

E.  B  and  E  are  parallel  for  a  part  of  their  duraIon.    •  If  we  consider  Massi,  we  have  no  overload  because  the  two  

acIviIes  he  is  involved  in  have  no  overlap.  

•  Mr  Cerami  cannot  work  for  16  hours  a  day  for  5  days,  so  we  have  a  problem.  What  can  we  do  to  allow  the  project  to  proceed?  

•  This  kind  of  problem  is  solved  through  resource  levelling  techniques.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES  

•  When  we  allocate  resources  we  have  to  consider  possible  constraints  in  the  resource  uIlizaIon.  

•  Once  a  resource  is  charged,  we  can  have  two  cases:  

–  Resource  overload  –  requested  resources  are  more  than  we  have.  This  situaIon  needs  to  be  fixed  otherwise  we  will  surely  have  a  delay.  

–  Resource  underload  –  requested  resources  are  less  than  we  have.  In  this  case  we  could  have  a  resource  under  use  that  increases  costs.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES    •  The  LEVELLING  TECHNIQUE  consists  in  moving  one  or  more  acIviIes  

through  the  Imeline  in  order  to  keep  the  resource  Load  Diagram  under  the  100%  level.  

•  Op.miza.on  –  we  can  level  resources  with  algorithms  from  the  OperaIonal  Research,  in  this  way  ,we  will  have  the  best  mathemaIcal    soluIon  by  opImizing  all  the  declared  targeted  variables  (ex.:  less  use  of  expensive  resources,  the  shortest  project  Ime,  best  sequence  of  criIcal  acIviIes…)  

•  Heuris.c–  this  method  consists  in  re-­‐allocaIng  acIviIes  through  the  Imeline  in  order  not  to  have  the  resource  100%  busy.  It  has  not  the  mathemaIcal  rigorousness  but  it  is  the  most  adopted.    

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES  

•  StarIng  from  the  plan,  we  analyze  every  resource  verifying  the  charge  level.    

•  When  we  find  an  overloaded  resource,  the  heurisIc  model  verifies  the  acIviIes  in  that  period  and  moves  the  acIvity  where  the  specific  resource  is  involved  in,  unIl  we  get  to  a  situaIon  where  resources  are  not  overloaded  any  more.  We  can  follow  defined  prioriIes.    

 

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES  

•  Mr  Cerami  was  overloaded  having  to  work  16  hours/day  for  5  days.  Try  to  level  the  resource!  

•  Mr  Cerami  is  involved  in  two  acIviIes:  B  and  E:  First  I  define  which  is  the  priority  task  and  then  I  chose  what  acIvity  is  moving  first;  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES  

•  If  we  assume  that  the  acIvity  B  takes  priority  over  E,  we  can  then  move  E  5  days  forward  and  we’ll  have  levelled  the  load  on  Cerami  calendar.  

•  Yet,  the  project  will  delay  and  end  on  day  24!    •  The  criIcal  paths  is  modified  too:  in  fact  acIviIes  C  and  D  

gain  scrolling  Ime!  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES  

•  If  we  check  the  Cerami  Load  Diagram,  we  will  see  that  is  levelled,  non  overloaded!  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES  

•  If  we  define  that  E  takes  the  priority,  we’ll  try  to  move  B:  

•  The  project  will  finish  on  day  24  and  A  and  B  will  be  criIcal  acIviIes.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES  •  If  more  than  one  resource  is  overloaded,  in  case  of  manual  levelling,  we  

need  to  define  a  levelling  order  and  then  level  one  resource  at  the  Ime.  

•  Criteria  to  order:  –  First,  the  shortest  acIviIes  –  First,  acIviIes  with  minor  impact  on  the  project  duraIon  –  First,  acIviIes  with  minor  end  date  –  First,  acIviIes  that  use  the  same  resource  –  First,  acIviIes  with  the  highest  resource  requirement  –  First,  acIviIes  with  minor  scrolling  Ime  –  First,  acIviIes  with  the  highest  criIcal  acIviIes  –  First,  acIviIes  with  the  highest  number  of  acIviIes  following  –  First,  acIviIes  with  the  highest  maximum  end  date  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES  

•  The  choice  between  two  different  levelling  methods  can  lead  to  different  outcomes  in  terms  of  project  lengthening  or  increase/decrease  of  criIcal  acIviIes.  

•  In  pracIce,  we  can  noIce  that  in  case  of  projects  with  a  significant  number  of  acIviIes  it  is  not  possible  to  esImate  all  conflicts  manually.  

•  You  then  have  to  use  a  special  somware  with  a  scheduling  tool  that  automaIcally  performs  the  levelling  once  the  work  parameters  have  been  set.    

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES  

•  A  secondary  target  of  levelling  techniques  is  to  regularize  the  resource  use  within  the  project  

•  In  fact,  the  best  project  situaIon  is  to  have  regularity  in  the  resource  load.  Irregular  loads  requires  highest  management  effort  

•  Pay  anenIon!  Very  omen  we  don’t  need  the  levelling  phase  in  case  of  Ime  limited  overloaded  situaIons.  In  these  cases  before  levelling  (and  causing  a  possible  delay),  we  can  take  the  following  acIons:  

•  Over,me,    •  Resources  increase,    •  Outsourcing  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES  

•  OverIme  –  We  modify  the  resouce  calendar  (we  define  a  resource  calendar  instead  of  a  

project  calendar)  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Resource  Planning  RESOURCE  LEVELLING  TECHNIQUES  

•  Adding  more  resources  –  In  this  case  the  variable  becomes  the  number  of  resources  I  can  

allocate  on  the  task.  By  doubling  resources,  Cerami  goes  back  to  a  normal  load.  

 ID Nome risorsa Tipo Iniziali Unità max Tariffa std. Tariffa str. Costo/Uso Attribuiti Calendario di base Codice1 Riffoni Lavoro R 1 € 0,00/h € 0,00/h € 0,00 In quote Standard2 Cerami Lavoro C 2 € 0,00/h € 0,00/h € 0,00 In quote Standard3 Massi Lavoro M 1 € 0,00/h € 0,00/h € 0,00 In quote Standard

•  Outsourcing  –           The  task  is  allocated  to  an  external  resource.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Project  Management  

3.  The  Project  Planning  

a.  Project  Plan  Techniques  a.  Time  planning  b.  Resource  planning  c.  Economic  planning  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  •  When  we  plan  a  project,  every  single  choice  on  resource  

allocaIon  concerning  HR,  instrumental  or  economic  resources  has  a  direct  impact  on  project  costs.  

•  Therefore,  it  is  necessary  to  define  an  economical/financial  plan  together  with  the  Ime  and  resource  plan.  This  is  called  Project  Budget.    

•  In  the  Project  Budget  we  can  find  all  the  forecasted  costs  necessary  to  perform  each  acIvity  and  the  performance  measures  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  •  The  project  economic  evaluaIon  can  be  read  through  two  

different  criteria:  

–  Effec.veness/Efficiency  –  the  ability  to  achieve  project  targets  (effecIveness)  in  economic  balanced  condiIons  and  with  less  resource  consumpIon  as  possible  (efficiency).  EffecIveness  and  efficiency  are  defined  in  costs,  ,me  and  quality.  

–  Project  target  –  that  is  the  target,  the  result,  it  defines  the  success  or  failure  of  an  entrepreneur,  an  idea,  in  terms  of  compeIIon,  market  success,  economics.  If  refers  to  ROI  criteria.  

•  We  will  mainly  consider  the  cost  measurement  (Efficiency/EffecIveness).  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  •  However,  evaluaIng  the  project  costs,  i.e.  the  economical/

financial  requirements  of  a  project,  is  very  hard:  –  Projects  are  a  whole  of  complex  and  non-­‐repeIIve  acIviIes,  with  a  

great  amount  of  logical  and  Ime  connecIons;  –  Projects  duraIon  goes  from  medium  to  long;  –  Projects  have  non-­‐repeIIve  outputs.  

•  Those  features  make  the  correlaIon  between  targets  and  results  very  hard  to  anIcipate.  RepeIIve  processes  are  referred  to  standard  processes  (predicIve),  but  projects  are  very  different.  

•  So  we  need  to  analyze  projects  WHILE  they  are  happening,  with  a  low  arranged  output  standardizaIon.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  

•  This  means  that  TIME  variable  is  taken  into  consideraIon  within  all  economical  comparisons  :    

–  During  the  forecast  phase  –  through  Budget  Review  techniques,  economical  simulaIons,…    

–  During  the  final  closing  phase  –  through  a  combined  evaluaIon  of  costs  and  acIvity  progress  performance  -­‐  Earned  Value  technique.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  BUDGET  REVIEW    •  Projects  acIviIes  have  non  linear  intensity  throughout  the  Ime  so  the  

economic  consumpIon  is  not  linear  either.  We  need  to  plan  in  advance  WHEN  we  will  have  costs.  1.  Analysis  of  forecasted  costs  for  each  acIvity  2.  DefiniIon  for  each  acIvity  of  the  medium  cost  for  Ime  unit                                        Cost  Slope  =  ac=vity  cost  /  ac=vity  dura=on  3.  We  will  define  a  period  and  we  will  evaluate,  for  each  period,  the  costs  we  

forecast  to  have.  By  this  easy  way,  we  can  build  a  sheet  called  Project  Cost  Schedule.  Through  the  Project  Cost  Schedule,  we  can  build  the  Gann  Cost  Schedule.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  BUDGET  REVIEW  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  BUDGET  REVIEW    

               

We  assume  a  period  of  3  weeks  

Activity Cost Duration Cost slopeeur week eur/week

Facility flow definition 3000 2 1.500 Volumes definition 1600 2 800 Layout 6000 2 3.000 Preliminary design 22000 4 5.500 Price list 20000 3 6.667 Contracts 8000 2 4.000 Executive design 18000 5 3.600 Area research 5000 2 2.500

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  BUDGET  REVIEW–  Project  Cost  Schedule  

Slot Activity Duration Cost slope TOTALweek eur/week eur/period

1-3 Fac flow def 2 1.500 3.000 Volumes def 1 800 800

3.800 4-6 Volume def 1 800 800

Layout 2 3.000 6.000 6.800

7-9 Preliminary design 3 5.500 16.500 16.500

10-12 Preliminary design 1 5.500 5.500 Price list 2 6.667 13.334

18.834 13-15 Price list 1 6.667 6.667

Contracts 2 4.000 8.000 14.667

16-18 Executive design 3 3.600 10.800 10.800

19-21 Executive design 2 3.600 7.200 Area research 1 2.500 2.500

9.700 22-24 Area research 1 2.500 2.500

2.500 TOTAL PROJECT COST 83.601

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  BUDGET  REVIEW–  Gan?  Cost  Schedule  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  BUDGET  REVIEW  –  Bar  Chart  Cost  Schedule  

4.  Then  we  build  the  Bar  Chart  Cost  Schedule,  where  we  will  see  the  financial  commitment  for  each  period.  

5.  Through  the  Gann  analysis  we  can  define  acIviIes  with  a  big  cost  slope  that  may  be  reallocated  to  have  a  bener  cost  distribuIon  (even  respecIng  targets).  

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

1-3 4-6 7-9 10-12 13-15 16-18 19-21 22-24

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  ECONOMICAL  ADVANTAGE  EVALUATION  –  Cost  slope  vs  Crash  ,ming  

•  A  project  may  require  extra  ac.vi.es  to  accelerate  Ime  and  reach  results  early  (like  overIme,  adding  resources,  fast  supplies).    

•  Very  omen  those  acIviIes  increase  project  costs  •  We  have  then  to  define  if  we  have  an  advantage  between  

normal  project  Ime  (normal  Iming)  or  accelerated  Ime  (crash  Iming)  

•  In  this  way  even  the  project  Ime  reducIon  will  be  evaluated  in  terms  of  economical  advantage  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  ECONOMICAL  ADVANTAGE  EVALUATION  –  Cost  slope  vs  Crash  ,ming  •  If  we  consider  just  one  acIvity,  the  correlaIon  between  cost  increase  and  

Ime  reducIon  is  expressed  by  a  new  cost  slope:  

Cost  slope  =  (crash  cost  –  normal  cost)  /  (normal  =ming  –  crash  =ming)  

•  We  have  to  consider  that:  –  The  duraIon  decrease  is  possible  by  operaIng  only  on  the  acIviIes  on  the  

criIcal  path  (otherwise  we  will  have  only  cost  increase  and  no  benefit)  –  Not  always  Ime  reducIon  allows  more  cost  savings  –  Very  omen  indirect  costs  (overheads)  are  allocated  according  to  the  project  

duraIon,  so  if  we  reduce  its  duraIon,  we  will  have  an  overhead  cost  reducIon!  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  

Cost  slope  =  (crash  cost  –  normal  cost)  /  (normal  =ming  –  crash  =ming)  =  (10.000-­‐6.000)  /  8-­‐6  =  2.000  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  ECONOMICAL  ADVANTAGE  EVALUATION  –  Cost  slope  vs  Crash  ,ming  •  We  need  to  find  a  balance  between  cost  saving  given  by  Ime  reducIon  

and  cost  increase  due  to  crash  acIviIes  •  In  this  way,  we  will  have  advantages  if  we  start  cuKng  =me  from  

ac=vi=es  with  the  lowest  cost  slope  which  are  part  of  the  cri.cal  path  •  However,  we  must  be  careful  because  the  overhead  cost  reducIon  has  a  

linear  trend,  but  the  direct  cost  increase  is  more  than  linear  because  we  decided  to  start  first  from  the  lowest  cost  slope  acIvity.    We  will  get  to  a  balance  point  beyond  which  overhead  cost  reduc=on  doesn’t  compensate  direct  cost  increase  any  more.  

•  If  we  define  a  daily  cost  coefficient  of  the  project  overhead,  we  can  say  that  the  total  project  cost  starts  to  decrease  when  we  reduce  ac.vi.es  having  cost  slope  lower  than  the  unitary  overhead  cost  coefficient,  and  they  increase  when  the  cost  slope  is  higher.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  ECONOMICAL  ADVANTAGE  EVALUATION  –  Cost  slope  vs  Crash  ,ming  Example    

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  ECONOMICAL  ADVANTAGE  EVALUATION  –  Cost  slope  vs  Crash  ,ming  Example  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  If  we  haven’t  a  budget  big  enough,  or  if  the  advantage  connected  to  the  crash  Ime  is  not  enough  to  jusIfy  the  cost  increase,  it  is  clever  looking  for  crash  values  only  for  some  criIcal  acIviIes  with  a  linle  cost  slope.      We  can  think  a  series  of  acIons  with  a  decreasing  marginal  improvement  connected  to  a  Ime  reducing.  We  can  define  the  stop  point  related  to  our  budget  possibility.  For  example:  our  available  budget  is  4.000€.    

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  If  we  add  to  the  model  also  the  indirect  costs,  we  can  see  that  the  two  trends  (decrease  of  indirect  costs  and  increase  of  direct  costs)  can  cross  in  a  point.  In  parIcular,  the  total  project  cost  will  decrease  when  each  cost  slope  related  to  direct  costs  will  have  a  value  smaller  than  the  unit  coefficient  of  the  indirect  costs.  The  total  project  cost  will  increase  when  the  costs  slope  will  be  bigger  than  the  unit  coefficient  of  the  indirect  costs.  This  means  that  beyond  some  values  reducing  Ime  is  too  expensive!  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  EARNED  VALUE      •  When  we  evaluate  a  project  under  an  economical  point  of  view,  we  

cannot  ignore  the  .me  variable.  

•  Earned  Value  expresses  the  project  progress  by  measuring  the  value  of  the  completed  project  part.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  EARNED  VALUE      First,  we  need  to  define  the  following  values:  

–  Scheduled  costs  of  planned  ac,vi,es  BCWS  (Budget  Cost  of  Work  Scheduled)  –  Scheduled  costs  of  completed  ac,vi,es  BCWP  (Budget  Cost  of  Work  

Performed)  –  Real  cost  of  completed  ac,vi,es  ACWP  (Actual  Cost  of  Work  Performed)  

•  The  project  progress  state  (earned  value)  is  the  BCWP,  that  is  the  economical  evaluaIon  of  performed  work,  expressed  with  the  same  criteria  used  in  the  budget  

 

                   Earned  Value  =  BCWP  =  budget  cost  of  completed  acIviIes    

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  EARNED  VALUE      We  can  calculate  :  

–  Cost  variance                                                                                Cost  variance  =  BCWP  –  ACWP    –  Cost  Performance  Index                                                                                            CPI  =  BCWP  /  ACWP    –  Schedule  variance                                                                                Schedule  variance  =  BCWP  –  BCWS    –  Schedule  Performance  Index                                                                                            SPI  =  BCWP  /  BCWS    

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  EARNED  VALUE  –  Graphic  meaning  The  BCWS  curve  shows  scheduled  Ime/costs;  the  BCWP  represents  actual  Ime/costs  with  

budgeted  costs,  the  ACWP  represents  actual  Ime/costs  with  actual  costs    

Costs  

Time  

A   B  

BCWS  

ACWP  

BCWP  

SV  schedule  variance  

CV  cost  variance  

Delay  

Cost  level  reached  at  that  date  based  on  the  work  really  performed  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  EARNED  VALUE  –  Matrix  SPI/CPI  •  Within  the  performance  evaluaIon,  the  correlaIon  CPI/SPI  analysis  allow  us  to  

understand  the  state  of  the  project  under  a  cost/Ime  profile  

UNCERTAIN  PERFORMANCE  

NEGATIVE  PERFORMANCE   UNCERTAIN  PERFORMANCE  

POSITIVE  PERFORMANCE  

SPI  

CPI  

1  

1  

+  

-­‐  

+  -­‐  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  EARNED  VALUE      The  Earned  value  technique  requires  cost  esImate  of  acIviIes  

completed  at  a  specific  date.  •  The  main  methods  to  measure  Earned  Value  are:  

–  Milestone  –  each  milestone  is  correlated  with  a  budget  value;  making  a  raIo  with  the  total  budget,  we  can  evaluate  the  completed  work;  

–  Formula  –  we  can  define  fixed  score  to  evaluate  acIvity  compleIon  (example:  we  have  an  acIvity  split  into  two  periods.  We  consider  0  score  when  the  acIvity  hasn’t  started  yet;  50/100  when  it  has  started  and  100/100  at  the  end)    

–  Percentage  of  compleIon  –  we  set  a  percentage  that  represents  the  acIvity  compleIon;  

–  Mixed  –  compleIon  percentage  with  milestone.  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  EARNED  VALUE      The  Earned  Value  can  get  forecasIng  informaIon  concerning  the  future  project  

trend:  that  is  the  total  esImated  cost  at  project  compleIon  EAC  (Es.mated  Costs  at  Comple.on).  

•  Among  various  methods  we  have  the  Cumula.ve  CPI  Es.mate  at  Comple.on.  This  method  says  that  total  costs  are  es,mated  on  the  basis  of  actual  costs  plus  budgeted  costs  at  comple,on,  adjusted  to  consider  the  performance  level  shown  up  to  that  date.  (compounded  CPI)  

 EAC  =  (total  bgt  –  earned  value)  /  CPI  (cumula=ve)  +  Real  effec=ve  costs  (actual  costs)    EAC  =  (total  bgt  –  BCWP)/CPI  +  ACWP  

CLAM

DA-­‐IM

 Giusepp

e  Gh

erardi  

Economic  Planning  EARNED  VALUE    -­‐  example    The  Earned  value,  BCWP,  at  a  defined  date  could  be  calculated  by:    1.  We  sum  all  the  budget  cost  of  completed  acIviIes  at  the  date  2.  For  WIP  acIviIes,  we  molIply  the  budget  cost  for  the  compleIIon  

percentage  for  each  acIvity  3.  We  sum  values  from  point  1  and  2.    

4.  We  compare  the  BCWP  and  BCWS  and  ACWP