PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER...

37
PROJECT STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI

Transcript of PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER...

1

PROJECT STATUS OF PROTOTYPE FAST

BREEDER REACTOR (PFBR) UNDER

CONSTRUCTION AT KALPAKKAM, INDIA

Tarun Kumar Mitra

Director (Technical), BHAVINI

Type : Fast Breeder

Reactor (pool

type)

Fuel : PuO2 + UO2

Reactor thermal Power : 1250 MWth.

Electrical output : 500/470 MWe

Coolant : Sodium

Gross thermal Efficiency : 40%

PFBR Project Details

PFBR REACTOR

ASSEMBLY

Sectional View of PFBR Reactor Assembly

PFBR is the first of its kind 500 MWe Fast Breeder Reactor in INDIA.

Sodium cooled mixed oxide fuel pool type reactor.

Forerunner of the second stage of the nuclear power program.

Largest and deepest excavated pit in Indian nuclear plants.

First Reactor on common RAFT.

Fabrication and manufacturing of critical NSSS components for the first

time at site by industry with close tolerances.

Salient Features

PFBR- Status of major equipments erection

All heavy large diameter reactor components like, Safety vessel, Main

vessel, Thermal Baffle, Grid plate, Inner vessel & Roof slab erection has

been completed.

Both small and large rotatable plugs erected and Insitu heavy density

concreting also have been completed.

Long components like steam generators, Decay Heat Exchanger, Hot &

Cold pool level detector housing etc., have been completed.

Fuel handling equipment like, Primary tilting mechanism, primary ramp ,

transfer pot and fuel building components have been erected and pre-

commissioning works are in progress.

Safety vessel Main vessel Thermal baffle

Grid plate Inner vessel Roof slab

MAJOR REACTOR COMPONENTS ERECTION

LRP & SRP Erection

IHX ERECTION

DHX ERECTION

SG ERECTION

PTM ERECTION OVER GRID PLATE

Both the primary and secondary sodium pumps have been erected .

CSRDM & DSRDM have been erected. Control plug has been erected.

Two nos. of AHX- Type (A) has been erected . Two more AHX ( Type-B)

erection under progress.

All the equipment below roof slab and inside main vessel has been erected

Two nos. of CCW pump has been erected in the concrete volute pump in

SWPH.

PFBR- Recent erection activities

completed

13

14

Primary sodium Pump Erection

PSP erection and assembly

CONTROL PLUG

ERECTION

CCW Pump Impeller erection

18

Reactor Top View

Commissioning – (systems completed)

• Water System

– Demineralized plant

– Raw water system

– Emergency & safety raw water system

– Emergency & safety service water system

• Electrical System

– Switch yard

– 6.6KV switchgear boards

– Battery charging

– Diesel Generators

• Fire protection system

– Fire alarm system

• Communication system

– Public Addressing system

• Air system

– Compressors

• Component handling system

– Under water trolley

– Fresh Sub Assembly

inspection facility

– Fresh Sub Assembly

Transfer chamber carriage

– All Cranes

Sodium piping system

20

Sodium piping termination to

Steam generator , IHX, DHX, SSP

and Tanks, Surge tanks , etc has

been completed.

Heater cables, Thermocouples,

Wire type leak detectors

installation completed.

Insulation and cladding also

completed for major sodium

systems.

Leak collection trays erection

under progress.

Pre-commissioning under progress

Piping work 100% completed.

I&C works are in progress and are nearing completion.

Erection and testing of field instruments , flow transmitters etc., are in

progress.

Utility Piping

SWPH

COMMISSIONING

6.6kv Switchgear

Battery banks

Battery Charger panels

PCC panels

MCC panels

Switch yard

Transmission

lines

Electrical systems

Switch yard

Majority of the electrical systems completed

Switch yard with Outgoing Transmission lines

Diesel Generator Facility

Diesel Generators commissioned

Nuclear Island & Power Island

Power Island – Turbine Building

Nuclear Island – Reactor Building

Turbine Building Progress

• Turbine on barring Gear has been successfully

achieved.

• Auxiliary boiler Commissioned.

• 97 % of the erection progress has been completed till

date.

27

28 TG Overall view

29

Auxiliary Boiler

Auxiliary Boiler

Commissioning completed.

Boiler light up

Safety valve floating

Steam blowing

DM PLANT COMMISIONING

KEY ACTIVITIES UNDER

PROGRESS

31

Pre-heating trials of main vessel commenced and is in progress

Pre-commissioning activities of sodium piping has commenced.

Commissioning of the auxiliary supporting systems are nearing completion.

RCB leak test commenced and under progress.

PFBR Project

progress 2.45%

Civil99.68

Mechanical

97.93

Electrical99.28

I&C93.31

Physical progress

till Apr-1497.55%

FBR 1&2

Pre-project activities completed

• Site selection – by Site Selection Committee

• Financial sanction for Pre-Project activities by Govt.

• Geo-technical investigations – Preliminary & additional.

• TOR ( Term Of Reference ) from MoEF obtained.

• Site Evaluation Report

• Plant layout finalized

• Design and construction drawings have been completed for the

construction of Site Assembly Shop (SAS).

• Detailed Project Report (DPR)

• Environmental Impact assessment (EIA) / Environmental Management

Plan (EMP) has been prepared and submitted to Tamil Nadu Pollution

Control Board (TNPCB)

Pre-project activities planned in the near future

Public hearing

Application for MoEF clearance

Application to govt. for financial sanction

• FBR 1 & 2 will be treated as a single project.

• Design will be similar as that of PFBR.

• First pour of concrete planned simultaneously.

Salient features

Project 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023

FBR-1

FBR-2

Preliminary Schedule for construction of FBR 1&2 project

Need for early launch of FBR 1&2

Thank You