Project Status & Right-of-Way Acquisition
description
Transcript of Project Status & Right-of-Way Acquisition
Community DevelopmentDepartme
nt
Project Status&
Right-of-Way Acquisition
Community DevelopmentDepartme
nt
FDOT DEVELOPMENT PROCESS
Community DevelopmentDepartme
nt
PROJECT LIMITSCypress Point Parkway to Florida Park Drive ~ 1.23 miles
Community DevelopmentDepartme
nt
• The widening of Palm Coast Parkway from a 4-lane divided, rural typical section to a 6-lane divided, urban typical section would consist of adding one travel lane along the outside lane in each direction, a distance of approximately 1.23 miles.
• The existing bridge over I-95 was built to accommodate future widening.
PROJECT SUMMARY
Community DevelopmentDepartme
nt
• Long Range Planning: A Needs Assessment for a project is conducted based
upon capacity and safety. July 1989 Flagler County adopted the following traffic
circulation policy as part of a Comprehensive Plan:“Projected traffic circulation system demand through the year 2000 will be met by undertaking the following projects:2.) Palm Coast Parkway from I-95 to Old Kings Road requires four (4) additional lanes by 1995; (2LD to 6LD)”
January 2000 Flagler County adopted the following policy as part of an updated Comprehensive Plan:
“Policy 2.3.1: Projected traffic circulation system demand through the year 2010 will be met by undertaking the following projects:1) Palm Coast Parkway from Cypress Point Parkway to Old Kings Roadrequires two (2) additional lanes by 2010: (4LD to 6LD).”
August 2003 City Council approved FDOT Work Program Priority List that identified this project as a project to be included on the Flagler County Priority List.
2004 City Council adopted Palm Coast’s 2020 Comprehensive Plan that included this specific project.
PROJECT DEVELOPMENT PROCESS
Community DevelopmentDepartme
nt
• PD&E Phase: 2006-2010 February 2006 City Council Approved a Local Agency
Program Agreement (LAP) with FDOT for the Project Development and Environmental Analysis Phase (PD&E)
The project was screened through FDOT’s Efficient Transportation Decision Making (ETDM) Process. This includes federal and state permitting and resource agency review and includes effects on resources such as archaeological, wetlands, floodplains, threatened & endangered species and mobility.
January 7, 2009 a Public Information Meeting was held. March 16, 2010 a Public Hearing was held. November 2010 the PD&E phase was completed and
approved by FDOT.
PROJECT DEVELOPMENT PROCESS
Community DevelopmentDepartme
nt
• Design Phase: 2011-2013 October 2010 City Council Approved a Local Agency
Program Agreement (LAP) with FDOT for the Design Phase.
April 12, 2012 a Public Meeting was held to update the public on the project status and review of the project design.
January 2013 the Final Design Plans were submitted.
PROJECT DEVELOPMENT PROCESS
Community DevelopmentDepartme
nt
• Right-of-Way Acquisition: 2012-2013 2012 the city submitted purchase offers to the property
owners of the lands necessary for easements or acquisition to complete the Palm Coast Parkway 6-Laning Project.
2012-2013 negotiations took place between the city and property owners.
February 26, 2013 city staff presents council with agenda item for the purchase of the necessary Right-of-Way.
PROJECT DEVELOPMENT PROCESS
Community DevelopmentDepartme
nt
• Construction Phase: Projected for 2013-2015 FDOT has allocated funding for the construction phase in
the current fiscal year budget. Agreements for this Phase of the project to be executed
prior to July 1, 2013. Bid and Award of Project anticipated to occur during the
summer of 2013. Construction to begin in the Fall of 2013 and to be
completed by the end of 2015.
PROJECT DEVELOPMENT PROCESS
Community DevelopmentDepartme
nt
PROJECT LAYOUT
Community DevelopmentDepartme
nt
PROJECT LAYOUT
Community DevelopmentDepartme
nt
• Reduce congestion (increase level of service and reduced travel times).
• Improve safety for vehicles and pedestrians as well as potential for accidents.
• Improve mobility for emergency vehicles.• Improve westward hurricane evacuation operations.• Provide an 8-foot sidewalk along the roadway and bridge in both
directions to accommodate pedestrians and bicyclists.• Provide dedicated turn lanes.• Provide concurrent left turns at Cypress Point Intersection and
Old Kings Road.• Extension of street lighting.• Enhanced Landscaping and conversion of irrigation to re-use.
PROJECT BENEFITS
Community DevelopmentDepartme
nt
TREE IMPACTS
Specimen Trees
13 Existing to be Removed
40 New to be Planted
25% over code requirements
Palm Trees
157 Existing to be Removed
203 New to be Planted
140 Extra palm trees over code requirements
Summary
366 Existing trees to be Removed
419 New trees to be Planted
*NO HISTORIC TREES ARE TO BE REMOVED AS PART OF THIS PROJECT*
Community DevelopmentDepartme
nt
FDOT$1,356,250.4
5
CITY $265,991.95
TOTAL: $1,622,242.40
PROJECT EXPENSES TO DATE
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
5 Parcels are necessary for the completion of this project.
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
Wachovia Bank National Association (Wells Fargo Bank)
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
Wachovia Bank National Association (Wells Fargo Bank) Parcel 102 (540sf) $20,000.00
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
Wachovia Bank National Association (Wells Fargo Bank)
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
Wachovia Bank National Association (Wells Fargo Bank)
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
Cypress Point at Palm Coast Owners Association, Inc.Parcel 100 (1,267sf) $25,920.00Parcel 101 (712sf) $14,640.00Parcel 801 (2,668sf) $54,427.20
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
Cypress Point at Palm Coast Owners Association, Inc.Parcel 100 (1,267sf) $25,920.00Parcel 101 (712sf) $14,640.00Parcel 801 (2,668sf) $54,427.20
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
Cypress Point at Palm Coast Owners Association, Inc.
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
Cypress Point at Palm Coast Owners Association, Inc.
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
Peggy Lane, LLC (Dunkin Donuts)
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
Peggy Lane, LLC (Dunkin Donuts)Parcel 104 (2,343sf) $60,900.00
Community DevelopmentDepartme
nt
CITY COUNCIL ACTION• Right-of-Way Acquisition
Peggy Lane, LLC (Dunkin Donuts)