Project: Talley Road Phase I Non-Tolled (BC03)
Transcript of Project: Talley Road Phase I Non-Tolled (BC03)
Limits: Potranco Road (FM 1957) to Wiseman Blvd.
Contractor: Texas Sterling Construction
Engineer: CP&Y, Inc.
Construction Cost: $22,305,572.62
Construction NTP: 11/11/19
Contract Completion Date: 07/05/22
Projected Completion Date: 04/25/22
Scope: Expand from an existing two-lane ruralroadway to a four-lane urban roadway consistingof two 12-foot travel lanes in each direction, amedian, curb, and sidewalk.
Status: 40% Paid Out, 41% Time used
Monthly Activity:
• Installing 16” D.I. Watermain on Talley Road
• Installing 24” RCP on Talley Road.
• Installing 4X4 SBC Boxes
• Installing culvert boxes
• Installing CMP 30” pipe and structure
• Placing and building forms for bridge deck.
Updated: March 09, 2021
ALAMO REGIONAL MOBILITY AUTHORITYCOUNTY OF BEXAR
Project: Talley Road Phase I – Non-Tolled (BC03)