Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Transcript of Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC...

Page 1: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop

Eric Martineau – February 3, 2016

Page 2: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Content

•  Current state of the wharf

•  Stabilization recommendation

•  Construction work

2  

Page 3: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Project Objective Ensure  the  stability  of  the  wharves  and  enable  the  use  of  the  wharf  and  its  ground  surface  for  port  opera8ons  over  the  medium  term.    

Q106 Q105

Page 4: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Situation actuelle •  Wooden  wharf  constructed  around  1925  •  Expected  lifespan:  25  years  •  Max.  deforma8ons  of  the  wharf:  1,860  mm  (Q105)  

 3,360  mm  (Q106)  

Page 5: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Rehabilitation Options Reconstruc8on  of  the  Wharf   $26,700,000  

Page 6: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Rehabilitation Options Wharf  Stabiliza8on  –  Scenario  1   $5,050,000  

Page 7: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Rehabilitation Options Wharf  Stabiliza8on  –  Scenario  2   $3,250,000  

Page 8: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Tie-beam Installation Diagram

Page 9: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Construction Work Worksite  

Page 10: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Construction Work Drilling  Work  

Page 11: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Construction Work Soil  Basin    

Page 12: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Construction Work Conflict  with  Exis8ng  Wharf  

Page 13: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Construction Work Tie-­‐beam  Installa8on  

Page 14: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016

Construction Work Tie-­‐beam  Tensioning  

Page 15: Project to stabilize wharves 105 and 106€¦ · Project to stabilize wharves 105 and 106 2016 RPIC Marine Infrastructure National Workshop Eric Martineau – February 3, 2016