Tarun Kumar Mitra
Director (Technical), BHAVINI
Type : Fast Breeder
Reactor (pool
type)
Fuel : PuO2 + UO2
Reactor thermal Power : 1250 MWth.
Electrical output : 500/470 MWe
Coolant : Sodium
Gross thermal Efficiency : 40%
PFBR Project Details
PFBR REACTOR
ASSEMBLY
PFBR is the first of its kind 500 MWe Fast Breeder Reactor in INDIA.
Sodium cooled mixed oxide fuel pool type reactor.
Forerunner of the second stage of the nuclear power program.
Largest and deepest excavated pit in Indian nuclear plants.
First Reactor on common RAFT.
Fabrication and manufacturing of critical NSSS components for the first
time at site by industry with close tolerances.
Salient Features
PFBR- Status of major equipments erection
All heavy large diameter reactor components like, Safety vessel, Main
vessel, Thermal Baffle, Grid plate, Inner vessel & Roof slab erection has
been completed.
Both small and large rotatable plugs erected and Insitu heavy density
concreting also have been completed.
Long components like steam generators, Decay Heat Exchanger, Hot &
Cold pool level detector housing etc., have been completed.
Fuel handling equipment like, Primary tilting mechanism, primary ramp ,
transfer pot and fuel building components have been erected and pre-
commissioning works are in progress.
Safety vessel Main vessel Thermal baffle
Grid plate Inner vessel Roof slab
MAJOR REACTOR COMPONENTS ERECTION
Both the primary and secondary sodium pumps have been erected .
CSRDM & DSRDM have been erected. Control plug has been erected.
Two nos. of AHX- Type (A) has been erected . Two more AHX ( Type-B)
erection under progress.
All the equipment below roof slab and inside main vessel has been erected
Two nos. of CCW pump has been erected in the concrete volute pump in
SWPH.
PFBR- Recent erection activities
completed
13
Commissioning – (systems completed)
• Water System
– Demineralized plant
– Raw water system
– Emergency & safety raw water system
– Emergency & safety service water system
• Electrical System
– Switch yard
– 6.6KV switchgear boards
– Battery charging
– Diesel Generators
• Fire protection system
– Fire alarm system
• Communication system
– Public Addressing system
• Air system
– Compressors
• Component handling system
– Under water trolley
– Fresh Sub Assembly
inspection facility
– Fresh Sub Assembly
Transfer chamber carriage
– All Cranes
Sodium piping system
20
Sodium piping termination to
Steam generator , IHX, DHX, SSP
and Tanks, Surge tanks , etc has
been completed.
Heater cables, Thermocouples,
Wire type leak detectors
installation completed.
Insulation and cladding also
completed for major sodium
systems.
Leak collection trays erection
under progress.
Pre-commissioning under progress
Piping work 100% completed.
I&C works are in progress and are nearing completion.
Erection and testing of field instruments , flow transmitters etc., are in
progress.
Utility Piping
SWPH
COMMISSIONING
6.6kv Switchgear
Battery banks
Battery Charger panels
PCC panels
MCC panels
Switch yard
Transmission
lines
Electrical systems
Switch yard
Majority of the electrical systems completed
Turbine Building Progress
• Turbine on barring Gear has been successfully
achieved.
• Auxiliary boiler Commissioned.
• 97 % of the erection progress has been completed till
date.
27
29
Auxiliary Boiler
Auxiliary Boiler
Commissioning completed.
Boiler light up
Safety valve floating
Steam blowing
KEY ACTIVITIES UNDER
PROGRESS
31
Pre-heating trials of main vessel commenced and is in progress
Pre-commissioning activities of sodium piping has commenced.
Commissioning of the auxiliary supporting systems are nearing completion.
RCB leak test commenced and under progress.
PFBR Project
progress 2.45%
Civil99.68
Mechanical
97.93
Electrical99.28
I&C93.31
Physical progress
till Apr-1497.55%
Pre-project activities completed
• Site selection – by Site Selection Committee
• Financial sanction for Pre-Project activities by Govt.
• Geo-technical investigations – Preliminary & additional.
• TOR ( Term Of Reference ) from MoEF obtained.
• Site Evaluation Report
• Plant layout finalized
• Design and construction drawings have been completed for the
construction of Site Assembly Shop (SAS).
• Detailed Project Report (DPR)
• Environmental Impact assessment (EIA) / Environmental Management
Plan (EMP) has been prepared and submitted to Tamil Nadu Pollution
Control Board (TNPCB)
Pre-project activities planned in the near future
Public hearing
Application for MoEF clearance
Application to govt. for financial sanction
• FBR 1 & 2 will be treated as a single project.
• Design will be similar as that of PFBR.
• First pour of concrete planned simultaneously.
Salient features
Project 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
FBR-1
FBR-2
Preliminary Schedule for construction of FBR 1&2 project
Need for early launch of FBR 1&2