Team GPXCleaner. Project Status Update #2. What has been done?. Many GUI improvements User controls and embedded map Point-reduction algorithm implemented Approx. 90% of implementation done. What is there to do?. Simple GUI vs. Expert GUI Improving usability Tooltips, m nemonics, ... - PowerPoint PPT Presentation
Transcript of Project Status Update #2
208-12-16
What has been done?
• Many GUI improvements– User controls and embedded map
• Point-reduction algorithm implemented
• Approx. 90% of implementation done
608-12-16
What is there to do?
• Simple GUI vs. Expert GUI
• Improving usability– Tooltips, mnemonics, ...
• Wildpoint detection and deletion– Parsing date/time in GPX format