What is ctcLink?• ctcLink is the implementation of a single, centralized
system of integrated software tools that will give students, faculty and staff anytime, anywhere access to a more efficient way of doing their college business.
• As the legacy system is replaced with modern technology, colleges will also redesign and align current business processes with streamlined, standardized processes, as delivered in the new software solution.
• This common suite of online tools will help create efficiencies system-wide, help us keep pace with innovations in teaching and learning, and provide the services students and staff expect in today’s digital world.
Today’s topics• ctcLink Project Team Activities
– Project kickoff activities with Ciber– Project Management– Global Solution / BPR– FirstLink Colleges– Organizational Change (Survey/Results/Outcomes)– Project Collaboration Site– Communications Tools– Project Team
• Project Roadmap• Next Steps
Project Team Activities• Project kickoff with Ciber
– Implementation planning, including project timeline; detailed work plan; schedule of events
– Project kick-off meetings with the ctcLink core project team
– ctcLink project team training– Project kick-off sessions with presidents, college
teams and FirstLink College teams/SMEs– Global Solutions process with system-wide SME
teams
Project Team Activities, cont.• Project Management
– Jeff Thompson, Collegiate Project Services– PM experience with several similar projects – Previously CIO at two different universities – Focusing on project startup activities
• Project Management Plan• Project Schedule• Budget / Expenditure Model• Project Management Tools• Risk Management / Issues Management
– Will coordinate vendor PM and future PMs at colleges
Project Team Activities, cont.• Global Solution / Business Process Redesign
– Global Solution: Aligning core business processes with the delivered solution (new software) and addressing any gaps or system-wide configuration deemed necessary.
– Analysis of current Business Process Documentation• Colleges and SBCTC providing existing documentation – Feb 15 • ctcLink team inputting into inventory catalog, analyzing for
similarities/differences in processes• Gain system-wide perspective on how colleges do things now and how
those processes will fit into the new system
– System-wide Subject Matter Experts Teams• Recruitment process underway soon• Core teams of SMEs for workshops March - May• Chance to test drive the delivered software solution• Review for any gaps
Project Team Activities, cont.• FirstLink College District Activities
– Readiness Survey and Results• OCM Team administered survey in November• Survey results analyzed• On-campus results sessions in January• Recommendations made based on results
– Communication methods / activities– Employee engagement timing and activities
– Business Process Documentation Pilot– Preliminary Staffing Plans, Project Management
Project Team Activities, cont.• Organizational Change Management (OCM)
– Readiness Survey with FirstLink Colleges– Outcome:
• OCM Plan improvements• Specific recommendations for each college
– Survey Tool Refinement– Refine Process – Offer to more colleges in near future to gauge
readiness, understanding and involvement of staff
Project Team Activities, cont.• Project Collaboration Site
– SharePoint/Office 365 ctcLink Collaboration Site– Building secure work areas– Project team, vendor team, college teams will have
access to collaborate within the site
Project Team Activities, cont.• Communications Tools
– On website: http://ctclink.sbctc.edu• Frequently Asked Questions – (Recently updated)
– Useful tool to answer high-level questions about the project
• College Resources page– List of College Teams/SMEs (know who’s on your
team)– Additional tools/resources (check it out!)
– Team email distribution lists• To share/discuss important information with college teams
– Quarterly Newsletter– ctcLinkCONNECT blog: ctcLink.wordpress.com
• Please sign up!• Ask colleagues to sign up
Project Roadmap
Global Solution: Align core business processes with new software, Build, Test FirstLink (pilot colleges): Configure, Test, Train, Go Live Waves: 8 colleges deployed per wave (TBD with Ciber)
20172013 2014 2015 2016
Global SolutionFeb - Aug
FirstLink CollegesMar 2013 - Aug 2014
Wave 1 CollegesAug - May
Wave 2 CollegesMay - Feb
Wave 3 CollegesFeb - Oct
Wave 4 CollegesOct - Jul
Next Steps in review• Business Process Documentation
– Analyze documentation• Identify areas of consistent business processes • Identify those that are widely varied across the colleges
– Identify challenging areas for data migration– Analysis of complex coding processes
• Unusual Action Codes, FAPC/Award Codes, Education Program Code, and reviewing MIS reporting inconsistencies
• Project kickoff • SME teams recruiting & session schedule• Global Solution / Business Process Analysis
Thank You! Questions?